Bid Notice-Vista Continuation High School Modernization- Bus Drop-Off Shade Canopy with ALTERNATE.pdf
PDF 142 KB Posted
- Solicitation number
- 6947
- Issued by
- Kern County, California
About this file
This is a Bid Notice for a construction project issued by the Kern High School District for the Vista Continuation High School Modernization project located at 200 P Street, Bakersfield, California. The project involves the design and installation of a turn-key pre-engineered bus drop-off shade canopy with associated alternate work. The scope encompasses all structural members, roof paneling, welding, bolting, grouting, concrete foundations with excavation and reinforcing steel, gutters, schedule 40 downspouts, powder coat finishing, and all necessary accessories including fasteners, brackets, equipment supports, hangers, and sheet metal flashings. Prime contractors are responsible for locating and protecting existing underground utilities, contacting underground service alert and governing authorities prior to construction commencement, providing off-site removal of spoils, coordinating with other trades including electrical contractors for light fixture installation, and submitting as-built documentation reflecting any field modifications.
The bid documentation specifies that prime contractors must comply with all contract documents and general conditions while managing their work through a cloud-based project management program called Procore. Contractors are required to acknowledge and comply with the California Incidental Take Permit and associated mortality reduction and den management plans. The contract excludes temporary fencing, temporary toilets, and dumpster provision, with the construction manager providing dumpsters. The project references DSA Number 03-125803 and is associated with DSA P.C. 04-123290 for design specifications. Contractors must provide proper sequencing to meet the Critical Path Method schedule and are responsible for all protective measures for their work, tools, materials, and equipment throughout the project duration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid Notice.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bus Drop-off Shade Canopy
PROJECT: Vista Continuation High School – New Campus 200 P Street Bakersfield, CA 93304
DSA NUMBER: 03-125803
OWNER: Kern High School District 5801 Sundale Ave.
Bakersfield, CA 93309
In addition to the items noted in the Contract Documents and General Conditions, which are applicable to ALL Prime Contractors, the Specific Scope of the Work shall include, but not necessarily be limited to the items listed below in accordance with the applicable drawings and specification section(s). Prime Contractors shall review all sections below and include any costs to comply in their base Bid. NOTE: The term “Provide” is defined as “to furnish and install, complete and ready for the intended use.” Be advised that every contractor is bidding as a Prime Contractor directly to the District.
SECTION A: SCOPE OF WORK
1. Provide the bus drop-off shade canopy per the DSA P.C. 04-123290 as provided in the contract documents.
2. Provide all structural members, roof paneling, welding, bolting, grouting, and accessories necessary for a complete installation.
3. Provide concrete foundations including excavation, reinforcing steel, backfill; coordinate with underground utility trades.
4. Provide gutters and schedule 40 downspouts.
5. Provide powder coat finish and finish touch-up required after installation shall be included in this bid package.
6. Prime Contractor is responsible for locating and protecting all existing underground utilities in area of construction.
7. Prime Contractor is responsible for contacting underground service alert and all governing authorities prior to start of any construction as specified.
8. Provide off-site removal of spoils generated from this work.
9. Provide all accessories including but not limited to fasteners, brackets, equipment supports, hangers, sheet metal flashings, and final connections.
10. Verify and coordinate all rough in information with other subcontractors. Coordinate with electrical contractor on light fixture installation.
11. Provide proper number of move-ins to meet installation as scheduled in the CPM schedule.
12. Prime Contractor shall provide all measures necessary to protect their work, tools, materials, equipment, and property as described in Articles 17 and 20 of the 33-General Conditions (Multiple Prime Project).
13. Prime Contractor will be responsible for all billings, submittals, schedule updates, drawing updates and required documents, as may be applicable to the project, through our cloud-based project management program, Procore.
14. Prime Contractor is to be aware of, and acknowledge the California Incidental Take Permit and the Mortality Reduction, Den Management, Den Replacement & Exclusion Fencing Plan provided as part of the contract documents. Prime contractor to take necessary measures to meet the avoidance guidelines.
15. Provide all as-built documentation reflecting any field modifications to the Construction Manager prior to final acceptance.
SECTION B: EXCLUSIONS
1. Temporary fencing
2. Temporary toilets
3. Dumpsters (use dumpsters provided by Construction Manager)
File details come from the government source that posted it. Updated .