This is an Invitation for Bid (IFB) document issued by the San Joaquin Regional Rail Commission (SJRRC) for the demolition, removal, hauling, and disposal of all above-ground structures and facilities located at 6362 and 6400 Blacktop Road in Rio Linda, California (Parcel -002). The project encompasses approximately 2.139 acres containing two concrete tilt-up building structures, paving, fencing, and landscaping. The scope includes mobilization and project management, site cleanup and closeout documentation, OSHA pre-demolition engineering surveys, health and safety planning, stormwater pollution protection planning, 24-hour site security, utility service disconnection and abandonment, demolition and removal of both buildings with hauling and disposal, hazardous materials abatement and removal, and installation of permanent chain-link fencing with gates. The IFB was issued on September 17, 2026, with a pre-bid site walk meeting scheduled for October 1, 2026, at 10:00 AM PDT at the project site. Written requests for clarification are due by October 8, 2026, at 2:00 PM PDT, with SJRRC issuing responses by October 15, 2026. Sealed bids are due by October 22, 2026, at 2:00 PM PDT for public opening. The contract duration is 120 working days from the Notice to Proceed, with liquidated damages of $5,000 per calendar day for failure to achieve substantial completion within the specified timeframe.
Bidding is on a stipulated sum basis with a base bid covering 11 lump-sum line items and allowances totaling $300,000 for unforeseen conditions, permits and fees, engineer-directed extra work, and removal of vehicles and miscellaneous materials. A bid bond of 10 percent of the total bid amount is required, with successful bidders required to post faithful performance and labor and materials bonds each equal to 100 percent of the contract price. Bidders must possess a valid California C-21 (Building Moving/Demolition) contractor's license or an A or B license with a C-21 licensed subcontractor; a C-22 license is required for asbestos abatement work. All bidders and subcontractors must be registered and qualified to perform public works pursuant to California Labor Code Section 1725.5 and must comply with prevailing wage requirements. This is a public works project subject to California Labor Code Sections 1770–1780, with prevailing wage rates determined by the State of California Director of Industrial Relations. The project is not federally funded. SJRRC reserves the right to waive any informality, reject any or all bids, and award the contract to the lowest responsive and responsible bidder. Bid protests must be submitted in writing within 15 calendar days after staff recommendation for award is made public.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IFB No. 27-R-28-00 Issued for Bid 00 01 01 - 1
INVITATION FOR BID FOR
NATOMAS STATION AND LAYOVER FACILITY
- EARLY DEMOLITION
CONTRACT NO. 27-R-28-00
PROJECT SPECIFICATIONS
95% DRAFT SUBMITTAL
12 JUN 2009
ISSUED for Bid September 17, 2026
Title Page 00 01 01
Contract No. 27-R-28-00 Issued for Bid 00 01 01 - 2
THIS PAGE DELIBERATELY LEFT BLANK
IFB No. 27-R-28-00 Issued for Bid 00 01 10 - 1
DOCUMENT 00 01 10
SAN JOAQUIN REGIONAL RAIL COMMISSION
TABLE OF CONTENTS
DOCUMENT DIVISION 00 PROCUREMENT AND CONTRACTING REQUIREMENTS
Introductory Information
00 01 01 Title Page
00 01 07 Seals Page
00 01 10 Table of Contents
00 01 11 Schedule of Events
Procurement Requirements
00 11 16 Notice Inviting Sealed Bids
00 21 13 Instructions to Bidders
00 27 00 Preconstruction Documents Checklist
00 41 13 Bid Form – Stipulated Sum
00 41 16 Schedule of Quantities and Prices (Sample Schedule of Values)
00 43 13 Bid Bond
00 43 16 Bidder's Declaration
00 43 36 List of Subcontractors
00 45 13 Bidder's Responsibility Statement
00 45 19 Non-Collusion Affidavit
00 45 51 State Debarment and Suspension Certification
00 45 53 Agreement to Comply with California Labor Law Requirements
00 45 54 Statement Acknowledging Penal and Civil Penalties Concerning the Contractors'
Licensing Laws
00 45 56 Not Used
00 45 63 Not Used
00 45 64 Not Used
00 45 65 Not Used
00 45 66 Disclosure of Lobbying Activities
Table of Contents 00 01 10
Contract No. 27-R-28-00 Issued for Bid 00 01 10 - 2
00 45 67 Not Used
00 45 68 Not Used
00 45 69.01 Not Used
00 45 69.02 Not Used
00 45 69.03 Request for Clarification and/or Bidders Questions
00 45 70 Not Used
00 45 71 Not Used
Contracting Requirements
00 50 50 Notice of Intent to Award for Construction
00 52 13 Contract – Stipulated Sum
00 61 14 Contract Surety Bond (Faithful Performance)
00 61 15 Contract Surety Bond (Labor and Materials)
00 72 00 General Conditions
00 73 00 Supplementary Conditions
SECTION DIVISION 01 GENERAL REQUIREMENTS
Summary
01 11 00 Summary of Work
01 11 16 Work by SJRRC
01 12 00 Multiple Contract Summary
01 14 23 Rules and Hours of Operation
01 14 24 Coordination with SJRRC
01 14 25 Procedures in Construction
01 14 26 Maintenance and Protection of Railroad Traffic
01 14 27 Legal Relations and Responsibility
01 19 00 Not Used
01 19 05 Environmental Resource Protection
Price and Payment Procedures
01 21 00 Allowances
01 22 00 Unit Prices
01 25 00 Substitution Procedures
01 26 00 Contract Modification Procedures
Contract No. 27-R-28-00 Issued for Bid 00 01 10 - 3
01 29 00 Payment Procedures
Administrative Requirements
01 31 00 Project Management and Coordination
01 32 00 Construction Progress Documentation
01 33 00 Submittal Procedures
Quality Requirements
01 41 00 Regulatory Requirements
01 42 00 References and Definitions
01 46 00 Quality Assurance and Quality Control
01 47 00 Contractor Key Personnel Qualifications and Requirements
01 48 00 Control of Work
Temporary Facilities and Controls
01 50 00 Temporary Facilities and Controls
01 57 13 Temporary Erosion and Sedimentation Control
Product Requirements
01 60 00 Not Used
Execution and Closeout Requirements
01 71 23 Survey and Field Engineering
01 73 29 Not Used
01 74 19 Construction Waste Management and Disposal
01 74 36 Not Used
01 77 00 Closeout Procedures
01 78 00 Closeout Submittals
01 79 00 Not Used
EXHIBITS
Exhibit 01 Scope of Work
Contract No. 27-R-28-00 Issued for Bid 00 01 10 - 4
END OF DOCUMENT
IFB No. 27-R-28-00 Issued for Bid 00 01 11 - 1
DOCUMENT 00 01 11
SCHEDULE OF EVENTS
This document is intended to provide firms with an overview of pre-award submission dates. This document does not include required dates for all items--it is not complete and is for convenience only. It is the Bidders’ responsibility to examine all of the bid documents for detailed information. All information provided herein is subject to change. If a change occurs, SJRRC will make reasonable efforts to deliver Addenda to all Bidders who are known by the SJRRC to have received a complete set of Bid Documents. SJRRC makes no guarantee that all Bidders will receive all Addenda.
Schedule of Events (pre-award)
IFB Available September 17, 2026
Pre-Bid Site Walk Meeting October 1, 2026 at 10:00 AM PDT
Written Request for Questions/Clarifications Due October 8, 2026 by 2:00 PM PDT
SJRRC will Issue Responses to Questions October 15, 2026
Bid Submission Due/Public Bid Opening October 22, 2026 By 2:00 PM PDT
Original and Stamped Submissions Due October 22, 2026
Schedule of Events 00 01 11
Contract No. 27-R-28-00 Issued for Bid 00 01 11 - 2
THIS PAGE LEFT DELIBERATELY BLANK
IFB No. 27-R-28-00 Issued for Bid 00 11 16 - 1
DOCUMENT 00 11 16
NOTICE INVITING SEALED BIDS
FOR
NATOMAS STATION AND LAYOVER FACILITY - EARLY DEMOLITION
PUBLIC NOTICE IS HEREBY GIVEN THAT SAN JOAQUIN REGIONAL RAIL COMMISSION
("SJRRC") invites sealed bids for a contract for the following described work:
The Project includes the demolition, removal, hauling and disposing of all above ground structures and facilities located on the east side of Blacktop Road, south of Elkhorn Boulevard, in unincorporated Sacramento County, California. Their addresses are listed as 6362 and 6400 Blacktop Road, Rio Linda, California in Parcel -002.
Environmental reports, hazardous materials assessments, waste characterization reports, and other related reference documents may be issued separately by Addendum during the bidding period as they become available. Certain reports may still be in preparation at the time of advertisement, and document titles may be revised prior to issuance. Bidders shall review all Addenda and incorporate the information, requirements, and associated costs contained therein into their bids.
Parcel -002 is nearly rectangular in shape and bounds Blacktop Road along its westerly side and the UPRR tracks along its easterly side. Parcel -002 contains approximately 2.139 acres according to County of Sacramento Assessor’s Maps. Parcel -002 has two concrete tilt-up building structures, paving, and fencing. There is some landscaping along the west boundary and parcel is finished with curb, gutter and sidewalk along Blacktop Road.
Notice Inviting Sealed Bids 00 11 16
Contract No. 27-R-28-00 Issued for Bid 00 11 16 – 2
A. TYPE OF BID: Bids shall be on a stipulated sum basis and shall cover the entire work;
segregated bids will not be accepted.
Bidders shall refer to Document 00 21 13 (Instructions to Bidders) for required documents and items to be submitted.
B. CONTRACT TIME: The work shall be completed within the number of Days stipulated in the
Contract Document 00 52 13.
C. PROCUREMENT AND CONTRACT DOCUMENTS: Will be available beginning on or about
September 17, 2026, and may be examined, free of charge, at the office of SJRRC located at:
San Joaquin Regional Rail Commission (SJRRC) 949 East Channel St.
Stockton, CA 95202
Beginning on or about September 17, 2026, to acquire Procurement and Contract Documents visit https://www.sjrrc.com/Contract-Opportunities/.
SJRRC uses PlanetBids™, a fully automated web-based vendor portal and bid management system. Whether you are a new vendor with SJRRC or an existing vendor, you must register your firm in order to receive contracting notifications, to view contracting opportunities, and to obtain copy of open solicitations. Prospective bidders are solely responsible for maintaining up to date and accurate information.
D. PREBID MEETING: Bidders are strongly encouraged to attend a pre-bid meeting on October
1, 2026, at 10:00 a.m. PDT, at:
San Joaquin Regional Rail Commission Owned Property Natomas Station and Layover Facility 6400 Blacktop Road Rio Linda, CA 95673
The meeting will be held at the site of work, located at 6400 Blacktop Road, Rio Linda, CA, 95673, to provide prospective bidders an opportunity to review conditions at the site and the work to be performed under the Contract. Those attending are required to wear Personal Protective Equipment (PPE).
All individuals planning to attend the pre-bid meeting in-person are asked to notify SJRRC at Procurements@sjrrc.com so that staff can properly plan.
E. BID SECURITY: All bids shall be accompanied by a cashier’s or certified check payable to the order of SJRRC, amounting to ten percent (10%) of the bid, or by a bond in said amount, on
Contract No. 27-R-28-00 Issued for Bid 00 11 16 – 3 the form provided by SJRRC as detailed in Document 00 21 13 Instructions to Bidders and payable to SJRRC, signed by the Bidder and a corporate surety.
F. NOT USED
G. RECEIPT OF BIDS AND BID OPENING: SJRRC will receive bids up to but no later than 2:00 p.m. PST, October 22, 2026, in electronic format (eBids) EXCLUSIVELY at SJRRC’s Vendor Portal at: https://www.sjrrc.com/Contract-Opportunities.
Bids will be publicly opened, examined and declared at 2:00 p.m. PDT, October 22, 2026.
SJRRC reserves the right to waive any informality or irregularity and to reject any and all bids.
Bidders, interested parties, and members of the public may participate via teleconference by calling (209) 800-8142 and entering conference ID: 677 398 827# when prompted or by joining the meeting at https://teams.microsoft.com/meet/243966381612840?p=rH4StfE6FVlHvE9X1V, entering Meeting ID: 243 966 381 612 840 and Meeting Passcode: 9Va6eZ7a . Results will be posted on the Vendor Portal.
The bid results displayed are preliminary and subject to change pending review and verification of applicable bid requirements, such as: Licensing, Bonding, Qualifications, etc.
Contracts will be awarded to the lowest responsive, responsible bidder; unless stated otherwise in the Invitation for Bid.
H. BONDS: The successful bidder will be required to post a faithful performance bond and a labor and materials bond, each in the sum of 100% of the contract price, on forms provided by SJRRC as detailed in Document 00 21 13 Instructions to Bidders.
At the time of bid submission, all bidders must upload and submit an electronic PDF copy of the aforementioned bid security. Whether in the form of a cashier’s check, a properly certified check or an approved corporate surety bond payable to SJRRC, the bid security must be uploaded to the Vendor Portal.
By 2:00 p.m. on October 26, 2026 all bidders must provide SJRRC with the original bid security.
Failure to submit the electronic version of the bid security at the time of bid submission AND failure to provide the original by 2:00 p.m. on October 26, 2026 will cause the bid to be rejected and deemed non-responsive.
Original Bid Bond shall be submitted to:
SJRRC Procurement and Contracts Department RE: Contract No. 27-R-28-00 949 East Channel Street
Contract No. 27-R-28-00 Issued for Bid 00 11 16 – 4
I. SUBSTITUTION OF SECURITIES. SJRRC will permit the successful bidder to substitute securities for any retention monies withheld to ensure performance of the contract, in accordance with Public Contract Code Section 22300.
J. NO FEDERAL COMPLIANCE: This Contract is NOT Federally assisted.
K. PREVAILING WAGE AND CONTRACTOR REGISTRATION.
1. This Project is a public works project and is subject to prevailing wage rates, compliance monitoring, and enforcement by the Department of Industrial Relations pursuant to California Labor Code §§ 1770-1780.
2. Subject to paragraph J, the provisions of the California Labor Code will be incorporated in and govern this contract award. Contractor agrees to pay each craft, classification or type of workman the prevailing wage determined by the State of California, Director of Industrial Relations, in the published wage scale determination, a copy of which is available at the principal office of SJRRC, and which shall be made available to any interested party on request, and to comply with California Labor Code §§ 1720-1781.
3. NOT USED.
4. SJRRC shall accept bids only from Bidders that (along with all Subcontractors listed in Document 00 43 36 Subcontractor List) are currently registered and qualified to perform public work pursuant to Labor Code § 1725.5.
5. Subject to Labor Code §§ 1771.1(c) and (d), any bid not complying with subparagraph 3 above shall be returned and not considered; provided that if Bidder is a joint venture (Business & Professions Code § 7029.1) or if federal funds are involved in the Contract (Labor Code § 1771.1(a)), SJRRC may accept a non-complying bid provided that Bidder and all listed Subcontractors are registered at the time of Contract award.
L. CONTRACTOR'S LICENSE: Contractor shall possess a C-21 (Building Moving/Demolition), or A or B provided the demolition work is performed by a C-21 licensed subcontractor California Contractor's License, valid and in good standing, at the time of award of the Contract, and shall maintain said license in good standing throughout the duration of the Contract. A C-22 license is required to perform asbestos abatement.
Contractor and/or its subcontractor(s) performing hazardous material abatement work shall additionally possess the following, valid and in good standing at the time of award and throughout the duration of the Contract:
1. Asbestos Certification (ASB), pursuant to Business and Professions Code Section
7058.5; and
2. Lead-Related Construction Certification, pursuant to 17 CCR Section 3500 et seq.
M. NOT USED.
Contract No. 27-R-28-00 Issued for Bid 00 11 16 – 5
N. REJECTION/CONSIDERATION OF BIDS: SJRRC reserves the right to waive any informality or irregularity in any bid received and to be the sole judge of the respective merits of the respective bids received. The contract award, if made, will be made to the lowest responsible and responsive bidder. SJRRC reserves the right to take all bids received under advisement for a period not exceeding one hundred and twenty (120) calendar days from and after the date upon which such bids are opened and declared, and all bids and bid guarantees submitted shall remain valid and subject to enforcement during that period of time.
O. QUESTIONS: Contact the San Joaquin Regional Rail Commission (SJRRC) through PlanetBids™ Vendor Portal or via email at Procurements@sjrrc.com. Notate this IFB number in all communications.
BY:
Martine Champion-Reese, Procurement Specialist
IFB No. 27-R-28-00 Issued for Bid 00 11 16 - 6
IFB No. 27-R-28-00 Issued for Bid 00 21 13 - 1
DOCUMENT 00 21 13
INSTRUCTIONS TO BIDDERS
A. BID DOCUMENTS
1. All Bidders must be pre-registered with the SJRRC Vendor Portal in order to submit an electronic bid.
2. To register with SJRRC and acquire Procurement and Contract Documents (collectively
“the Bid Documents”) visit https://www.sjrrc.com/Contract-Opportunities/.
3. Bid Documents may be examined at:
SJRRC
949 E. Channel Street
B. EXAMINATION OF DOCUMENTS, SITE, AND LOCAL CONDITIONS
1. Bidders must satisfy themselves as to the location of the work, transportation facilities, soil conditions, underground conditions, groundwater, and all other matters which may influence their bids. Submittal of a bid constitutes acknowledgment that the Bidder has investigated and is satisfied as to the conditions to be encountered, as to the character, quality and quantity of work to be performed and the material, equipment and other devices to be furnished and as to the requirements of the Procurement Documents and the Contract Documents.
2. Bidders shall, before submitting a Bid, carefully study and satisfy themselves by personal examination of the work site, drawings, specifications, and other contract documents, and by any other means as they may believe necessary, as to the actual physical conditions, requirements, and difficulties under which the work must be performed. See specific requirements contained in Document 00 72 00 General Conditions Article 1-2 Pre-Bid Investigations.
C. INTERPRETATION OR CORRECTION OF PROCUREMENT OR CONTRACT DOCUMENTS
1. In the event Bidder has any question as to the meaning or understanding of any part of the Procurement Documents or the Contract Documents, or the nature, conditions of the work or amount of work necessary for satisfactory completion of the job or Bidder finds an error, inconsistency, or ambiguity in any of the Procurement Documents or Contract Documents, Bidder’s exclusive remedy with respect thereto shall be to make a written Request for Clarification in the time frame set forth in Paragraph 3, below prior to submitting its Bid. Requests for Clarification or interpretation of the Procurement Documents or the Contract Documents shall be addressed in writing (following
Instruction to Bidders 00 21 13
Contract No. 27-R-28-00 Issued for Bid 00 21 13 - 2 instructions in Document 00 45 69.03) and shall be submitted through the SJRRC Vendor Portal at http://www.sjrrc.com/Contract-Opportunities.
It shall be the Bidder’s responsibility to ensure that any such request is submitted to SJRRC in the time frame set forth in Paragraph 3, below, in order to allow for the SJRRC to issue a written Addenda. The procedure and time limits set forth in this Article C are mandatory and are bidder’s sole and exclusive remedy in the event of any question as to the meaning of any part of the Procurement Documents or the Contract Documents, or any error, inconsistency, or ambiguity in any of the documents, Bidder’s failure to comply with these procedures shall constitute a waiver of any right to further pursue the matter, including filing a bid protest as otherwise provided in this Document 00 21 13, a Government Code Claim or legal proceedings. A bidder may not rely on a Request for Clarification submitted by another Bidder but must timely submit its own. No Bidder shall at any time after submittal of a bid make any claim or assertion that there was any misunderstanding or lack of information regarding the nature, conditions of the work or amount of work necessary for satisfactory completion of the job.
2. If necessary, SJRRC shall make clarifications, interpretations, corrections, and changes to the Procurement Documents or the Contract Documents by Addenda issued as provided below. Purported clarifications, interpretations, corrections, and changes to the Procurement Documents or Contract Documents made in any other manner shall not be binding on SJRRC, and Bidders shall not rely upon them. These Procurement Documents and Contract Documents, and any addenda are the sole source of information provided by SJRRC as the basis for any Bid. Any other information derived from SJRRC, the Engineer, or from their employees or records will not relieve the Bidder from risks or responsibilities of fulfilling the contract.
3. Requests for clarification or interpretation must be submitted in writing no later than the date and time established in Document 00 01 11 Schedule of Events, to allow time for SJRRC to respond.
D. ADDENDA
1. SJRRC reserves the right to revise or amend the Invitation for Bids (IFB) or specifications up to the time set for opening the bids. Such revisions and amendments, if any, shall be issued by addenda to this solicitation, and shall be part of the Contract Documents.
Copies of such addenda shall be posted via PlanetBids and a notification sent to all prospective Bidders of the IFB. In the event that an addendum sets forth material changes, additions or deletions is issued when there is seventy-two (72) hours or less to the bid opening date and, pursuant to Public Contract Code section 4104.5., SJRRC will extend the bid opening date by no less than three (3) business days. Clarification notices that do not significantly impact the Bidders ability to submit a bid shall not result in an extension of the bid opening date.
Contract No. 27-R-28-00 Issued for Bid 00 21 13 - 3
2. Only questions answered by formal written addenda shall be binding. Oral and other interpretations or clarification shall be without legal effect. It is the Bidder’s responsibility to be informed of any addenda(s) that have been issued and to include all such information in its Bid.
3. Addenda will be issued only in writing. SJRRC will make reasonable efforts to deliver Addenda to all Bidders who are known by the SJRRC to have received a complete set of Bid Documents. SJRRC makes no guarantee that all Bidders will receive all Addenda.
4. Copies of Addenda will be made available for inspection at the office where Bid
Documents are on file for inspection, as indicated on the Invitation to Bid.
5. Each Bidder shall be responsible for ascertaining, prior to submitting its bid, that it has received all issued Addenda. Each Bidder shall acknowledge receipt of all Addenda on Document 00 41 13 Bid Form. Failure to acknowledge receipt of Addenda on the bid form may render the bid non-responsive.
E. NOT USED
F. NOT USED
G. TYPE OF BID
1. Bids shall be made on a stipulated sum basis and shall include the entire work.
Segregated bids will render the bid nonresponsive, and it will not be accepted.
H. FORM OF BID
1. Each bid must be made on Document 00 41 13, Bid Form.
2. Each bid must be accompanied by all items identified as “Submit with Bid” in Document 00 27 00 Preconstruction Documents Checklist.
I. PREPARATION OF BID DOCUMENTS:
1. Bidders are cautioned against making erasures or alterations of any kind on their bids.
Bids which contain omissions, erasures, alterations, conditions or additions not called for, or irregularities of any nature may be rejected at the sole discretion of SJRRC.
2. Unauthorized conditions, limitations, or provisions attached to the bid will render it non-responsive and cause its rejection. The completed bid forms shall be without interlineations, alterations, or erasures. Alternative bids will not be considered unless specifically requested. Oral, telegraphic, or telephonic bids or modifications will not be considered.
Contract No. 27-R-28-00 Issued for Bid 00 21 13 - 4
J. SIGNATURE AND AUTHORITY REQUIREMENTS
1. If the bid is made by an individual, it shall be signed and his or her full name and address shall be given; if it is made by a partnership it shall be signed with the partnership name by a general partner thereof, who shall also list the name and address of each other member of such partnership; if made by a corporation, it shall be signed under the name of the corporation by at least two of its duly authorized officers, one of whom is the corporation's chairman of the board, president, or any vice president, and the other of whom is the secretary, any assistant secretary, the chief financial officer, the treasurer or any assistant treasurer. The corporation’s name shall be set forth along with the signatures.
2. If Contract is awarded to a corporation (or to a joint venture with a corporate member)
SJRRC may, before SJRRC executes Contract, require Bidder to furnish evidence of its corporate existence, of its right to enter into contracts in the State of California, and of the authority of the officers signing the Contract and bonds for the corporation to do so.
K. BID SECURITY
1. Each bid shall be accompanied by a cashier's or certified check payable to SJRRC, amounting to ten percent (10%) of the bid, or by a bond in said amount payable to SJRRC, signed by the Bidder and a California-admitted corporate surety. The bid bond shall be in the form of Document 00 43 13 Bid Bond.
2. Failure to enter into a valid contract, including the execution of Document 00 52 13
Contract and submittal of all bonds and insurance coverages required by the Contract Documents, with the SJRRC within the required time, shall constitute a material breach and subject the bid bond to forfeiture to the extent provided by law.
3. SJRRC may thereafter award the Contract to the next lowest responsive responsible bidder. In such event, the amount of Bidder's security shall be applied by SJRRC to the difference between the Bidder's bid and the bid of the next lowest responsive responsible bidder, and the surplus, if any, shall be returned to the Bidder if cash or a check is used, or to the surety on Bidder's bond if a bond is used.
4. The bid security of all Bidders will be returned when SJRRC receives a fully executed contract accompanied by the proper bonds, evidence of insurance, and all other items required to be submitted therewith, from the ultimately successful Bidder.
Notwithstanding the foregoing, SJRRC may, in its sole discretion, return prior to that time Bidder’s bid security to (i) all Bidders who have been determined to be non-responsive or non-responsible, or (ii) any other Bidder which SJRRC does not believe has a reasonable likelihood of receiving an award of Contract.
Contract No. 27-R-28-00 Issued for Bid 00 21 13 - 5
L. BONDS AND INSURANCE
1. Upon award of the contract, the successful bidder shall provide a Faithful Performance and a Labor and Materials Bond, each in the sum of 100% of the contract sum.
2. All bonds shall be issued by a California admitted surety insurer. Bonds shall be in the forms of Document 00 61 14 Contract Surety Bond (Faithful Performance) and Document 00 61 15 Contract Surety Bond (Labor and Materials).
3. Also, upon award of the contract, the successful bidder shall furnish evidence that it has obtained all insurance required under the contract. All policies required under the contract shall be issued by insurers authorized to do business in the State of California and with a rating of at least A: VII in the latest edition of Best’s Insurance Guide. See SC- 13 and Document 00 27 00 Preconstruction Documents Checklist for a listing of such items.
4. All bonds and evidence of insurance required under this Article must be submitted with the executed Contract as provided in Article Z below.
M. SUBCONTRACTORS
1. In accordance with California law, each Bidder must submit with its bid, on Document 00 43 36 List of Subcontractors, the name and business address of each proposed subcontractor who will perform work or labor or render services to the Contractor in excess of one-half percent (½ %) of the total bid or, in the case of streets or highways, one-half percent (½ %) or $10,000, whichever is greater, and shall state the portion of the work which will be done by each such subcontractor. The successful bidder shall be prohibited from performing work on this project with a subcontractor who is ineligible to perform work on the project pursuant to Section 1777.1 or 1777.7 of the Labor Code.
N. IDENTIFICATION AND SUBMITTAL OF BID
1. Each bid and all required documents must be received in electronic format (eBids) EXCLUSIVELY at the SJRRC Vendor Portal at: https://www.sjrrc.com/Contract- Opportunities/.
2. Required Documents will be made available in the Vendor Portal and either labeled as
“Envelope A” or “Envelope B” requirement.
3. Each Bidder shall include in its Envelope A Document 00 41 13 Bid Form – Stipulated Sum and any other document which Document 00 27 00 Preconstruction Documents Checklist indicates.
4. Each Bidder shall include in its Envelope B Document 00 45 13 Bidder’s Responsibility
Contract No. 27-R-28-00 Issued for Bid 00 21 13 - 6
Statement and any other document which Document 00 27 00 Preconstruction Documents Checklist indicates.
5. SJRRC’s Vendor Portal is responsible for bid tabulations. Upon the bidder’s entry of their bid, the system will ensure that all required fields are entered. The system will not accept a bid for which any required information is missing. This includes all necessary pricing, subcontractor listing(s) and any other essential documentation and supporting materials and forms requested or contained in these Bid Documents in Section H.2 above.
6. BIDS REMAIN SEALED UNTIL BID DEADLINE. eBids are transmitted into the SJRRC’s
Vendor Portal via hypertext transfer protocol secure (https) mechanism using SSL 128- 256 bit security certificates issued from Verisign/Thawte which encrypts data being transferred from client to server. Bids submitted prior to the “Bid Due Date and Time” are not available for review by anyone other than the submitter who has until the “Bid Due Date and Time” to change, rescind or retrieve its proposal should it desire to do so.
7. BIDS MUST BE SUBMITTED BY BID DUE DATE AND TIME. Once the bid deadline is reached, no further submissions are accepted into the system. Once the Bid Due Date and Time has lapsed, bidders, proposers, the general public, and SJRRC staff are able to immediately see the results online. SJRRC staff may then begin reviewing the submissions for responsiveness, and other issues. SJRRC may require any Bidder to furnish statement of experience, financial responsibility, technical ability, equipment, and references.
8. Submission of the electronic bid into the system may not be instantaneous. Due to the speed and capabilities of the user’s internet service provider (ISP), bandwidth, computer hardware and other variables, it may take time for the bidder’s submission to upload and be received by the SJRRC’s Vendor Portal. It is the bidder’s sole responsibility to ensure their bids are received on time by the SJRRC’s Vendor Portal. SJRRC is not responsible for bids that do not arrive by the required date and time.
9. ACCESSIBILITY AND AMERICANS WITH DISABILITIES ACT (ADA) COMPLIANCE:
To request a copy of this solicitation in an alternative format, contact the Procurement and Contracts Department at least five (5) working days prior to the Bid/Proposal due date to ensure availability.
10. Pursuant to the terms contained in the Contract Documents, high-cost materials may be purchased immediately following SJRRC’s selection of a Bidder; those materials on hand but not incorporated into the work are eligible for a progress payment.
Contract No. 27-R-28-00 Issued for Bid 00 21 13 - 7
O. MODIFICATION OR WITHDRAWAL OF BID
1. Any bid may be withdrawn without forfeiture of bid security at any time prior to the bid due date and time. The withdrawal of any bid shall not prejudice the right of a Bidder to file a new bid prior to the deadline established in the Notice Inviting Sealed Bids.
2. Unauthorized conditions, limitations, or provisions attached to the bid will render it informal and may cause its rejection. The completed bid forms shall be without interlineations, alterations, or erasures. Alternative bids will not be considered unless specifically requested. Oral, telegraphic, or telephonic bids or modifications will not be considered.
P. NOT USED
Q. DISQUALIFICATION OF BIDDERS
1. A Bidder will be disqualified if the Bidder, acting as a prime contractor, has an interest in more than one bid. In that event, all of that Bidder's bids will be rejected and the Bidder will be disqualified. This restriction does not apply to subcontractors or suppliers who may submit quotations to more than one Bidder, and while doing so, may also submit a bid as a prime contractor.
R. STATE AND FEDERAL REQUIREMENTS
1. Contractor's License: A California class [“A/B”] contractor’s license is required to bid this contract. Bids will not be accepted from a Contractor who is not licensed in accordance with the laws of the State of California.
2. Prevailing Wage: The provisions of the California Labor Code will be incorporated in and govern this contract award. Bidder agrees to pay to each craft, classification, or type of workman the prevailing wage determined by the State of California, Director of Industrial Relations, in the published wage scale determination, a copy of which is available at the principal office of SJRRC and which shall be made available to any interested party on request, and to comply with California Labor Code §§ 1777.5, 1776.
Contractor shall also post a copy of the prevailing wages at the job site. If the Federal Prevailing wage established under the Davis Bacon Act is higher than the wage established under the wage established under the California Labor Code for any craft, contractor will comply with the Davis Bacon Act.
3. Required Contractor and Subcontractor Registration. SJRRC shall accept Bids only from Bidders that (along with all Subcontractors listed in Document 00 43 36 Subcontractors List) are currently registered and qualified to perform public work pursuant to Labor Code Section 1725.5. Subject to Labor Code Sections 1771.1(c) and (d), any Bid not complying with this paragraph shall be returned and not considered; provided that
Contract No. 27-R-28-00 Issued for Bid 00 21 13 - 8 if Bidder is a joint venture (Business & Professions Code Section 7029.1) or if federal funds are involved in the Contract (Labor Code Section 1771.1(a)), SJRRC may accept a non-complying Bid provided that Bidder and all listed Subcontractors are registered at the time of Contract award.
4. Federal Compliance: NOT USED.
5. Other Requirements: See the forms listed in the Contract and provided in Division 00.
S. PRE-BID MEETING
1. A pre-bid conference will be held on the date established in Document 00 11 16 Notice Inviting Sealed Bids, Section D of the IFB.
T. LIQUIDATED DAMAGES
1. This Contract includes provisions for liquidated damages as specified in Document 00 52 13, Article 1.g.
U. BID OPENING
1. See the Notice Inviting Sealed Bids for the date, time, and place for opening of bids.
2. SJRRC will open all Bidders’ Envelope A’s as indicated above, initially evaluate them for responsiveness, and determine an apparent low bidder. SJRRC will not open Envelope B’s publicly, and except for the apparent low bidder’s Envelope B (or as otherwise provided in Paragraph 3 below), they will remain unopened.
3. If any apparent low bidder is determined to be non-responsive or non-responsible, SJRRC may proceed to examine the next apparent low bidder’s Envelope B and proceed for all purposes as if this apparent low bidder were the original apparent low bidder.
V. DISCREPANCIES IN BIDS
1. If there is more than one item on the Bid Form, the bidder shall furnish a price for all bid items. Failure to do so will render the bid non-responsive and shall cause its rejection.
2. The bidder shall state in figures the specific sums which it proposes to supply the labor, materials, supplies, or machinery, and completely perform the Contract. The total amount of each item bid, and the total amount of the bid shall be stated in figures. Discrepancies between the multiplication of units of work and unit prices (if any) will be resolved in favor of the unit prices. Any discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum. Subject to the
Contract No. 27-R-28-00 Issued for Bid 00 21 13 - 9 other rules in this paragraph 2, discrepancies between written words (if any) and figures will be resolved in favor of the words.
3. SJRRC will make its best efforts to notify the bidders of any found discrepancy in a timely matter along with any needed corrective actions. While SJRRC will make its best efforts, it is the Bidders responsibility to comply with any deadlines as required by law.
4. Pursuant to Public Contract Code sections 5100-5110, Bidders shall not be relieved of the bid unless by consent of SJRRC. SJRRC must receive a Bidder’s written request to withdraw its Bids prior to the Bid opening time fixed in this Document 00 21 13. For SJRRC to consent to a Bidder’s request to withdraw its bid, the Bidder must establish to SJRRC’s reasonable satisfaction that:
(a) A mistake was made, specifying in the notice in detail how the mistake occurred.
(b) Bidder gave SJRRC written notice within five working days, excluding Saturdays, Sundays, and state holidays, after the opening of the bids of the mistake.
(c) The mistake made the bid materially different than the Bidder intended it to be.
(d) The mistake was made in filling out the bid and not due to error in judgment or to carelessness in inspecting the site of the work, or in reading the plans or specifications.
SJRRC has sole discretion to consent to a bid withdrawal.
5. A Bidder who claims a mistake or who forfeits their bid security shall be prohibited from participating in further bidding on the project on which the mistake was claimed or security forfeited.
W. EVALUATION AND CONSIDERATION OF BIDS
1. SJRRC reserves the right to reject any and all bids and waive any inconsequential defect or minor irregularity in any bid received and to be the sole judge of the respective merits of the respective bids received. SJRRC reserves the right to reject any or all nonconforming, non-responsive, unbalanced, or conditional bids, and to reject the Bid of any bidder if it believes that it would not be in the best interest of SJRRC to make an award to that bidder, whether because the Bid is not responsive or the bidder is not qualified or of doubtful financial ability or fails to meet any other pertinent standard or criteria established by SJRRC. For purposes of this Paragraph, an “unbalanced Bid” is one having nominal prices for some work items and enhanced prices for other work items.
2. The Contract award, if made, will be made to the lowest responsible and responsive bidder. The apparent low bid will be determined solely on the Total Bid Price based on terms contained in Document 00 41 13 Bid Form – Stipulated Sum. All Bidders are required to submit Bids on all Bid items (including any alternates). SJRRC has absolute discretion to determine the lowest responsible and responsive Bidder.
Contract No. 27-R-28-00 Issued for Bid 00 21 13 - 10
3. SJRRC may retain the Bid, bid securities or bid bonds of other than the Apparent Low
Bidder for a period of one hundred and twenty (120) calendar days after award or full execution of the Contract, whichever first occurs.
4. The Contract will not be awarded to any Bidder that cannot give satisfactory assurance of its ability to perform the contract. Each Bidder may be required to furnish satisfactory evidence that it has sufficient means and facilities and has had ample experience in the type of work contemplated herein to deliver the materials, furnish the equipment and devices, and complete the installation in accordance with the specifications and within the time limit guaranteed.
5. In selecting the lowest responsible, and responsive bidder, consideration will be given to the general competence of the bidder for the performance of the work covered by the bid.
To receive favorable consideration, a bidder may be required to present evidence that it has successfully performed similar work of comparable magnitude or submit other evidence satisfactory to SJRRC that it or its associates are personally competent to manage the proposed undertaking and to carry it forward to a successful conclusion.
Professional integrity and honesty of purpose shall be essential requirements. A showing of adequate financial resources may be required but will not alone determine whether a bidder is competent to undertake the proposed work.
6. Only manufacturers or contractors of established reputation, or their duly authorized dealers or agents, having proper facilities for the manufacture of the materials or equipment and for servicing same, or for proper execution of the work called for in the Contract, will be considered in making the award. See Article F. above for prequalification requirements for certain Subcontractors.
7. Owner reserves the right to reject any or all bids as may be required to provide for the best interests of SJRRC.
X. BID PROTESTS.
1. Any Bid protest must be received in writing to SJRRC’s offices at 949 E. Channel Street, Stockton CA 95202, before 2:00 p.m. of the fifteenth (15) calendar day after staff recommendation for award has been made public. SJRRC will use reasonable efforts to deliver by email a copy of Document 00 50 50 Notice of Intent to Award to all bidders who submitted bids no later than the business day after issuance, although any delay or failure to do so will not extend the bid protest deadline described above.
2. The initial protest document must:
a. Specifically identify the Contract to which the protest relates.
b. Contain a complete statement of the basis for the protest, including specific reference(s) to the specific portions of the document(s) that form the basis for the
Contract No. 27-R-28-00 Issued for Bid 00 21 13 - 11 protest.
c. Specify the ruling or relief desired from SJRRC.
d. Include the name, address, telephone number, and email address of the person representing the protesting bidder.
e. Expressly request the members of SJRRC Protest Review Panel to hold a conference, to discuss the merits of the protest, if the protesting bidder desires such a conference. (Failure to expressly request such a conference in the initial protest document shall conclusively waive any right of the bidder to request such a conference.)
3. Only bidders who SJRRC otherwise determines are responsive and responsible are eligible to protest a bid; protests from any other bidder (or anyone else, such as prospective subcontractors) will not be considered. In order to determine whether a protesting bidder is responsive and responsible, SJRRC may open and evaluate information contained in any of protesting bidder’s bid envelopes which are not otherwise opened at the public bid opening, and conduct the same investigation and evaluation as SJRRC is entitled to make regarding an apparent low bidder.
4. The bidder filing the protest must concurrently transmit a copy of the initial protest document and any attached documentation to all other parties with a direct financial interest that may be adversely affected by the outcome of the protest. Such parties shall include all other bidders who appear to have a reasonable prospect of receiving an award depending upon the outcome of the protest.
5. No formal briefs or other technical forms of pleading or motion are required, but the initial protest document and other submissions should be concise, logically arranged, clear, and legible.
6. Any additional information requested or required by SJRRC from the protesting bidder, or interested parties, shall be submitted as expeditiously as possible, but in no case later than five (5) days after the receipt of such request unless specifically approved in writing before expiration of that five (5) day period by SJRRC.
7. The procedure and time limits set forth in this Article are mandatory and are a bidder’s sole and exclusive remedy in the event of a bid protest. A bidder’s failure to comply with these procedures shall constitute a waiver of any right to further pursue the bid protest, including filing a Government Code Claim or legal proceedings. A bidder may not rely on a protest submitted by another bidder but must timely pursue its own protest.
8. Materials submitted by a protesting bidder will not be withheld from any interested party outside of SJRRC or from any governmental entity which may be involved in the protest, except to the extent that the withholding of information is permitted or required by law or regulation. If the protesting bidder considers that the protest contains proprietary materials which should be withheld, a statement advising of this fact may be affixed to the
Contract No. 27-R-28-00 Issued for Bid 00 21 13 - 12 front page of the protest document and the alleged proprietary information must be so identified wherever it appears.
9. Protest submissions received by SJRRC after the time periods specified above shall be deemed to be untimely and shall be denied on that basis.
Y. ADDITIONAL POST-AWARD DELIVERABLES
1. See Document 00 73 00 Supplementary Conditions SC-10 for certain deliverables/submittals required for the successful Contractor.
Z. EXECUTION OF CONTRACT
1. Contractor shall execute Document 00 52 13 Contract – Stipulated Sum and returned with the prescribed executed bonds, insurance certificates and all other items required to be submitted with the Contract identified in SC-02 and Document 00 27 00 Preconstruction Documents Checklist within ten (10) days after receipt by the Contractor of the Notice of Award. Failure to return the signed and executed Contract with the prescribed items within the ten (10) day limit shall be just cause for the annulment of the award and the forfeiture of the Bidder’s Bid Bond.
2. SJRRC shall issue Notice to Proceed within a reasonable time (or as agreed at the pre-construction meeting) following receipt of all required Contractor items and SJRRC’s execution of the Contract.
3. The work shall be commenced within ten (10) calendar days after receipt of Notice to
Proceed and must be completed within the time allowed after the date specified in the Notice to Proceed, or if no starting date is specified, within the time limit allowed from the date on which work actually started.
4. Following award of Contract, SJRRC will prepare a Conformed Contract reflecting
Addenda (and other procurement documents) issued during bidding, which will, failing objection, constitute the approved Contract Documents and shall be referred throughout this IFB as the “Contract”.
AA. TAXES
1. The bid prices set forth in the Bid Form shall include all Federal, State and local taxes applicable to the work or materials furnished and no claims for additional costs of any such tax shall be made.
BB. INELIGIBLE CONTRACTORS AND SUBCONTRACTORS
Contract No. 27-R-28-00 Issued for Bid 00 21 13 - 13
1. SJRRC will reject a Bid from a Bidder who is ineligible to bid or work on, or be awarded, a public works project pursuant to Labor Code Section 1777.1 or 1777.7. Bidders and the Contractor who is awarded the Project Contract shall not utilize, or allow work by, any subcontractor who is ineligible to bid or work on, or be awarded, a public works project pursuant to Labor Code Section 1777.1 or 1777.7. (See Public Contract Code Section 6109.) The California Division of Labor Standards Enforcement publishes a list of debarred contractors and subcontractors on the Internet at www.dir.ca.gov/DLSE/debar.html.
CC. PUBLIC RECORDS
1. This IFB and any material submitted by a proposer in response to this IFB and opened by SJRRC are subject to public inspection under the California Public Records Act (Government Code § 7920 et seq.) (Act), unless exempt by law. Bids will remain confidential, to the extent permitted by law until SJRRC Board has authorized award and executed the contract.
2. If Bidder believes any communication contains trade secrets or other information that is exempt from disclosure under the Act, the Bidder shall request that SJRRC withhold from disclosure the proprietary information by marking each page containing such exempt information as confidential and identify the specific Section of the Act as the authority forth the exemption at the time of submission of its proposal responding to this IFB.
Bidder may not designate its entire Proposal or Bid as confidential. Bidder may not designate its Cost/Price Proposal or Bid forms (if opened by SJRRC) as confidential.
3. If Bidder requests that SJRRC withhold from disclosure information identified as confidential, and SJRRC complies with the Bidder’s request, Bidder shall assume all responsibility for any challenges resulting from the non-disclosure, indemnify and hold harmless SJRRC from and against all damages (including but not limited to attorneys’ fees that may be awarded to the party requesting the Bidder information), and pay any and all cost and expenses related to the withholding of Bidder information, including SJRRC’s legal fees and costs incurred in any court or other legal proceeding. Bidder shall not make a claim, sue or maintain any legal action against SJRRC or its directors, officers, employees or agents in connection with the withholding from disclosure of Bidder information.
4. If Bidder does not request that SJRRC withhold from disclosure information identified as confidential as set forth herein, SJRRC shall have no obligation to withhold the information from disclosure and may release the information sought without any liability to SJRRC.
5. Information disclosed in the Pre-Qualification Statement and the attendant opened submissions are the property of SJRRC unless Bidder makes specific reference to data that is considered proprietary. Subject to the requirements in the Act, reasonable efforts will be made to prevent the disclosure of information except on a need-to-know basis
Contract No. 27-R-28-00 Issued for Bid 00 21 13 - 14 during the evaluation process.
IFB No. 27-R-28-00 Issued for Bid 00 27 00 - 1
DOCUMENT 00 27 00
PRECONSTRUCTION DOCUMENTS CHECKLIST
The following documents are required to be completed and submitted by the Contractor at the times specified by an X opposite each title. However, this Document 00 27 00 is provided solely for Bidders’ convenience, and any conflict between any information contained in this Document and any other provision of the Procurement Documents or Contract Documents shall be governed by the other provision.
Submit prior to Bid Submission (If/As Required) Submit with Bid (All Bidders) – Include in Envelope A unless otherwise indicated Submit with Contract (Awardee Only) Submit after Notice to Proceed (Awardee Only)
BID FORM AND OTHER BID DOCUMENTS
X Bid Form – Stipulated Sum X Schedule of Quantities and Prices X Bid Bond X Bidder's Declaration X List of Subcontractors X Bidder's Responsibility Statement (include in Envelope B) X Non-Collusion Affidavit X State Debarment and Suspension Certification X Agreement to Comply with California Labor Law Requirements
X Statement Acknowledging Penal and Civil Penalties Concerning the Contractors' Licensing Laws
X Addenda Acknowledgements (included on Bid Form)
CONTRACT AND RELATED DOCUMENTS
X Contract – Stipulated Sum X Contract Surety Bond (Faithful Performance) X Contract Surety Bond (Labor and Materials) X Certificate of Workers Compensation Insurance X Certificate of Employer's Liability Insurance X Certificate* of Comprehensive General Liability Insurance X Certificate* of Automobile Liability Insurance X Certificate* of FELA Insurance (to the extent required) X Certificate* of Contractor’s Pollution Liability Insurance X Certificate* of Umbrella/Excess Coverage X Certificate* of Professional Liability Coverages Insurance X Certificates* of insurance of the Subcontractors (if any) identified in SC-02 *(With copy of policy and endorsements)
PRE-CONSTRUCTION SUBMITTALS:
X Preliminary Schedule of Values X Preliminary Schedule of Submittals X Preliminary Construction Progress Schedule X Contractor’s Safety Plan X Waste Management Plan X Qualifications for Key…