Bid Notice-Rock Creek WRRF Gravity Belt Thickener Drain Piping Replacement.pdf

PDF 113 KB Posted

Attached to
Rock Creek WRRF Gravity Belt Thickener Drain Piping Replacement
Solicitation number
6372.094
Issued by
Washington County, Oregon

About this file

This is a Bid Notice Advertisement for Bids issued by Clean Water Services (Oregon) for the Rock Creek Water Resource Recovery Facility Gravity Belt Thickener Drain Piping Replacement Project No. 6372.094. The project requires furnishing all labor, materials, and equipment to provide temporary bypass piping for existing Gravity Belt Thickener drains, demolish and remove existing filtrate/emergency overflow welded steel drain pipes (10" to 14"), remove drain components within the Solids Process Recycling wet well, perform video inspection of approximately 15 linear feet of remaining pipe, and install a new 12" polyvinyl chloride filtrate/emergency overflow pipe to reconnect multiple wet wells and floor drains. The work site is located at 3235 SE River Road, Hillsboro, Oregon 97123, and will occur on the Ground Level and Lower Level Pipe Tunnel of the Thickening and Dewatering Buildings. Sealed bids must be submitted electronically via Equity Hubs' Bid Locker at https://bidlocker.us/details/6000 by 2:00 p.m. local time on September 8, 2026, with First-Tier Subcontractor Disclosure Forms due by 4:00 p.m. the same day. A mandatory prebid conference and site visit will be held at 9:00 a.m. local time on August 25, 2026 at the Rock Creek WRRF Engineering Building Dewatering Conference Room. Public bid opening will occur at 2:00 p.m. on September 8, 2026 via telephone conference at 503.681.4499.

The estimated construction cost is $300,000. Bidders must be registered with the Oregon Construction Contractors Board prior to bid submission and must comply with Oregon public works requirements under ORS 279C.800 to 279C.870, including amendments made by House Bill 2688 effective July 1, 2026. Bid security is required with the original delivered to Steve Waldron at the Owner's Office or Durham Treatment Plant Services Building within five business days after the Bid Deadline. The successful bidder will be required to furnish additional bonds and insurance as prescribed in the Bidding Documents. This is a public works project; asbestos requirements do not apply. All bidding documents and amendments are available on the Bid Locker website, and bidders are responsible for checking the website daily for updates. Technical and administrative inquiries should be directed to Steve Waldron at 503.547.8134 or waldrons@cleanwaterservices.org.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

6372.094 SECTION 00030: ADVERTISEMENT FOR BIDS

SECTION 00030

ADVERTISEMENT FOR BIDS

Sealed Bids for construction of the Rock Creek WRRF Gravity Belt Thickener Drain Piping

Replacement Project No. 6372.094 (Project) will be accepted by Steve Waldron, Procurement

Specialist, electronically via Equity Hubs’ Bid Locker at https://bidlocker.us/details/6000 (Bid

Locker) until 2:00:00 p.m., local time, on September 8, 2026 (Bid Deadline). Any Bids received after the specified time will not be considered. It is each Bidder’s responsibility, when submitting its Bid electronically via Bid Locker, to ensure timely delivery by submitting its Bid sufficiently in advance of the Bid Deadline. Before Bidders can submit their Bids, they will need to register with Bid Locker at https://bidlocker.us/Home/bidlockerus. There is no cost to register.

First-Tier Subcontractor Disclosure Forms must be electronically submitted to Bid Locker at or before 4:00:00 p.m. local time on the same day (Disclosure Deadline). If Bidder fails to submit a disclosure form with the information required by the stated Disclosure Deadline, the Bid will be deemed nonresponsive and will not be considered. Clean Water Services (Owner) will not accept

Bids by facsimile or email.

Bids will be publicly opened and read aloud by telephone conference at 2:00 p.m. local time on

September 8, 2026. Bidders can attend the opening by calling the telephone conference number

503.681.4499.

Contractor shall complete the work as specified or indicated in Owner’s Contract Documents for the Project. The Project generally consists of the following:

Furnish all labor, materials, and equipment necessary to:

A. Provide temporary bypass piping to direct flows from the existing Gravity Belt Thickener

(GBT) drains to the backwash pump suction header.

B. Demolish and remove the existing Filtrate/Emergency Overflow (FILT/EOF) welded steel drain pipe (10” to 14”) connecting the WASSTRIPATE wet well and GBTs to the Solids

Process Recycling (SPR) wet well.

C. Demolish and remove the 14” drain elbow and drop pipe inside the SPR wet well. Video inspect approximately 15 linear feet of the remaining 14” FILT/EOF pipe.

D. Install a new 12” polyvinyl chloride FILT/EOF pipe to reconnect the WASSTRIPATE wet well, GBT drains, and floor drains to the SPR wet well.

E. Install related equipment, temporary items, and appurtenances necessary to complete the

Work and to provide a complete and functional system in accordance with the Contract

Documents.

The Work Site is located at Rock Creek Water Resource Recovery Facility, 3235 SE River Road, Hillsboro, Oregon 97123 (Site). The Work will occur on the Ground Level and Lower Level

Pipe Tunnel of the Thickening and Dewatering Buildings.

The Work is a public works project subject to ORS 279C.800 to 279C.870. Bidders are advised that amendments made to ORS 279C.800 by Oregon State Legislature House Bill 2688 (HB

2688) became operative July 1, 2026 and public works contracts entered into on or after this date

6372.094 SECTION 00030: ADVERTISEMENT FOR BIDS

are subject to HB 2688 related law changes. Bidders’ attention is directed to the provisions of

Section 00300 Bids Forms paragraph 5.1.6.

The estimated construction cost of the Work is $300,000

The Bidding Documents are entitled “Rock Creek WRRF Gravity Belt Thickener Drain Piping

Replacement Project No. 6372.094.”

All Bidding Documents and Bid Results can be downloaded from Bid Locker at https://bidlocker.us/details/6000. It is the Bidder’s responsibility to refer daily to Bid Locker’s website to check for any available amendments or addenda, response to inquiries or questions, cancellations, or notices of intent to award, and any and all information regarding this opportunity. It is not Owner’s responsibility to notify participating Bidders by email or by any other means of any of the above. Copies of this advertisement can be obtained on the Bid Locker website or Owner’s website at https://dynamic.cleanwaterservices.org/Bids. If problems are experienced downloading the documents, please contact Steve Waldron at waldrons@cleanwaterservices.org.

Each Bid must be submitted on the prescribed Bid Form and accompanied by Bid security as prescribed in the Instructions to Bidders. Bidders must deliver the original of the Bid security to

Steve Waldron either by first class mail to Administration Building Complex, 2550 SW

Hillsboro Hwy, Hillsboro, Oregon 97123 (Owner’s Office), or by hand delivery to the Durham

Treatment Plant Services Building, 16060 SW 85th Avenue, Tigard, OR 97224, within five business days after the Bid Deadline.

The Successful Bidder will be required to furnish the additional bond(s) and insurance prescribed in the Bidding Documents.

Prior to submission of its Bid, Bidder shall be registered with the Oregon Construction

Contractors Board.

The Work does not involve asbestos, so the requirements of ORS 468A.700 through 468A.760 shall not apply.

Bidders must be qualified in accordance with the applicable parts of ORS 279C in order to submit a Bid for public work in Oregon.

For questions regarding technical and administrative issues, contact Owner: Steve Waldron, at

503.547.8134, or by email to waldrons@cleanwaterservices.org.

Prospective Bidders are required to attend a mandatory prebid conference and Site visit that will begin at 9:00 a.m. local time on August 25, 2026 in the Rock Creek WRRF Engineering

Building Dewatering Conference Room and last approximately one hour. Representatives of

Owner and Engineer will be present to discuss the Project.

Owner reserves its right to reject all Bids or any Bid not conforming to the intent and purpose of the Bidding Documents.

Dated this 17th day of August, 2026.

File details come from the government source that posted it. Updated .