This is a bid notice and project manual for the Phase V Communication Facilities Replacement Project (Group A) issued by the California Department of General Services on behalf of the California Department of Forestry and Fire Protection (CalFire) for three communication tower sites in Humboldt and Shasta Counties. The project encompasses replacement work at Pratt Mountain (1512A), Bunchgrass Mountain (1512B), and Mt. Pierce (1512E), with major scope elements including site demolition, excavation, structural steel and self-supporting tower erection, perimeter chain-link fencing, cast-in-place concrete foundations, concrete masonry unit vault construction, electrical panelboards, switchgear installation, standby generator systems, HVAC equipment, plumbing, antenna systems, and associated electrical and communications infrastructure. Sealed bids are due by 2:00 p.m. on September 30, 2026, with a public bid opening scheduled for October 1, 2026, at 10:00 a.m. in West Sacramento, California. Mandatory pre-bid site inspections are required on September 16–17, 2026, with meetings at Bunchgrass Mountain (1:00 p.m. on September 16) and Mt. Pierce and Pratt Mountain (9:00 a.m. on September 17). Contract award is anticipated within 45 days of bid opening. The project manual comprises five books including general procurement requirements, site-specific specifications for each of the three locations, and appendices containing geotechnical investigations, environmental commitment tables, and antenna equipment information.
Bids must be submitted on a lump sum basis with an allowance of $210,000 for unforeseen underground conditions across all three sites. Contractors must hold a California State License Classification A or B, with specialty contractor licenses C-16 (Fire Protection) and C-57 (Well Drilling) required either directly by the prime contractor or through first-tier subcontractors. A mandatory 3% Disabled Veteran Business Enterprise (DVBE) participation requirement applies, with a DVBE incentive program offering bid adjustments of 1–5% for participation exceeding the minimum threshold. A 5% small business preference is available for certified small businesses, and non-small businesses may qualify for the preference by committing to subcontract at least 25% of the net bid price to certified small businesses or microbusinesses. Performance and payment bonds, each in the amount of 100% of the contract price, are required. All contractors and subcontractors must be registered with the California Department of Industrial Relations and comply with prevailing wage requirements based on August 2026 DIR rates. The project is subject to California Air Resources Board fleet vehicle compliance requirements, and bidders must report any use of Generative Artificial Intelligence in bid deliverables. Funding is subject to availability through the state's normal budget process and the Architecture Revolving Fund. The project consultant is GHD, Inc., with Project Director Courtney Wetsell at the Department of General Services.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATE OF CALIFORNIA DEPARTMENT OF GENERAL SERVICES
REAL ESTATE SERVICES DIVISION
PROJECT MANAGEMENT AND DEVELOPMENT BRANCH
PROJECT MANUAL – Book I of V
INTRODUCTORY INFORMATION
BIDDING REQUIREMENTS
CONTRACTING REQUIREMENTS
SPECIFICATIONS
FOR:
PHASE V COMMUNICATION FACILITIES REPLACEMENT –
GROUP A:
1512A - PRATT MTN.
1512B - BUNCHGRASS MTN.
1512E - MT. PIERCE
CALIFORNIA DEPARTMENT OF FORESTRY AND FIRE
PROTECTION (CALFIRE)
HUMBOLDT & SHASTA COUNTIES, CALIFORNIA
Courtney Wetsell, Project Director 279.799.4650 West Sacramento, California
Consultants: GHD, Inc.
08/14/26 1512A, 1512B, 1512E
PROJECT TITLE PAGE
RESDMSTR: 02/03/2014v1 00 01 01 - 1 01512A, B, E
DOCUMENT 00 01 01
PROJECT TITLE PAGE
Title: REPLACE COMMUNICATION FACILITIES, PHASE V – GROUP A:
1. PRATT MOUNTAIN
2. BUNCHGRASS MOUNTAIN
3. MT. PIERCE
Client Agency: DEPARTMENT OF FORESTRY AND FIRE
PROTECTION (CALFIRE)
Location: PRATT MOUNTAIN/ BUNCHGRASS
MOUNTAIN/ MT.PIERCE
HUMBOLDT & SHASTA COUNTIES,
CALIFORNIA
Project Number: 1512A, 1512B, 1512E
Project Director: Courtney Wetsell State of California Department of General Services Real Estate Services Division Project Management and Development Branch 707 Third Street, 4th Floor West Sacramento, California 95605 Telephone Number: 279.799.
Email: Courtney.Wetsell@dgs.ca.gov
Consultant: GHD, Inc.
Matt Weber, Project Manager 943 Reserve Drive Roseville, CA 95678 Telephone Number: (916) 296-3222 Email: Matt.Weber@ghd.com
CERTIFICATIONS PAGE
RESDMSTR: 02/03/2014v1 00 01 05 - 1 001512A, B, E
DOCUMENT 00 01 05
CERTIFICATIONS PAGE
PROJECT TITLE:
1. PRATT MOUNTAIN
2. BUNCHGRASS MOUNTAIN
3. MT. PIERCE
CLIENT AGENCY :
LOCATION:
PROJECT NUMBER :
OWNER :
PROJECT DIRECTOR :
CONSULTANT
REPLACE COMMUNICATION FACILITIES, PHASE V –
GROUP A:
DEPARTMENT OF FORESTRY AND FIRE PROTECTION
(CALFIRE)
A - PRATT MOUNTAIN
(Coordinates: 41°29'56.58"N, 124° 3'36.30"W)
B - BUNCHGRASS MTN.
(Coordinates: 41°29'56.58"N, 124° 3'36.30"W)
E - MT. PIERCE
(Coordinates: 41°29'56.58"N, 124° 3'36.30"W)
HUMBOLDT & SHASTA COUNTIES, CALIFORNIA
1512A, 1512B, 1512E
STATE OF CALIFORNIA
Courtney Wetsell Department of General Services Project Management and Development Branch 707 Third Street, 4th Floor West Sacramento, California 95605 Telephone Number: 279.799.4650 Email: Courtney.Wetsell@dgs.ca.gov
GHD, Inc. Matt.Weber@ghd.com
RESDMSTR: 02/03/2014v1 00 01 05 - 2 001512A, B, E
REGULATORY REVIEWS:
RESDMSTR: 02/03/2014v1 00 01 05 - 3 001512A, B, E
See Site Books 2, 3, & 4 for site Specific Regulatory Stamps
See Site Books 2, 3, & 4 for site Specific Regulatory Stamps
DSA ACCESS COMPLIANCE SFM
TABLE OF CONTENTS
RESDMSTR: 6/20/2025 00 01 10 - 1 1512A, B, E
DOCUMENT 00 01 10
TABLE OF CONTENTS
PROCUREMENT AND CONTRACTING REQUIREMENTS GROUP
BOOK I
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
INTRODUCTORY INFORMATION
Pages Document 00 01 01 Project Title Page .......................................................................... 1 only 00 01 05 Certifications Page ........................................................................ 1 through 3 00 01 10 Table of Contents .......................................................................... 1 through 9 00 01 15 List of Drawings ............................................................................. 1 through 8
BIDDING REQUIREMENTS
Document 00 11 00 Invitation for Bids ........................................................................... 1 through 4 00 21 00 Instructions to Bidders ................................................................... 1 through 8 Appendix 00 21 00.01 Request for Bidding Interpretation ................................................. 1 only Document 00 22 00 Supplementary Instructions to Bidders .......................................... 1 only 00 22 10 DVBE Participation Program Requirements ................................... 1 through 3 00 41 00 Bid Form (Sample) ........................................................................ 1 through 10 00 43 13 Bidder’s Bond (Sample) ................................................................. 1 only 00 43 16 Certified Small Business Subcontractor(s) Summary (Sample) ..... 1 through 2 00 45 46 Payee Data Record (Sample) ........................................................ 1 through 2 00 91 13 Addendum (Sample)……………………………………………………1 through 3
CONTRACTING REQUIREMENTS
Document 00 52 00 Agreement (Sample) ..................................................................... 1 only 00 61 13 Performance Bond (Sample) ......................................................... 1 only 00 61 14 Payment Bond to Accompany Construction Contract (Sample) ..... 1 only 00 63 63 Construction Contract Change Order (Sample) ............................. 1 only 00 72 00 General Conditions of the Contract for Construction ...................... 1 through 31 00 73 00 Supplementary Conditions ............................................................. 1 through 13
SPECIFICATIONS GROUP
GENERAL REQUIREMENTS SUBGROUP
DIVISION 01 - GENERAL REQUIREMENTS
Section 01 10 00 Summary ....................................................................................... 1 through 8 01 21 00 Allowances .................................................................................... 1 through 2 01 25 00 Substitution Procedures ................................................................. 1 through 2
RESDMSTR: 6/20/2025 00 01 10 - 2 1512A, B, E
01 29 00 Payment Procedures ..................................................................... 1 through 4 01 31 00 Project Management and Coordination .......................................... 1 through 6 01 32 00 Construction Progress Documentation .......................................... 1 through 7 01 32 33 Photographic Documentation ........................................................ 1 through 3 01 33 00 Submittal Procedures .................................................................... 1 through 8 01 33 29.08 Buy Clean California Act Requirements ......................................... 1 through 2 01 40 00 Quality Requirements .................................................................... 1 through 6 01 50 00 Temporary Facilities and Controls ................................................. 1 through 7 01 56 39 Temporary Tree and Plant Protection ............................................ 1 through 5 01 57 23 Temporary Storm Water Pollution Control ..................................... 1 through 4 01 60 00 Product Requirements ................................................................... 1 through 5 01 64 00 Owner-furnished Products ............................................................. 1 through 3 01 73 00 Execution ...................................................................................... 1 through 7 01 74 19 Construction Waste Management and Disposal ............................ 1 through 5 Form 01 74 19.01 Construction Waste Estimate (A,B,& E) ......................................... 1 only 01 74 19.02 Waste Management Report (A, B & E) .......................................... 1 through 2 Section 01 74 20 Recycled Content Certification (A, B & E) ...................................... 1 through 3 Form 01 74 20.01 Recycled Content Certification Worksheet (Example) .................... 1 through 2 01 74 20.02 State Agency Buy Recycled Campaign Procurement Summary (Example) (A, B & E) ...................................................................................... 1 through 2 Section 01 75 00 Starting and Adjusting ................................................................... 1 through 3 01 77 00 Closeout Procedures ..................................................................... 1 through 12 Form STD 817 Prime Contractor’s Certifications – DVBE Subcontractor Report ... 1 through 5 01 77 00.01 Contractor’s Certification of Small Business Participation .............. 1 only 01 77 00.02 Contractor’ Certification of Small Business Participation ................ 1 only Section 01 79 00 Demonstration and Training .......................................................... 1 through 4
BOOK II - PRATT MTN.
DIVISION 02 – EXISTING CONDITIONS
Section 02 4000 Demolition ..................................................................................... 1 through 2 02 41 16 Groundwork for Structures ............................................................. 1 through 3
DIVISION 03 – CONCRETE
Section 03 10 00 Concrete Forming and Accessories ............................................... 1 through 5 03 20 00 Concrete Reinforcing ..................................................................... 1 through 3 03 30 00 Cast-In-Place Concrete ................................................................. 1 through 8
DIVISION 04 – MASONRY
Section 04 22 00 Concrete Unit Masonry .................................................................. 1 through 9
DIVISION 05 – METALS
Section 05 05 23 Metal Fastenings ........................................................................... 1 through 9 05 12 00 Structural Steel Framing ................................................................ 1 through 3 05 30 00 Metal Decking ................................................................................ 1 through 3 05 41 00 Steel Studs .................................................................................... 1 through 4
DIVISION 06 – WOOD, PLASTICS, AND COMPOSITES
RESDMSTR: 6/20/2025 00 01 10 - 3 1512A, B, E
Section 06 10 00 Rough Carpentry ........................................................................... 1 through 2
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
Section 07 21 00 Thermal Insulation ......................................................................... 1 through 2 07 92 00 Joint Sealants ................................................................................ 1 through 4
DIVISION 08 – OPENINGS
Section 08 11 13 Standard Hollow Metal Doors ........................................................ 1 through 2 08 12 13 Hollow Metal Frames ..................................................................... 1 through 2 08 71 00 Door Hardware .............................................................................. 1 through 3
DIVISION 09 – FINISHES
Section 09 20 00 Plaster and Gypsum Board ............................................................ 1 through 2 09 54 53 Fiberglass Reinforced Panel .......................................................... 1 through 2 09 67 16 Epoxy Flooring .............................................................................. 1 through 3 09 91 00 Painting ......................................................................................... 1 through 7
DIVISION 13 – SPECIAL CONSTRUCTION
Section 13 36 13.13 Self-Supporting Steel Communications Tower ............................... 1 through 8 13 50 00 Antennas ....................................................................................... 1 through 17
DIVISION 15 – RESERVED (NOT USED)
DIVISION 16 – RESERVED (NOT USED)
DIVISION 17 – RESERVED (NOT USED)
DIVISION 18 – RESERVED (NOT USED)
DIVISION 19 – RESERVED (NOT USED)
FACILITY SERVICES SUBGROUP
DIVISION 20 – RESERVED (NOT USED)
DIVISION 22 – PLUMBING
Section 22 00 00 Plumbing ....................................................................................... 1 through 15
DIVISION 23 – HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
Section 23 00 00 Heating, Ventilating and Air Conditioning ....................................... 1 through 17 23 05 00 General Requirements for Mechanical Work ................................. 1 through 15
DIVISION 24 – RESERVED (NOT USED)
DIVISION 25 – INTEGRATED AUTOMATION (NOT USED)
DIVISION 26 – ELECTRICAL
RESDMSTR: 6/20/2025 00 01 10 - 4 1512A, B, E
Section 26 01 00 Basic Electrical Requirements ....................................................... 1 through 9 26 01 26 Electrical Testing ........................................................................... 1 through 9 26 05 19 Low-Voltage Power Conductors and Cables .................................. 1 through 10 26 05 26 Grounding and Bonding ................................................................. 1 through 16 26 05 29 Electrical Hangers and Supports ................................................... 1 through 5 26 05 33.13 Conduit .......................................................................................... 1 through 10 26 05 33.16 Electrical Boxes ............................................................................. 1 through 3 26 05 36 Interior Cable Tray ......................................................................... 1 through 3 26 05 43 Underground Ducts and Structures ............................................... 1 through 6 26 05 48 Seismic Restraint for Electrical Equipment .................................... 1 only 26 05 53 Electrical Identification ................................................................... 1 through 7 26 24 16 Panelboards .................................................................................. 1 through 8 26 27 26 Wiring Devices .............................................................................. 1 through 7 26 27 26.10 Miscellaneous Electrical Devices ................................................... 1 through 4 26 28 16 Overcurrent Protection Devices ..................................................... 1 through 7 26 32 13 Standby System Generator Set ..................................................... 1 through 14 26 36 23 Automatic Transfer Switches ......................................................... 1 through 10 26 51 13 Interior Lighting .............................................................................. 1 through 9
DIVISION 27 – COMMUNICATIONS
Section 27 53 19 Internal Cellular, Paging and Antenna Systems ............................. 1 only
DIVISION 28 – ELECTRONIC SAFETY AND SECURITY (NOT USED)
DIVISION 29 – RESERVED (NOT USED)
SITE AND INFRASTRUCTURE SUBGROUP
DIVISION 30 – RESERVED (NOT USED)
DIVISION 31 – EARTHWORK
Section 31 01 50 Maintenance of Excavation Support and Protection ....................... 1 through 2 31 10 00 Site Preparation (Clearing and Grubbing) ...................................... 1 only 31 20 00 Earth Moving ................................................................................. 1 through 11 31 23 13 Subgrade Preparation ................................................................... 1 through 8 31 23 16.26 Rock Removal ............................................................................... 1 through 2 31 23 33 Trenching and Backfill ................................................................... 1 through 7 31 25 00 Erosion and Sedimentation Control ............................................... 1 through 5 31 25 13 Storm Water Pollution Prevention Plan .......................................... 1 through 2
DIVISION 32 – EXTERIOR IMPROVEMENTS
Section 32 11 23 Aggregate Base Courses ............................................................... 1 only 32 31 13 Chain Link Fence ........................................................................... 1 through 4
DIVISION 33 – UTILITIES (NOT USED)
DIVISION 34 – TRANSPORTATION (NOT USED)
RESDMSTR: 6/20/2025 00 01 10 - 5 1512A, B, E
DIVISION 35 – WATERWAY AND MARINE CONSTRUCTION (NOT USED)
DIVISION 36 – RESERVED (NOT USED)
DIVISION 37 – RESERVED (NOT USED)
DIVISION 38 – RESERVED (NOT USED)
DIVISION 39 – RESERVED (NOT USED)
PROCESS EQUIPMENT SUBGROUP (NOT USED)
BOOK III – BUNCHGRASS MTN
DIVISION 02 – EXISTING CONDITIONS
Section 02 40 00 Demolition ..................................................................................... 1 through 2 02 41 16 Groundwork for Structures ............................................................. 1 through 3
DIVISION 03 – CONCRETE
Section 03 10 00 Concrete Forming and Accessories ............................................... 1 through 5 03 20 00 Concrete Reinforcing ..................................................................... 1 through 3 03 30 00 Cast-In-Place Concrete ................................................................. 1 through 8
DIVISION 04 – MASONRY
Section 04 22 00 Concrete Masonry Unit .................................................................. 1 through 9
DIVISION 05 – METALS
Section 05 05 23 Metal Fastenings ........................................................................... 1 through 9 05 12 00 Structural Steel Framing ................................................................ 1 through 3 05 30 00 Metal Decking ................................................................................ 1 through 3 05 41 00 Steel Studs .................................................................................... 1 through 4
DIVISION 06 – WOOD
Section 06 10 00 Rough Carpentry ........................................................................... 1 through 2
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
Section 07 21 00 Thermal Insulation ......................................................................... 1 through 2 07 92 00 Joint Sealants ................................................................................ 1 through 4
DIVISION 08 – WINDOWS AND DOORS
Section 08 11 13.13 Standard Hollow Metal Doors ........................................................ 1 through 2 08 12 13 Hollow Metal Frames ..................................................................... 1 through 2 08 71 00 Door Hardware .............................................................................. 1 through 3
DIVISION 09 – FINISHES
Section 09 20 00 Plaster Gypsum Board................................................................... 1 through 2
RESDMSTR: 6/20/2025 00 01 10 - 6 1512A, B, E
09 54 53 Fiberglass Reinforced Panel .......................................................... 1 through 2 09 67 16 Epoxy Flooring .............................................................................. 1 through 3 09 91 00 Painting ......................................................................................... 1 through 7
DIVISION 13 – SPECIAL CONSTRUCTION
Section 13 36 13.13 Self-Supporting Steel Communications Tower ............................... 1 through 8 13 50 00 Antennas ....................................................................................... 1 through 17
DIVISION 22 – PLUMBING
Section 22 00 00 Plumbing ....................................................................................... 1 through 14
DIVISION 23 – HEATING, VENTILATING AND AIR CONDITIONING
Section 23 00 00 Heating, Ventilating and Air Conditioning ....................................... 1 through 17 23 05 00 General Requirements for Mechanical Work ................................. 1 through 15
DIVISION 26 – ELECTRICAL
Section 26 01 00 Basic Electrical Requirements ....................................................... 1 through 9 26 01 26 Electrical Testing ........................................................................... 1 through 9 26 05 19 Low-Voltage Power Conductors and Cables .................................. 1 through 10 26 05 26 Grounding and Bonding ................................................................. 1 through 16 26 05 29 Electrical Hangers and Supports ................................................... 1 through 4 26 05 33.13 Conduit .......................................................................................... 1 through 10 26 05 33.16 Electrical Boxes ............................................................................. 1 through 3 26 05 36 Interior Cable Tray ......................................................................... 1 through 3 26 05 43 Underground Ducts and Structures ............................................... 1 through 6 26 05 48 Seismic Restraint for Electrical Equipment .................................... 1 only 26 05 53 Electrical Identification ................................................................... 1 through 7 26 24 16 Panelboards .................................................................................. 1 through 8 26 27 26 Wiring Devises .............................................................................. 1 through 7 26 27 26.10 Miscellaneous Electrical Devices ................................................... 1 through 4 26 28 16 Overcurrent Protection Devices ..................................................... 1 through 7 26 32 13 Stanby System Generator Set ....................................................... 1 through 15 26 36 23 Automatic Transfer Switches ......................................................... 1 through 10 26 51 13 Interior Lighting .............................................................................. 1 through 9
DIVISION 27 – COMMUNICATIONS
Section 27 53 19 Internal Cellular, Paging and Antenna Systems ............................. 1 only
DIVISION 31 – EARTHWORK
Section 31 01 50 Maintenance of Excavation Support and Protection ....................... 1 through 2 31 10 00 Site Preparation (Clearing and Grubbing) ...................................... 1 only 31 20 00 Earth Moving ................................................................................. 1 through 11 31 23 13 Subgrade Preparation ................................................................... 1 through 8 31 23 16.26 Rock Removal ............................................................................... 1 through 2 31 23 33 Trenching and Backfill ................................................................... 1 through 7 31 25 00 Erosion and Sedimentation Control ............................................... 1 through 5 31 25 13 Strom Water Pollution Prevention Plan .......................................... 1 through 2
RESDMSTR: 6/20/2025 00 01 10 - 7 1512A, B, E
DIVISION 32 – EXTERIOR IMPROVEMENTS
Section 32 11 23 Aggregate Base Courses ............................................................... 1 only 32 31 13 Chain Link Fence ........................................................................... 1 through 4
BOOK IV - MT. PIERCE
DIVISION 02 – EXISTING CONDITIONS
Section 02 40 00 Demolition ..................................................................................... 1 through 2 02 41 16 Groundwork for Structures ............................................................. 1 through 3
DIVISION 03 – CONCRETE
Section 03 10 00 Concrete Forming and Accessories ............................................... 1 through 5 03 20 00 Concrete Reinforcing ..................................................................... 1 through 3 03 30 00 Cast-In-Place Concrete ................................................................. 1 through 8
DIVISION 04 – MASONRY
Section 04 22 00 Concrete Masonry Units ................................................................ 1 through 9
DIVISION 05 – METALS
Section 05 05 23 Metal Fastenings ........................................................................... 1 through 9 05 12 00 Structural Steel Framing ................................................................ 1 through 3 05 30 00 Metal Decking ................................................................................ 1 through 3 05 41 00 Steel Studs .................................................................................... 1 through 4
DIVISION 06 – WOOD, PLASTICS AND COMPOSITES
Section 06 10 00 Rough Carpentry ........................................................................... 1 through 2
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
Section 07 21 00 Thermal Insulation ......................................................................... 1 through 2 07 92 00 Joint Sealants ................................................................................ 1 through 4
DIVISION 08 – OPENINGS
Section 08 11 13.13 Standard Hollow Metal Doors ........................................................ 1 through 2 08 12 13 Hollow Metal Frames ..................................................................... 1 through 2 08 71 00 Door Hardware .............................................................................. 1 through 3
DIVISION 9 – FINISHES
Section 09 20 00 Plaster Gypsum Board................................................................... 1 through 2 09 54 53 Fiberglass Reinforced Panel .......................................................... 1 through 2 09 67 16 Epoxy Flooring .............................................................................. 1 through 3 09 91 00 Painting ......................................................................................... 1 through 7
DIVISIOIN 13 – SPECIAL CONSTRUCTION
Section 13 36 13.13 Self-Supporting Steel Communications Tower ............................... 1 through 8
RESDMSTR: 6/20/2025 00 01 10 - 8 1512A, B, E
13 50 00 Antennas ....................................................................................... 1 through 18
DIVISION 22 – PLUMBING
Section 22 00 00 Plumbing ....................................................................................... 1 through 14
DIVISION 23 – HEATING, VENTILATING AND AIR CONDITIONING
Section 23 00 00 Heating, Ventilating and Air Conditioning ....................................... 1 through 17 23 05 00 General Requirements for Mechanical Work ................................. 1 through 15
DIVISION 26 – ELECTRICAL
Section 26 01 00 Basic Electrical Requirements ....................................................... 1 through 9 26 01 26 Electrical Testing ........................................................................... 1 through 9 26 05 19 Low-Voltage Power Conductors and Cables .................................. 1 through 10 26 05 26 Grounding and Bonding ................................................................. 1 through 16 26 05 29 Electrical Hangers and Supports ................................................... 1 through 4 26 05 33.13 Conduit .......................................................................................... 1 through 10 26 05 33.16 Electrical Boxes ............................................................................. 1 through 3 26 05 36 Interior Cable Tray ......................................................................... 1 through 3 26 05 43 Underground Ducts and Structures ............................................... 1 through 6 26 05 48 Seismic Restraint for Electrical Equipment .................................... 1 only 26 05 53 Electrical Identification ................................................................... 1 through 7 26 24 16 Panelboards .................................................................................. 1 through 8 26 27 26 Wiring Devices .............................................................................. 1 through 7 26 27 26.10 Miscellaneous Electrical Devices ................................................... 1 through 4 26 28 16 Overcurrent Protection Devices ..................................................... 1 through 7 26 32 13 Standby System Generator Set ..................................................... 1 through 14 26 36 23 Automatic Transfer Switches ......................................................... 1 through 10 26 51 13 Interior Lighting .............................................................................. 1 through 9
DIVISION 27 – COMMUNICATIONS
Section 27 53 19 Internal Cellular, Paging and Antenna System ............................... 1 only
DIVISION 31 – EARTHWORK
Section 31 01 50 Maintenance of Excavation Support and Protection ....................... 1 through 2 31 10 00 Site Preparation (Clearing and Grubbing) ...................................... 1 only 31 20 00 Earth Moving ................................................................................. 1 through 11 31 23 13 Subgrade Preparation ................................................................... 1 through 8 31 23 16.26 Rock Removal ............................................................................... 1 through 2 31 23 33 Trenching and Backfill ................................................................... 1 through 7 31 25 00 Erosion and Sedimentation Control ............................................... 1 through 5 31 25 13 Strom Water Pollution Prevention Plan .......................................... 1 through 2
DIVISION 32 – EXTERIOR IMPROVEMENTS
Section 32 11 23 Aggregate Base Courses ............................................................... 1 only 32 31 13 Chain Link Fence ........................................................................... 1 through 4
RESDMSTR: 6/20/2025 00 01 10 - 9 1512A, B, E
BOOK V - APPENDICES
A. Geotechnical Investigations:
A Pratt Final Geotechnical
Investigation 1 through 37
B Bunchgrass Final Geotechnical Investigation
1 through 39
E Pierce Final Geotechnical Investigation
1 through 52
B. Environmental Commitment Tables
A Pratt EC Table 1 through 6 B Bunchgrass EC Table 1 through 6 E Mt. Pierce EC Table 1 through 5
C. Miscellaneous Tower Equipment Information
1 Antenna Testing &
Analysis 1 through 11
2 Antenna Wrapping Procedure
1 through 5
3 Cal OES PSC & General Contractor Inspection and Acceptance Criteria
1 through 4
4 Grounding Requirement for Vault and Tower
1 through 13
5 Tower Install Coax - Waveguide
1 through 3
END OF DOCUMENT
LIST OF DRAWINGS
RESDMSTR: 02/03/2014 00 01 15 - 1 01512A, B, E
DOCUMENT 00 01 15
PRATT MTN. – INCREMENT 1
Sheet Number Description
GENERAL
PM -G001 COVER SHEET
PM -G002 DRAWING INDEX, DESIGN CRITERIA AND SITE ORIENTATION
PM -G003 ABBREVIATIONS AND SYMBOLS
CIVIL
PM -C101 EXISTING SITE DEMOLITION AND CONSTRUCTION
SEQUENCING PLAN
PM -C102 SITE AND GRADING PLAN
PM -C501 CIVIL SECTIONS AND DETAILS
PM-C502 COMMON SITE DETAILS
ARCHITECTURAL
PM -A101 VAULT FLOOR PLAN, ROOF PLAN AND BUILDING
ELEVATIONS
PM -A102 GENERATOR VAULT PLANS, ELEVATIONS AND SECTION
PM -A501 ARCHITECTURAL DETAILS
PM -A502 ARCHITECTURAL DETAILS
STRUCTURAL
PM -S001 STRUCTURAL NOTES
PM -S101 VAULT FOUNDATION AND ROOF FRAMING PLAN AND
SECTION
PM -S102 TOWER FOUNDATION PLAN AND ELEVATION
PM -S501 COMMON STRUCTURAL DETAILS
PM -S502 STRUCTURAL DETAILS
PM -S503 STRUCTURAL DETAILS
PM -S701 FEEDLINE BRIDGE
PM -S702 FEEDLINE BRIDGE
MECHANICAL
PM -M001 MECHANICAL SYMBOLS, LEGEND, ABBREVIATIONS, AND
GENERAL NOTES
PM -M101 LARGE VAULT – HVAC
PM -M102 GENERATOR VAULT – HVAC
PM -M501 MECHANICAL DETAILS
PM -M601 MECHANICAL SCHEDULES
RESDMSTR: 02/03/2014 00 01 15 - 2 01512A, B, E
ELECTRICAL
PM -E001 ELECTRICAL SYMBOLS LEGEND, ABBREVIATIONS AND
GENERAL NOTES
PM -E101 ELECTRICAL SITE PLAN
PM -E102 LARGE VAULT – LIGHTING, POWER, EQUIPMENT AND
GROUNDING
PM -E103 GENERATOR VAULT LIGHTING, POWER, EQUIPMENT AND
GROUNDING
PM -E104 LARGE VAULT INTERIOR ELEVATIONS – 1
PM -E105 LARGE VAULT INTERIOR ELECATIONS – 2
PM -E501 ELECTRICAL DETAILS – 1
PM -E502 ELECTRICAL DETAILS – 2
PM -E503 ELECTRICAL DETAILS – 3
PM -E504 ELECTRICAL DETAILS – 4
PM -E505 ELECTRICAL DETAILS – 5
PM -E506 ELECTRICAL DETAILS – 6
PM -E601 SINGLE LINE DIAGRAM AND LOAD CALCULATION
PM -E602 ELECTRICAL SCHEDULES – 1
PM -E603 ELECTRICAL SCHEDULES – 2
PM -E604 ALARM STATUS REPORTING SCHEMATICS
PM -E605 ALARM POINT DESCRIPTIONS
PM -E606 INTERCONNECT DIAGRAM VHF ANTENNAS AND RF
CABLING – 1
PM -E607 INTERCONNECT DIAGRAM VHF ANTENNAS AND RF
CABLING – 2
PM -E608 INTERCONNECT DIAGRAM VHF ANTENNAS AND RF
CABLING – 3
PM -E609 SITE ANTENNA LAYOUT AND PRESSURIZATION
EQUIPMENT – 1
PM -E610 SITE ANTENNA LAYOUT AND PRESSURIZATION
EQUIPMENT – 2
PM-E611 -48VDC CRIS OES INTERCONNECT DIAGRAM
PM-E612 -48VDC MW OES INTERCONNECT DIAGRAM
PM-E613 +12VDC OES INTERCONNECT DIAGRAM
TOWER STRUCTURAL DRAWINGS
T-1 COVER SHEET & DRAWING INDEX
S-1 ELEVATION VIEW/NOTES
S-1.1 SST SECTION ALLOWABLE MEMBER FORCES
S-1.2 MONOPOLE SECTIONS ALLOWABLE FORCES
S-2 UPPER POLE
S-3 LOWER POLE
S-4 TOWER SECTION 13V - NESTED POLE
RESDMSTR: 02/03/2014 00 01 15 - 3 01512A, B, E
S-5 TOWER SECTION 13V
S-6 TOWER SECTION 15ST
S-6.1 TOWER SECTION 15ST CONT.
S-7 TOWER SECTION 17ST
S-7.1 TOWER SECTION 17ST CONT.
S-8 TOWER SECTION 19ST
S-9 TYPICAL GRATING/BRACING
S-10 TYPICAL HANDRAIL/DIAGONAL PIPE LIGHTING ROD
EXTENTSION, & SAFETY CLIMB KITS
S-11 CENTER MAST
S-12 COAX CAGE / CLIMBING LADDER, ANTI-CLIMB, & BUS BAR
S-13 ANTENNA LOCATION ELEVATION VIEWS
S-13.1 ANTENNA LOCATION PLAN VIEWS
S-14 FULLY LOADED FACE MOUNTED MICROWAVES
S-14.1 FULLY LOADED LEG MOUNTED MICROWAVES
S-14.2 FULLY LOADED VHF/UHF ANTENNA LOCATIONS
S-15 MW ICE BRIDGE DETAILS
S-15.1 MW ANTENNA ICE SHIELD DETAILS
S-16 MICROWAVE MOUNT KITS
S-17 UHF / VHF ANTENNA MOUNT KITS
S-18 LEG – ELEVATION ID PLATES
S-19 TOWER FOUNDATION SLAB/PIERS
RADIO AND MICROWAVE ANTENNA MOUNTING BRACKETS DRAWINGS
CO-TA1 COVER SHEET AND INDEX
CO-TA1.1 DSA 103
CO-TA2 TOWER STRUCTURAL NOTES
CO-TA3 SITE PRO BRACKET DETAILS
CO-TA5.2 TOWER ANTENNA MOUNTING DETAILS (AMPHENOL ANTEL)
CO-TA6 TOWER ANTENNA MOUNTING DETAILS
(ANDREW/COMMSCOPE)
CO-TA7.2 TOWER ANTENNA MOUNTING DETAILS (SINCLAIR)
CO-TA9 TOWER ANTENNA MOUNTING DETAILS (M2/KRECO)
CO-TA10 TOWER ANTENNA MOUNTING DETAILS
(COMMSCOPE/RFS/SINCLAIR)
CO-TA12 TOWER ANTENNA MOUNTING DETAILS (SCALA)
CO-TA18.1 TOWER ANTENNA MOUNTING DETAILS (TELEWAVE)
BUNCHGRASS MTN. – INCREMENT 2
GENERAL
BG-G001 COVER SHEET
BG-G002 DRAWING INDEX, DESIGN CRITERIA AND SITE ORIENTATION
BG-G003 ABBREVIATIONS AND SYMBOLS
CIVIL
BG-C101 EXISTING SITE DEMOLITION AND CONSTRUCTION
RESDMSTR: 02/03/2014 00 01 15 - 4 01512A, B, E
SEQUENCING PLAN
BG-C102 SITE AND GRADING PLAN
BG-C501 COMMON SITE DETAILS
BG-C502 COMMON SITE DETAILS
ARCHITECTURAL
BG-A101 VAULT FLOOR PLAN AND ROOF PLAN AND BUILDING
ELEVATIONS
BG-A501 ARCHITECTURAL DETAILS
BG-A502 ARCHITECTURAL DETAILS
STRUCTURAL
BG-S001 STRUCTURAL NOTES
BG-S101 VAULT FOUNDATION, ROOF FRAMING PLAN AND
SECTION
BG-S102 TOWER FOUNDATION PLAN AND ELEVATION
BG-S501 COMMON STRUCTURAL DETAILS
BG-S502 STRUCTURAL DETAILS
BG-S503 STRUCTURAL DETAILS
BG-S701 FEEDLINE BRIDGE
BG-S702 FEEDLINE BRIDGE
MECHANICAL
BG-M001 MECHANICAL SYMBOLS, LEGEND, ABBREVIATIONS, AND
GENERAL NOTES
BG-M101 MEDIUM VAULT – HVAC
BG-M501 MECHANICAL DETAILS
BG-M601 MECHANICAL SCHEDULES
ELECTRICAL
BG-E001 ELECTRICAL SYMBOLS LEGEND, ABBREVIATIONS AND
GENERAL NOTES
BG-E101 ELECTRICAL SITE PLAN
BG-E102 MEDIUM VAULT – LIGHTING, POWER, EQUIPMENT AND
GROUNDING
BG-E103 MEDIUM VAULT INTERIOR ELEVATIONS
BG-E501 ELECTRICAL DETAILS – 1
BG-E502 ELECTRICAL DETAILS – 2
BG-E503 ELECTRICAL DETAILS – 3
BG-E504 ELECTRICAL DETAILS – 4
BG-E505 ELECTRICAL DETAILS – 5
BG-E506 ELECTRICAL DETAILS – 6
BG-E601 SINGLE LINE DIAGRAM AND LOAD CALCULATION
BG-E602 ELECTRICAL SCHEDULES – 1
BG-E603 ELECTRICAL SCHEDULES – 2
BG-E604 ALARM STATUS REPORTING SCHEMATICS
BG-E605 ALARM POINT DESCRIPTIONS
BG-E606 INTERCONNECT DIAGRAM VHF ANTENNAS AND RF
CABLING – 1
RESDMSTR: 02/03/2014 00 01 15 - 5 01512A, B, E
BG-E607 INTERCONNECT DIAGRAM VHF ANTENNAS AND RF
CABLING – 2
BG-E608 SITE ANTENNA LAYOUT AND PRESSURIZATION
EQUIPMENT – 1
BG-E609 SITE ANTENNA LAYOUT AND PRESSURIZATION
EQUIPMENT – 2
BG-E610 -48VDC CRIS OES INTERCONNECT DIAGRAM
BG-E611 -48VDC MW OES INTERCONNECT DIAGRAM
BG-E612 +12VDC OES INTERCONNECT DIAGRAM
WESTERN UTILITY TELECOM, INC. DRAWING INDEX
T-1 COVER SHEET & DRAWING INDEX
S-1 ELEVATION VIEW/NOTES
S-1.1 SST SECTION ALLOWABLE MEMBER FORCES
S-1.2 MONOPOLE SECTION ALLOWABLE MEMBER FORCES
S-2 UPPER POLE
S-3 LOWER POLE
S-4 TOWER SECTION 13V NESTED POLE
S-5 TOWER SECTION 13V
S-6 TOWER SECTION 15ST
S-6.1 TOWER SECTION 15ST CONT.
S-7 TOWER SECTION 17ST
S-7.1 TOWER SECTION 17ST CONT.
S-8 TOWER SECTION 19ST
S-9 TYPICAL GRATING/BRACING
S-10 TYPICAL HAND RAIL/DIAGNOL PIPE LIGHTING ROD
EXTENSION, SAFETY & SAFETYCLIMB KITS
S-11 CENTER MAST
S-12 COAX CAGE/CLIMBING LADDER, ANTI-CLIMB, & BUS BAR
S-13 ANTENNA LOCATION ELEVATION VIEWS
S-13.1 ANTENNA LOCATION PLAN VIEWS
S-14 FULLY LOADED FACE MOUNTED MICROWAVES
S-14.1 FULLY LOADED LEG MOUNTED MICROWAVES
S-14.2 FULLY LOADED VHF/UHF ANTENNA LOCATIONS
S-15 MW ICE BRIDGE DETAILS
S-15.1 MW ANTENNA ICE SHIELD DETAILS
S-16 MICROWAVE MOUNT KITS
S-17 UHF/VHF ANTENNA MOUNT KITS
S-18 LEG/ELEVATION ID PLATES
S-19 TOWER FOUNDATION SLAB/PIERS
SATE OF CALIFORNIA
CO-TA1 COVER SHEET AND INDEX
CO-TA1.1 DSA 103
CO-TA2 TOWER STRUCTURAL NOTES
CO-TA3 SITE PRO BRACKET DETAILS
CO-TA5.2 TOWER ANTENNA MOUNTING DETAILS (AMPHENOL ANTEL)
CO-TA6 TOWER ANTENNA MOUNTING DETAILS
(ANDREW/COMMSCOPE)
CO-TA7.2 TOWER ANTENNA MOUNTING DETAILS (SINCLAIR)
RESDMSTR: 02/03/2014 00 01 15 - 6 01512A, B, E
CO-TA9 TOWER ANTENNA MOUNTING DETAILS (M2/KRECO)
CO-TA10 TOWER ANTENNA MOUNTING DETAILS
(COMMSCOPE/RFS/SINCLAIR)
CO-TA10.1 TOWER ANTENNA MOUNTING DETAILS (RFS/SINCLAIR)
CO-TA14.1 TOWER ANTENNA MOUNTING DETAILS (SCALA)
CO-TA18 TOWER ANTENNA MOUNTING DETAILS (TELEWAVE)
MT. PIERCE – INCREMENT 3
GENERAL
MP-G001 COVER SHEET
MP-G002 DRAWING INDEX, DESIGN CRITERIA AND SITE ORIENTATION
MP-G003 ABBREVIATIONS AND SYMBOLS
CIVIL
MP-C101 EXISTING SITE DEMOLITION AND CONSTRUCTION
SEQUENCING
MP-C102 SITE AND GRADING PLAN
MP-C501 CIVIL SECTIONS AND DETAILS
MP-C502 COMMON SITE DETAILS
ARCHITECTURAL
MP-A101 VAULT FLOOR PLAN, ROOF PLAN AND BUILDING
ELEVATIONS
MP-A102 GENERATOR VAULT PLANS, ELEVATIONS AND SECTION
MP-A501 ARCHITECTURAL DETAILS
MP-A502 ARCHITECTURAL DETAILS
CIVIL
MP-S001 STRUCTURAL NOTES
MP-S101 VAULT FOUNDATION AND ROOF FRAMING PLAN AND
SECTION
MP-S102 TOWER FOUNDATION PLAN AND ELEVATION
MP-S501 COMMON STRUCTURAL DETAILS
MP-S502 STRUCTURAL DETAILS
MP-S503 STRUCTURAL DETAILS
MP-S701 FEEDLINE BRIDGE
MP-S702 FEEDLINE BRIDGE
MECHANICAL
MP-M001 MECHANICAL SYMBOLS, LEGEND, ABBREVIATIONS, AND
GENERAL NOTES
MP-M101 LARGE VAULT – HVAC
MP-M102 GENERATOR VAULT – HVAC
RESDMSTR: 02/03/2014 00 01 15 - 7 01512A, B, E
MP-M501 MECHANICAL DETAILS
MP-M601 MECHANICAL SCHEDULES
ELECTRICAL
MP-E001 ELECTRICAL SYMBOLS LEGEND, ABBREVIATIONS AND
GENERAL NOTES
MP-E101 ELECTRICAL SITE PLAN
MP-E102 LARGE VAULT – LIGHTING, POWER, EQUIPMENT AND
GROUNDING
MP-E103 GENERATOR VAULT – LIGHTING, POWER, EQUIPMENT AND
GROUNDING
MP-E104 LARGE VAULT – INTERIOR ELEVATIONS – 1
MP-E105 LARGE VAULT – INTERIOR ELEVATIONS – 2
MP-E501 ELECTRICAL DETAILS – 1
MP-E502 ELECTRICAL DETAILS – 2
MP-E503 ELECTRICAL DETAILS – 3
MP-E504 ELECTRICAL DETAILS – 4
MP-E505 ELECTRICAL DETAILS – 5
MP-E506 ELECTRICAL DETAILS – 6
MP-E601 SINGLE LINE DIAGRAM AND LOAD CALCULATION
MP-E602 ELECTRICAL SCHEDULES – 1
MP-E603 ELECTRICAL SCHEDULES – 2
MP-E604 ALARM STATUS REPORTING SCHEMATICS
MP-E605 ALARM POINT DESCRIPTIONS
MP-E606 INTERCONNECT DIAGRAM VHF ANTENNAS AND RF
CABLING – 1
MP-E607 INTERCONNECT DIAGRAM VHF ANTENNAS AND RF
CABLING – 2
MP-E608 INTERCONNECT DIAGRAM VHF ANTENNAS AND RF
CABLING – 3
MP-E609 INTERCONNECT DIAGRAM VHF ANTENNAS AND RF
CABLING – 4
MP-E610 INTERCONNECT DIAGRAM VHF ANTENNAS AND RF
CABLING – 5
MP-E611 SITE ANTENNA LAYOUT AND PRESSURIZATION
EQUIPMENT – 1
MP-E612 SITE ANTENNA LAYOUT AND PRESSURIZATION
EQUIPMENT – 2
PM-E613 -48VDC CRIS OES INTERCONNECT DIAGRAM
PM-E614 -48VDC MW OES INTERCONNECT DIAGRAM
PM-E615 +12VDC OES INTERCONNECT DIAGRAM
TOWER STRUCTURAL SHEETS
T-1 COVER SHEET/DRAWING INDEX
S-1 ELEVATION VIEW/NOTES
S-1.1 SST SECTION ALLOWABLE MEMBER FORCES
S-1.2 MONOPOLE SECTION ALLOWABLE MEMBER FORCES
S-2 UPPER POLE
S-3 LOWER POLE
S-4 TOWER SECTION 13V – NESTED POLE
RESDMSTR: 02/03/2014 00 01 15 - 8 01512A, B, E
S-5 TOWER SECTION 13V
S-6 TOWER SECTION 15ST
S-6.1 TOWER SECTION 15ST CONT.
S-7 TOWER SECTION 17ST
S-7.1 TOWER SECTION 17ST CONT.
S-8 TOWER SECTION 19ST
S-9 TYPICAL GRATING/BRACING
S-10 TYPICAL HAND RAIL/DIAGANOL PIPE, LIGHTING ROD
EXTENSION, & SAFETY CLIMB KITS
S-11 CENTER MAST
S-12 COAX CAGE/CLIMBING LADDER, ANTI-CLIMB, & BUS BAR
S-13 ANETNNA LOCATION ELEVATION VIEWS
S-13.1 ANTENNA LOCATION PLAN VIEWS
S-14 FULLY LOADED FACE MOUNTED MICROWAVES
S-14.1 FULLY LOADED LEG MOUNTED MICROWAVES
S-14.2 FULLY LOADED VHF/UHF ANTENNA LOCATIONS
S-15 MW ICE BRIDGE DETAILS
S-15.1 MW ANTENNA ICE SHIELD DETAILS
S-16 MICROWAVE MOUNT KITS
S-17 UHF/VHF ANTENNA MOUNT KITS
S-18 LEG/ELEVATION ID PLATES
S-19 TOWER FOUNDATION SLAB/PIERS
STRUCTURAL DETAILS FOR RADIO AND MICROWAVE ANTENNA MOUNTING
BRACKETS
CO-TA1 COVER SHEET AND INDEX
CO-TA1.1 DSA 103
CO-TA2 TOWER STRUCTURAL NOTES
CO-TA3 SITE PRO BRACKET DETAILS
CO-TA4 TOWER ANTENNA MOUNTING DETAILS (ANDREW)
CO-TA5.2 TOWER ANTENNA MOUNTING DETAILS (AMPHENOL ANTEL)
CO-TA6 TOWER ANTENNA MOUNTING DETAILS
(ANDREW/COMMSCOPE)
CO-TA6.1 TOWER ANTENNA MOUNTING DETAILS
(ANDREW/COMMSCOPE)
CO-TA7 TOWER ANTENNA MOUNTING DETAILS (HUSTLER/ANTENNA
EXPERT/DIAMOND)
CO-TA7.2 TOWER ANTENNA MOUNTING DETAILS (SINCLAIR)
CO-TA9 TOWER ANTENNA MOUNTING DETAILS (M2/KRECO)
CO-TA10 TOWER ANTENNA MOUNTING DETAILS
(COMMSCOPE/RFS/SINCLAIR)
CO-TA11.2 TOWER ANTENNA MOUNTING DETAILS (DB SPECTRA/SCALA)
CO-TA13 TOWER ANTENNA MOUNTING DETAILS (SCALA)
CO-TA14 TOWER ANTENNA MOUNTING DETAILS (SCALA)
CO-TA14.1 TOWER ANTENNA MOUNTING DETAILS (SCALA)
CO-TA15 TOWER ANTENNA MOUNTING DETAILS (SINCLAIR)
CO-TA17 TOWER ANTENNA MOUNTING DETAILS (SINCLAIR)
CO-TA18 TOWER ANTENNA MOUNTING DETAILS (TELEWAVE)
INVITATION FOR BIDS
RESDMSTR: 10/01/2025 00 11 00 - 1 01512A, B, E
STATE OF CALIFORNIA
DEPARTMENT OF GENERAL SERVICES
PROJECT MANAGEMENT AND DEVELOPMENT BRANCH
DOCUMENT 00 11 00
SEALED BIDS: DGS will receive sealed bids at 707 Third Street, West Sacramento, California 95605, before 2:00 P.M., September 30th, 2026. Bids received after this date/time will not be considered received on time.
A public bid opening will be held on October 1st, 2026 at 10:00 AM. at 707 Third Street, West Sacramento, CA 95605. Bidders may attend virtually or in person. Bidders attending the bid opening in-person will need to meet and sign in at the security guard station in the lobby at the mailing address below. At the public bid opening, all bids received before 2:00 P.M., September 30th, 2026 will be opened and recorded onto a Preliminary Bid Tabulation. Bidders do not need to attend the bid opening as the Preliminary Bid Tabulation will be made available immediately after the bid opening is completed and it will be emailed to invited bidders.
The bid opening may be attended virtually via the following link:
Join: https://teams.microsoft.com/meet/264492875348787?p=UAkX2oxkmfDlBIlCCe Meeting ID: 264 492 875 348 787 Passcode: vN9qX22n
HAND DELIVERED BIDS: Shall be placed in the DGS/OBAS Bid/Proposal Drop Box located in the lobby at 707 3rd Street in West Sacramento. The Drop Box will be opened at 2:00 p.m. Tuesday through Thursday and bids/proposals in the box will be certified as being received before 2:00 p.m.
that day.
If mailing bids, ensure the outside of the mailing reads:
ATTENTION: PAVAN RANDHAWA
PHASE V COMMUNICATION FACILITIES REPLACEMENT: GROUP A
1512A - PRATT MTN.
1512B - BUNCHGRASS MTN.
1512E - MT. PIERCE
CALIFORNIA DEPARTMENT OF FORESTRY AND FIRE
PROTECTION (CALFIRE)
HUMBOLDT & SHASTA COUNTIES, CALIFORNIA
PROJECT NO. 1512A, 1512B, 1512E
DO NOT OPEN
DEPARTMENT OF GENERAL SERVICES
OFFICE OF BUSINESS AND ACQUISITION SERVICES
707 3RD STREET, MS 508, WEST SACRAMENTO, CA 95605
The bids shall include all Work pursuant to the Drawings and Project Manual, and Addenda as may be issued prior to bid opening date.
Scope of Work: Major components of Project Work consist of Demolition, excavation, structural steel, fencing, cast in place concrete, CMU block wall vault construction, panelboards, switchgear, generator, tower erection and related work.
RESDMSTR: 10/01/2025 00 11 00 - 2 01512A, B, E
License: Contractors' State License Classification required to bid Project is A or B.
[Refer to Document 00 22 00, Supplementary Instructions to Bidders, Subparagraph 2.1.3 [and 2.1.4], regarding performance of work of a [Fire Protection specialty contractor license classification C-16] [and] [Well Drilling specialty contractor license classification C-57].
Certificate of Reported Compliance (CRC) – Fleet Vehicles: As a condition of Contract award, prior to Contract execution, Contractor shall submit copies of the valid CRCs for any fleet retained by the Contractor or any listed Subcontractor, for which any vehicles subject to the California Air Resources Board In-Use Off-Road Diesel Fueled Fleet Regulations, Section 2449(i), Title 12, California Code of Regulations, are used in the completion of the work included in the Contract.
More information on the In-Use Off-Road Diesel-Fueled Fleets Regulation can be found at the following link: https://ww2.arb.ca.gov/our-work/programs/use-road-diesel-fueled-fleets-regulation
Generative Artificial Intelligence (GenAI): The State of California seeks to realize the potential benefits of GenAI, through the development and deployment of GenAI tools, while balancing the risks of these new technologies.
Bidder must notify the State in writing if it: (1) intends to provide GenAI as a deliverable to the State; or (2), intends to utilize GenAI, including GenAI from third parties, to complete all or a portion of any deliverable that materially impacts: (i) functionality of a State system, (ii) risk to the State, or (iii) Contract performance. For avoidance of doubt, the term “materially impacts” shall have the meaning set forth in State Administrative Manual (SAM) § 4986.2 Definitions for GenAI.
Failure to report GenAI to the State may result in disqualification. The State reserves the right to seek any and all relief to which it may be entitled to as a result of such non-disclosure.
Upon notification by a Bidder of GenAI as required, the State reserves the right to incorporate GenAI Special Provisions into the final contract or reject bids/offers that present an unacceptable level of risk to the State.
Government Code § 11549.64 defines “Generative Artificial Intelligence (GenAI)” as an artificial intelligence system that can generate derived synthetic content, including text, images, video, and audio that emulates the structure and characteristics of the system’s training data.
Availability of Funds: Award of this contract is subject to the availability of funds through the State’s normal budget process and/or transfer of funds to the Department of General Services through the Architecture Revolving Fund.
Pre-bid Site Inspection: Bids will only be accepted from those Contractors having attended BOTH MANDATORY pre-bid site inspection tours on September 16th & 17th, 2026.
The tour of the sites begins with a project orientation meeting on September16th, 2026 and then proceeds by escort to the first tower site at Bunchgrass Mtn. (also known as Hatchet Mtn.).
Representatives of the State and prospective bidders shall meet at 1:00 PM at 19400 Bunch Grass Lookout Rd., Montgomery Creek, CA.
The tour will continue September 17th, 2026, at which time representatives of the State and prospective bidders shall meet at 9:00 A.M. at 50 West Center Street, Rio Dell, CA, and then proceed by escort to the 2nd tower, Mt. Pierce. Following that tour, the 3rd and final meeting location shall be at 324 Alderpoint Rd, Garberville, CA for a tour of Pratt Mountain. The tour and pre-bid site inspection will conclude upon the return escort down the mountain and off private land.
The State’s requirements for Disabled Veteran Business Enterprise (DVBE) participation and other Contract requirements will be presented. Prime Contractors are encouraged to have their Key
RESDMSTR: 10/01/2025 00 11 00 - 3 01512A, B, E
Administrator and DVBE office coordinator attend to receive this information and to have their questions answered. Attendance for the entire inspection is required in order for bidders to be eligible to submit a bid.
Executive Order N-6-22: The Bidder must be advised of Executive Order N-6-22 Russia Sanctions. On March 4, 2022, Governor Gavin Newsom issued Executive Order (EO) N-6-22 regarding Economic Sanctions against Russia and Russian entities and individuals. “Economic Sanctions” refers to sanctions imposed by the U.S. government in response to Russia’s actions in Ukraine, as well as any sanctions imposed under state law. By submitting a bid, Bidder represents that it is not a target of Economic Sanctions. Should the State determine Bidder is a target of Economic Sanctions or is conducting prohibited transactions with sanctioned individuals or entities, that shall be grounds for rejection of the Bidder’s bid any time prior to contract execution, or, if determined after contract execution, shall be grounds for termination by the State.
Drawings and Project Manual: Bid forms, plans, specifications, and addenda will be available for download at http://www.caleprocure.ca.gov. Click on “Start Search”. In the Event Name field, enter the project number and click “Search”. While viewing the Event Details, click on “View Event Package” to view bid forms.
It is recommended that all vendors register as a bidder through the Cal eProcure website at https://www.caleprocure.ca.gov/pages/bidder-vendor.aspx. This will allow for automatic notifications if there is any modification to the Event such as the posting of an addendum or additional documentation.
Bid: Submit on Lump Sum basis with Allowances as set forth in Bid Forms.
DVBE: Participation in Disabled Veterans Business Enterprises (DVBE) program may be required for this project. Refer to Project Manual Document 00 21 00, Project Manual Document 00 22 10 and Bid Forms for requirements. Bidders are advised to commence the required DVBE procedures immediately upon receipt of drawings and project manual.
DVBE Bid Incentive: The DVBE Incentive program is being applied on this project. Refer to Project Manual Document 00 21 00, Article 18.5.
Small Business Preference: Refer to Project Manual Document 00 21 00, Article 5.5
Non-Small Business Subcontractor Preference: Refer to Project Manual Document 00 21 00, Article 5.6
Bonds: Successful bidder shall furnish payment and performance bonds, each in the amount of 100 percent of the Contract price.
Non-Discrimination Program (Government Code § 12990): Refer to Project Manual Document 00 72 00, General Conditions of the Contract for Construction.
Labor Code: Pursuant to Labor Code § 1774, the Contractor to whom the contract is awarded, and any subcontractor under him, shall pay not less than the specified general prevailing rates of per diem to all workers employed in the execution of the contract. Pursuant to Labor Code § 1770 et seq., the Department of Industrial Relations (DIR) has ascertained general prevailing rate of per diem wages in the locality in which the work is to be performed.