This is an AIA Document A101-2017 Standard Form of Agreement between Owner and Contractor for a stipulated sum construction project involving School District No. 1 in the City and County of Denver, Colorado and an unnamed contractor for the West High School Field Abatement project. The contract document establishes the fundamental terms governing the construction work, including provisions for contract execution, work scope, commencement and completion dates, payment terms, and dispute resolution. The contractor shall achieve Substantial Completion by a date to be specified, with Final Completion required within 30 calendar days thereafter. Commencement occurs on the first business day following the contractor's receipt of the signed Intent to Award, which will only be issued after the Agreement is signed by both parties, approved by the School District's Board of Education, and all required bonds and insurance documentation is received. Progress payments are made monthly based on Applications for Payment reviewed by the Architect, with a five percent retainage withheld from each payment prior to Substantial Completion.

The contract sum is left blank in this template document and will be subject to additions and deductions as provided in the Contract Documents. Liquidated damages are established for failure to achieve Substantial Completion and Final Completion, with specific daily amounts to be inserted by the parties. Final payment, constituting the entire unpaid balance minus disputed sums and authorized deductions, is due within 30 days of the Owner's Director of Planning, Design and Construction approval. The contractor must comply with Davis-Bacon prevailing wage requirements if federal funding is utilized, maintain required insurance and performance bonds per AIA Document A201-2017, and ensure that Certified Minority and Women Business Enterprises perform a specified percentage of the project work. The contract is governed by Colorado law with exclusive venue in the City and County of Denver, and incorporates sustainability measures consistent with the Owner's goal of achieving an energy use intensity of 48 for all buildings.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Document A101® – 2017 Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 18:54:26 MDT on 06/12/2025 under Subscription No.20250093517 which expires on , is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (640e2aedf442e4498d0967f6)

ADDITIONS AND DELETIONS:

The author of this document may have revised the text of the original AIA standard form. An Additions and Deletions Report that notes revisions to the standard form text is available from the author and should be reviewed. A vertical line in the left margin of this document indicates where the author has added to or deleted from the original AIA text.

This document has important legal consequences. Consultation with an attorney is encouraged with respect to its completion or modification.

The parties should complete A101®–2017, Exhibit A, Insurance and Bonds, contemporaneously with this Agreement. AIA Document A201®–2017, General Conditions of the Contract for Construction, is adopted in this document by reference. Do not use with other general conditions unless this document is modified.

ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document.

AGREEMENT made as of the day of in the year (In words, indicate day, month and year.)

BETWEEN the Owner:

(Name, legal status, address and other information)

School District No. 1 in the City and County of Denver and State of Colorado 1860 Lincoln Street Denver, CO 80203 and the Contractor:

(Name, legal status, address and other information) for the following Project:

(Name, location and detailed description)

The Architect:

(Name, legal status, address and other information)

The Owner and Contractor agree as follows.

Exhibit G

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 18:54:26 MDT on 06/12/2025 under Subscription No.20250093517 which expires on , is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (640e2aedf442e4498d0967f6)

TABLE OF ARTICLES

1 THE CONTRACT DOCUMENTS

2 THE WORK OF THIS CONTRACT

3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION

4 CONTRACT SUM

5 PAYMENTS

6 DISPUTE RESOLUTION

7 TERMINATION OR SUSPENSION

8 MISCELLANEOUS PROVISIONS

9 ENUMERATION OF CONTRACT DOCUMENTS

EXHIBIT A WAGE DETERMINATION

EXHIBIT B CODE OF CONDUCT AND CONFLICT OF INTEREST CERTIFICATION

ARTICLE 1 THE CONTRACT DOCUMENTS

§ 1.1 The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary, and other Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed in this Agreement, and Modifications issued after execution of this Agreement, all of which form the Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations, or agreements, either written or oral. An enumeration of the Contract Documents, other than a Modification, appears in Article 9. Any reference to Contract Documents or any documents included in the Contract Documents and/or supplemented for this Project, shall refer to the Contract Documents as amended for this Project.

§ 1.2 This Agreement represents the entire and integrated agreement between the Owner and the Contractor and supersedes all prior negotiations, representations or agreements, either written or oral. Any revision, amendment, or modification to the Standard Form of this Agreement shall be valid, binding, and enforceable only if said revision, amendment or modification is made conspicuous by being underlined, lined-through, or highlighted in this Agreement signed by Contractor and the Owner’s Board of Education or designee as identified in Owner’s Board of Education Regulation DJA-R. In the event of conflict, terms and conditions contained in the Agreement shall take precedence over terms and conditions contained in the General Conditions and the terms and conditions in the General Conditions shall take precedence over all other terms and conditions contained in the other Contract Documents. If the Request for Proposals and the Proposal are included in the Contract Documents, then the Request for Proposals shall take precedence over the Proposal, unless specifically agreed otherwise herein.

§ 1.3 The Owner’s Board of Education or designee as identified in Owner’s Board of Education Regulation DJA-R is the only representative of the Owner, an independent school district, having the power to enter into or amend a contract, to approve changes in the scope of the Work, to approve and execute a Change Order or Construction Change Directive modifying the Contract Sum, or to agree to an extension to the date of Substantial or Final Completion or to terminate a contract.

ARTICLE 2 THE WORK OF THIS CONTRACT

The Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in the Contract Documents to be the responsibility of others.

ARTICLE 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION

§ 3.1 The date of commencement of the Work shall be:

[ X ] Established as follows:

(Insert a date or a means to determine the date of commencement of the Work.)

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 18:54:26 MDT on 06/12/2025 under Subscription No.20250093517 which expires on , is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (640e2aedf442e4498d0967f6)

The commencement date will be the first business day after the Contractor’s receipt of the signed Intent to Award. The Intent to Award shall not be issued by Owner until the Agreement has been signed by the Contractor, approved by the Owner’s Board of Education, signed by the Owner’s Board of Education or designee as identified in Owner’s Board of Education Regulation DJA-R, and Owner and Architect have received all required payment and performance bonds and insurance, in compliance with Article 11 of AIA Document A201-2017.

§ 3.2 The Contract Time shall be measured from the date of commencement of the Work.

§ 3.3 Substantial Completion § 3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work:

[ X ] By the following date:

§ 3.3.2 Omitted.

§ 3.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.3, liquidated damages, if any, shall be assessed as set forth in Section 4.5.

ARTICLE 4 CONTRACT SUM

§ 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor’s performance of the Contract.

The Contract Sum shall be ($ ), subject to additions and deductions as provided in the Contract Documents.

§ 4.2 Alternates § 4.2.1 Alternates, if any, included in the Contract Sum:

Item Price

§ 4.3 Allowances, if any, included in the Contract Sum:

(Identify each allowance.)

Item Price

§ 4.4 Unit prices, if any:

(Identify the item and state the unit price and quantity limitations, if any, to which the unit price will be applicable.)

Item Units and Limitations Price per Unit ($0.00)

§ 4.5 Liquidated damages § 4.5.1 Substantial Completion. Time is of the essence in all phases of the Work. It is specifically understood and agreed by and between Owner and Contractor that time is of the essence in the Substantial Completion of the Project and Owner shall sustain damages as a result of Contractor’s failure, neglect or refusal to achieve said deadlines. Such damages are, and will continue to be, impracticable and extremely difficult to determine. Execution of this Agreement under these specifications shall constitute agreement by Owner and Contractor that the amounts stated below are the minimum value of the costs and damages caused by failure of Contractor to complete the Work within the allotted or agreed extended times of Substantial Completion, that such sums are liquidated damages and shall not be construed as a penalty, and that such sums may be deducted from payments due Contractor if such delay occurs. It is expressly understood that the said sum per day is agreed upon as a fair estimate of the pecuniary damages which will be sustained by the Owner in the event that the Work is not completed within the agreed time, or

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 18:54:26 MDT on 06/12/2025 under Subscription No.20250093517 which expires on , is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (640e2aedf442e4498d0967f6) within the agreed extended time, if any, otherwise provided for herein. Said sum shall be considered as liquidated damages only and in no sense shall be considered a penalty, said damages being caused by, but not limited to, additional compensation for personnel, attorney’s fees, architectural fees, engineering fees, program management fees, inspection fees, storage costs, food service costs, transportation costs, utilities costs, costs of temporary facilities, loss of interest on money, and other increased costs, all of which are difficult to exactly ascertain. Failure to complete the Work within the designated or agreed extended dates of Substantial Completion, shall be construed as a breach of this Agreement. It is expressly agreed as a part of the consideration inducing the Owner to execute this Agreement that the Owner may deduct from any Payment made to the Contractor a sum equal to [INSERT AMOUNT] per calendar day for each and every additional calendar day beyond the agreed date of Substantial Completion.

§ 4.5.2 Final Completion. In addition, timely Final Completion is an essential condition of this Agreement. Contractor agrees to achieve Final Completion of the Agreement within 30 calendar days of the designated or agreed extended date of Substantial Completion. It is specifically understood and agreed by and between Owner and Contractor that time is of the essence in the Final Completion of the Project and Owner shall sustain additional damages as a result of Contractor’s failure, neglect or refusal to achieve said deadline. Such damages are, and will continue to be, impracticable and extremely difficult to determine.

Execution of this Agreement under these specifications shall constitute agreement by Owner and Contractor that the amounts stated below are the minimum value of the costs and damages caused by failure of Contractor to complete the Work within the allotted or agreed extended times for Final Completion, that such sums are liquidated damages and shall not be construed as a penalty. It is expressly understood that the said sum per day is agreed upon as a fair estimate of the pecuniary damages which will be sustained by the Owner in the event that the Work is not finally completed within the agreed time, or within the agreed extended time, if any, otherwise provided for herein. Said sum shall be considered as liquidated damages only and in no sense shall be considered a penalty, said damages being caused by, but not limited to, additional compensation for the following categories of damages to the Owner: potential hazards to students, staff and visitors, additional architectural, engineering, program management fees (and fees of any other consultants); increased administrative or operational expenses; additional attorney’s fees; increased maintenance and custodial costs and additional, utilities, security and clean-up costs, and other increased costs. Failure to complete the Work within the designated or agreed extended dates of Final Completion, shall be construed as a breach of this Agreement. Owner and Contractor agree that should Contractor fail to achieve Final Completion of the Agreement by the deadline, Owner shall continue to be damaged to a greater degree by such delay. Contractor and Owner agree that the amount of liquidated damages for each calendar day Final Completion is delayed beyond the date set for Final Completion shall be the sum of [INSERT AMOUNT] per day. Owner may deduct such liquidated damages from any Payment made to Contractor before or at Final Payment; or, if sufficient funds are not available, then Contractor shall pay Owner, the amounts specified per day for each and every calendar day the breach continues after the deadline for Final Completion of the Work.

§ 4.5.3 Such damages shall be in addition to, and not in lieu of, any other rights or remedies Owner may have against Contractor for failure to timely achieve Final Completion, and damages for failure to achieve Substantial Completion and failure to achieve Final Completion may run concurrently. If the Work is not finally completed by the time stated in the Agreement, or as extended, no payments for Work completed beyond that time shall be made until the Project reaches Final Completion.

§ 4.6 Other:

(Insert provisions for bonus or other incentives, if any, that might result in a change to the Contract Sum.)

ARTICLE 5 PAYMENTS

§ 5.1 Progress Payments

§ 5.1.1 Based upon Applications for Payment reviewed by the Architect, the Owner shall make progress payments on account of the Contract Sum to the Contractor as provided below and elsewhere in the Contract Documents.

§ 5.1.2 The period covered by each Application for Payment shall be one calendar month.

§ 5.1.3 Omitted.

§ 5.1.4 Each Application for Payment shall be based on the most recent schedule of values submitted by the Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Contract Sum among the various portions of the Work. The schedule of values shall be prepared in such form, and supported by such data to substantiate its

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 18:54:26 MDT on 06/12/2025 under Subscription No.20250093517 which expires on , is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (640e2aedf442e4498d0967f6) accuracy, as the Owner may require. This schedule of values shall be used as a basis for reviewing the Contractor’s Applications for Payment.

§ 5.1.5 Applications for Payment shall show the percentage of completion of each portion of the Work as of the end of the period covered by the Application for Payment.

§ 5.1.6 In accordance with AIA Document A201™–2017, General Conditions of the Contract for Construction, and subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows:

§ 5.1.6.1 The amount of each progress payment shall first include:

.1 That portion of the Contract Sum properly allocable to completed Work;

.2 That portion of the Contract Sum properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the completed construction, or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing; and

.3 That portion of Construction Change Directives that the Architect determines, in the Architect’s professional judgment, to be reasonably justified to the extent approved by the Owner in writing, as provided in the General Conditions of the Contract for Construction.

§ 5.1.6.2 The amount of each progress payment shall then be reduced by:

.1 The aggregate of any amounts previously paid by the Owner;

.2 The amount, if any, for Work that remains uncorrected and for which the Architect has previously withheld a

Certificate for Payment as provided in Article 9 of AIA Document A201–2017;

.3 Any amount for which the Contractor does not intend to pay a Subcontractor or material supplier, unless the

Work has been performed by others the Contractor intends to pay;

.4 For Work performed or defects discovered since the last payment application, any amount for which the

Architect may withhold payment, or nullify a Certificate of Payment in whole or in part, as provided in Article 9 of AIA Document A201–2017; or amounts certified by the Architect and disputed by the Owner; and

.5 Retainage withheld pursuant to Section 5.1.7.

§ 5.1.7 Retainage § 5.1.7.1 For each progress payment made prior to Substantial Completion of the Work, the Owner shall withhold the following amount, as retainage, from the payment otherwise due: Five Percent (5%).

(Insert a percentage or amount to be withheld as retainage from each Application for Payment. The amount of retainage may be limited by governing law.)

§ 5.1.7.2 Reduction or limitation of retainage, if any, shall be as follows:

(If the retainage established in Section 5.1.7.1 is to be modified prior to Substantial Completion of the entire Work, including provisions for such modifications)

NONE

§ 5.1.7.3 Except as set forth in this Section 5.1.7.3, upon Final Completion of the Work, the Contractor may submit an Application for Payment that includes the retainage withheld from prior Applications for Payment pursuant to this Section 5.1.7.

§ 5.1.8 Omitted.

§ 5.1.9 Except with the Owner’s prior written approval or as otherwise provided in the general conditions, the Contractor shall not make advance payments to suppliers for materials or equipment which have not been delivered and stored at the site. When materials are stored off site, Contractor must provide insurance and proof of materials.

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 18:54:26 MDT on 06/12/2025 under Subscription No.20250093517 which expires on , is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (640e2aedf442e4498d0967f6)

§ 5.1.10 If Owner is entitled to deduct liquidated damages, or any other damages or amounts provided in the Contract Documents, including clean-up fees, then Owner shall be entitled to deduct such liquidated damages, amounts and fees at any time.

§ 5.1.11 If Contractor fails or refuses to complete the Work, or has unsettled claims with Owner, any payment to Contractor shall be subject to deduction for such amounts as the Architect if applicable, shall determine as the cost for completing incomplete Work and the value of unsettled claim.

§ 5.2 Final Payment § 5.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum minus disputed sums, authorized deductions and liquidated damages, shall be made by the Owner to the Contractor after

.1 the Contractor has fully performed the Contract except for the Contractor’s responsibility to correct nonconforming Work as provided in Article 12 of AIA Document A201–2017, and to satisfy other requirements, if any, which extend beyond final payment;

.2 the Contractor has provided all documents required by Sections 3.5 et seq. and 9.10.2 et seq. of AIA Document A201-2017;

.3 a final Certificate for Payment has been issued by the Architect; and

.4 Owner’s Director of Planning, Design and Construction has accepted the Work and approved the Final Payment.

§ 5.2.2 The Owner’s final payment of undisputed sums to the Contractor shall be made no later than 30 days after Owner’s Director of Planning Design and Construction approves Final Payment. After final payment, Owner will release retainage upon approval of completion of work by the Owner’s Director of Planning, Design and Construction per the Contract Documents.

§ 5.3 Omitted.

ARTICLE 6 DISPUTE RESOLUTION

§ 6.1 Initial Decision Maker

All disputes relating to this Agreement shall be resolved pursuant to the terms of Article 15 of the AIA Document A201-2007, as amended.

(If the parties mutually agree, insert the name, address and other contact information of the Initial Decision Maker, if other than the Architect.)

ARTICLE 7 TERMINATION OR SUSPENSION

§ 7.1 The Contract may be terminated by the Owner or the Contractor as provided in Article 14 of AIA Document A201– 2017.

§ 7.2 The Work may be suspended by the Owner as provided in Article 14 of AIA Document A201–2017.

ARTICLE 8 MISCELLANEOUS PROVISIONS

§ 8.1 Where reference is made in this Agreement to a provision of AIA Document A201–2017 or another Contract Document, the reference refers to that provision as amended or supplemented by other provisions of the Contract Documents.

§ 8.2 The Owner’s representative:

(Name, address, email address, and other information of DPS Project Manager)

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 18:54:26 MDT on 06/12/2025 under Subscription No.20250093517 which expires on , is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (640e2aedf442e4498d0967f6)

§ 8.3 The Contractor’s representative:

(Name, address, email address, and other information)

§ 8.4 Neither the Owner’s nor the Contractor’s representative shall be changed without ten days’ prior notice to the other party.

§ 8.5 Insurance and Bonds § 8.5.1 The Contractor shall purchase and maintain insurance as set forth in AIA Document 201-2017, the General Conditions.

§ 8.5.2 The Contractor shall provide bonds as set forth in AIA Document A201–2017, the General Conditions.

§ 8.6 Notice in electronic format, pursuant to Article 1 of AIA Document A201–2017, may be given in accordance with AIA Document E203™–2013, Building Information Modeling and Digital Data Exhibit, if completed, or as otherwise set forth below:

(If other than in accordance with AIA Document E203–2013, insert requirements for delivering notice in electronic format such as name, title, and email address of the recipient and whether and how the system will be required to generate a read receipt for the transmission.)

§ 8.7 Certified MWBE’s The Owner is a public school district that operates according to equal opportunity contracting policies and laws. Owner intends and expects that its contracting processes, including those relating to professional designers and consultants such as consultants and any subconsultants, shall provide equal opportunity without regard to gender, race, ethnicity, religion, age, or disability, and that Owner’s vendors shall make available equal opportunities to the extent third parties are engaged to provide goods and services to Owner as subcontractors, consultants, vendors, or otherwise. Accordingly, Contractor and any subconsultants shall not discriminate on any of the foregoing grounds in the performance of this Agreement and shall make available equal opportunities to the extent third parties are engaged to provide services in connection with performance of the Agreement. Joint ventures, partnerships, or other cooperative relationships between contractors or vendors and Minority Business Enterprises, Women Business Enterprises, and Diverse Business Enterprises may be considered one indication of good faith intention to comply with this requirement. Contractor shall disseminate information regarding all opportunities to subcontracting parties under this Agreement in a manner reasonably calculated to reach all qualified potential sub-contractors and -consultants who may be interested and shall maintain records demonstrating such activities. Contractor shall report to the Project Manager all Subconsultants proposed to be retained under this Agreement along with their classifications in the minority contracting community (Hispanic, Black, Asian, American Indian or Women) and the amount of fee or payment anticipated for each.

Owner may require such report before executing this Agreement. Contractor has committed that Certified Minority, Women Business Enterprises (“MWBEs”) will perform [insert percentage]% of the Project’s base bid or the Guaranteed Maximum Price as calculated by the percentage of the Project’s total payments that are made to Certified MWBEs.

§ 8.7.1 The Contractor and the Contractor’s Subcontractors shall not discriminate against any employee or applicant for employment because of race, color, gender, sexual orientation, gender identity, transgender status, religion, national origin, immigration/citizenship status, ancestry, age, marital status, pregnancy status, veteran status, disability, or any class otherwise protected by Owner policy or law. The Contractor agrees to post in conspicuous places, available to employees and applicants, notices setting forth the Contractor’s nondiscrimination policies.

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 18:54:26 MDT on 06/12/2025 under Subscription No.20250093517 which expires on , is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (640e2aedf442e4498d0967f6)

§ 8.7.2 The Contractor and the Contractor’s Subcontractors shall, in all solicitations or advertisements for employees placed by them or on their behalf, state that all qualified applicants will receive consideration for employment without regard to race, religion, age, disability, sex, national origin, or any class otherwise protected by Owner policy or law.

§ 8.8 Federal Funding § 8.8.1 ESSER Funded Projects. If this box is checked , Owner is paying for this Project using funds from the Elementary and Secondary School Emergency Relief (ESSER) Fund. Contractor must comply with federal requirements including applicable Uniform Guidance Requirements, Davis-Bacon prevailing wage requirements, and all of the U.S. Department of Education’s applicable regulations regarding construction at 34 CFR §§ 76.600 and 75.600-75.618, as well as OMB Standard Forms 24B and D (Assurances for Non-Construction and Construction Programs).

§ 8.8.2 Davis-Bacon Act. If this box is checked , Contractor must comply with the Davis-Bacon Act (40 U.S.C. 3141-3144, and 3146-3148) as supplemented by Department of Labor regulations (29 CFR Part 5, “Labor Standards Provisions Applicable to Contracts Covering Federally Financed and Assisted Construction”), and all other laws applicable to federally-assisted construction projects. In accordance with the statute, Contractor must pay wages to laborers and mechanics at a rate not less than the prevailing wages specified in a wage determination made by the Secretary of Labor. In addition, Contractor must pay wages not less than once a week. The current prevailing wage determination issued by the Department of Labor that applies to this Project is attached to this Agreement and incorporated herein as Exhibit A. Contractor must comply with the Copeland “Anti-Kickback” Act (40 U.S.C. 3145), as supplemented by Department of Labor regulations (29 CFR Part 3, “Contractors and Subcontractors on Public Building or Public Work Financed in Whole or in Part by Loans or Grants from the United States”).

The Act provides that each contractor must be prohibited from inducing, by any means, any person employed in the construction, completion, or repair of public work, to give up any part of the compensation to which he or she is otherwise entitled. The non-Federal entity must report all suspected or reported violations to the Federal awarding agency.

§ 8.9 Other provisions:

§ 8.9.1 The Agreement shall be governed by the laws of the State of Colorado, and any litigation shall be conducted in state district court. Mandatory and exclusive venue shall be in the City and County of Denver, Colorado.

§ 8.9.2 The Contractor cannot be related to any employee of the Owner if such a relationship would create a material financial interest or result in the violation of DPS Board Policy GBEA by either Contractor or the employee of the Owner. The Contractor agrees to abide by the Code of Conduct and Conflict of Interest Certification attached to this Agreement and incorporated herein as Exhibit B.

§ 8.9.3 The Contractor may not assign its responsibilities, duties, obligations and rights under this Agreement, without the express written consent of the Owner. This does not prevent Contractor from engaging subcontractors to perform various phases of the Project, but Contractor shall be fully responsible to Owner for the work, actions and omissions of all such subcontractors.

§ 8.9.4 This Agreement, in its entirety, shall be binding upon all the parties hereto, their respective successors, heirs, executors, administrators or assigns.

§ 8.9.5 Execution of this Agreement shall constitute approval and acceptance of all terms, covenants and conditions as modified and contained in the Contract Documents.

§ 8.9.6 This Agreement is subject to all applicable federal, state, and local laws, regulations, rules and other workplace requirements and standards applicable to the provision of the Services including, without limitation, all laws, regulations and rules cited in § 22-1-135, C.R.S.; all laws, regulations and rules governing wages and overtime, civil rights/employment discrimination, equal employment, safety and health, verifiable security background checks, employees’ citizenship, withholdings, pensions, reports, record keeping, and campaign contributions and political finance. Invalidity of any portion of this Agreement under the laws of the State of Colorado or of the United States shall not affect the validity of the remainder of this Agreement.

§ 8.9.7 Unless otherwise noted, terms in this Agreement shall have the same meaning as those in the edition of AIA Document A201-2007, General Conditions of the Contract for Construction, as amended for the Project.

§ 8.9.8 Contractor stipulates that Owner is a political subdivision of the State of the Colorado, and, as such, enjoys immunities from suit and liability as provided by the constitution and laws of the State of Colorado. By entering into this Agreement, Owner does not waive any of its immunities from suit and/or liability, except as otherwise specifically provided herein, and as specifically authorized by law.

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 18:54:26 MDT on 06/12/2025 under Subscription No.20250093517 which expires on , is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (640e2aedf442e4498d0967f6)

§ 8.9.9 This Agreement may be executed simultaneously in two (2) counterparts, each of which shall be deemed to be an original, but which together shall constitute one and the same agreement.

§ 8.9.10 Each party consents to the use of electronic signatures by the other party.. This Agreement, and any other documents requiring a signature under this Agreement, may be signed electronically by each party. The parties agree not to deny the legal effect or enforceability of this Agreement solely because it is in electronic form or because an electronic record was used in its formation. The parties agree not to object to the admissibility of this Agreement in the form of an electronic record, or a paper copy of an electronic document, or a paper copy of a document bearing an electronic signature, on the ground that it is an electronic record or electronic signature or that it is not in its original form or is not an original.

§ 8.9.11 The parties each represent and warrant to each other that the persons signing this Agreement are authorized signatories for the entities represented. The Owner’s signature authority for this Agreement is governed by the Owner’s Board of Education Regulation DJA-R.

ARTICLE 9 ENUMERATION OF CONTRACT DOCUMENTS

§ 9.1 This Agreement is comprised of the following documents:

.1 AIA Document A101™–2017, Standard Form of Agreement Between Owner and Contractor .2 Wage Determination, Exhibit A .3 Code of Conduct and Conflict of Interest Certification, Exhibit B .4 AIA Document A201™–2017, General Conditions of the Contract for Construction

.5 Drawings

Number Title Date

.6 Specifications

Section Title Date Pages

.7 Addenda, if any:

Number Date Pages

Portions of Addenda relating to bidding or proposal requirements are not part of the Contract Documents unless the bidding or proposal requirements are also enumerated in this Article 9.

.8 Other Exhibits:

(Check all boxes that apply and include appropriate information identifying the exhibit where required.)

[ X ] AIA Document E204™–2017, Sustainable Projects Exhibit, dated as indicated below:

(Insert the date of the E204-2017 incorporated into this Agreement.)

[ X ] The Sustainability Plan:

The Owner’s goal is to incorporate Sustainable Measures into the design, construction, maintenance and operations of the Project to achieve a benefit to the environment, enhance the health and well-being of building occupants, and work towards the Owner’s goal of reaching an energy use intensity (EUI) of 48 for all buildings. This goal includes, but is not limited to:

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 18:54:26 MDT on 06/12/2025 under Subscription No.20250093517 which expires on , is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (640e2aedf442e4498d0967f6)

- Utilizing electrification options to replace natural gas

- Implementing energy modeling of existing and proposed design to evaluate cost and EUI differences

- Reusing/retrofitting existing materials/equipment when possible rather than full replacement

- End of life considerations for material and equipment

The Architect shall work with the Owner, the Owner’s consultants, and Architect’s consultants to discuss potential Sustainable Measures; examine strategies for implementation of the Sustainable Measures; and discuss the potential impact of the Sustainable Measures on the Project schedule, the Owner’s program, the Owner’s budget for the Cost of the Work, and the Owner’s Climate Action Policy and subsequent Plan.

[ ] Supplementary and other Conditions of the Contract:

Document Title Date Pages

.9 Other documents, if any, listed below:

(List here any additional documents that are intended to form part of the Contract Documents. AIA Document A201™–2017 provides that the advertisement or invitation to bid, Instructions to Bidders, sample forms, the Contractor’s bid or proposal, portions of Addenda relating to bidding or proposal requirements, and other information furnished by the Owner in anticipation of receiving bids or proposals, are not part of the Contract Documents unless enumerated in this Agreement. Any such documents should be listed here only if intended to be part of the Contract Documents.)

RFP/CONTRACTOR’S PROPOSAL

This Agreement will be effective when all parties have signed it. The date of this Agreement will be the date this Agreement is signed by the last party to sign it (as indicated by the date associated with that party’s signature).

CONTRACTOR

[COMPANY NAME]

By: Date:

Print Name:

Title:

AIA TEMPLATE APPROVED BY OFFICE OF

GENERAL COUNSEL: April 2024

“SCHOOL DISTRICT NO. 1”

APPROVED:

By:

AIA Document A101 – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017. All rights reserved. “The American Institute of Architects,” “American Institute of Architects,” “AIA,” the AIA Logo, and “AIA Contract Documents” are trademarks of The American Institute of Architects. This draft was produced at 18:54:26 MDT on 06/12/2025 under Subscription No.20250093517 which expires on , is not for resale, is licensed for one-time use only, and may only be used in accordance with the AIA Contract Documents® Terms of Service. To report copyright violations, e-mail docinfo@aiacontracts.com.

User Notes: (640e2aedf442e4498d0967f6)

Senior Project Manager, Planning, Design & Construction

By:

Heather Bock Director, Construction

By:

Troy Garner Executive Director, Planning, Design & Construction

By:

Trena Marsal Chief Operations Officer

By:

Dr. Carrie Olson Board of Education, President