Blaine_Res_Specifications_and_Statement_of_work.pdf
PDF 179 KB Posted
- Attached to
- 2024 BLAINE COUNTY RESERVOIRS
- Solicitation number
- 140L3624Q0085
About this file
This document appears to be a set of specifications and a statement of work for the 2024 Blaine County Reservoirs project. The work includes decommissioning 4 reservoir sites, constructing 4 new pits, and repairing 3 reservoir sites. Specific details are provided for the various work tasks at each location, including dimensions, slopes, and excavation quantities. The statement of work covers site preparation, excavation, embankment development, and core trenching requirements. It also addresses project meetings, work scheduling, permits, and measurement/payment terms. The related federal contract opportunity is Solicitation Number 140L3624Q0085, issued by the Department of the Interior Bureau of Land Management for the 2024 Blaine County Reservoirs project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation_Package_Construction_Revised_0001.pdf | ||
| Sol_140L3624Q0085_Amd_0001.pdf | ||
| B08_Past_Performance_Questionnaire.doc | DOC document | |
| Sol_140L3624Q0085.pdf | ||
| B03_WD_MT20230077_REV_Date_07_05_2024.pdf | ||
| Drawings_signed_2-27-24_RPS_bh.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2024 BLAINE RESERVOIRS
PART IV - SPECIFICATIONS
INDEX
DIVISION 1 - GENERAL REQUIREMENTS TITLE
01009 General Information and Requirements 01019 Government Furnished Property 01060 Permits
DIVISION 2 - SITE WORK TITLE
MT 02291 Minor Earth Dams and Pits
01009 - 1
DIVISION 1 SECTION 01009
GENERAL REQUIREMENTS GENERAL INFORMATION AND
REQUIREMENTS
Rev. 5-91.
PART 1: GENERAL
1.01 SUMMARY:
A. Description of work: Furnishing labor, equipment, supplies and materials to decommission 4 sites, construct 4 new pits and repair 3 sites.
1. Arch Res: (Decommission) Embankment will be removed and excavation will be placed within old highwater line. Dimensions shown on Work Data Sheet.
3. S. Coal Pit: (New) Typical Pit Drawing
2. N. Coal Pit: (New) Typical Pit Drawing
4. S Coal Res: (Decommission) Embankment will be removed and excavation will be placed within old highwater line. Dimensions shown on Work Data Sheet.
5. Fast Res: (Decommission) Remove Embankment and place in impoundment area. Reservoir will be dry when construction begins. New Pit constructed down drainage of old Reservoir.
6. Fast Res Pit: (New) Typical Pit Drawing
7. N. Frk. Res: (Repair) Current spillway has head cut. Construct Core Trench in spillway and replace with embankment across spillway. at a 3:1 slope. Cut new spillway on west side of embankment. Pay quantities will reflect excavation of spillway, core trench and Uncompacted Embankment over existing spillway on east side of existing embankment.
8. Wadeish Res: (Repair) Typical Res Drawings. Embankment rebuild. Headcut in center of embankment.
Embankment raised 2 feet.
9. Works Pit: (Decommission) Existing pit leaks. Place spoil from adjacent to pit back into pit.
10. Rework Pit: (New) New Pit constructed upstream from existing Works Pit that will be reclaimed.
11. Croak Reservoir: (Repair) Strip the embankment of vegetation. Place additional 2 feet on top of
DIVISION 1 SECTION
01009
GENERAL REQUIREMENTS GENERAL INFORMATION AND
REQUIREMENTS
Rev. 5-91
01009 - 2 existing embankment to regain freeboard of Dam.
B. Location: Work under this Contract is located in Blaine County, State of Montana. The work locations are shown on the drawings.
C. Work Data Sheet: Designates the type and quantity of work required at each project location, and dimensions required for typical drawings.
1.02 DEFINITIONS:
A. Approvals: Approval of the submittals is an indication that the Contractor's submittals have been reviewed and that there are no objections, except as noted. Approval of deviations shall apply only to those deviations or omissions from the requirements of the drawings and specifications brought to the Contracting Officer's attention in writing.
1.03 SUBMITTALS:
A. Scope: Submittals include the work schedule
1.04 QUALITY ASSURANCE:
A. Codes and Standards: The work shall comply with codes and standards applicable to each type of work and as listed in the individual sections of these specifications. This Contract incorporates materials, applications, and tests by reference with the same force and effect as if they were given full text.
B. Conflict: Where conflict occurs between reference documents and project specifications, the project specifications shall govern.
1.05 PROJECT/SITE CONDITIONS:
A. Access to the Work:
1. Access to the work shall be provided by and at the Contractor's expense. Prior to the building of access roads across lands under the jurisdiction of the Bureau of Land Management, the Contractor shall obtain approval of the Contracting Officer.
2. Public or private access roads damaged by the Contractor shall be
GENERAL REQUIREMENTS GENERAL INFORMATION AND
01009 - 3 restored, at the Contractor's expense, to the same condition they were in at the commencement of work.
3. Access construction shall be accomplished with regard for environmental considerations.
4. Utilities: Before starting excavation, establish the location and extent of overhead and underground utilities in the work area. Protect active utility services uncovered by excavation. Damage to any utilities shall be repaired or replaced at the Contractor’s expense.
Repair to damaged utilities shall be started immediately unless otherwise authorized by the Contracting Officer. (Montana Utility Mark Out Telephone No. 1-800-424-5555)
B. Environmental Considerations:
1. Operations of the Contractor (including storage of materials, project office, camping area, and equipment parking) upon Government premises shall be confined to areas approved by the Contracting Officer.
The surrounding landscape shall not be disturbed In the event that it is disturbed, the Contractor shall restore that area at the Contractors expense. Government premises adjacent to the construction site will be made available for use by the Contractor without cost whenever such use will not interfere with other Government activities.
2. Motorized equipment brought in from outside local areas shall be clean to help prevent the spread of noxious weeds. Power washing may be required.
3. Work will not be allowed on the site during winter and spring months due to Wildlife Issues associated with the Environmental Assessments.
The Environmental Assessments specify that NO construction will be allowed between December 1st and JuLY 15th due to Mule Deer, Pronghorn winter range and Greater Sage Grouse nesting habitat.
1.06 SEQUENCING AND SCHEDULING:
A. Work Schedule: The schedule shall be submitted at the pre-work conference. When requested, the Contractor shall submit an updated schedule within 3 calendar days.
PART 2: PRODUCTS
(There are no applicable requirements.)
GENERAL REQUIREMENTS GENERAL INFORMATION AND
01009 - 4
PART 3: EXECUTION
3.01 PROJECT MEETINGS:
A. Pre-Work Conference:
1. Notification: A pre-work conference will be held prior to the start of work. The Contractor will be notified in advance of meeting time, date and place. The purpose will be to review required work, project drawings and specifications, construction schedules, payroll and payments, and administrative provisions of the Contract.
2. Attendance: The Contractor, subcontractors and the person or persons responsible for coordination of the work shall be present at the meeting.
3. Presentation: The Contractor shall be prepared to summarize and explain procedures planned for the project and present the submittals requested in the specifications.
B. Progress Meetings:
1. Location: Meetings shall be held at the project site, or as determined by the Contracting Officer.
2. Notification: Meetings may be called by either the Contracting
Officer or the Contractor. Request shall state who should attend.
C. Final Inspection:
1. Location: Meeting shall be held at the project site, or as determined by the Contracting Officer.
2. Notification: The Contractor shall notify the Contracting Officer at least 3 working days before the scheduled completion date so the Government can schedule final inspection.
3. Attendance: Contractor shall require the superintendent be present during this inspection.
3.02 WORK LAYOUT:
A. Requirements: The Government will set construction stakes to give the Contractor measurements, lines and grades necessary for the work executed under the Contract. Baseline monuments or benchmarks disturbed or removed during construction shall be reset by the Contractor at the Contractor's expense.
GENERAL REQUIREMENTS GENERAL INFORMATION AND
01009 - 5
3.03 PROJECT MONUMENT:
A. Requirements: The Contractor shall install a Government-furnished project monument at the location designated by the Contracting Officer.
PART 4: MEASUREMENT AND PAYMENT
4.01 METHOD OF MEASUREMENT:
A. Units: The work described in this section will not be measured for payment.
4.02 BASIS OF PAYMENT:
A. Payment: No direct payment for the work described under this section will be made. Contractors shall include consideration for this item in the bid price for other scheduled items of the Contract.
END OF SECTION
01019 - 1
DIVISION 1 SECTION 01019
GENERAL REQUIREMENTS GOVERNMENT FURNISHED PROPERTY
Rev. 3-93
PART 1: GENERAL
1.01 SUMMARY:
A. Section includes: The materials to be furnished by the Government and their locations.
1.02 DELIVERY, STORAGE, AND HANDLING:
A. Location: Government-furnished property will be provided by the Bureau of Land Management, Havre Field Station, 3990 Highway 2 West, Havre, Montana, Phone
(406) 262-2820.
B. Time: Property will be available Monday through Friday between the hours of 8:00 a.m. and 12:00 noon, and 1:00 p.m. and 4:00 p.m., except on holidays.
C. Return of Unused Property: Unused material shall be returned to the same location, and during the same time periods, as listed above.
D. Loading/Offloading/Transporting Property: The Contractor shall load and transport materials to worksites.
PART 2: PRODUCTS
2.01 MATERIALS:
A. Materials to be Furnished by the Government:
Specification Materials Section Description Quantity Unit
01009 Project Monument 4 Each
PART 3: EXECUTION (There are no applicable requirements)
PART 4: MEASUREMENT AND PAYMENT
4.01 METHOD OF MEASUREMENT: The work described in this section will not be measured for payment.
4.02 BASIS OF PAYMENT:
A. Payment: No direct payment for the work described under this section will be made. Contractors shall include consideration for this item in the bid price for other scheduled items of the Contract.
DIVISION 1 - GENERAL REQUIREMENTS
SECTION 01060 – PERMITS
PART 1 - GENERAL
1.01 WORK INCLUDED:
Except as otherwise noted, identify, obtain, maintain, and proceed in conformity with all required permits for the Work.
Obtain all Permits necessary for the completion of the Work. Any costs associated with these Permits are included as part of the Contract Price as incidental costs.
1.02 SUBMITTALS:
Prior to proceeding with the work authorized by the Permit, supply to the GOVERNMENT a copy of all Permits obtained. Perform all compliance testing required by the permits. Submit results of compliance testing directly to the appropriate review agency. Provide copies of all results to GOVERNMENT.
PART 2 - PRODUCTS - NONE
PART 3 - EXECUTION - NONE
END OF SECTION 01060
MT-02291 - 1
DIVISION 2 SECTION MT-O2291
SITE WORK MINOR EARTH DAMS AND PITS
Rev. 12-91
Part 1: GENERAL
1.01 WORK INCLUDED:
A. Description: Clearing, grubbing, excavation, embankment development, and core trenching for construction of earth dams and pits as shown on the drawings and in the Work Data Sheet. Furnishing labor, equipment, supplies and materials to decommission 4 sites, construct 4 new pits and repair 3 sites.
1. Arch Res: (Decommission) Embankment will be removed and excavation will be placed within old highwater line. Dimensions shown on Work Data Sheet.
3. S. Coal Pit: (New) Typical Pit Drawing
2. N. Coal Pit: (New) Typical Pit Drawing
4. S Coal Res: (Decommission) Embankment will be removed and excavation will be placed within old highwater line. Dimensions shown on Work Data Sheet.
5. Fast Res: (Decommission) Remove Embankment and place in impoundment area. Reservoir will be dry when construction begins. New Pit constructed down drainage of old Reservoir.
6. Fast Res Pit: (New) Typical Pit Drawing
7. N. Frk. Res: (Repair) Current spillway has head cut. Construct Core Trench in spillway and replace with embankment across spillway. at a 3:1 slope. Cut new spillway on west side of embankment. Pay quantities will reflect excavation of spillway, core trench and Uncompacted Embankment over existing spillway on east side of existing embankment.
8. Wadeish Res: (Repair) Typical Res Drawings. Embankment rebuild. Headcut in center of embankment.
Embankment raised 2 feet.
9. Works Pit: (Decommission) Existing pit leaks. Place spoil from adjacent to pit back into pit.
10. Rework Pit: (New) New Pit constructed upstream from existing Works Pit that will be reclaimed.
11. Croak Reservoir: (Repair) Strip the embankment of vegetation. Place additional 2 feet on top of existing
MT-02291 - 2
embankment to regain freeboard of Dam.
1.02 PROJECT CONDITIONS:
A. Work Limits: Work limits will be staked and control points established by the Government. Contractor shall not borrow outside staked areas (usually located below reservoir high water lines) without prior written approval form the Contracting Officer.
B. Climatic Conditions: No work required under this section will be allowed when materials are frozen or excessively wet.
C. Haul Distance: The maximum haul distance shall not exceed 1,500 feet, measured by the straight line distance from the center of mass of the embankment to the farthest point in the borrow area.
PART 2: PRODUCTS
2.01 MATERIALS:
A. Waste Material: Waste material is defined as brush, trees, stumps, frozen lumps, non-plastic silt, and oversized rocks. Oversized rocks are of such size and shape that will interfere with the uniform placement of earthfill materials in layers of specified thickness.
B. Topsoil: Topsoil material shall be considered to be that material which will sustain plant growth and includes sod, roots, and other small vegetative matter which con be uniformly placed to a thickness of 3 inches without protruding from the finished grade.
C. Permeable Material: Sand, gravel, and rock.
D. Common Excavation: Materials to be removed from excavation. Common excavation includes rip able material. Material shall be considered rip able if the Contractor is able to rip material with a rear-mounted, heavy duty, single-tooth, ripping attachment mounted on a crawler tractor having a power rating of at least 195 net horsepower.
E. Embankment: Embankment materials shall be free of topsoil and waste material. Excavation required for embankment pay quantities shall be subject to the same material requirements as common excavation.
PART 3: EXECUTION.
3.01 PREPARATION:
A. Clearing, Stripping, Grubbing: The area to be excavated and the surface area to be covered by embankments shall be:
1. Cleared of waste material. The Contractor shall conserve available topsoil.
2. Stripped of topsoil, with the topsoil deposited in stockpiles at designated locations.
DIVISION 2 SECTION MT-02291
Rev. 12-91
MT-02291 - 3
3. Grubbed to remove remaining waste material.
B Bank Sloping: Slopes not otherwise designated within the foundation area, including channel banks, shall be trimmed to a slope not steeper than 3:1.
Suitable material resulting from the bank sloping operation shall be removed and deposited in the embankment, or stockpiled for use in the embankment.
C Utilities: Before starting excavation, establish the location and extent of overhead and underground utilities in the work area. Protect active utility services uncovered by excavation. Damage to any utilities shall be repaired or replace at the Contractor’s expense. Repair to damaged utilities shall be started immediately unless otherwise authorized by the State of Montana. (Montana Utility Mark Out Telephone No. 1-800-424-5555)
3.02 INSTALLATION:
A. Placement of Topsoil: After construction of the embankment and excavation areas is completed, the stockpiled topsoil shall be uniformly placed to a depth of 3 inches over the downstream slope of embankments which are 3:1 or greater, areas above the highwater line, including the top and upstream slopes of embankments, spillways, borrow pits, and waterfowl islands to form a seedbed for planting.
B. Foundation: After the required preparation has been completed and the core trenches, when required on the Work Summary Chart or drawings, have been excavated, the foundation shall be scarified. Scarifying shall consist of ripping furrows to a depth of 6 to 8 inches. Furrows shall be a maximum of 3 feet apart and parallel to the axis of the embankment.
C. Excavation: Suitable excavated materials shall be placed directly in required embankments or if authorized, placed in temporary stockpiles and later placed in the embankment. Excavation material from core trenches for pit reservoirs shall not be stockpiled. Required excavation which is in excess of the requirements for embankment shall be designated as waste. Waste materials shall be uniformly placed immediately below the downstream toe of the embankment in a manner that will not leave windrows. The Contractor shall use care not to disturb existing vegetation in natural spillways or sod watercourse areas below excavated spillways.
D. Embankment:
1. Materials shall be placed parallel to the axis of the embankment in even, continuous, approximately horizontal layers not more than 8 inches in thickness. The full cross section of the fill shall be maintained as each successive layer is placed.
2. Successive loads of material shall be placed to produce a distribution of material throughout the embankment that is free from lenses, pockets, streaks, or layers of material differing
MT-02291 - 4
substantially in texture or gradation form surrounding material.
3. Travel of equipment shall be distributed evenly over the entire width of the embankment to obtain the maximum uniform compaction possible while placing material. Over compaction along the hauling route, which causes lenses to develop, shall be avoided. Should lenses develop, the Contractor shall scarify these areas prior to placing the next lift of material.
4. Permeable materials shall be placed downstream of the embankment core trench in the embankment to act as a underdrain or shall be placed above the high-water line of the embankment.
3.03 FIELD QUALITY CONTROL:
A. Uncompacted Embankment: Routing equipment as described above will be sufficient compaction. The Contractor will not be required to perform additional passes of his hauling equipment to increase the degree of compaction.
PART 4: MEASUREMENT AND PAYMENT
4.01 METHOD OF MEASUREMENT:
A. General: Unless otherwise provided the slope stake basis of measurement for earthwork will be used. Slope stake measurements taken prior to construction will be used provided the work has been acceptably completed in conformity to the staked lines and slopes. When changes in the original slope stakes are approved, final cross-section or comparable measurements will be taken of the completed work. Clearing, stripping, and grubbing of waste material and topsoil, stockpiling and placing topsoil , and scarifying foundations will not be measured for payment.
B. Common Excavation: Common excavation material will be measured in the original space occupied and includes:
1. Excavated material from designated borrow areas, water retention pits, pit cut spillways, and pit core trenches which is placed directly in water retention pit embankments and retention dam embankments.
2. Excavated materials designated and placed as waste.
3. Excavated material which is suitable for placement in minor retention dam embankment but authorized to be placed in temporary stockpiles. Stockpiled material which is subsequently placed in an
MT-02291 - 5
embankment will also be included for payment under the respective pay item for embankment.
4. Separate payment for material excavated and placed directly in minor retention dam embankment or embankments from borrow areas, cut spillways, and core trenches will not be made under common excavation but will be considered for payment as embankment only.
5. When it is impractical to measure material in the original space occupied due to erratic locations of small deposits, three dimensional measurements of hauling vehicles will be used.
C. Embankment: Embankment material which includes the space occupied by the embankment and dam core trench will be measured in-place for minor retention dams. Embankment shall be classified as compacted or uncompacted as designated on the Work Summary Chart. The existing reservoir shall have their top and front slopes reconstructed.
D. Units: Measurements will be recorded in feet and volumes will be computed in cubic yards.
1. Nonprismoidal volumes will be calculated by the average end area method.
Formula: Volume = L(A1 + A2) / 27(2)
Where: L = Horizontal distance between cross sections.
A = Area of the cross section.
27 = Conversion factor for cubic feet to cubic yards.
2 = Divisor (averages of two areas).
4.02 BASIS OF PAYMENT:
A. Payment: Prices and payment will be full compensation for the work described in this section. Payment will be made under:
Pay Item Pay Unit MT-02291(1) Common Excavation ...........................Cubic Yard
MT-02291(2) Embankment-Uncompacted........................Cubic Yard
WORK DATA SHEET
2024 BLAINE RESERVOIRS
COMMON EXCAVATION
MT-02291(1)
WORK COMMON DIMENSIONS
MAP PROJECT LOCATION EXCAVATION (FEET) SLOPES EMBANKMENT
NO. NUMBER NAME TN RE SEC.Q. Q. (CU.YDS) L x W x D END SIDE SHAPE
1. 447170 Arch Res 34 20 3 SE NW 1370 84 61 12 3:1 3:1 -
GPS 48.73924 -109.101505
Open Face
2. 1000192 N. Coal Pit 34 20 3 SE NE 3230 140 90 10 2:1 2:1 -
GPS 48.739195 -109.094162
Open Fac
3. 1000196 S. Coal Pit 34 20 3 SE SE 2020 130 80 10 3:1 3:1 -
GPS 48.729332 -109.091126
Open Face
4. 1000197 S Coal Res 34 20 3 NW SE 290 80 10 5 2:1 2:1 -
GPS 48.731223 -109.095650
Open Face
5. 443872 Fast Res 34 20 2 NW SW 1550 350 25 7 2:1 2:1 -
GPS 48.733399 -109.086037
Open Face
6. 443872 Fast Res Pit 34 20 2 NW SW 2020 130 80 10 3:1 3:1 -
GPS 48.734456 -109.085492
Open Face
7. 006310 N. Frk. Res 36 20 13 SW SW 280 123 25 2 3:1 3:1 - GPS 48.881468 -109.066312 Open Face
9. 022065 Works Pit 34 21 7 NE SE 2450 138 80 10 4:1 2:1 None
GPS 48.719075 -109.027324
10. 022065 Rework Pit 34 21 7 NW SE 1980 130 80 10 3:1 3:1 -
GPS 48.718975 -109.028881
Open Face
TOTAL 15,190 CU. YDS
Open Face Pit means the borrow from the excavation will be placed adjacent to the pit and not to be placed down drainage to store additional water.
Pg 1 of 2
Fill EMBANKMENT UNCOMPACTED
MT-02291(2)
CENTERLINE CORE TRENCH
WORK EMBANKMENT MAX. MAX. SIDE MIN.
MAP PROJECT LOCATION UNCOMPACTED LENGTH FILL SLOPE SLOPE DEPTH
NO. NUMBER NAME TN RE SEC. Q. Q. (CU.YD) (FEET) (FEET) US DS US DS (FEET) SPILLWAY
7. 006310 N. Frk. Res 36 20 13 SW NW 290 53 8 3:1-3:1 3:1-3:1 CUT
GPS 48.881468 -109.066312
8. 443818 Wadeish Res 34 21 8 NE NW 1020 140 10 3:1-3:1 3:1-3:1 3 NONE
GPS 48.725337 -109.013321
11. 446862 Croak Res 32 25 17 SE SW 190 100 2.5 3:1-3:1 NONE 3 NONE
GPS 48.673109 -108.969582
TOTAL 1500 CU. YDS.
Pg 2 of 2
| PART IV 2024.BR.2024 |
| 01009.NBR.2024 |
| 01019 NBR_2024 |
| 01060.NBR.2024 |
| PART 1 - GENERAL |
| 1.01 WORK INCLUDED: |
| 1.02 SUBMITTALS: |
| PART 2 - PRODUCTS - None |
| PART 3 - EXECUTION - None |
| MT-02291 2024NBR.2024 |
| WORK.DATA.BR.2024 |
| MAP PROJECT LOCATION EXCAVATION (FEET) SLOPES EMBANKMENT |
| NO. NUMBER NAME TN RE SEC.Q. Q. (CU.YDS) L x W x D END SIDE SHAPE |
| CENTERLINE CORE TRENCH |
| NO. NUMBER NAME TN RE SEC. Q. Q. (CU.YD) (FEET) (FEET) US DS US DS (FEET) SPILLWAY |