BRMP_Map.pdf

PDF 15 MB Posted

Attached to
San Lorenzo River Levee Burrowing Rodent Mitigation Project
Solicitation number
IFB No. PW-0215
Issued by
Santa Cruz County, San Francisco City, California

About this file

The image is a detailed map titled "SLR FEMA - Burrowing Rodent Mitigation Project" covering an area in Santa Clara and Santa Cruz Counties. The map shows six distinct zones (Zones 1-6) along the San Lorenzo River levees, ranging from the Highway 1 bridge to the Santa Cruz Boardwalk parking lot trestle bridge. The map is an aerial view with a grid overlay, providing precise geographical boundaries for the burrowing rodent mitigation project area, with a scale ranging from 0 to 0.5 miles.

The map serves as a critical visual reference for the San Lorenzo River Levee Burrowing Rodent Mitigation Project, illustrating the specific geographic locations where rodent control and levee stabilization efforts will be implemented. The zones are strategically marked to highlight the areas requiring intervention, with both waterside and landside boundaries clearly defined. This mapping will assist contractors in understanding the precise scope and location of the burrowing rodent management program, which aims to address potential threats to levee integrity and prepare for FEMA certification.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Santa Clara County, Santa Cruz County, Maxar, Microsoft

ZONE 3

ZONE 6

ZONE 5

ZONE 2

ZONE 1

Approximate Project Area

SLR FEMA - Burrowing Rodent Mitigation Project

0 0.1 0.2 0.3 0.4 0.50.1

Miles

ZONE 4

APPENDIX A

NOTICE INVITING SEALED PROPOSALS OR BIDS
BID FORM
List of Subcontractors Form
Contractor Reference Information
LABOR AND MATERIAL BOND
FAITHFUL PERFORMANCE BOND
Contractor’s Certificate Relating to Worker’s Compensation
Good Faith Effort Statement for Local Hire
In conformance with Chapter 3.10 of the Municipal Code, each Contractor and subcontractor shall complete and submit this Statement following Award of Contract and prior to issuance of the Notice to Proceed.
Project Title:
Name and Title of Person Completing Statement:
Name of Contractor or Subcontractor:
Date Statement Completed:
Address:
Contractor (or Subcontractor) estimates that fifty percent (50%) or more of its workforce for this project meets the local hire requirements of this contract: ( Yes ( No*
*If no, complete the following table:
Local Hiring
GENERAL CONDITIONS
1. Failure to Execute Contract
2. Contractor's Insurance
3. Claims
4. Time of Completion
5. Failure to Complete the Work on Time (Liquidated Damages)
6. Existing Facilities
7. Water Pollution Control Program (WPCP) and/or Storm Water Pollution Prevention Program (SWPPP)
8. Maintenance and Clean-Up
9. State of California Department of Transportation Standard Specifications
10. Notification of Project Commencement
11. Project Schedule
12. Progress and Final Payment
13. Extra Work
The occurrence of any one or more of the following events will constitute a default by Contractor and justify termination for cause:
- Contractor’s persistent failure to perform the Work in accordance with the Contract Documents (including, but not limited to, failure to supply sufficient skilled workers or suitable materials or equipment, or failure to adhere to the Progress Sched...
- Failure of Contractor to perform or otherwise comply with a term of the Contract Documents;
- Contractor’s disregard of Laws or Regulations of any public body having jurisdiction; or Contractor’s repeated disregard of the authority of City or Engineer.
If one or more of the events identified above occurs, then after giving Contractor (and any surety) at least fourteen (14) calendar days’ written notice of City’s intent to terminate the Contract, City may proceed to:
- declare Contractor to be in default, and give Contractor (and any surety) written notice that the Contract is terminated; and
- enforce the rights available to City under any applicable performance bond.
Subject to the terms and operation of any applicable performance bond, if City has terminated the Contract for cause, City may exclude Contractor from the Site, take possession of the Work and all materials and equipment stored at the Site for which C...
City may proceed with termination of the Contract under this Section, unless Contractor within seven (7) days of the date of the notice of intent to terminate begins to correct Contractor’s failure to perform and proceeds diligently to cure such failure.
If the contract is terminated as provided herein, Contractor shall not be entitled to receive any further payment. If the unpaid balance of the Contract Price exceeds the cost to complete the Work, including all related claims, costs, losses, and dama...
Where Contractor’s services have been so terminated by City, the termination will not affect any rights or remedies of City against Contractor then existing or which may thereafter accrue, or any rights or remedies of City against Contractor or any su...
Upon fourteen (14) calendar days’ written notice to Contractor, the City may, without cause and without prejudice to any other right or remedy of City, terminate the Contract. In such case, Contractor shall submit a claim for payment including require...
- completed and acceptable Work executed in accordance with the Contract Documents prior to the effective date of termination;
- expenses sustained prior to the effective date of termination in performing services and furnishing labor, materials, or equipment as required by the Contract Documents in connection with uncompleted Work; and
- other reasonable expenses directly attributable to termination, including costs incurred to prepare a termination for convenience cost proposal.
City shall not be liable for costs incurred by Contractor, or any Subcontractor or supplier, after receipt of a notice of termination.
City shall deduct from Contractor any advance payments made to Contractor related to the terminated portion of the Contract Documents, any claim which City may have against Contractor in connection with the Contract Documents, and any other applicable...
C. Contractor May Stop Work or Terminate
If, through no act or fault of Contractor, or Subcontractor, or any employee or agent of Contractor or any Subcontractor, (1) the Work is suspended for more than 180 consecutive days by City or under an order of court or other public authority, or (2)...
In lieu of terminating the Contract and without prejudice to any other right or remedy, if City has failed to act on an application for payment by Contractor within thirty (30) days after it is submitted, or City has failed for sixty (60) days to pay ...

TECHNICAL SPECIFICATIONS

File details come from the government source that posted it. Updated .