The document is a set of electrical engineering drawings for the Weld County Jail UPS Replacement project located at 2110 O Street in Greeley, Colorado. The drawings, prepared by G2 Consulting Engineers, detail a comprehensive electrical system upgrade focusing on replacing the existing Uninterruptible Power Supply (UPS) system. The project encompasses electrical single-line diagrams, demolition work, panel schedules, and overall power plans for the first, second, and third levels of the facility. The drawings specify the installation of a new 40kW (40kVA) 480:208V UPS with integral bypass from Schneider Electric, including routing of new feeders, removal of existing transformers and equipment, and integration with the facility's existing electrical infrastructure.
The project involves precise electrical system modifications, including installing a new UPS transformer (SUP1E), routing new feeders to various existing branch circuit panels (EYL1A, EYL3A, EYL3B), and removing obsolete equipment. The work requires careful coordination with the facility's existing electrical systems, including emergency and standard power distribution panels. The drawings indicate multiple levels of electrical infrastructure, with specific attention to maintaining continuity of power in a critical infrastructure setting like a county jail. Work notes emphasize the need for minimal disruption, with instructions to coordinate shutdowns with the owner's representative and ensure proper installation and testing of new electrical equipment.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BID SPECS - JAIL 2 WEST - UPS UPGRADE - 46.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SHEET
NUMBER SHEET TITLE
ELECTRICAL DRAWING INDEX
IS
SU
E
FO
R
PE
RM
IT
/12
/20
TOTAL: 9
E0.00 ELECTRICAL INDEX, LEGENDS, AND NOTES
ISSUED FOR REFERENCE ONLY
ISSUED FOR CONSTRUCTION
ELECTRICAL SYMBOLS LIST
(NOT ALL SYMBOLS MAY APPEAR IN THESE DRAWINGS)
RECESSED MOUNTED LINEAR
SURFACE MOUNTED LINEAR
FLANGED MOUNTED LINEAR
SUSPENDED MOUNTED LINEAR
LINEAR STRIP
WALL MOUNTED LINEAR
WALL BRACKET
OPEN DOWNLIGHT, SURFACE OR RECESSED
RECESSED ADJUSTABLE DOWNLIGHT
TRACK AND TRACK HEAD
DECORATIVE FIXTUREJ
LIGHTING CONTROL STATIONLCS
EXIT SIGN, SINGLE FACE, CHEVRONS AS
EXIT SIGN, DUAL FACE, CHEVRONS AS
SHADING INDICATES WIRING DEVICES ON
EMERGENCY POWER SOURCE
INDICATED
INDICATED
SWITCH, SINGLE POLES
a
SWITCH, THREE POLES
3a
DIMMER SWITCH, SINGLE POLED
a
DIMMER SWITCH, THREE POLES
3a
OCCUPANCY SWITCH, SINGLE POLE,O
a
DUAL-TECHNOLOGY, UON
CEILING MOUNTED OCCUPANCY SWITCH,JOC
SINGLE POLE, DUAL-TECHNOLOGY, UON
CONTROL STATION
JUNCTION BOXJJ
DUPLEX RECEPTACLE
DOUBLE DUPLEX RECEPTACLE
DUPLEX RECEPTACLE, GFCI
DUPLEX RECEPTACLE, HALF-SWITCHED
SPECIALTY RECEPTACLE (NEMA/IEC)
ILLUMINATED SIGNAGESIGN
S
COMBINATION DISCONNECT/MOTOR
STARTER, 30 AMP, SIZE '1' UON
DISCONNECT SWITCH, NON-FUSED,
HEAVY-DUTY, 30 AMP, UON
DISCONNECT SWITCH, FUSED,
HEAVY DUTY, 30 AMP, UON
N
F
LA-1,3,5
HOMERUN: (6) #12 AWG + (1) #12 AWG GRD,
CU, TO PANEL 'LA' CIRCUITS 1, 3, 5 - 3/4''C
MECHANICAL/PLUMBING EQUIPMENT
DESIGNATION
FCU
PANELBOARD, FLUSH MOUNT
PANELBOARD, SURFACE MOUNT
DISTRIBUTION TRANSFORMERT
SWITCH, MANUAL MOTOR STARTERS
M
TYPICALTYP
UNLESS OTHERWISE NOTEDUON
WEATHER-PROOFWP
EXISTING TO REMAIN(E)
RELOCATED(R)
EXISTING TO BE REMOVED(X)
HORSEPOWERHP
VARIABLE FREQUENCY DRIVEVFD
COUNTERCTR
GROUNDGRD
TWIN-HEAD EMERGENCY LIGHT
NIGHT LIGHT (UNSWITCHED)NL
FUSE PER EQUIPMENT NAMEPLATEFPEN
POLE MOUNTED LIGHT
EXISTING TO BE RELOCATED(E/R)
RECESSED CLOCK RECEPTACLE
CONTACTOR
PHOTOCELLPC
FURNISHED BY OTHERSFBO
FLUSH FLOOR DUPLEX RECEPTACLE
CIRCUITING IN WALL OR ABOVE CEILING
CIRCUITING IN FLOOR OR BELOW GRADE
OVERHEADO/H
DUPLEX RECEPTACLE - CEILING MOUNTED
CIRCUITING WITH ISOLATED GROUND
CONDUCTOR
EXIT SIGN, SINGLE FACE, CHEVRONS AS
INDICATED, INTEGRAL EMERGENCY LIGHT
DUPLEX RECEPTACLE, ISOLATED GROUND
CEILING MOUNTED DAYLIGHTJDS
SENSOR, 0-10V UON
UNDERCOUNTERU/C
# POWER/TELECOM RISER
EXIT SIGN, LOW-LEVEL
BOLLARD LIGHT FIXTURE
IN-GRADE DOWNLIGHT
FIRE-SMOKE DAMPERFSD
TELECOM SYMBOLS LIST
(NOT ALL SYMBOLS MAY APPEAR IN THESE DRAWINGS)
C
JS
V
WAP
TELECOM OUTLET: PROVIDE FLUSH MOUNT
4S JUNCTION BOX WITH 2-GANG OPENING AND
MUD-RING. ROUTE (1) 3/4" CONDUIT TO
ACCESSIBLE ABOVE CEILING SPACE COMPLETE
WITH PULLSTRING. FUTURE CABLING BY OTHERS.
CEILING MOUNT SPEAKER
WALL MOUNT SPEAKER
D2
V2
D1/V1
TELECOM OUTLET COMPLETE WITH CABLING/,
JACKS, CONVENTIONS AS FOLLOWS:
D = DATA
V = VOICE
# = QUANTITY OF CABLES/RJ45 JACKS, EACH
JS
WIRELESS ACCESS POINT
CCTV SYSTEM CAMERA
VOLUME CONTROL STATION
FLUSH FLOOR TELECOM OUTLET
TV A/V SYSTEM SCREEN OUTLET
P = POINT-OF-SALE
TELECOM RACK, 2-POST, 45U, UON
TELECOM RACK, 4-POST, 45U, UON
PLYWOOD MOUNTING BACKBOARD,
3/4" THICK, 8'-0" TALL, WIDTH AS
DRAWN, WHITE FIRE RETARDANT
PAINT FINISH, #6 CU GROUND WIRE
TELECOM CABINET, FLUSH MOUNT
TELECOM CABINET, SURFACE MOUNT EQUIPMENT ROOMER
TELECOM ROOMTR
MICROPHONE INPUT JACKM
AVI A/V SYSTEM INTERFACE TOUCHPAD,
+48'' AFF UON
CARD READER, +48" AFF UONCR
CLOCK OUTLET
JP WALL MOUNT PUBLIC ADDRESS
SYSTEM SPEAKER
INTERCOMM
WALL MOUNT BELL
IC
E0.02 ELECTRICAL SPECIFICATIONS
E0.20 DEMOLITION WORK ELECTRICAL SINGLE-LINE
E0.30 PANEL SCHEDULES
E1.00 FIRST LEVEL OVERALL POWER PLAN
E1.01 SECOND LEVEL OVERALL POWER PLAN
E1.02 THIRD LEVEL OVERALL POWER PLAN
E2.00 ENLARGED POWER PLANS
E0.21 NEW WORK ELECTRICAL SINGLE LINE
DRAWN
PROJECT #
DATE
FIRM NAME
2024067.00
11/12/2024
SCALE
AS NOTED
CHECKED
REVISION/ISSUENO. DATE
5000 GOODMAN STREET
UNIT 100
TIMNATH CO 80547
(970) 460-7400
G2CE.COM
SEAL
CONSULTANT FIRM NAME
W
EL
D
CO
UN
TY
JA
IL
UP
S
RE
PL
AC
EM
EN
T
O S
TR
EE
T
GR
EE
LE
Y, C
O
PROJECT DESCRIPTION
SHEET DESCRIPTION
SHEET NUMBER
G2 G2
E0.00
ELECTRICAL INDEX,
LEGENDS, AND
NOTES
11/12/2024
ELECTRICAL SPECIFICATIONS
PART 1 - GENERAL
A. GENERAL
1. GENERAL CONDITIONS, SPECIAL REQUIREMENTS, OR GENERAL REQUIREMENTS OF THE PROJECT SPECIFICATIONS MANUAL (WHERE PROVIDED) ARE MADE PART OF THIS SPECIFICATION AND HAVE THE SAME FORCE AND EFFECT AS IF COMPLETELY
REPRODUCED.
2. DEFINITIONS: THE WORD "WORK" SHALL MEAN LABOR AND ANY INCIDENTAL ITEMS OR SERVICES NECESSARY FOR THE PROPER INSTALLATION AND OPERATION OF THE COMPLETE SYSTEMS NOTED ON THESE DRAWINGS AND ASSOCIATED SPECIFICATIONS. THE WORD "PROVIDE" SHALL MEAN FURNISH, INSTALL, FEED, MAKE FINAL CONNECTIONS, COMMISSION AND LEAVE IN AN APPROVED
COMPLETE OPERATING CONDITION.
3. WORK SHALL BE PROVIDED IN ACCORDANCE WITH THE LATEST ADOPTED EDITIONS OF THE APPLICABLE NATIONAL ELECTRICAL CODE (NEC), INTERNATIONAL BUILDING CODE (IBC), INTERNATIONAL ENERGY CONSERVATION CODE (IECC), NFPA 110, AND ALL
OTHER APPLICABLE FEDERAL, STATE, AND LOCAL REGULATIONS INCLUDING AMENDMENTS.
4. OBTAIN AND PAY FOR ALL PERMITS, FEES AND INSPECTIONS REQUIRED FOR THIS WORK.
5. THE CONTRACTOR SHALL BE RESPONSIBLE FOR THE PROPER FITTING OF MATERIAL INTO THE BUILDING AS INDICATED ON THE
DRAWINGS, WITHOUT INTERFERENCE WITH OTHER WORK, AND SHALL MAKE REASONABLE MODIFICATIONS IN THE LAYOUTS NEEDED TO PREVENT CONFLICT WITH OTHER TRADES, TO PROVIDE ACCESS AND FOR THE PROPER EXECUTION OF THE WORK.
6. THE WORK SHALL BE COORDINATED WITH THE WORK OF OTHER TRADES INCLUDING CONTRACT DOCUMENTS, SHOP DRAWINGS, AND EXISTING SYSTEMS (WHERE APPLICABLE).
7. DO NOT SCALE DRAWINGS AS THEY ARE DIAGRAMMATIC AND SCHEMATIC IN NATURE. CONTRACTOR SHALL PROVIDE NECESSARY ITEMS TO COMPLETE THE WORK ACCORDING TO INDUSTRY STANDARDS. IT IS THE INTENT OF THE DRAWINGS AND SPECIFICATIONS TO CALL OUT FOR FINISHED WORK, TESTED AND READY FOR OPERATION. ARRANGEMENT OF EQUIPMENT AND ROUTING OF RACEWAYS INDICATED ON DRAWINGS SHALL BE ROUTED PLUMB AND AT RIGHT ANGLES TO BUILDING STRUCTURE. INSTALLATION
OF SYSTEMS MAY REQUIRE MODIFICATION DUE TO UNFORESEEN CONDITIONS.
8. VERIFY ALL SIZES DIMENSIONS, AND CONDITIONS BEFORE STARTING ANY WORK. ANY DEVIATIONS OR ISSUES SHALL BE
TRANSMITTED TO THE ARCHITECT FOR REVIEW.
9. CONTRACTOR SHALL SUBMIT A BID BASED ON MANUFACTURER NAMES LISTED UNLESS "OR EQUAL" IS INDICATED. SUBSTITUTION REQUESTS WILL BE REVIEWED BY THE ENGINEER PROVIDED THEY ARE SUBMITTED A MINIMUM OF SEVEN (7) BUSINESS DAYS PRIOR TO THE BID DATE. CLOSING ACCEPTABILITY OF SUBSTITUTION WILL BE SOLELY DETERMINED BY THE OWNER.
10. IT IS THE INTENT OF THESE DRAWINGS AND SPECIFICATIONS TO ESTABLISH A STANDARD OF QUALITY.
11. EXAMINATION OF BIDDING DOCUMENTS:
11.1. EACH BIDDER SHALL EXAMINE THE BIDDING DOCUMENTS CAREFULLY AND, NOT LATER THAN SEVEN (7) DAYS PRIOR TO THE DATE OF RECEIPT AND SHALL MAKE WRITTEN REQUEST TO THE ARCHITECT FOR INTERPRETATION OR CORRECTION OF ANY DISCREPANCIES, AMBIGUITY, INCONSISTENCY OR ERROR THEREIN WHICH HE MAY DISCOVER. ANY INTERPRETATION OR CORRECTION WILL BE ISSUED AS AN ADDENDUM BY THE ARCHITECT. ONLY A WRITTEN INTERPRETATION OR CORRECTION BY ADDENDUM SHALL BE BINDING, NO BIDDER SHALL RELY UPON INTERPRETATIONS OR CORRECTIONS GIVEN BY ANOTHER METHOD. IF DISCREPANCIES, AMBIGUITY, INCONSISTENCY OR ERROR ARE NOT COVERED BY ADDENDUM OR WRITTEN DIRECTIVE, CONTRACTOR SHALL INCLUDE IN HIS BID, LABOR, MATERIALS AND METHODS OF CONSTRUCTION RESULTING IN HIGHER COST. AFTER AWARD OF CONTRACT, NO ALLOWANCE OR EXTRA COMPENSATION WILL BE MADE IN BEHALF OF THE CONTRACTOR DUE TO HIS FAILURE TO MAKE THE WRITTEN REQUESTS
AS DESCRIBED ABOVE.
11.2. THE COMPANY/CONTRACTOR SUBMITTING THE REQUEST WILL BE RESPONSIBLE FOR ITS PROMPT DELIVERY. FAILURE TO SO REQUEST CLARIFICATION OF ANY INADEQUACY, OMISSION, OR CONFLICT WILL NOT RELIEVE THE CONTRACTOR OF ANY RESPONSIBILITY. THE SIGNING OF THE CONTRACT WILL BE AS CONSIDERED AS IMPLICITLY DENOTING THAT THE CONTRACTOR HAS A THOROUGH COMPREHENSION OF THE FULL INTENT AND SCOPE OF THE WORKING DRAWINGS AND
SPECIFICATIONS.
12. WORK SHALL BE PERFORMED IN A WORKMANLIKE MANNER TO THE SATISFACTION OF THE ARCHITECT.
13. GUARANTEE THE INSTALLATION AGAINST DEFECTS IN MATERIALS AND WORKMANSHIP WHICH MAY OCCUR UNDER NORMAL USAGE
FOR A PERIOD OF ONE YEAR AFTER OWNERS ACCEPTANCE. DEFECTS SHALL BE PROMPTLY REMEDIED WITHOUT COST TO THE
OWNER.
14. SYSTEMS SHALL BE TESTED FOR PROPER OPERATION. IF TEST SHOW THAT WORK IS DEFECTIVE, CONTRACTOR SHALL MAKE
CORRECTIONS NECESSARY AT NO COST TO THE OWNER.
15. CONTRACTOR SHALL BE RESPONSIBLE FOR REPLACING EQUIPMENT WHICH IS DAMAGED DUE TO INCORRECT FIELD WIRING PROVIDED UNDER THIS SECTION OR FACTORY WIRING IN EQUIPMENT PROVIDED UNDER THIS SECTION.
16. SYSTEMS SHALL BE PROVIDED COMPLETE, OPERABLE AND READY FOR CONTINUOUS OPERATIONS. LIGHTS, SWITCHES, RECEPTACLES, MOTORS, ETC. SHALL BE CONNECTED AND OPERABLE.
17. ALL ELECTRICAL SYSTEMS COMPONENTS SHALL BE LISTED OR LABELED BY U.L. OR OTHER NATIONALLY RECOGNIZED TESTING
LABORATORIES (NRTL).
18. IN INSTANCES WHERE THE PROJECT DOES NOT INCLUDE AN ARCHITECT, THE ENGINEER SHALL RECEIVE ALL CORRESPONDENCE
AS DIRECTED HEREIN.
B. EXISTING CONDITIONS
1. THIS PROJECT INVOLVES CONSTRUCTION INSIDE AN EXISTING STRUCTURE. CONTRACTORS, BY SUBMITTING A BID ARE DEEMED TO BE COMPLETELY FAMILIAR WITH THE EXISTING CONDITIONS OF THE BUILDING AS IT INFLUENCES THE WORK DESCRIBED. NO CLAIMS FOR EXTRA COMPENSATION WILL BE CONSIDERED FOR EXISTING CONDITIONS VISIBLE OR REASONABLY INFERABLE FROM
A CAREFUL EXAMINATION OF THE EXISTING BUILDING CONDITIONS.
2. CONTRACTOR SHALL INSPECT THE EXISTING FIELD CONDITIONS AT THE SITE AND THE CONTRACT DOCUMENTS PRIOR TO THE START OF ANY WORK TO DETERMINE WHAT EFFECT THE EXISTING CONDITIONS WILL HAVE ON THE WORK. CONTRACTOR SHALL REPORT DISCREPANCIES TO THE ARCHITECT AND INCLUDE IN HIS BID ALL COSTS REQUIRED TO MAKE HIS WORK MEET EXISTING
CONDITIONS.
3. CONTRACTOR SHALL CONNECT THEIR WORK TO VARIOUS EXISTING ELECTRICAL SYSTEMS. THE NEW WORK SHALL BE COMPATIBLE
WITH THE EXISTING SYSTEM CONDITIONS.
4. CARE SHALL BE TAKEN DURING INSTALLATION OF THE NEW WORK, AS NOT TO DAMAGE OR INTERRUPT THE EXISTING BUILDING SYSTEMS AND SERVICES INSTALLED. DAMAGE TO EXISTING SYSTEMS AND EQUIPMENT CAUSED BY CONTRACTOR DURING THE INSTALLATION OF THEIR WORK SHALL BE REPAIRED AND/OR REPLACED AT THE CONTRACTORS EXPENSE TO THE SATISFACTION OF
THE BUILDING OWNER.
5. SHUTDOWN OF EXISTING SYSTEMS FOR CONNECTION TO EXISTING SERVICES SHALL BE COORDINATED WITH THE OWNER.
CONTRACTOR SHALL SUBMIT REQUESTS WHERE THEY AFFECT THE OPERATION OF THE BUILDING SYSTEMS AT LEAST ONE (1) WEEK IN ADVANCE OF ANY REQUIRED SHUTDOWN. THE ACTUAL SHUTDOWN PERIOD SHALL BE AS SHORT AS POSSIBLE AND AT A
TIME AGREED TO BY THE OWNER.
6. DEMOLITION SHALL BE COORDINATED WITH OWNER, ARCHITECT, AND GENERAL CONTRACTOR.
7. CONTRACTOR SHALL REPORT ANY EQUIPMENT DISCREPANCIES FOUND TO THE ARCHITECT WITHIN FIVE (5) DAYS OF DISCOVERY.
8. CONTRACTOR SHALL REPORT DISCREPANCIES TO THE ARCHITECT AND INCLUDE IN HIS BID ALL COSTS REQUIRED TO MAKE HIS
WORK MEET THE EXISTING CONDITIONS.
9. PROVIDE ELECTRICAL DEMOLITION REQUIRED. REFER TO ARCHITECTURAL DEMOLITION DRAWINGS FOR LOCATION AND EXTENT OF
DEMOLITION REQUIRED. CONTRACTOR SHALL VISIT SITE PRIOR TO BID TO DETERMINE THE EXTENT OF WORK INVOLVED. PROVIDE LABOR AND MATERIALS AS REQUIRED TO MAINTAIN AND/OR RESTORE CONTINUITY OF SERVICE TO EXISTING CIRCUITS.
10. CONTRACTOR SHALL BE RESPONSIBLE TO FIELD VERIFY EXISTING EQUIPMENT OR CIRCUITS THAT ARE REMAINING TO BE RECONNECTED TO NEW OR EXISTING SWITCHGEAR. PROVIDE SWITCHES RECEPTACLES, CONDUIT, WIRE, ETC., AS REQUIRED TO
RESTORE CONTINUITY OF CIRCUIT(S).
11. CONTRACTOR SHALL PROVIDE NECESSARY DEMOLITION TO REMOVE EXISTING UNUSED CONDUIT, WIRE, CABLE, JUNCTION BOXES, RECEPTACLES, SWITCHES, LIGHTS, FIRE ALARM DEVICES, ETC. COMPLETE WITH ASSOCIATED CIRCUIT TO SOURCE.
12. EXISTING LIGHT FIXTURES, SWITCHGEAR, ELECTRICAL EQUIPMENT, ETC. BEING REMOVED SHALL BE RETURNED TO THE OWNER, EXCEPT FOR THOSE BEING RELOCATED.
C. SUBMITTALS
1. CONTRACTOR SHALL SUBMIT SHOP DRAWINGS AND TECHNICAL DATA SHEETS FOR EQUIPMENT AND MATERIALS SPECIFIED. THE ENGINEER SHALL REVIEW SHOP DRAWINGS AND TECHNICAL DATA SHEETS FOR CONFORMANCE WITH THE CONTRACT DOCUMENTS
AND ISSUE A WRITTEN ASSESSMENT TO THE OWNER PRIOR TO COMMENCEMENT OF WORK.
2. CONTRACTOR SHALL IDENTIFY ANY DEVIATIONS IN THE SHOP DRAWINGS FROM THE DESIGN DOCUMENTS.
3. SUBSTITUTIONS SHALL BE SUBMITTED TO THE ARCHITECT FOR CONSIDERATION PRIOR TO BIDDING. SUBSTITUTIONS SHALL BE
PRE-APPROVED IN WRITING. THE CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING REQUIREMENTS ASSOCIATED WITH SUBSTITUTED EQUIPMENT OR MATERIALS WITH OTHER BUILDING TRADES. CONTRACTOR SHALL IDENTIFY AND ANNOTATE REVISED REQUIREMENTS PER BUILDING TRADE ON THE SHOP DRAWINGS. CONTRACTOR SHALL ALSO IDENTIFY COST DEBITS OR CREDITS IN
WRITING FOR THE PROPOSED CHANGES PER BUILDING TRADE.
4. CONTRACTOR SHALL BE RESPONSIBLE FOR ENGINEERING FEES NECESSARY TO CHANGE PERMIT DOCUMENTS BASED ON
ALTERNATE SUBMITTAL PACKAGES/EQUIPMENT SUBSTITUTIONS.
5. PRESENT SHOP DRAWING SUBMITTAL DATA AT ONE TIME, IN ELECTRONIC PORTABLE DOCUMENT FORMAT (.PDF) IN A NEAT AND ORDERLY MANNER. PARTIAL SUBMITTALS WILL NOT BE ACCEPTED. SUBMITTALS SHALL INCLUDE BUT NOT BE LIMITED TO LIGHTING FIXTURES, SWITCHGEAR, PANELBOARDS, WIRING DEVICES, SAFETY SWITCHES, FUSES, MOTOR CONTROLLERS, LAMPS, CONDUIT, FITTINGS, TRANSFORMERS AND LIGHTING CONTROLS.
6. CONTRACTORS FAILURE TO ORDER OR RELEASE ORDER FOR MATERIALS AND/OR EQUIPMENT WILL NOT BE ACCEPTED AS A
REASON TO SUBSTITUTE ALTERNATE MATERIALS OR EQUIPMENT.
D. DRAWINGS
1. CONTRACTOR SHALL MAINTAIN, TWO (2) SETS OF WHITE PRINTS OF DRAWINGS PERTAINING TO THE WORK. ONE (1) SET OF PRINTS SHALL BE KEPT ON SITE AND CHANGES OR DEVIATIONS FROM THE CONTRACT DRAWINGS SHALL BE CAREFULLY NOTED AS
CHANGES OR DEVIATIONS ARE MADE.
E. OPERATING AND MAINTENANCE INSTRUCTIONS
1. CONTRACTOR SHALL PROVIDE THREE (3) COPIES OF MANUFACTURER'S OPERATING AND MAINTENANCE INSTRUCTIONS FOR EACH PIECE OF EQUIPMENT AND SYSTEM. COPIES SHALL BE COMPILED IN SETS AND PLACED IN A HARD COVER THREE RING BINDER WITH INDEX PAGE AND INDEX TABS. ALL NAME TAG INFORMATION SUCH AS THE MANUFACTURER'S, TYPE, SIZE, CAPACITY, SERIAL
NUMBER, ETC. SHALL BE INCLUDED AS PART OF THE MANUAL.
2. PROVIDE WRITTEN OPERATING INSTRUCTIONS WITH DIAGRAMS FOR ELECTRICAL EQUIPMENT.
3. OPERATING AND MAINTENANCE MANUALS SHALL BE SUBMITTED TO THE ARCHITECT FOR REVIEW.
PART 2 - PRODUCTS
A. GENERAL
1. PROVIDE EQUIPMENT AS SPECIFIED AND/OR SCHEDULED AND IN ACCORDANCE WITH MANUFACTURER'S PUBLISHED INSTALLATION INSTRUCTIONS. EQUIPMENT SHALL OPERATE ACCORDING TO THE MANUFACTURER'S "OWNERS OPERATING AND MAINTENANCE
MANUAL" TROUBLE-FREE.
B. WIRE AND CABLE
1. WIRE SHALL BE COPPER, 75°C RATED FOR GENERAL USE. FOR HID FIXTURES AND WIRING WITHIN 3 INCHES OF FLUORESCENT BALLASTS WIRE SHALL BE COPPER MINIMUM 90°C RATED. SIZES INDICATED ARE FOR INSTALLATION IN A MAXIMUM 30°C AMBIENT.
CONDUCTOR AMPACITY SHALL DERATED FOR HIGHER AMBIENT INSTALLATIONS.
C. RACEWAYS AND FITTINGS
1. ALL WIRING SHALL BE INSTALLED IN LISTED METALLIC RACEWAYS. RACEWAYS IN SLAB-ON-GRADE OR BELOW GRADE SHALL BE SCHEDULE 40 PVC, WITH PVC WRAPPED (OR EQUIVALENT PROTECTION) RIGID STEEL ELBOWS AT BENDS AND TRANSITIONS FROM BELOW TO ABOVE GRADE. EMT FITTINGS SHALL BE STEEL. CONNECTORS SHALL BE INSULATED THROAT TYPE.
2. RGS OR IMC SHALL BE USED IN ALL AREAS SUBJECT TO WEATHER OR MECHANICAL DAMAGE.
3. ALL CIRCUITING SHALL BE CONCEALED. WHERE CONCEALMENT IS IMPRACTICAL, AND WITH THE SPECIFIC APPROVAL FROM THE
ARCHITECT, SURFACE RACEWAY AND OUTLETS MAY BE INSTALLED, FINISHED TO MATCH ADJACENT SURFACES.
4. METAL-CLAD (TYPE MC) CABLE MAY BE USED IN THE FOLLOWING LIMITED LOCATIONS:
4.1. 6'-0" MAXIMUM LIGHT FIXTURE WHIPS.
4.2. DEAD-END RUNS TO THE LAST WIRING DEVICE ON A CIRCUIT.
4.3. IN AREAS CONSIDERED "TIGHT" WITHIN MILLWORK AND CASEWORK INSTALLATIONS.
5. TYPE ENT RACEWAY IS NOT ALLOWED.
6. NON-METALLIC AND FLEXIBLE METAL CONDUITS SHALL HAVE A CODE SIZED COPPER GROUNDING CONDUCTOR. INCREASE
CONDUIT SIZE AS REQUIRED.
D. DISTRIBUTION EQUIPMENT
1. SWITCHBOARDS, DISTRIBUTION BOARDS, PANELBOARDS, DISCONNECT SWITCHES, MOTOR CONTROL CENTERS, ETC. SHALL BE FURNISHED BY SQUARE D (SCHNEIDER ELECTRIC), GENERAL ELECTRIC, EATON CUTLER HAMMER, OR SIEMENS. FLOOR MOUNTED
EQUIPMENT SHALL INSTALLED ATOP 4" HIGH CONCRETE HOUSEKEEPING PADS.
2. PROVIDE ENGRAVED NAMEPLATES MECHANICALLY FASTENED WITH A MINIMUM OF TWO (2) SCREWS ON ALL SWITCHBOARDS, PANELBOARDS DISCONNECT SWITCHES, MOTOR CONTROL CENTERS, TRANSFORMERS, ETC. INDICATING EQUIPMENT DESIGNATION (OR DESIGNATION OF EQUIPMENT SERVED), VOLTAGE, AND SOURCE. EXAMPLE: "PANEL HPA, SERVED FROM SWITCHBOARD 'MSB', 480/277V, 3PH, 4W".
3. DISCONNECT SWITCHES SHALL BE HEAVY-DUTY TYPE. FUSIBLE SWITCHES SHALL ACCEPT CLASS 'R' FUSES ONLY AND REJECT OTHERS. INSTALL DISCONNECT SWITCH ON TWO (2) 24" LONG UNITSTRUT CHANNELS DRILLED AND BOLTED TO HVAC UNIT FRAME WHERE POSSIBLE (COORDINATE LOCATION WITH HVAC MANUFACTURER TO AVOID WARRANTY INFRACTIONS). SILICONE SEAL ALL
HOLES IN UNIT.
4. CIRCUIT BREAKERS SHALL BE BOLT-ON TYPE AND FUSES SHALL BE BUSSMAN OR APPROVED EQUIVALENT. CIRCUIT BREAKERS SHALL BE FULLY RATED IN EXCESS OF AVAILABLE FAULT CURRENT LEVELS. SERIES RATING OF EQUIPMENT IS PROHIBITED.
5. WIRE TERMINATION PROVISIONS FOR PANELBOARDS, CIRCUIT BREAKERS, SAFETY SWITCHES, AND ALL OTHER ELECTRICAL
APPARATUS SHALL BE LISTED AS SUITABLE FOR 75°C.
6. ALL EQUIPMENT SUCH AS SWITCHBOARDS, DISTRIBUTION BOARDS, DISCONNECT SWITCHES, TRANSFORMERS AND PANELBOARDS SHALL BE BY THE SAME MANUFACTURER. ALL FUSES PROVIDED SHALL BE OF THE SAME MANUFACTURER.
7. PROVIDE HANDLE TIES OR MULTI-POLE CIRCUIT BREAKERS FOR SIMULTANEOUS OPERATION OF ALL MULTI-WIRE BRANCH CIRCUITS.
8. PROVIDE ARC-FLASH LABELING ON ALL DISTRIBUTION EQUIPMENT.
9. ALL DISCONNECT SWITCHES SHALL HAVE COPPER BLADES AND TERMINALS.
E. WIRING DEVICES
1. WIRING DEVICES SHALL BE SPECIFICATION GRADE AND RATED AT 20 AMPERES. THE DEVICE PLATES SHALL BE LEXAN OR NYLON UNLESS OTHERWISE NOTED. THE COLOR OF THE DEVICES AND COVERPLATES SHALL BE AS DIRECTED BY THE ARCHITECT.
2. SMOKE-DETECTORS SHALL BE SELF-CONTAINED WITH AUDIBLE ALARM, UL LISTED AND COMPLY WITH NFPA STANDARD 72.
INTERCONNECT DETECTORS WITHIN A DWELLING UNIT OR GUESTROOM TO SOUND A COMMON ALARM.
3. ALL 120 VOLT 15- AND 20-AMPERE RECEPTACLES LOCATED IN DWELLING UNITS, GUEST ROOMS AND SUITES, AND CHILD CARE
FACILITIES SHALL BE TAMPER-RESISTANT TYPE.
4. LIGHT SWITCHES IN PUBLIC AREAS SHALL BE SPECIFICATION GRADE ROCKER TYPE, UON. LIGHT SWITCHES IN BACK OF HOUSE
AREAS SHALL BE SPECIFICATION GRADE TOGGLE TYPE, UON.
F. BOXES
1. FLUSH FLOOR OUTLETS SHALL BE CAST IRON, QUANTITY OF GANGS AND CONDUIT ENTRIES AS REQUIRED. PROVIDE BRASS COVERPLATE FOR THE OUTLET TYPES INDICATED. PROVIDE CARPET OR TILE FLANGE TO MATCH FLOOR FINISH.
2. BOXES SHALL BE A MINIMUM OF 4" SQUARE WITH REQUIRED EXTENSIONS AND PLASTER OR TILE RINGS.
G. LIGHT FIXTURES
1. RECESSED FIXTURES INSTALLED INDOORS SHALL BE THERMALLY PROTECTED.
2. FIXTURES INDICATED AS BEING EMERGENCY SHALL BE PROVIDED WITH BATTERY POWERED INVERTER UNIT MOUNTED IN, OR
ADJACENT TO, FIXTURE. PROVIDE UNIT WITH FULLY AUTOMATIC TWO-RATE CHARGER, NICKEL CADMIUM BATTERY, AC "ON" PILOT LIGHT, AND TEST SWITCH. DESIGN AND WIRE UNIT TO AUTOMATICALLY TRANSFER TO BATTERY SUPPLY UPON LOSS OF NORMAL AC POWER AND TO OPERATE ONE LAMP AT 1300 LUMENS MINIMUM FOR LINEAR LAMPS, 700 LUMENS FOR COMPACT LAMPS FOR A MINIMUM OF 90-MINUTES. LED LUMEN LEVELS VARY, AND SHALL BE AS SPECIFIED. ALL EMERGENCY LIGHTING UNITS SHALL BE CONNECTED TO AN UNSWITCHED SOURCE. IN LOCATIONS ACCEPTABLE TO THE AUTHORITY HAVING JURISDICTION, EMERGENCY LIGHTING MAY BE CONNECTED TO THE EMERGENCY LEG OF A GENERATOR POWER SYSTEM IN LIEU OF BATTERY POWER.
PART 3 - EXECUTION
A. GENERAL
1. FINAL CONNECTIONS AND ROUGH-IN REQUIREMENTS TO EQUIPMENT SHALL BE PER MANUFACTURER'S APPROVED WIRING DIAGRAMS, DETAILS, AND INSTRUCTIONS. IT SHALL BE THE CONTRACTOR'S RESPONSIBILITY TO PROVIDE MATERIALS AND EQUIPMENT COMPATIBLE WITH EQUIPMENT ACTUALLY SUPPLIED INCLUDING ALL RACEWAYS, BOXES, WIRING, WIRING DEVICES, ETC.
2. CONTRACTOR SHALL PROVIDE CONTROLS, INTERLOCKS, ACCESSORIES, ETC. AS REQUIRED FOR MOTOR CONTROL. EACH STARTER SHALL CONTAIN 120V CONTROL TRANSFORMER, LED PILOT LIGHT, AND PUSHBUTTONS OR SELECTOR SWITCH AS REQUIRED, IN ADDITION TO OTHER ITEMS (AUXILIARY CONTACTS, DOOR SWITCHES, RELAYS, ETC.) REQUIRED. REFER TO CONTROL DRAWINGS AND CONTROL DIAGRAMS FOR ADDITIONAL CONDUIT, WIRE, RELAYS, TRANSFORMERS, CONNECTIONS, ETC. REQUIRED FOR A
COMPLETE AND OPERABLE SYSTEM.
3. EMPTY RACEWAY SYSTEMS SHALL HAVE A #12 PULLWIRE OR EQUAL AND SHALL BE IDENTIFIED AT JUNCTION, PULL AND TERMINATION POINTS, USING PERMANENT METALLIC TAGS. TAG SHALL INDICATE INTENDED USE OF CONDUIT, ORIGINATION AND TERMINATION POINTS OF EACH INDIVIDUAL CONDUIT. STUB CONDUIT OUT 6" INTO AN ACCESSIBLE AREA. CAP OPEN ENDS NOT
TERMINATED IN A JUNCTION BOX.
4. VERIFY EXACT LOCATION OF EQUIPMENT TO BE FURNISHED BY OTHERS PRIOR TO ROUGH-IN.
5. RECEPTACLES WHICH ARE SHOWN WALL MOUNTED ON THE ELECTRICAL DRAWINGS ON WALLS WHICH, ON THE ARCHITECTURAL
DRAWINGS AND ELEVATIONS ARE SHOWN AS GLASS OR PARTITIONS, SHALL BE FLUSH FLOOR DUPLEX RECEPTACLES MOUNTED ADJACENT TO BASE OR WALLS. COORDINATE MOUNTING HEIGHTS AND LOCATIONS OF OUTLETS AND DEVICES WITH
ARCHITECTURAL MILLWORK DRAWINGS AND INTERIOR ELEVATIONS.
6. PROVIDE SEPARATE NEUTRAL CONDUCTOR FOR EACH ARC-FAULT, GROUND FAULT, OR DIMMED CIRCUIT.
7. PROVIDE MAINTENANCE RECEPTACLE WITHIN 25'-0" OF ALL MECHANICAL, MOTORIZED, OR REFRIGERATION EQUIPMENT.
8. WHERE MECHANICAL EQUIPMENT IS INSTALLED ABOVE A GYPSUM BOARD CEILING REQUIRING ACCESS THROUGH AN ACCESS
PANEL, PROVIDE A RECEPTACLE, SWITCH, AND LIGHT IN THE CEILING SPACE AT THE ACCESS LOCATION.
9. RECESSED LIGHT FIXTURES INSTALLED IN GYPSUM BOARD OR PLASTER CEILINGS SHALL HAVE PLASTER FRAMES INSTALLED PRIOR
TO THE CEILING MATERIAL.
10. MULTI-BALLASTED OR DRIVER FLUORESCENT OR LED FIXTURES SHALL BE DUAL-SWITCHED UNLESS NOTED OTHERWISE.
11. LIGHT FIXTURES RECESSED IN T-BAR CEILING SHALL BE SUPPORTED INDEPENDENTLY OF THE CEILING SYSTEM WITH A MINIMUM OF
TWO (2) #12 HANGAR WIRES UP TO STRUCTURE. SECURE HANGAR WIRES TO CORNERS OF FIXTURE. CLIP FIXTURE TO GRID ON TWO (2) SIDES WITH FACTORY-FURNISHED CLIPS. FINAL CONNECTION TO FIXTURE SHALL BE MADE WITH A FLEXIBLE U.L.
APPROVED ASSEMBLY.
12. CONTRACTOR SHALL REFER TO FOOD SERVICE DRAWINGS FOR EXACT LOCATIONS AND ADDITIONAL ELECTRICAL REQUIREMENTS.
PROVIDE JUNCTION BOXES, RECEPTACLES, CONNECTIONS, CONDUITS (TO INCLUDE SODA AND LIQUOR DISPENSING SYSTEMS), WIRE, INTERLOCKS, CONTROLS, ETC. AS REQUIRED BY THE FOOD SERVICE EQUIPMENT SUPPLIER.
13. SEE DIVISION 23 DRAWINGS FOR LOCATION OF MECHANICAL EQUIPMENT. PROVIDE SERVICE TO AND CONNECT EQUIPMENT AS REQUIRED. PROVIDE FUSES OR HACR-TYPE CIRCUIT BREAKERS FOR AIR CONDITIONING EQUIPMENT SIZED IN ACCORDANCE WITH MANUFACTURER'S NAMEPLATE. WHERE FACTORY-PROVIDED DISCONNECT SWITCHES ARE UTILIZED, THEY SHALL BE RATED TO
EXCEED THE AVAILABLE FAULT CURRENT AT THE EQUIPMENT.
14. HVAC CONTROLS: PROVIDE LINE VOLTAGE WIRING, RACEWAYS, AND POWER CONNECTIONS AS REQUIRED TO ACCOMMODATE HVAC CONTROL SYSTEMS. COORDINATE REQUIREMENTS WITH TEMPERATURE CONTROL, MECHANICAL, PLUMBING, AND GENERAL CONTRACTORS PRIOR TO BID. NO EXTRAS WILL BE ALLOWED FOR FAILURE TO COMPLY WITH THIS REQUIREMENT. LOW VOLTAGE HVAC CONTROL RACEWAY SYSTEMS SHALL BE PER THE TEMPERATURE CONTROLS CONTRACTOR. THESE DOCUMENTS DO NOT
INDICATE ALL CONNECTION POINTS NECESSARY FOR A COMPLETE AND OPERABLE SYSTEM.
15. PANEL DIRECTORIES SHALL BE REMOVABLE. ROOM NAMES AND NUMBERS SHALL BE AS DIRECTED BY OWNER. DIRECTORIES
SHALL BE TYPED AND INSTALLED UNDER CLEAR PLASTIC COVERS.
16. PROVIDE DYMO-TAPE TAG PRINTED LABEL INSIDE COVER OF EACH FUSIBLE SWITCH, INDICATING SIZE AND TYPE OF FUSES
PROVIDED.
17. PROVIDE TWO (2) SETS OF THREE (3) SPARE FUSES FOR EACH SIZE AND TYPE PROVIDED ON THIS PROJECT. INSTALL FUSES IN A HINGED DOOR, SHEET METAL STORAGE CABINET EQUIPPED WITH CLIPS OR CUBICLES, EACH MARKED WITH THE SIZE AND TYPE OF FUSE STORED THEREIN. PROVIDE NAMEPLATE "SPARE FUSES". INSTALL IN LOCATIONS AS DIRECTED BY OWNER.
18. PROVIDE 4" HIGH CONCRETE EQUIPMENT PADS FOR FLOOR MOUNTED EQUIPMENT SUCH AS SWITCHBOARDS, MOTOR CONTROL CENTERS, TRANSFORMERS, ETC. COORDINATE WITH DISTRIBUTION EQUIPMENT TO ENSURE ALL SWITCH AND CIRCUIT BREAKER
HANDLES ARE BELOW 6'-6" TO THE HIGHEST POINT.
19. CONTRACTOR SHALL PROVIDE NEW UPDATED TYPE WRITTEN PANEL DIRECTORIES FOR EXISTING AND NEW CIRCUITS BEING
UTILIZED FOR COMPLETION OF THIS PROJECT.
20. FINAL CONNECTIONS TO MOTORS, TRANSFORMERS, AND OTHER VIBRATING AND/OR ROTATING EQUIPMENT SHALL BE MADE WITH SEAL-TITE FLEXIBLE FLEXIBLE CONDUIT WITH APPROVED FITTINGS (3''0" MAXIMUM LENGTH). DO NOT SECURE CONDUITS OR
DEVICES TO DUCTWORK OR OTHER MECHANICAL EQUIPMENT.
21. DEVICES INSTALLED IN FIRE-RATED WALLS SHALL HAVE NELSON FSP PUTTY PADS INSTALLED TO MAINTAIN FIRE INTEGRITY - ONE PAD PER HOUR OF RATING. CONDUIT PENETRATING FIRE-RATED WALLS SHALL COMPLY WITH THE REQUIREMENTS OF U.L. SYSTEM 147A FOR SINGLE CONDUITS OR U.L. SYSTEM 322 FOR MULTIPLE CONDUITS. DEVICES INSTALLED IN SOUND-RATED WALLS SHALL HAVE NELSON FSP (STC 54) SOUND RATED PUTTY PADS INSTALLED TO MAINTAIN THE SOUND INTEGRITY OF THE WALL.
22. RECEPTACLES INSTALLED OUTSIDE, ON THE BUILDING EXTERIOR OR ROOF, IN KITCHENS OR WITHIN 6'-0" MEASURED HORIZONTALLY FROM A SINK OR DRINKING FOUNTAIN UNLESS LOCATED BELOW A COUNTER OR OTHERWISE PROTECTED SHALL BE
GFCI TYPE OR PROTECTED BY A GFCI CIRCUIT BREAKER.
23. COORDINATE THE LOCATION OF LIGHTING FIXTURES WITH THE ARCHITECTURAL REFLECTED CEILING PLAN. UNLESS VERIFIED IN
WRITING THE REFLECTED CEILING PLAN LOCATIONS SHALL GOVERN.
24. COORDINATE THE LOCATION OF WALL MOUNTED EQUIPMENT WITH THE ARCHITECTURAL INTERIOR AND EXTERIOR ELEVATIONS.
UNLESS OTHERWISE VERIFIED IN WRITING THE ARCHITECTURAL DRAWINGS SHALL GOVERN.
PART 4 - DESIGN-BUILD FIRE ALARM AND DETECTION SYSTEM
PERFORMANCE CRITERIA
A. GENERAL
1. CONTRACTOR SHALL PROVIDE, INSTALL, TEST, AND COMMISSION A FULLY OPERATIONAL, APPROVED, FIRE ALARM AND DETECTION
SYSTEM.
2. FIRE ALARM AND DETECTION SYSTEM SHALL BE PROVIDED BY THIS CONTRACTOR, PERFORMED UNDER A DESIGN-BUILD DELIVERY
METHOD.
3. FIRE ALARM AND DETECTION SYSTEM SHALL BE IN FULL COMPLIANCE WITH ALL LOCAL, STATE, FEDERAL, AND ADA REQUIREMENTS.
4. CONTRACTOR SHALL PROVIDE SUBMITTALS. SUBMITTAL REQUIREMENTS:
4.1. SUBMITTALS SHALL BE APPROVED BY AUTHORITIES HAVING JURISDICTION PRIOR TO SUBMITTING THEM TO THE
ARCHITECT.
4.2. SHOP DRAWINGS SHALL BE PREPARED BY PERSONS WITH THE FOLLOWING QUALIFICATIONS:
4.2.1. TRAINED AND CERTIFIED BY MANUFACTURER IN FIRE-ALARM SYSTEM DESIGN.
4.2.2. NICET-CERTIFIED, FIRE ALARM TECHNICIAN; LEVEL III MINIMUM.
4.2.3. LICENSED OR CERTIFIED BY AUTHORITIES HAVING JURISDICTION.
4.3. DELEGATED-DESIGN: FOR NOTIFICATION APPLIANCES AND SMOKE AND HEAT DETECTORS, IN ADDITION TO THE SUBMITTALS LISTED ABOVE, INDICATE COMPLIANCE WITH PERFORMANCE REQUIREMENTS AND DESIGN CRITERIA, INCLUDING ANALYSIS DATA SIGNED AND SEALED BY THE QUALIFIED PROFESSIONAL ENGINEER RESPONSIBLE FOR THEIR
PREPARATION.
4.3.1. DRAWINGS SHOWING THE LOCATION OF EACH NOTIFICATION APPLIANCE AND SMOKE AND HEAT DETECTOR, RATINGS OF EACH, AND INSTALLATION DETAILS AS NEEDED TO COMPLY WITH LISTING CONDITIONS OF THE
DEVICE.
4.3.2. DESIGN CALCULATIONS: CALCULATE REQUIREMENTS FOR SELECTING THE SPACING AND SENSITIVITY OF DETECTION, COMPLYING WITH NFPA 72. CALCULATE SPACING AND INTENSITIES FOR STROBE SIGNALS AND
SOUND-PRESSURE LEVELS FOR AUDIBLE APPLIANCES.
4.3.3. INDICATED AUDIBLE APPLIANCES REQUIRED TO PRODUCE SQUARE WAVE SIGNAL PER NFPA 72.
5. EXISTING FIRE ALARM EQUIPMENT (WHERE APPLICABLE) SHALL BE MAINTAINED AND FULLY OPERATIONAL UNTIL NEW EQUIPMENT
PROVIDED UNDER THIS PROJECT HAS BEEN TESTED AND ACCEPTED. NEW COMPONENTS SHALL BE COMPATIBLE WITH, AND OPERATE AS AN EXTENSION OF, EXISTING SYSTEM. PROVIDE SYSTEM MANUFACTURERS CERTIFICATION THAT ALL COMPONENTS
PROVIDED HAVE BEEN TESTED AS, AND WILL OPERATE AS, A SYSTEM.
6. WARRANTY: CONTRACTOR SHALL AGREE TO REPAIR OR REPLACE FIRE ALARM SYSTEM EQUIPMENT AND COMPONENTS THAT FAIL IN MATERIALS OR WORKMANSHIP FOR A PERIOD OF NOT LESS THAN ONE YEAR FROM THE DATE OF SUBSTANTIAL COMPLETION.
7. COMPLY WITH NFPA 72, NFPA 101, AND REQUIREMENTS OF AUTHORITIES HAVING JURISDICTION FOR INSTALLATION AND TESTING OF FIRE-ALARM EQUIPMENT. INSTALL ALL ELECTRICAL WIRING TO COMPLY WITH REQUIREMENTS IN NFPA 70 INCLUDING, BUT NOT
LIMITED TO, ARTICLE 760, "FIRE ALARM SYSTEMS."
B. SYSTEM DESCRIPTION
1. NONCODED, UL-CERTIFIED ADDRESSABLE SYSTEM, WITH MULTIPLEXED SIGNAL TRANSMISSION AND VOICE/STROBE EVACUATION
MEETING AUDIBILITY AND INTELLIGIBLE REQUIREMENTS.
2. AUTOMATIC SENSITIVITY CONTROL OF CERTAIN SMOKE DETECTORS.
3. ALL COMPONENTS PROVIDED SHALL BE LISTED FOR USE WITH THE SELECTED SYSTEM.
4. ELECTRICAL COMPONENTS, DEVICES, AND ACCESSORIES SHALL BE LISTED AND LABELED AS DEFINED IN NFPA 70, BY A QUALIFIED
TESTING AGENCY, AND MARKED FOR INTENDED LOCATION AND APPLICATION.
C. OPERATIONAL DESCRIPTION
1. NOTE: THE FOLLOWING DESCRIPTIONS REPRESENT A MASTER LIST. NOT ALL DEVICES, SYSTEMS, AND FUNCTIONS LISTED HEREIN MAY BE REPRESENTED ON THIS PROJECT. APPLICABILITY SHALL BE DETERMINED BY QUALIFIED SYSTEM DESIGN PROFESSIONAL.
2. FIRE-ALARM SIGNAL INITIATION SHALL BE BY ONE OR MORE OF THE FOLLOWING DEVICES AND SYSTEMS:
2.1. MANUAL STATIONS.
2.2. HEAT DETECTORS.
2.3. FLAME DETECTORS.
2.4. SMOKE DETECTORS.
2.5. DUCT SMOKE DETECTORS.
2.6. AIR-SAMPLING SMOKE-DETECTION SYSTEM (VESDA).
2.7. CARBON MONOXIDE DETECTORS.
2.8. COMBUSTIBLE GAS DETECTORS.
2.9. AUTOMATIC SPRINKLER SYSTEM WATER FLOW.
2.10. PREACTION SYSTEM.
2.11. FIRE-EXTINGUISHING SYSTEM OPERATION.
2.12. FIRE STANDPIPE SYSTEM.
2.13. DRY SYSTEM PRESSURE FLOW SWITCH.
2.14. FIRE PUMP RUNNING.
3. FIRE-ALARM SIGNAL SHALL INITIATE THE FOLLOWING ACTIONS:
3.1. CONTINUOUSLY OPERATE ALARM NOTIFICATION APPLIANCES.
3.2. IDENTIFY ALARM AND SPECIFIC INITIATING DEVICE AT FIRE-ALARM CONTROL UNIT.
3.3. TRANSMIT AN ALARM SIGNAL TO THE REMOTE ALARM RECEIVING STATION.
3.4. UNLOCK ELECTRIC DOOR LOCKS IN DESIGNATED EGRESS PATHS.
3.5. RELEASE FIRE AND SMOKE DOORS HELD OPEN BY MAGNETIC DOOR HOLDERS.
3.6. ACTIVATE VOICE/ALARM COMMUNICATION SYSTEM.
3.7. SWITCH HEATING, VENTILATING, AND AIR-CONDITIONING EQUIPMENT CONTROLS TO FIRE-ALARM MODE.
3.8. ACTIVATE SMOKE-CONTROL SYSTEM (SMOKE MANAGEMENT) AT FIREFIGHTERS' SMOKE-CONTROL SYSTEM PANEL.
3.9. ACTIVATE STAIRWELL AND ELEVATOR-SHAFT PRESSURIZATION SYSTEMS.
3.10. CLOSE SMOKE DAMPERS IN AIR DUCTS OF DESIGNATED AIR-CONDITIONING DUCT SYSTEMS.
3.11. ACTIVATE PREACTION SYSTEM.
3.12. RECALL ELEVATORS TO PRIMARY OR ALTERNATE RECALL FLOORS.
3.13. ACTIVATE ELEVATOR POWER SHUNT TRIP.
3.14. ACTIVATE EMERGENCY LIGHTING CONTROL.
3.15. ACTIVATE EMERGENCY SHUTOFFS FOR GAS AND FUEL SUPPLIES.
3.16. RECORD EVENTS IN THE SYSTEM MEMORY.
3.17. RECORD EVENTS BY THE SYSTEM PRINTER.
3.18. INDICATE DEVICE IN ALARM ON THE GRAPHIC ANNUNCIATOR.
4. SUPERVISORY SIGNAL INITIATION SHALL BE BY ONE OR MORE OF THE FOLLOWING DEVICES AND ACTIONS:
4.1. VALVE SUPERVISORY SWITCH.
4.2. HIGH- OR LOW-AIR-PRESSURE SWITCH OF A DRY-PIPE OR PREACTION SPRINKLER SYSTEM.
4.3. ALERT AND ACTION SIGNALS OF AIR-SAMPLING DETECTOR SYSTEM.
4.4. ELEVATOR SHUNT-TRIP SUPERVISION.
4.5. FIRE PUMP RUNNING.
4.6. FIRE-PUMP LOSS OF POWER.
4.7. FIRE-PUMP POWER PHASE REVERSAL.
4.8. INDEPENDENT FIRE-DETECTION AND -SUPPRESSION SYSTEMS.
4.9. USER DISABLING OF ZONES OR INDIVIDUAL DEVICES.
4.10. LOSS OF COMMUNICATION WITH ANY PANEL ON THE NETWORK.
5. SYSTEM TROUBLE SIGNAL INITIATION SHALL BE BY ONE OR MORE OF THE FOLLOWING DEVICES AND ACTIONS:
5.1. OPEN CIRCUITS, SHORTS, AND GROUNDS IN DESIGNATED CIRCUITS.
5.2. OPENING, TAMPERING WITH, OR REMOVING ALARM-INITIATING AND SUPERVISORY SIGNAL-INITIATING DEVICES.
5.3. LOSS OF COMMUNICATION WITH ANY ADDRESSABLE SENSOR, INPUT MODULE, RELAY, CONTROL MODULE, REMOTE
ANNUNCIATOR, PRINTER INTERFACE, OR ETHERNET MODULE.
5.4. LOSS OF PRIMARY POWER AT FIRE-ALARM CONTROL UNIT.
5.5. GROUND OR A SINGLE BREAK IN INTERNAL CIRCUITS OF FIRE-ALARM CONTROL UNIT.
5.6. ABNORMAL AC VOLTAGE AT FIRE-ALARM CONTROL UNIT.
5.7. BREAK IN STANDBY BATTERY CIRCUITRY.
5.8. FAILURE OF BATTERY CHARGING.
5.9. ABNORMAL POSITION OF ANY SWITCH AT FIRE-ALARM CONTROL UNIT OR ANNUNCIATOR.
5.10. VOICE SIGNAL AMPLIFIER FAILURE.
5.11. HOSE CABINET DOOR OPEN.
6. SYSTEM SUPERVISORY SIGNAL ACTIONS:
6.1. INITIATE NOTIFICATION APPLIANCES.
6.2. IDENTIFY SPECIFIC DEVICE INITIATING THE EVENT AT FIRE-ALARM CONTROL UNIT.
6.3. RECORD THE EVENT ON SYSTEM PRINTER.
6.4. AFTER A TIME DELAY OF 200 SECONDS (OR PER AHJ REQUIREMENTS), TRANSMIT A TROUBLE OR SUPERVISORY SIGNAL
TO THE REMOTE ALARM RECEIVING STATION.
6.5. TRANSMIT SYSTEM STATUS TO BUILDING MANAGEMENT SYSTEM.
6.6. DISPLAY SYSTEM STATUS ON GRAPHIC ANNUNCIATOR.
DRAWN
PROJECT #
DATE
FIRM NAME
2024067.00
11/12/2024
SCALE
AS NOTED
CHECKED
REVISION/ISSUENO. DATE
5000 GOODMAN STREET
UNIT 100
TIMNATH CO 80547
(970) 460-7400
G2CE.COM
SEAL
CONSULTANT FIRM NAME
W
EL
D
CO
UN
TY
JA
IL
UP
S
RE
PL
AC
EM
EN
T
O S
TR
EE
T
GR
EE
LE
Y, C
O
PROJECT DESCRIPTION
SHEET DESCRIPTION
SHEET NUMBER
G2 G2
E0.02 - E0.02
1600/3
(MAIN)
(E) MAIN SERVICE SWITCHBOARD 'MSB-1'
1600A 277/480 VOLT, 3 PHASE, 4 WIRE, 65,000 AIC
NEUTRALGROUND
TVSS
100/3ST
KW
600/3
(E) EMERGENCY GENERATOR 'EG-1'
350 KW (437.5KVA), 600 AMPS
277/480 VOLT, 3 PHASE, 4 WIRE, 65,000 AIC
NEUTRALGROUND
(E) SERVICE LATERAL: (6) SETS OF - (4 - 500KCMIL ALUMINUM) 4"C
PROVIDE AND INSTALL PER XCEL ENERGY
STANDARDS AND SPECIFICATIONS.
T
(E) UTILITY SERVICE
TRANSFORMER 'T1'
(ESTIMATED 1000 KVA)
(E) PRIMARY FEEDER TO
UTILITY CO POINT OF SERVICE
(BY XCEL ENERGY) (E)
M
(E) UTILITY CO. METERING
4" CONCRETE
HOUSEKEEPING PAD
(TYPICAL)
REMOTE SHUNT-TRIP
STATION (LOCATION PER
FIRE MARSHAL)
1"C
ST
ANNUNCIATOR
ANNUNCIATOR
EMERGENCY ELEC. ROOM
MAIN LEVEL
SECOND LEVEL
THIRD LEVEL
ROOF
(E) SWITCHBOARD 'ESB'
200A - 480/277V, 3-PHASE, 4-WIRE, 65K AIC
BUS SPACE:
(2) 100/3
100/3100/3
(EMERGENCY)
(E) ATS 'ATS-E1'
(200A/4P)
'EH1A'
PANEL
200/3
(E) ATS 'ATS-Y1'
(600A/4P)
ELEV
ST
ELEV
ST
ELEV
ST
200/3 100/3
70/3
'EYL3A'
PANEL
(E) MAIN EMERGENCY SWITCHBOARD 'MESB'
600A - 480/277V, 3-PHASE, 4-WIRE, 65K AIC
BUS SPACE:
(2) 200/3
600/3200/3
200/3 600/3
BUS SPACE:
(2) 100/3
(E) SWITCHBOARD 'EYSB'
600A - 480/277V, 3-PHASE, 4-WIRE, 65K AIC
(EMERGENCY STANDBY)
225/3 225/3 225/3 225/3 400/3
T
75 KVA
(E) XFMR 'T-L1A'
(480-208/120V)
PANEL
'L1A'
SECTION 2
PANEL
'L1A'
SECTION 1
PANEL
'H1A'
T
75 KVA
(E) XFMR 'T-L1B'
(480-208/120V)
PANEL
'L1B'
SECTION 2
PANEL
'L1B'
SECTION 1
PANEL
'H1B'
T
45 KVA
(E) XFMR 'T-L2A'
(480-208/120V)
PANEL
'L2A'
SECTION 1
PANEL
'L2A'
SECTION 2
PANEL
'H2A'
T
75 KVA
PANEL
'L2B1'
PANEL
'L2B2'
PANEL
'H2B'
T
PANEL
'L3A'
SECTION 1
PANEL
'L3A'
SECTION 2
PANEL
'H3A'
T
PANEL
'L3B'
SECTION 1
PANEL
'L3B'
SECTION 2
PANEL
'H3B'
T 45 KVA
(X) XFMR 'T-EYL'
(480-208/120V)
'EYL1A'
PANEL
PANEL
'EYL2''EH2'
PANEL
'EH3A'
PANEL
C
T
(E)
(E) XFMR 'T-L2B'
(480-208/120V)
45 KVA
(E) XFMR 'T-L3A'
(480-208/120V)
75 KVA
(E) XFMR 'T-L3B'
(480-208/120V)
PANEL
'HL'
'ESHB'
PANEL
'ESHA'
PANEL
600/3
225/3
SECTION 1
SECTION 2
'ESHA'
PANEL
100/3100/3
'EH1B'
PANEL
'EYL1B'
PANEL
40 HP40 HP 20 HP
200/3 200/3 100/3
(2) BUSSED SPACE
200/3
SECTION 2
SECTION 1
'ESHB'
PANEL
ISC = 22,600AX
ISC = 21,506A
X
ISC = 9,642A X
ISC = 8,284 X
ISC = 8,284A X
ISC = 5,875A X
ISC = 19,499A X ISC = 12,138A X
ISC = 16,433A X ISC = 9,099A X
ISC = 13,206A X
ISC = 17,106A X ISC = 12,138A X
'EH2B'
PANEL
'EH3B'
PANEL
(E) CT CABINET / SPLICE
CABINET, LOCATED NEXT
TO THE UTILITY TRANSFORMER
ISC = 16,603A
X
ISC = 11,282AX
ISC = 4,465A X
ISC = 4,465A X
ISC = 4,465A X
ISC = 11,899A
X
ISC = 8,928A X
ISC = 8,928A X
'EYL3B'
PANEL
AREA OF WORK
(E)
(E) (E)
(E)
(E)
(E) (E)
(E)
(E)(E)(E)
(E) (E)
(E) (E) (E) (E) (E) (E) (E) (E) (E)
(E)(E)
(E) (E)
(E)(E)(E) (E)
(E)(E)(E)
(E) (E)
(E) (E) (E) (E)
(E)
(E) (E)
(E)(E)
(X)
(E)
(E)
(E) (E)
(E)
(E)
(E)
(E)
(E)
(E) (E)
(E)
(E) (E)
(E)(E) (E)
(E)(E)
(E)(E)
(E)
(E)(E)
(E) (E)
(E) (E)
(E)
(E) (E)
(E)(E) (E) (E)
(X)
(E)
(E)
(E
(E)
(E) (X)
(E)
(E)
(X) 9KVA 120/240V UPS-3-309
40/2
40/2
40/2
(X) EXTERNAL BYPASS UBS-1
(E) (E)(E)(E)
(E)(E)
(E) (E)
(E)(E)(E)(E)(E)(E)(E)(E)(E) (E) (E) (E) (E) (E) (E)
(E)
DRAWN
PROJECT #
DATE
FIRM NAME
2024067.00
11/12/2024
SCALE
AS NOTED
CHECKED
REVISION/ISSUENO. DATE
5000 GOODMAN STREET
UNIT 100
TIMNATH CO 80547
(970) 460-7400
G2CE.COM
SEAL
CONSULTANT FIRM NAME
W
EL
D
CO
UN
TY
JA
IL
UP
S
RE
PL
AC
EM
EN
T
O S
TR
EE
T
GR
EE
LE
Y, C
O
PROJECT DESCRIPTION
SHEET DESCRIPTION
SHEET NUMBER
G2 G2
E0.20
DEMOLITION WORK
ELECTRICAL
SINGLE-LINE
DEMOLITION NOTES:
1. EXISTING TRANSFORMER AND ASSOCIATED LINE AND LOAD SIDE CABLING SHALL BE DEMOLISHED UPON
COMPLETION OF NEW UPS INSTALLATION.
2. EXISTING UPS AND BYPASS SHALL BE DEMOLISHED UPON COMPLETION OF INSTALLATION OF NEW
SYSTEM.
3. MAKE EXISTING CIRCUIT BREAKER 'SPARE' UPON COMPLETION OF NEW WORK.
4. REMOVE FEEDER WIRING AND CONDUIT TO SOURCE.
SCALE:
E0.20
DEMOLITION WORK SINGLE LINE DIAGRAM
NTS
1600/3
(MAIN)
(E) MAIN SERVICE SWITCHBOARD 'MSB-1'
1600A 277/480 VOLT, 3 PHASE, 4 WIRE, 65,000 AIC
NEUTRALGROUND
TVSS
100/3ST
KW
600/3
(E) EMERGENCY GENERATOR 'EG-1'
350 KW (437.5KVA), 600 AMPS
277/480 VOLT, 3 PHASE, 4 WIRE, 65,000 AIC
NEUTRALGROUND
SERVICE LATERAL: (6) SETS OF - (4 - 500KCMIL ALUMINUM) 4"C
PROVIDE AND INSTALL PER XCEL ENERGY
STANDARDS AND SPECIFICATIONS.
T
(E) UTILITY SERVICE
TRANSFORMER 'T1'
(ESTIMATED 1000 KVA)
PRIMARY FEEDER TO
UTILITY CO POINT OF SERVICE
(BY XCEL ENERGY) (E)
M
(E) UTILITY CO. METERING
4" CONCRETE
HOUSEKEEPING PAD
(TYPICAL)
REMOTE SHUNT-TRIP
STATION (LOCATION PER
FIRE MARSHAL)
1"C
ST
ANNUNCIATOR
ANNUNCIATOR
EMERGENCY ELEC. ROOM
MAIN LEVEL
SECOND LEVEL
THIRD LEVEL
ROOF
(E) SWITCHBOARD 'ESB'
200A - 480/277V, 3-PHASE, 4-WIRE, 65K AIC
BUS SPACE:
(2) 100/3
100/3100/3
(EMERGENCY)
(E) ATS 'ATS-E1'
(200A/4P)
'EH1A'
PANEL
200/3
(E) ATS 'ATS-Y1'
(600A/4P)
ELEV
ST
ELEV
ST
ELEV
ST
200/3 100/3
70/3
(E) MAIN EMERGENCY SWITCHBOARD 'MESB'
600A - 480/277V, 3-PHASE, 4-WIRE, 65K AIC
BUS SPACE:
(2) 200/3
600/3200/3
200/3 600/3
BUS SPACE:
(2) 100/3
(E) SWITCHBOARD 'EYSB'
600A - 480/277V, 3-PHASE, 4-WIRE, 65K AIC
(EMERGENCY STANDBY)
225/3 225/3 225/3 225/3 400/3
T
75 KVA
(E) XFMR 'T-L1A'
(480-208/120V)
PANEL
'L1A'
SECTION 2
PANEL
'L1A'
SECTION 1
PANEL
'H1A'
T
75 KVA
(E) XFMR 'T-L1B'
(480-208/120V)
PANEL
'L1B'
SECTION 2
PANEL
'L1B'
SECTION 1
PANEL
'H1B'
T
45 KVA
(E) XFMR 'T-L2A'
(480-208/120V)
PANEL
'L2A'
SECTION 1
PANEL
'L2A'
SECTION 2
PANEL
'H2A'
T
75 KVA
PANEL
'L2B1'
PANEL
'L2B2'
PANEL
'H2B'
T
PANEL
'L3A'
SECTION 1
PANEL
'L3A'
SECTION 2
PANEL
'H3A'
T
PANEL
'L3B'
SECTION 1
PANEL
'L3B'
SECTION 2
PANEL
'H3B'
'EH2'
PANEL
'EH3A'
PANEL
C
T
(E)
(E) XFMR 'T-L2B'
(480-208/120V)
45 KVA
(E) XFMR 'T-L3A'
(480-208/120V)
75 KVA
(E) XFMR 'T-L3B'
(480-208/120V)
PANEL
'HL'
'ESHB'
PANEL
'ESHA'
PANEL
600/3
225/3
SECTION 1
SECTION 2
'ESHA'
PANEL
100/3100/3
'EH1B'
PANEL
40 HP40 HP 20 HP
200/3 200/3 100/3
(2) BUSSED SPACE
200/3
SECTION 2
SECTION 1
'ESHB'
PANEL
ISC = 22,600AX
ISC = 21,506A
X
ISC = 9,642A X
ISC = 8,284 X
ISC = 8,284A X
ISC = 5,875A X
ISC = 19,499A X ISC = 12,138A X
ISC = 16,433A X ISC = 9,099A X
ISC = 13,206A X
ISC = 17,106A X ISC = 12,138A X
'EH2B'
PANEL
'EH3B'
PANEL
(E) CT CABINET / SPLICE
CABINET, LOCATED NEXT
TO THE UTILITY TRANSFORMER
ISC = 16,603A
X
ISC = 11,282AX
ISC = 4,465A X
ISC = 4,465A X
ISC = 11,899A
X
ISC = 8,928A X
ISC = 8,928A X
AREA OF WORK
(E)
(E) (E)
(E)
(E)
(E) (E)
(E)
(E)(E)(E)
(E) (E)
(E) (E) (E) (E) (E) (E) (E) (E) (E)
(E)(E)
(E) (E)
(E)(E)(E) (E)
(E)(E)(E)
(E) (E)
(E) (E) (E) (E)
(E)
(E) (E)
(E)(E)
(E)
(E) (E)
(E)
(E)
(E)
(E)
(E)
(E) (E)
(E)
(E) (E)
(E)(E) (E)
(E)(E)
(E) (E)
(E) (E)
(E)
(E) (E)
(E)(E) (E) (E)
(E)(E)
(E)
'EYL1A'
PANEL
(E)
'EYL1B'
PANEL
(E)
PANEL
'EYL2'
(E)
'EYL3B'
PANEL
(E)
'EYL3A'
PANEL
(E)
(E)
(E)
(E)
(3) #1THWN CU, (1) #8 GRD CU, 1-1/2"C.
UPS TRANSFROMER 'SUP1E'
40 KW 480-208/120V 3 PH
EXTERNAL BYPASS CABINET
(MAKE-BEFORE-BREAK)
80/3
NEW
(E) (E)
#2 CU
(3) #3 THWN CU, & (1) #8 THWN CU GRD, 1.5"C
200/3
150/3
150/3
60KVA
(E)
(4) #1/0 THWN CU, (1) #6 THWN CU GRD, 1.5"C
(E) (E)(E)(E)
(E)(E)
(E)(E)(E)(E)(E)(E)(E)(E)(E) (E) (E) (E) (E) (E) (E)
WORK NOTES:
1. INSTALL NEW UPS SYSTEM. REFER TO POWER PLAN FOR
SPECIFICATIONS.
2. PROVIDE NEW CIRCUIT BREAKER AT EXISTING
DISTRIBUTION PANEL. VERIFY MANUFACTURER
INFORMATION AND BREAKER TYPE PRIOR TO ANY
PURCHASE. COORDINATE ANY SHUT DOWN WITH
OWNER'S REPRESENTATIVE.
3. PROVIDE NEW CIRCUIT BREAKER IN EXISTING PANEL.
REFER TO PANEL SCHEDULE. VERIFY MANUFACTURER
INFORMATION PRIOR TO ANY PURCHASE.
4. ROUTE NEW FEEDER TO BACKFEED EXISTING PANE EYL3B.
5. PROVIDE 3/4" RACEWAY TO ACCESSIBLE LOCATION FOR
DATA ACCESS TO NEAREST IT ROOM. REFER TO OVERALL
PLAN.
SCALE:
E0.21
NEW WORK SINGLE LINE DIAGRAM
NTS
DRAWN
PROJECT #
DATE
FIRM NAME
2024067.00
11/12/2024
SCALE
AS NOTED
CHECKED
REVISION/ISSUENO. DATE
5000 GOODMAN STREET
UNIT 100
TIMNATH CO 80547
(970) 460-7400
G2CE.COM
SEAL
CONSULTANT FIRM NAME
W
EL
D
CO
UN
TY
JA
IL
UP
S
RE
PL
AC
EM
EN
T
O S
TR
EE
T
GR
EE
LE
Y, C
O
PROJECT DESCRIPTION
SHEET DESCRIPTION
SHEET NUMBER
G2 G2
E0.21
NEW WORK
ELECTRICAL SINGLE
LINE
DRAWN
PROJECT #
DATE
FIRM NAME
2024067.00
11/12/2024
SCALE
AS NOTED
CHECKED
REVISION/ISSUENO. DATE
5000 GOODMAN STREET
UNIT 100
TIMNATH CO 80547
(970) 460-7400
G2CE.COM
SEAL
CONSULTANT FIRM NAME
W
EL
D
CO
UN
TY
JA
IL
UP
S
RE
PL
AC
EM
EN
T
O S
TR
EE
T
GR
EE
LE
Y, C
O
PROJECT DESCRIPTION
SHEET DESCRIPTION
SHEET NUMBER
G2 G2
E0.30
PANEL SCHEDULES
EYL3A
EYL2EYL1B
EYL1A
WORK NOTES:
1. PROVIDE NEW CIRCUIT BREAKER AT EXISTING BRANCH CIRCUIT PANEL. VERIFY MANUFACTURER
INFORMATION AND BREAKER TYPE PRIOR TO ANY PURCHASE. COORDINATE ANY SHUT DOWN WITH
OWNER'S REPRESENTATIVE.
2 MAKE EXISTING BREAKER SPARE UPON REMOVAL OF EXISTING UPS.
EYL3B
L3A
UP
W
V.5
V
U
T.5
T
S.5
S
R.5
R
Q
P.5
P
N
M.5
M
14.7
14.7
14.3
14.3
A.3
B
C.5
F
H
H.2
K
X
STAIR 2
1-S2
ELEV. 2
1-E2
STAIR 4
1-S4
CLASSROOM
1-198
AIR POD
1-197
AIR POD
1-176
CLASSROOM
1-175
CLASSROOM
1-156
AIR POD
1-155
AIR POD
1-134
CLASSROOM
1-133
CLASSROOM
1-114
AIR POD
1-113
POD 12
(DAYROOM)
1-185
POD 14
(DAYROOM)
1-143
POD 16
(DAYROOM)
1-101
LAUNDRY
1-102
JAN.
1-103
PROF. VISIT
1-104
PROF. VISIT
1-105
CELL
1-108
SHOWER
1-106
MECH.
CHASE
MC1
MECH.
CHASE
MC2
JAN.
1-304
CLASSIFICATION
SCREENING
1-305
POD 17
(DAYROOM)
1-301
PROF. VISIT
1-302
MEDICAL
SCREENING
1-303
ELEV. 1
1-E1
STAIR 1
1-S1
ELEV.
EQUIPMENT
RM
1-E1A
POD 18
(DAYROOM)
1-337
LAUNDRY
1-404
CLASSIFICATION
SCREENING
1-323
JAN
1-322MEDICAL
SCREENING
1-321
PROF. VISIT
1-319
BOILER
ROOM
1-300
VIDEO CONF.
1-312
VIDEO CONF.
1-402
ELEC. RM
1-406
SPRINKLER
RM
1-405
MENS RR
1-504
WOMENS RR
1-503
ELEV. LOBBY
1-L2
ELEV.
EQUIPMENT
RM
1-E2A
VEST.
1-C04
CORRIDOR
1-518
ELECTRICAL
1-329
STAIR 3
1-S3
IDF
1-501
WORK
1-519
OFFICE
1-521
OFFICE
1-522
CONF.
1-523
OFFICE
1-524
PHARM.
STORAGE
1-517
R.R.
1-516
EXAM
1-515
ELEV. EQPT.
RM.
1-E3A
OFFICE
1-509
EXAM
(DENTAL)
1-513
EXAM
1-512
INMATE
SUPPLY
STORAGE
1-403
OFFICE
1-508
NURSE
STATION
1-506
WAITING
1-505
ELEV. 3
1-E3
STOR.
1-511
OFFICE
1-507
POD 15
(DAYROOM)
1-122
LAUNDRY
1-126
JAN.
1-125
PROF. VISIT
1-124
PROF. VISIT
1-123
CELL
1-138 SHOWER
1-141
LAUNDRY
1-144
JAN.
1-145
PROF. VISIT
1-146
PROF. VISIT
1-147
CELL
1-151
SHOWER
1-148
POD 13
(DAYROOM)
1-164
LAUNDRY
1-168 JAN.
1-167
PROF. VISIT
1-166
PROF. VISIT
1-165CELL
1-181
SHOWER
1-183
LAUNDRY
1-186
JAN.
1-187
PROF. VISIT
1-188
PROF. VISIT
1-189
CELL
1-193
SHOWER
1-191
CELL
1-109
CELL
1-107
CELL
1-111
CELL
1-112
CELL
1-118
CELL
1-117
CELL
1-116
CELL
1-115 CELL (AC.)
1-119
CELL
1-152
CELL
1-149
CELL
1-153
CELL
1-154
CELL
1-161
CELL
1-159
CELL
1-158
CELL
1-157
CELL (AC.)
1-162
CELL
1-194
CELL
1-192
CELL
1-195
CELL
1-196
CELL
1-203
CELL
1-202
CELL
1-201
CELL
1-199
CELL (AC.)
1-204
MECH.
CHASE
MC3
MECH.
CHASE
MC4
MECH.
CHASE
MC5
MECH.
CHASE
MC6
CORRIDOR
1-C07
MECH.
ACCESS
MC9
MECH.
ACCESS
MC7
MECH.
ACCESS
MC8
PROF. VISIT
1-408
SALLY PORT
1-100
BLDG
BREEZEWAY
1-C08
N.5 N.5
Q.5
L
A
EXTERIOR
CORRIDOR
1-C02
EXTERIOR
CORRIDOR
1-C01
EXTERIOR
CORRIDOR
1-C03
CORRIDOR
1-C05
CORRIDOR
1-C06
OFFICE
1-401
CORRIDOR
1-C09
JAN.
1-502
HALLWAY
1-514
STOR.
1-500
CORRIDOR
1-C10
CLASSROOM
1-409
LINT
COLLECT
1-407
CELL (AC.)
1-127
CELL
1-128
CELL
1-129
CELL
1-131
CELL
1-132
CELL
1-135
CELL
1-136
CELL
1-137
CELL
1-139
CELL
1-174
CELL
1-173
CELL
1-172
CELL
1-171
CELL (AC.)
1-169
CELL
1-177
CELL
1-178
CELL
1-179
CELL
1-182
CELL
1-335
CELL
1-334
CELL
1-333
CELL
1-332
CELL
1-331
CELL
1-328
CELL
1-327
CELL
1-326
CELL
1-325
CELL (AC.)
1-324
SHOWER
1-336
SHOWER
1-318
CELL
1-317
CELL
1-316
CELL
1-315
CELL
1-314
CELL
1-313
CELL
1-311
CELL
1-309
CELL
1-308
CELL
1-307
CELL (AC.)
1-306
ACCESS CONTROL PANEL
E2.00
E2.00
(E) PANEL EYL1B
(E)PANEL EYL1A
DRAWN
PROJECT #
DATE
FIRM NAME
2024067.00
11/12/2024
SCALE
AS NOTED
CHECKED
REVISION/ISSUENO. DATE
5000 GOODMAN STREET
UNIT 100
TIMNATH CO 80547
(970) 460-7400
G2CE.COM
SEAL
CONSULTANT FIRM NAME
W
EL
D
CO
UN
TY
JA
IL
UP
S
RE
PL
AC
EM
EN
T
O S
TR
EE
T
GR
EE
LE
Y, C
O
PROJECT DESCRIPTION
SHEET DESCRIPTION
SHEET NUMBER
G2 G2
E1.00
FIRST LEVEL
OVERALL POWER
PLAN
SCALE: N
E1.00
FIRST LEVEL OVERALL POWER PLAN
1/16" = 1'-0"
DN
20 19 18 16
W
V.5
V
U
T.5
T
S.5
S
R.5
R
Q
P.5
P
N
M.5
M
14.7 14.3
A.3
A.3
B
C.5
F
H
H
H.2
H.2
K
X
ELEV. 2
2-E2
STAIR 2
2-S2
STAIR 4
2-S4
STAIR 1
2-S1
ELEV. 1
2-E1
VIDEO CONF.
2-302
MEDICAL
WARD POD 24
(DAYROOM)
2-305
CLASSROOM
2-313
AIR POD
2-314
STAIR 3
2-S3
WOMENS RR
2-403
MENS RR
2-404
WOMENS
BATH
2-406
ELEV. LOBBY
2-L2
PROF. VISIT
2-303
STORAGE
2-408
MENS BATH
2-405
TRAINING
ROOM
2-409
IDF
2-401
LAUNDRY
2-309
JAN.
2-311
SIMULATION
RM.
2-507
CORRIDOR
2-C02
ELEV. 3
2-E3
POD 23
(DAYROOM)
2-101
POD 22
(DAYROOM)
2-122
POD 21
(DAYROOM)
2-143
POD 20
(DAYROOM)
2-164
POD 19
(DAYROOM)
2-185
SHOWER
2-106
LAUNDRY
2-102
PROF. VISIT
2-104
JAN.
2-103
CELL
2-199
CELL
2-201
CELL
2-202
CELL
2-203
CELL (AC.)
2-204
CELL
2-115
CELL
2-112
CELL
2-111
CELL
2-109
CELL
2-108
CELL
2-107
CELL
2-116
CELL
2-117
CELL
2-118
CELL
2-132
CELL
2-131
CELL
2-129
CELL
2-128
CELL
2-135
CELL
2-136
CELL
2-137
CELL
2-138
CELL
2-139
CELL
2-149
CELL
2-151
CELL
2-152
CELL
2-153
CELL
2-154
CELL
2-157
CELL
2-158
CELL
2-159
CELL
2-161
CELL
2-174
CELL
2-173
CELL
2-172
CELL
2-171
CELL
2-177
CELL
2-178
CELL
2-179
CELL
2-181
CELL
2-182
CELL
2-192
CELL
2-193
CELL
2-194
CELL
2-195
CELL
2-196
SHOWER
2-141
SHOWER
2-148
SHOWER
2-183
SHOWER
2-191
CELL (AC.)
2-119
CELL (AC.)
2-127
CELL (AC.)
2-162
CELL (AC.)
2-169
LAUNDRY
2-126
JAN.
2-125
PROF. VISIT
2-124
PROF. VISIT
2-123
LAUNDRY
2-144
JAN.
2-145
PROF. VISIT
2-146
PROF. VISIT
2-147
LAUNDRY
2-168
JAN.
2-167
PROF. VISIT
2-166
PROF. VISIT
2-165
LAUNDRY
2-186
JAN.
2-187
PROF. VISIT
2-188
PROF. VISIT
2-189
PROF. VISIT
2-105
MECH.
ACCESS
MC11
MECH.
ACCESS
MC10
CLASSROOM
2-114
CLASSROOM
2-133
AIR POD
2-113
AIR POD
2-134
AIR POD
2-155
CLASSROOM
2-156
CLASSROOM
2-175
AIR POD
2-176
AIR POD
2-197
CLASSROOM
2-198
CUSTODIAL
STORAGE
2-508
ELEV. LOBBY
2-L1
CORRIDOR
2-C08
JAN.
2-402 CONFERENCE
2-501
CORRIDOR
2-C06
TRAINING
2-506
M. RR
2-504
F. RR
2-505
PART.
CLOSET
2-512
COFFEE BAR
2-502
CONFERENCE
2-509
CLASSROOM
2-320
CLOSET
2-513
CLOSET
2-511
STOR.
2-503
L
A
A
VEST.
2-C01
OFFICE
2-301
CORRIDOR
2-C04
CORRIDOR
2-C05
RR VEST.
2-407
CORRIDOR
2-C07
CORRIDOR
2-C09
EXTERIOR
CORRIROR
2-C11
ELEV. LOBBY
2-L3
VEST.
2-C10
STORAGE
2-310
CELL
2-306
CELL
2-307
MEDICAL
OFFICE
2-304
CELL
2-308
CELL
2-319
CELL
2-318
CELL
2-317
CELL
2-316
CELL (AC.)
2-315
SHOWER
2-312
STORAGE
2-510
E2.00
(E) PANEL EYL2
DRAWN
PROJECT #
DATE
FIRM NAME
2024067.00
11/12/2024
SCALE
AS NOTED
CHECKED
REVISION/ISSUENO. DATE
5000 GOODMAN STREET
UNIT 100
TIMNATH CO 80547
(970) 460-7400
G2CE.COM
SEAL
CONSULTANT FIRM NAME
W
EL
D
CO
UN
TY
JA
IL
UP
S
RE
PL
AC
EM
EN
T
O S
TR
EE
T
GR
EE
LE
Y, C
O
PROJECT DESCRIPTION
SHEET DESCRIPTION
SHEET NUMBER
G2 G2
E1.01
SECOND LEVEL
OVERALL POWER
PLAN
SCALE: N
E1.01
SECOND LEVEL OVERALL POWER PLAN
W
V.5
V
U
T.5
T
S.5
S
R.5
R
Q
P.5
P
N
M.5
M
14.7
14.7
14.3
14.3
A.3
B
B
C.5
C.5
F
F
H
H
H.2
H.2
K
K
X
STAIR 4
3-S4
STAIR 1
3-S1
ELEV 1
3-E1
STAIR 2
3-S2
ELEV. 2
3-E2
STAFF (M)
LOCKERS
3-405
CORRIDOR
3-C02
STAIR 3
3-S3
WOMENS RR
3-303
MENS RR
3-304
ELEV. LOBBY
3-L2
22 BED
22 BED
IDF
3-301
22 BED
CONF.
3-417
STAFF
LOUNGE
3-416
OPEN
OFFICES
3-421
OFFICE
3-414
OFFICE
3-412
OFFICE
3-415
OFFICE
3-413
CORRIDOR
3-C05
STAFF (F)
LOCKERS
3-409
ELEV. 3
3-E3
SOG CONF.
3-403
SOG
EQUIPMENT
3-401
SOG
STORAGE
3-402
CELL
3-157
CELL
3-156
CELL
3-155
CELL
3-154
CELL
3-153
CELL
3-158
CELL
3-163
CELL
3-162
CELL
3-161
CELL
3-159
CELL
3-164 SHOWER
3-165
CELL
3-174
CELL
3-173
CELL
3-172
CELL
3-171
CELL
3-175
SHOWER
3-169
CELL
3-181
CELL
3-179
CELL
3-178
CELL
3-177
CELL
3-176
CELL
3-182
CELL
3-147
CELL
3-146
CELL
3-145
CELL
3-144
CELL
3-143
CELL
3-148
CELL
3-141
CELL
3-139
CELL
3-138
CELL
3-137
CELL
3-142
SHOWER
3-136
CELL
3-129
CELL
3-128
CELL
3-127
CELL
3-126
CELL
3-131
SHOWER
3-132
CELL
3-124
CELL
3-123
CELL
3-122
CELL
3-121
CELL
3-119
CELL
3-125
CELL
3-114
CELL
3-113
CELL
3-112
CELL
3-111
CELL
3-109
CELL
3-115
CELL
3-108
CELL
3-107
CELL
3-106
CELL
3-105
CELL
3-104
SHOWER
3-103
22 BED
22 BED
CUSTODIAL
STORAGE
3-424
ELEV. LOBBY
3-L1
POD 19
(DAYROOM)
3-167
POD 20
(DAYROOM)
3-151
POD 21
(DAYROOM)
3-134
POD 22
(DAYROOM)
3-117
POD 23
(DAYROOM)
3-101
MASTER
CONTROL
3-307
MASTER
CONTROL
R.R.
3-306
CORRIDOR
3-C04
MASTER
CONTROL
EQPT.
3-309
STORAGE
3-308
VIDEO
VIEWING
3-305
COFFEE
WORK AREA
FACP
OFFICE
3-418
CELL
3-216
CELL
3-217
CELL
3-218
CELL
3-215
CELL (AC.)
3-214
CELL
3-224
CELL
3-219
CELL
3-221
CELL
3-222
CELL
3-223
CELL
3-203
CELL
3-205
CELL
3-206
CELL
3-207
CELL
3-204
SHOWER
3-211
SHOWER
3-225
CELL
MAINTENANCE
ACCESS
3-208
HALLWAY
3-202
CELL
MAINTENANCE
ACCESS
3-220
ELEV. LOBBY
3-L3
CELL
MAINTENANCE
ACCESS
3-212
STORAGE
3-201
N.5
L
A
OFFICE
3-419SHOWER
3-406
RR
3-407
OFFICE
3-404
SHOWER
3-411
JAN.
3-302
RR
3-408
CORRIDOR
3-C03
CORRIDOR
3-C06
POD 25
CLOSE
WATCH
3-209
LACTATION
3-420
SHAFT
M. LOCKER
VEST.
3-405A
F. LOCKER
VEST.
3-409A
SHAFT
CELL
MAINTENANCE
ACCESS
3-208
LAUNDRY
3-166
LAUNDRY
3-168
JAN.
3-183
JAN.
3-152
JAN.
3-149
LAUNDRY
3-135
LAUNDRY
3-133
JAN.
3-118
JAN.
3-116
LAUNDRY
3-102
SH
AF
T
SHAFT
SHAFT
NOTE: CLOSE WATCH CELLS ARE
ASSEMBLED ON-SITE
(FLOOR WILL BE POURED IN PLACE
CONCRETE OVER METAL DECK)
SHIPS LADDER
TO ROOF
STAIR ACCESS
OFFICE
3-404A
CLOSE
3-213
WATCH
POD 26
SHAFT
E2.00
E2.00
(E) PANEL EYL3A
(E) PANEL EYL3B
(E) PANEL EYL3A
(E) PANEL L3A
DRAWN
PROJECT #
DATE
FIRM NAME
2024067.00
11/12/2024
SCALE
AS NOTED
CHECKED
REVISION/ISSUENO. DATE
5000 GOODMAN STREET
UNIT 100
TIMNATH CO 80547
(970) 460-7400
G2CE.COM
SEAL
CONSULTANT FIRM NAME
W
EL
D
CO
UN
TY
JA
IL
UP
S
RE
PL
AC
EM
EN
T
O S
TR
EE
T
GR
EE
LE
Y, C
O
PROJECT DESCRIPTION
SHEET DESCRIPTION
SHEET NUMBER
G2 G2
E1.02
THIRD LEVEL
OVERALL POWER
PLAN
SCALE: N
E1.02
THIRD LEVEL OVERALL POWER PLAN
PROF. VISIT
1-319
WOMENS RR
1-503
IDF
1-501
PROF. VISIT
JAN.
1-502
(E) FIRE ALARM PANEL
(E) FIRE ALARM PANEL
(E) PANEL EYL1B
(E) DAS
(E) SPLIT
(E) AC
(E ) U
PS
(E)8
(E)
(E)
(E)
(E)
WOMENS RR
2-403
IDF
2-401
PROF. VISIT
JAN.
2-402
CORRIDOR
2-C05(E) FIRE ALARM PANEL
(E) FIRE ALARM PANEL
(E) PANEL EYL2
(E) SPLIT
(E) AC
(E ) U
PS
(E)8 (E)
(E)
(E) (E)
(E)
WOMENS RR
3-303
IDF
3-301
JAN.
3-302
SHAFT
(E) FIRE ALARM PANEL
(E) FIRE ALARM PANEL
(E) PANEL EYL3A(E) DAS
(E) SPLIT
(E ) U
PS
(E) AC
(E)8
(E)
(E)
(E) (E)
14.7 14.3
3 2
ELEV. LOBBY
3-L2
MASTER
CONTROL
EQPT.
3-309
JAN.
3-183
F
T
(E) PANEL 'H3B'
(E) XFMR 'T-L3B'
(E) PANEL 'L3B (SECT. 2)'
(E) PANEL 'L3B (SECT. 1)'
(E) PANEL 'ESHB'
(E) PANEL 'EH3B'
(E) LCP3B (E) BAS
CONTROL
PANEL
(E) (3) 4 POST RACKS
SERVER
(E) CRAC UNIT
(E) ELECTRICAL GUTTER (X) UPS-1 (E) PANEL 'EYL3B'
UPS
ATS
(E) CRAC
(E) MARSHALLING CABINETS
(X)
(X)
ELECTRICAL
1-329
BLDG
BREEZEWAY
CORRIDOR
1-C09
CELL
1-331 T
FACP
Y-1
(E) A
TS
E1
(E)PANEL EYL1A
(E) PANEL ESB
(E) DISTRIBUTION PANEL EYSB
UPS / B
ATTERY CABINET(S)
T
(X) EXISTING
TRANSFORMER 'X-EYL'
(E) A
TS
(E) AC
(E) SPLIT
(N) UPS XFMR 'SUP1E'
(E) CONDUIT RACK
(E) DISTRIBUTION
PANEL MESB
(X)
(X)
AC
S
2 POLE
10 11
3'-0 " M
IN.
CU
101 F
L3A-(26,28) REFER TO 3RD LEVEL OVERALL PLAN
(2 #10 THWN CU, (1) #10 CU GRD, 1"C
EXTEND CIRCUIT TO INTERIOR UNIT
30/2 NEMA 3R
36", WP
14.7 14.3
3 2
DRAWN
PROJECT #
DATE
FIRM NAME
2024067.00
11/12/2024
SCALE
AS NOTED
CHECKED
REVISION/ISSUENO. DATE
5000 GOODMAN STREET
UNIT 100
TIMNATH CO 80547
(970) 460-7400
G2CE.COM
SEAL
CONSULTANT FIRM NAME
W
EL
D
CO
UN
TY
JA
IL
UP
S
RE
PL
AC
EM
EN
T
O S
TR
EE
T
GR
EE
LE
Y, C
O
PROJECT DESCRIPTION
SHEET DESCRIPTION
SHEET NUMBER
G2 G2
E2.00
ENLARGED POWER
PLANS
WORK NOTES:
1. ROUTE NEW FEEDER FROM EXISTING DISTRIBUTION PANEL EYSB TO NEW UPS TRANSFORMER. REFER
TO SINGLE LINE FOR FEEDER INFORMATION.
2. PROVIDE AND INSTALL 40KW (40KVA) 480:208V, INTEGRAL BYPASS UPS, “SCHNEIDER ELECTRIC”
#SYMMETRA PX40 N+1, 2 HOUR RUN TIME.
3. REMOVE EXISTING TRANSFORMER, CONCRETE PAD AND LINE AND LOAD SIDE FEEDERS AT COMPLETION