Hobble Creek Pathway Bid Notice Summary
This bid notice from the State of Idaho announces a construction project for the Hobble Creek Pathway involving site preparation, demolition, and new pathway construction. The project scope encompasses removal of the existing greenbelt path and construction of a new concrete greenbelt path according to provided drawings and specifications. Work includes saw cutting and demolition of existing concrete walkways and asphalt paving, landscaping modifications, and removal of existing trees. The project also involves minor site grading, earthwork, and drainage improvements, concrete sidewalk repair, irrigation system repair, and landscape restoration. The notice provides bidders with project details necessary to prepare competitive proposals for the complete pathway construction and related site work.
The bid notice establishes the formal solicitation process for contractors interested in undertaking this Idaho state or local public works project. Specific pricing terms, contract award dates, project timelines, and bidder meeting schedules would be detailed in the complete bid documents. Contractors should review all associated drawings, specifications, and supplementary documents to understand full project requirements and submit proposals accordingly by the established deadline.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIAL PROVISIONS
Hobble Creek Path, Boise
100% Submittal
September 24, 2026
Special Provisions Hobble Creek Pathway September 16, 2026 Page 1 of 48
Special Provisions
GENERAL NOTES
1. BASIS OF PAYMENT
Except as modified herein, the various work called for on the Bid Schedule shall be performed, measured and paid for as indicated on said Bid Schedules and as provided in the 2025 IDAHO STANDARDS FOR PUBLIC WORKS CONSTRUCTION (hereafter referred to as the ISPWC) and ACHD Supplemental Specifications. The Contractor is required to be a holder of the ISPWC and all ACHD Supplemental Specifications. No separate payment will be made for items not specifically called out in the Bid Schedule. Any such work shall be considered incidental to other items of work, and no separate payment will be made.
CONSTRUCTION IN THE PUBLIC RIGHT-OF-WAY
All construction in the public right-of-way shall conform to the current edition of the ISPWC and the ACHD Supplemental Specifications. No exceptions to District Policy, Standards and the ISPWC will be allowed unless specifically and previously approved in writing by the district.
BASIS OF QUANTITIES
Unless otherwise specified herein, all quantities are based upon in-place, completed and accepted units.
2. PRELIMINARY MATTERS
Contractor shall obtain approval of the proposed project work sequence with Boise Parks and Recreation prior to beginning construction.
Contractor is required to provide project correspondence via Procore Construction Management Software. Software links and access will be provided to contractor by agency following the project Notice to Proceed. General contractor to coordinate project submittals, requests for information, and payment utilizing Procore software.
PRELIMINARY SCHEDULE
Within 10 days after the Notice to Proceed, contractor shall submit for review:
1. Preliminary progress schedule indicating the times (number of days or dates) for starting and completing the various stages of the work, including any milestones specified in the Contract.
2. A preliminary schedule of submittals.
3. A preliminary schedule of values for all the work, which includes quantities and prices of items which when added together equal the contract price and subdivides the work into component parts in sufficient detail to serve as the basis for progress payments during performance of work.
September 16, 2026 Page 2 of 48
3. CONTRACT DOCUMENTS: INTE NT, REQUIRMENTS, REUSE
The contract documents are complementary; what is required by one contract document is binding as if required by all.
It is the intent of the contract documents to describe a functionally complete project (or part thereof) to be constructed in accordance with the contract documents.
Unless otherwise stated in the contract documents, if there is a discrepancy between the electronic versions of the contract documents (including any printed copies derived from such electronic versions) and the printed record version, the printed record version will govern.
The contract supersedes prior negotiations, representations, and agreements, whether written or oral.
Project Manager will issue clarifications and interpretations of the contract documents as provided herein.
Any provision or part of the contract documents held to be void or unenforceable under any Law or Regulation will be deemed stricken, and all remaining provisions will continue to be valid and binding upon Owner and Contractor, which agree that the contract documents will be reformed to replace such stricken provision or part thereof with a valid and enforceable provision that comes as close as possible to expressing the intention of the stricken provision.
During the performance of the work and until final payment, contractor and owner shall submit to the Project Manager in writing all matters in question concerning the requirements of the contract documents (sometimes referred to as requests for information or interpretation RFIs) or relating to the acceptability of the work under the contract documents, as soon as possible after such matters arise. Project manager will be the initial interpreter of the requirements of the contract documents, as soon as possible after such matters arise. Project manager will be the initial interpreter of the requirements of the contract documents, and judge of the acceptability of the work.
Project Manager will, with reasonable promptness, render written clarification, interpretation, or decision on the issue submitted, or initiate an amendment or supplement to the contract documents. Project Manager’s written clarification, interpretation, or decision will be final and binding on contractor, unless it appealed by submitting a change proposal, and or owner, unless it appeals by filing a claim.
BASIS FOR ADJUSTMENT OF CONTRACT TIME – In the adjustment of Contract Time the Project Manager will consider causes that included, but are not limited to:
1. Failure of the Agency to execute the contract by the projected date in the special provision, or to submit the Notice to Proceed within the time stated:
2. Errors, changes, or omissions in the Supplemental Drawings, or Specifications;
3. Failure of the Agency or Entities acting for the Agency to act promptly in carrying out Contract duties and obligations;
4. Acts or omissions of the Agency or Entities acting for the Agency that result in unreasonable delay;
5. Right-of-Way and access delays.
6. Permit delays for permits to be provided by Agency as listed in the special Provisions.
September 16, 2026 Page 3 of 48
The Project Manager will not consider requests for adjustment of Contract Time based on any of the following:
1. Contentions that insufficient Contract Time was originally specified in the Contract;
2. Delays that do not affect the specified or Adjusted Contract Time;
3. Shortage or inadequacy of Materials, Equipment or labor;
4. Late delivery of Material and Equipment to be incorporated into the Work, except under those conditions referenced;
5. Different areas of Material source;
6. Substitution of Equipment;
7. Reasonably predictable weather conditions; or
8. Other matters within the Contractor’s control or Contract responsibility.
DELAY IN CONTRACTOR’S PROGRESS
1. The project completion date in this Contact includes reasonably predictable weather days.
2. The following reasonably predicted weather days are incorporated into the contract:
a. January 7
b. February 6
c. March 6
d. April 6
e. May 6
f. May 6
g. June 4
h. July 1
i. August 1
j. September 1
k. October 3
l. November 6
m. December 7
SCOPE OF WORK
This project includes the removal of existing greenbelt path and construction of new concrete greenbelt path per drawings and specifications.
The scope of work for this contract includes:
Saw cutting, demolition, and remove of existing concrete walk, asphalt paving, landscaping, and existing trees.
Minor site grading, earthwork, and drainage.
September 16, 2026 Page 4 of 48
Concrete sidewalk repair.
Irrigation repair.
Landscape repair.
4. COMMENCEMENT AND PROGRESS OF THE WORK
All staking, grading and elevation lines to be provided by a licensed Idaho surveyor at the expense of the contractor to achieve the elevations, grades and drainage included in the plan set.
The Contractor shall stake out the layout for all work under this contract from established elements, i.e., Points of Beginning, corner points and others, as indicated on the site plans. All staking shall be approved by Boise Parks & Recreation prior to commencement of any work.
The Contractor shall incur all expenses for the provision of all stakes, templates, platforms, equipment, tools, materials, and labor as may be required in laying out any part of the work.
Contractor shall layout and set construction stakes and marks to establish the lines, grades, slopes, cross sections, and elevations for sitework.
Owner shall provide engineering survey to establish reference points for construction which in Engineer’s judgement are necessary to enable contractor to proceed with the work. Contractor shall be responsible for laying out the work, shall protect and preserve the established reference points and property monument, and shall make no changes or relocations without prior written approval of owner. Contractor shall report to Engineer whenever any reference point or property monument is lost or destroyed or requires relocation because of necessary changes in grades or locations and shall be responsible for accurate replacement of such reference points or property monuments by professionally qualified personnel.
5. CONTRACT TIME
The total contract time allocated for this work is 90 Days including 18 Weather Days. The contract is anticipated to be fully executed on November 19, 2026.
Contractor must do the following upon receipt of notice to proceed:
Within 7 days - Submit drawings for required permitting.
Within 14 days – All drawings and documents are accepted with corrections for permitting.
Contractor must begin onsite work no later than 45 days from Notice to Proceed or upon permit approval.
No work may begin onsite until all permits are approved and a pre-construction meeting has been held by Boise Parks and Recreation.
The completion date for all contract work is February 17, 2027.
6. DELAYS IN CONTRACTOR’S PROGRESS
The liquidated damages for failure to complete the Work on time required will be $500.00 per calendar Day.
September 16, 2026 Page 5 of 48
7. CONTRACTOR’S RESPONSI BILITIES
The Contractor shall not begin Work prior to 7:00 a.m. nor continue Work past 6:30 p.m. weekdays and 8:00 a.m. and 6:30 p.m. on weekends, unless approved otherwise.
Contractor shall be solely responsible for the means, methods, techniques, sequences, and procedures of construction.
At all times during the progress of the work, contractor shall assign a competent resident superintendent who will not be replaced without written notice to owner and Engineer except under extraordinary circumstances.
8. SERVICES, MATERIALS, AND EQUIPME NT
Unless otherwise specified in the contract documents, contractor shall provide and assume responsibility for all service, materials, equipment, labor, transportation, construction equipment and machinery, tool, appliances, fuel, power, light, heat, telephone, water, sanitary facilities, temporary facilities, and all other facilities and incidentals necessary for the performance, testing, start up and completion of the work, whether or not such items are specifically called for in the contract documents.
All materials and equipment incorporated into the work must be new and of good quality except as otherwise provided in the contract documents. All special warranties and guarantees required by the specifications will expressly run to the benefit of owner. If required by Engineer, contractor shall furnish satisfactory evidence (including reports of required tests) as to the source, kind, and quality of materials and equipment.
All materials and equipment must be stored, applied, installed, connected, erected, protected, used, cleaned and conditioned in accordance with the instructions of the applicable supplier, except as otherwise may be provided in the contract documents.
Storage of construction equipment, materials, supplies, temporary office or sanitary facilities shall occur inside the fenced construction zone. No personal vehicles shall be stored onsite except for contractor-owned vehicles engaged with material supply or active construction.
The contractor shall temporarily fence the perimeter of the worksite for each block and specified herein. The fence shall be maintained in a secure and upright position for the duration of the project.
9. CONSTRUCTION PHASING & TRAFFIC CONTROL
The Contractor shall submit detailed construction phasing and traffic control plans to ACHD and The City for review and approval prior to construction. The traffic control plans shall address advanced construction signing and detailed traffic control for each phase of work and shall address pedestrian detours whenever construction activities necessitates closure of any existing pedestrian facilities.
Existing stop control within the project limits shall remain in effect at all times. This may require removing and resetting existing signs during construction. All costs associated with Construction Phasing and Traffic Control, including but not limited to maintaining minimum travel lanes as required, shall be considered incidental to other items of work and no separate payment will be made.
Contractor shall complete all work on a block-by-block basis as outlined in Scope of Work.
Contractor to begin construction of one block, repair and complete all work prior to proceeding to next block of work.
September 16, 2026 Page 6 of 48
10. ADA DURING CONSTRUCTION
The needs and control of all road users (motorists, bicyclists, and pedestrians within the highway and/or public right-of-way, including persons with disabilities in accordance with the Americans with Disabilities Act of 1990 (ADA), Title II, Paragraph 35.130) through a temporary traffic control “TTC” zone shall be an essential part of highway construction, utility work, maintenance operations, and the management of traffic incidents. The primary function of TTC is to provide for the reasonably safe and efficient movement of road users through or around TTC zones while reasonably protecting workers, responders to traffic incidents, and equipment.
Temporary facilities, including reasonably safe pedestrian routes around work sites, are also covered by the accessibility requirements of the Americans with Disabilities Act of 1990 (ADA) (Public Law 101-336, 104 Stat.327, July 26, 1990. 42 USC 12101-12213 (as amended)). Implementation of TTC plans and installation and maintenance of devices shall be the responsibility of the Contractor performing the construction, alteration and/or maintenance of the highway or public right-of-way.
When an existing continuous sidewalk or street crossing route cannot be maintained for pedestrians because of construction, either temporary walkways with curb ramps are to be provided, or the construction shall be phased to maintain access to the affected addresses. Contractors shall be allowed flexibility as long as the requirements are met.
The location of the construction project and whether or not accessible facilities are present shall also determine the extent of the temporary facilities needed. The Contractor is only required to maintain practical continuity where accessible facilities already exist. On low speed rural roads that do not have sidewalks and are used by cyclists, no additional measures are needed as the bicycles can share the available travel lanes with other traffic. On moderate to higher speed rural roads, if a bike lane exists then it should be properly detoured, complete with signage, to provide a safe route through or around the work area. If a road or bridge project affects vehicular traffic to a business, residence, school or any other type of pedestrian generating location with existing accessible facilities, then pedestrian and handicapped access must be maintained.
A continuous route for all pedestrians, including the disabled and bicyclists, shall be maintained at all times. When existing pedestrian facilities are disrupted, closed, or relocated in a TTC zone, the temporary facilities shall be detectable and include accessibility features consistent with the features present in the existing pedestrian facility. The temporary route should enable pedestrians to bypass the construction site while minimizing the retracing of their steps or going significantly out of their way. Additional consideration must be given to the disabled since they may not have the physical or cognitive ability to improvise (e.g. balancing along the curb or a very narrow path) or use unofficial alternatives (e.g. using an adjacent grass surface). Temporary routes must meet the accessibility guidelines of the ADA for permanent facilities and shall be marked with the proper signage. Should existing crosswalks at signalized intersections be closed or made inaccessible, temporary crosswalks should be painted in an accessible location. Temporary signals should include pedestrian phases.
Contractors shall not block temporary walkways with Contractor parking, materials piles, signs, rubble or rubbish. Construction equipment and equipment operation must be separated from the temporary walkways. At work zones where higher volumes of pedestrian traffic or school children exist, pedestrian fences or other protective barriers may be needed to prevent access into the construction area.
September 16, 2026 Page 7 of 48
11. ACCESS DURING CONSTRUCTION
Access to adjacent properties shall be maintained at all times. This shall include providing an adequate surface (free of protruding rocks, holes and mud) for all emergency vehicles and pedestrians. The cost to maintain access shall be considered incidental to other items of work and no separate payment will be made.
12. PROTECTION OF TREES & BUSHES
The Contractor shall be responsible for protecting the existing trees not called out for removal within the project area and must use practicable care in the protection of trees, tree branches and tree roots within the construction limits. Excavation for the proposed improvements shall be carried out in a way that avoids root damage as much as practicable. This may require handwork, which shall be considered incidental to other items of work, and no separate payment will be made.
Protect all trees in place, unless otherwise approved. Tree pruning and root pruning shall be performed by a certified arborist.
Damage Clause – Damage to trees or bushes during construction will be assessed against Contractor per dollar amount of replacement value. The value and damage amount will be determined by ratings of the International Society of Arboriculture Shade Tree Evaluation, Latest Edition, as facilitated by Boise Parks & Recreation Urban Forestry Division.
Furnish all work, services, materials, and related items only as necessary to complete the work indicated in the specifications, plans and details.
Protection of Existing Irrigation Systems - Contractor shall protect and maintain the operation of all existing irrigation systems. All portions of the irrigation system must be functional and the system operable at the end of each workday. No portion of the irrigation system may be shut down or out of use for longer than 24 hours. All damage to the existing system must be repaired within 24 hours.
City of Boise to coordinate any required tree pruning with contractor at preconstruction meeting.
13. COORDINATION WITH UTILITIES
It shall be the Contractor’s responsibility to contact and coordinate with the various utility companies as necessary for the successful completion of the project. This coordination effort shall include, but not be limited to, working other than normal operation hours to permit the relocation of utilities and construction of the roadway within the time frame of this contract. The cost to contact and coordinate with utilities shall be considered incidental to other items of work and no separate payment will be made.
Utility information is shown only for surface features, and if provided by the owner of the utility for non-surface features. The information shown is for reference purposes only and does not necessarily represent actual field conditions. The Engineer assumes no liability for the accuracy of the information shown, or conflicts due to inaccurate or incomplete utility information. The Contractor shall call Dig Line a minimum of 48 hours prior to any excavation to request utility locations at 1-800-342-1585.
The Contractor shall expose all existing utility crossings to verify locations and elevations prior to any other construction that may affect those utilities. The cost associated with exposing the existing utilities is considered incidental to the project and no separate payment will be made.
September 16, 2026 Page 8 of 48
Utilities require a two-week window to complete their relocations and adjustments after clearing, grubbing, tree trimming and tree removal. These utility windows may impact the Contractor’s schedule by that amount of time. Contractor is to coordinate with utilities to schedule construction windows. Utility adjustments, relocations or replacements may not be completed prior to construction. The Contractor shall coordinate and accommodate work with utility companies. The utility company contacts are located on the Project Clearance Summary Sheet of the project plan sheets.
14. DAMAGE BE YOND CONSTRUCTION LIMITS
Damage to property outside the construction limits of this project shall be promptly repaired by the Contractor. The cost of these repairs shall be considered incidental to other items of work, and no separate payment will be made. The Contractor shall obtain a release from the property owner specifying that they are satisfied with the repair work. A copy of the letter shall be submitted to the CITY. Final release of contract retainage will not be authorized until this provision has been met.
15. RETAIN & PROTECT EXISTING ITEMS
All items outside of the right-of-way and temporary construction easements shall be retained and protected unless specifically noted otherwise on the plans.
16. TRENCHING
All excavation and trenching shall meet OSHA requirements. Trenches shall be backfilled and properly compacted, closed at the end of each day, and barricaded, as needed.
17. STORM DRAIN & IRRIGATION FLOWS
The Contractor is responsible for transmitting existing storm drain and irrigation flows during construction. Maintaining these flows may require the Contractor to install temporary collection points for transmitting and bypassing the systems to complete the project tasks. All costs associated with transmitting both existing storm drain and irrigation flows, including flows from the temporary water quality best management practices, on the project shall be considered incidental to other items of work and no separate payment will be made.
18. ASPHALT AND CONCRETE CUTTING
All cutting of existing asphalt pavement and concrete shall be by saw. The costs associated with cutting existing asphalt pavement and concrete shall be considered incidental to other items of work and no separate payment will be made.
19. TRENCHES AND PIPE BEDDING
All backfill for storm drain and irrigation pipes shall be Type A-1 according to the specifications set forth in the current edition of the ISPWC section 306 (Trench Backfill). Pipe bedding for storm drain and gravity irrigation shall be Class A-1 according to the specifications set forth in the current edition of the ISPWC Section 305 - Pipe Bedding. All costs associated with trenching and pipe bedding shall be included in the individual pipe bid items, and no separate payment will be made.
20. SOURCES
The Contractor shall use approved commercial sources for Uncrushed Aggregate Base, Crushed Aggregate for Base Type I, plant mix/superpave pavement aggregates, Portland cement concrete aggregates, structural fill, trench bedding and backfill.
September 16, 2026 Page 9 of 48
21. EXC ESS MATERIAL SITE
The Contractor shall be responsible for providing a site for the disposal of excess or unsuitable materials. If bituminous material is to be disposed of, the site shall meet the requirements of the Idaho Department of Environmental Quality. No separate payment will be made for the acquisition or operation of the sites, or for loading, hauling or unloading the materials at the site.
22. PROPERTY OWNER COORDINATION
The Contractor shall coordinate items of work affecting adjacent property with the property owners or their agents. The Contractor shall prepare a public notice flier describing the project, the anticipated duration and any anticipated changes to current traffic patterns. After approval by the City, this flier shall be delivered by the Contractor to property owners within a 1,000-foot radius of the project limits. This work shall be considered incidental to other items of work, and no separate payment will be made.
23. WARNING & REGULATORY SIGNS
Existing warning and regulatory signing shall be retained and protected throughout the project limits unless otherwise noted. This may require multiple relocations, which shall be incidental to other bid items. Existing warning and regulatory signs that are designated for removal and replacement and do not conflict with construction traffic control signs shall be maintained during construction and, if necessary, relocated to locations where the signs are visible to traffic and serve their original purpose, which shall be incidental to other bid items.
24. ON SITE SUPERVISION
The General Contractor shall provide competent on-site supervision during all construction activities, including SUBCONTRACTOR activities. The superintendent shall be identified at the preconstruction conference and shall at a minimum be on-site from the notice to proceed date to the completion date. If for any reason the superintendent needs to be replaced by the General Contractor, a written notice must be submitted to the City within five (5) working days before the event occurs.
25. MEASUREMENT AND PAYMENT
PAYMENT for all work described by the Plans and Specifications to construct this project shall be the lump sum amounts given in the Contractor's proposal / bid schedule, which price and payment includes all labor, materials, equipment, bonds, warranties, taxes, insurances, mobilization, cleanup, traffic control, permits, tests, shop drawings, submittal, freight, and incidental costs necessary to construct the improvements shown on the Plans and described in the Specifications and Contract Documents.
26. VARIATIONS IN QUANTITIES
Detailed pricing information shall be provided for all negotiated pricing adjustments.
27. TESTING AND CONSTRUCTION OBSERVATION
All testing and observation shall be performed in accordance with the ISPWC and ACHD Supplemental Specifications or as outlined in the plans and these special provisions. The contractor is solely responsible for scheduling all inspection and testing as required. All costs of retesting for
September 16, 2026 Page 10 of 48 previously failed tests shall be back charged to the responsible Contractor. All costs of re-inspecting failed items shall also be back charged to the responsible Contractor.
28. PRECONSTRUCTION MEETING
Prior to scheduling a preconstruction meeting the contractor shall submit all material certifications and required submittals as outlined in the Submittals section of the ISPWC and the ACHD Supplemental Specifications. The contractor shall submit a traffic control phasing plan for review.
Said traffic control plan shall be in accordance with the MUTCD 2009 traffic control devices, ISPWC, plans, and as outlined in these special provisions.
Once it is determined that all material requiring submittals have been received, a preconstruction meeting shall be held a minimum of three (3) working days prior to the start of all work including work on utilities and infrastructure. The General Contractor shall coordinate the preconstruction meeting. The Design Engineer, the City of Boise’s representatives, and all contractors, subcontractors and / or utility contractors shall be present.
Before any work at the site is started, a conference attended by Owner, Contractor, Engineer, and others as appropriate will be held to establish a working understanding among the parties as to the work, and to discuss the schedule referred to above, procedures for handling shop drawings, samples, and other submittals, processing applications for payment, electronic or digital transmittals, and maintaining required records.
At this meeting, Owner and Contractor each shall designate, in writing, a specific individual to act as its authorized representative with respect to the services and responsibilities under the contract.
Such individuals shall have the authority to transmit and receive information, render decisions relative to the Contract, and otherwise act on behalf of each respective party.
29. WEEKLY PROJECT MEETINGS
The Contractor shall coordinate and hold a weekly project meeting. The meetings will be held at the same time and place each week and at a time that best accommodates each party's schedule. The meeting time and place will be determined at the preconstruction meeting. It shall be the responsibility of the Contractor to provide a meeting place, schedule, attend, conduct, and provide a weekly meeting agenda and a look ahead schedule. All costs shall be considered incidental to other project items, and no separate payment will be made.
No payment will be made to contractor until acceptable schedules are submitted to the Project Manager.
The progress schedule will be acceptable to Project Manager if it provides an orderly progression of the work to be completed with contract times. Such acceptance will not impose on project manager responsibility for the progress schedule, for sequencing, scheduling, or progress of the work, nor interfere with or relieve contractor from contractor’s full responsibility, therefore.
Contractor’s schedule of values will be acceptable to Project Manager if it provides a workable arrangement for reviewing and processing the required submittals.
Contractor’s schedule of values will be acceptable to Project Manager as to form and substance if it provides a reasonable allocation of the contract price to the component parts of the work.
If a schedule is not acceptable, contractor will have an additional 10 days to revise and resubmit the schedule.
September 16, 2026 Page 11 of 48
Contractor is required to include any weather delays in the progress schedule and update projected delivery of project.
Provide reasonably predicted weather delays in the Project schedule and their impact on all-weather sensitive activities. Show weather limitations that may affect the Project schedule.
30. PROJECT MAINTENANCE DURING CONSTRUCTION
The Contractor shall be responsible for project maintenance throughout the life of the contract. This responsibility includes, but is not limited to blading, sweeping, proper and adequate drainage, access for emergency equipment, appropriate access for property owners, and dust control. All project maintenance activities shall also conform to requirements specified in any project permits.
BMP’s at the project site shall be the sole responsibility of the contractor.
The Contractor shall be responsible for maintaining both on-site and off-site roadway facilities that are adversely affected by construction activities, including hauling. This maintenance may include, but is not limited to, street sweeping to eliminate tracking (within the project limits, adjacent streets, private driveways, and parking lots), and roadway repairs due to truck and equipment traffic. Required roadway facility maintenance shall be at the discretion of CITY.
The Contractor shall provide a water truck and driver for dust abatement use at CITY’s discretion.
Failure to adequately provide dust control shall be adequate cause for stopping work. The costs to provide dust control by other than the Contractor shall be deducted from the progress estimates.
The Contractor shall backfill trenches as soon as possible the same day the trench is excavated. Pipe and conduit crossings, manholes, and miscellaneous construction in existing roadways remaining open to traffic shall be constructed with temporary asphalt patches.
The cost of all project maintenance and roadway facility work, including temporary asphalt patches if needed, shall be considered incidental to other items of work and no separate payment will be made.
31. PRE-QUALIFICATIONS
The Contractor is required to be a current holder of the ISPWC, ACHD Supplemental Specifications, and have a current Public Works License for the State of Idaho (prior to contract Award). Copies of the ISPWC may be obtained from the Local Highway Technical Assistance Council (LHTAC) telephone
(208) 344-0565. A complete set of Plans, Contract Documents, ISPWC and ACHD Supplemental Specifications shall be maintained at the Project site at all times.
32. ENVIRONMENTAL COMPLIANCE
The Contractor shall secure an EPA Construction General Permit, a City issued Erosion & Sediment Control Permit and prepare an Erosion and Sediment Control Plan (ESCP), as necessary, to include all work. In addition, all local and state sediment control requirements must be complied with.
Permits shall include all utility relocations (by utility companies) necessary to complete the project as the utility companies will operate under the Contractor’s EPA Construction General Permit and
ESCP.
33. RECORD DOCUMENTS
Contractor shall maintain in a safe place at the site once printed copy of all drawings, specifications, addenda, change orders, work change directives, field orders, written interpretations and clarifications, and approved shop drawings. Contractor shall keep such record documents in good
September 16, 2026 Page 12 of 48 order and annotate them to show changes made during construction. These record documents, together with all approved samples, will be available to Engineer for reference. Upon completion of the work, contractor shall deliver these record documents to Engineer.
34. PERMITS
The Contractor shall secure all required permits to do work within the right-of-way at least forty-eight (48) hours prior to construction. Contractor to fill out and obtain City of Boise permits. Permit forms are included in Appendix L (fees approximately $845.50).
MODIFICATIONS TO ISPWC SPECIFICATIONS
ITEM 202.4.1.A.1 – EXCAVATION
ON PAGES 14 & 15 OF SECTION 202 OF THE ISPWC, PART 4.1.A, replace the entire section with the following:
This item shall be paid for per bid schedule with no final measurement, for which the price and payment shall constitute full compensation for excavating, loading, hauling, spreading, blending, shaping, drying, watering and compacting excavated material that is acceptable for the use as on-site borrow for embankment fill, and for all tools, labor and incidentals necessary to complete the work and all appurtenances not itemized on the Bid Schedule.
Placing on-site borrow for embankment fill is incidental to the excavation pay item and no separate payment will be made.
Payment for this item shall be made under:
Grading Bid Item
ITEM 801.4.1.B.1 – 6” MINUS UNCRUSHED AGGREGATE BASE
ON PAGE 1 OF SECTION 801 OF THE ISPWC, PART 2.1.B - MATERIALS, add the following:
The material shall have a minimum R-value of 60.
ON PAGE 2 OF SECTION 801 OF THE ISPWC, PART 2.1 - MATERIALS, add the following:
E. For estimating purposes a unit weight of 135 lb/ft3 was used to calculate the tonnage.
Grading Bid Item
ITEM 802.4.1.A.1 – CRUSHED AGGREGATE FOR BASE TYPE I
ON PAGE 7 OF SECTION 802 OF THE ISPWC, PART 4.1.A, replace the entire section with the following:
This item shall be per bid schedule with no final measurement, for which the price and payment shall constitute full compensation for loading, hauling, spreading, blending, shaping, drying, watering and compacting crushed aggregate base type I material, and for all tools, labor and incidentals necessary to complete the work and all appurtenances not itemized on the Bid Schedule.
September 16, 2026 Page 13 of 48
The plan quantity listed on the Bid Schedule represents the mass/weight of crushed aggregate base type I material required to construct the crushed aggregate base as shown on the project plans and standard drawings and as described in the ISPWC and these Special Provisions.
Grading Bid Item
1006.4.1.C.1 – INLET PROTECTION
ON PAGE 2 OF SECTION 1006 OF THE ISPWC, PART 2.1, add the following:
B. Inlet protection shall be Stormguard Sediment Catch Basin Inserts installed according to manufacturer’s recommendations.
(REPLACE) ISPWC-DIVISION 900, SECTION 901, 902, AND 903 WITH THE FOLLOWING:
(ADD) SECTION 900, Irrigation Systems
PART 1 GENERAL
1.1 SECTION INCLUDES:
A. Contractor shall furnish all labor, materials, tools, equipment and incidentals for the proper execution and completion of all sprinkler work.
B. The irrigation plans are a schematic design and may require adjustment. Do not install the sprinkler system as shown if it is evident that obstructions, grade differences, or differences in area dimensions create conditions different than anticipated in the design. Bring all such obstructions or differences to the attention of the Boise Park & Recreation Representative. In the event this notification is not performed before construction begins on a part of the system where discrepancies exist, any revision necessary to make the system operate as designed will be the responsibility of the contractor at no additional expense to the agency.
C. Coordinate with other trades affecting and being affect by the work of this section.
D. Coordinate all existing utility locations. Verify the location of any underground utilities prior to beginning work and maintain locate marks throughout construction.
E. Preserve and protect existing improvements and vegetation in areas to remain undisturbed for duration of the project. Return to condition found if damaged.
a. Preserve and protect survey monuments, benchmarks, and other reference points. If disturbed, or destroyed, replace as directed and at no expense to the owner.
b. Preserve and protect active utilities and maintain in continuous operation for duration of the project. Repair or replace all damage to known utilities at no expense to the owner.
c. Use all means necessary to protect materials and work of this Section and all other Sections before, during, and after installation. In the event of damage, immediately make all repairs and replacements as directed by Owner’s Representative.
F. Required Inspections – The following inspections will be required at a minimum:
September 16, 2026 Page 14 of 48
a. Upon completion of layout and flagging, prior to commencement of excavation or installation work.
b. Upon completion of the main line and control wires, with all valves installed, prior to backfilling.
c. At start and end of mainline pressure test.
d. Upon completion of lateral piping, prior to backfilling.
e. After forming but prior to pouring concrete bases for controller cabinets.
f. Upon completion of the entire system, at which time the system will be reviewed, and a punch-list generated if required.
g. Upon completion of the punch-list work, at which time the system will be accepted, provided that the system is in first-class operating condition, and provided that the Contractor has complied with all other terms of the Contract.
h. Make any corrections identified at each review prior to proceeding with additional work.
G. The Contractor shall be responsible for the provisions of barricades, any safety guards, and other temporary structures as required to protect the work area from the public.
1.2 RELATED SECTIONS:
1.3 SUBSTITUTIONS:
A. Substitutions must be submitted electronically for approval to Boise Parks & Recreation.
1.4 SUBMITTALS FOR REVIEW
A. Product Data – Submit a list of proposed material for approval before arranging for procurement of any materials. If any initially proposed materials are not approved, submit substitutes for approval. Any materials installed without approval will be subject to removal and replacement with acceptable material as the Contractor’s expense. Include all material to be used showing manufacture’s name, catalog numbers, catalog cuts, technical data, and manufacturer’s installation, operation, and maintenance instructions for each product.
B. Test Reports – Verify meter location, size, PSI, and GPM. Conduct flow test to verify GPM. Submit results of test to Boise Park & Recreation.
C. Record Drawings – Contractor shall always maintain a current and legible set of irrigation plans in a safe and accessible location on site for review by Inspector.
Design changes and actual locations of pipes and valves shall be noted on the plans daily as the irrigation system is constructed.
September 16, 2026 Page 15 of 48
a. Indicate two dimensions for all valves (including quick couplers and drain valves) and stub-outs.
b. Indicate approximate locations and route changes to mainline piping, lateral line piping, and head layout.
D. Owner’s copy of Backflow Prevention Device test report.
E. Maintenance data for inclusion in ‘Operations and Maintenance Manual’ specified in Section ‘Contract Closeout’ for the following:
a. Seasonal activities of start-up, shutdown, and winterization, including blow-out operation of sprinkler system with compressed air.
b. Backflow preventers, including instructions for testing.
c. Automatic control valves.
d. Sprinklers.
e. Controllers.
f. Irrigation system record drawings.
PART 2 MATERIALS
2.1 Furnish only commercial quality materials and equipment. All items proposed for use will be subject to testing and ensure compliance with the Specifications. Provide materials of the same function that are the same manufacturer.
A. Use only new materials.
B. Protect against damage.
C. Store packaged materials in manufacturer’s original container with legible labels intact.
D. Store plastic pipes on firm, level support, protected against direct sunlight.
E. Store plastic pipe cement at room temperature or as recommended by manufacturer.
2.3 All items proposed for use will be subject to testing to ensure compliance with the Specifications.
2.4 Main & Lateral Line Pipe
A. PVC (Polyvinyl Chloride) Type I, NSF approved per ASTM-D1784, D-1785/D-2665, and US Product Standard PS 21-70, 22-70. All PVC pipes shall be continuously marked with manufacture’s name, kind of pipe, material, IPS, class, or schedule.
P.V.C. pipe shall be virgin, high impact polyvinyl chloride pipe, conforming to commercial standards CS 207-60.
B. Mainlines, laterals and fittings with solvent weld type joints are required except where head assemblies, valves, etc., require threaded joints.
C. All pipes shall be Schedule 40 for line sizes 3/4", 1", 1 1/4", 1 1/2", and 2".
September 16, 2026 Page 16 of 48
D. All pipes shall be Class 200 for line size 2 1/2", 3", 4", and 6".
E. Mainlines and laterals 4" and larger shall be gasketed pipe with all fittings being mechanical ductile iron.
F. Sleeves: PVC (Polyvinyl Chloride) Type I, NSF approved as per ASTM-D1784, D- 1785/ D-2665, and US Product Standard PS21-70, 22-70. All PVC pipe shall be continuously marked with manufacture’s name, kind of pipe, material, IPS, class or schedule. All pipe shall be Schedule 40 with solvent-weld connection fittings unless otherwise noted on Plans.
G. Sleeve Marker: 2” diameter aluminum sleeve marker Part CD2-U manufactured by Berntsen International Inc, Madison WI, (800) 518-0934 or approved equal.
Marker to have the following text “BOISE PARKS AND RECREATION” at the top of the marker and “SLEEVE” labeled with the arrow aligned to the orientation of sleeve below.
H. Pipe shall homogeneous throughout and be free from defects, cracks, holes, foreign materials, wrinkles, dents, and blisters.
I. Pipe and fittings shall be of American Manufactured.
J. Drip Irrigation: Makes and models shown on the plans or approved equal. Only use fittings of the same manufacturer as the emission devices.
K. Swing Joints:
a. Spray heads and Rotor Heads: Swing joint risers as detailed, with one Schedule 80 threaded risers, three Schedule 40 st. ell, Field assembled, swing pipe, snap, and “funny pipe” risers, and “Marlex” fittings are not allowed. No premanufacture swing joints permitted.
L. Reclaimed, or Reuse water. Furnish PVC pipe that is tinted purple and imprinted with the warning “Caution: Reclaimed Water – Do Not Drink” Provide pipe meeting the same AWWA and ASTM specifications as the potable water pipe sizes on which they are based.
M. Fittings – PVC (Polyvinyl Chloride) Type I, white Schedule 40 and grey Schedule 80, approved per ASTM D-1784, ASTM D-2466, and ASTM-D2467 or ASTM-D2464, as
September 16, 2026 Page 17 of 48 applicable. All PVC fittings shall be marked with manufacturer’s name, kind of pipe, material, IPS, class or schedule. Use of male adapters and cross fittings is not allowed.
N. Repair Fittings:
1. 3” and under: PVC Compression coupler or approved equal. No slip fix couplers allowed.
2. Over 3”: 211 JCM Ductile iron coupling or approved equal.
3. Not allowed: Slip-Fix Fittings, Telescoping Coupling, Kwik Repair, or similar methods.
2.5 PVC Cleaner and Primer – “Weld-on Purple P-70” or approved equal.
2.6 PVC Solvent Cement – “Weld-on 711”, “Christy’s Gray Heavy PVC Cement” or approve equal.
The expiration date shall not be exceeded.
2.7 Pipe Joint Tape – Teflon tape or approved on all threaded metal and PVC joints. Tape is to be food and water safe on all potable connections. Teflon paste may be used on metal threaded joints only.
2.8 Unless otherwise specified, water procurement, installation, and associated costs will be the responsibility of the Agency.
2.9 Backflow Prevention devices – Backflow prevention devices will be shown on the plans. Furnish and install backflow prevention devices meeting the requirements of the State of Idaho and the local water purveyor regulations.
A. Below grade install - Wilkins “950XLT2” or approved equal. Size as shown on Plans.
B. Above grade install – Wilkins 975XL2 RPBA or approved equal. Size as shown on the Plans.
2.10 Flow Sensor
A. 2” and below – Rainbird FS200B-2 Brass Tee Flow Sensor or approved equal. Size as shown on plans.
B. 2.5” to 4” – Badger M2000 or approved equal. Size as shown on the plans.
C. 6” and above – Badger M2000 or equivalent w/ metal body and flanges.
2.11 Valves
September 16, 2026 Page 18 of 48
A. Angled Gate Valves
1. LEEMCO lateral connection system and saddle tee or approved equal. Size per plan.
B. Manual Drain Valves:
1. 2” and under - Matco-Norca or approved equal. Size as shown on the plans.
2. Over 2” - Resilient Wedge Gate Valve size as shown on the plans.
C. Quick Coupling Valve: Rainbird “44LRC” or approved equal. For non-potable water systems Rain Bird “44NP” or approved equal.
D. Isolation Valve:
1. 2” and under - Matco-Norca or approved equal. Size as shown on the plans.
2. Over 2” - LEEMCO Mechanical restrained Wedge Gate Valve or approved equal.
Size as shown on the plans.
E. Electric Remove Control Valves: Rainbird PESB valves, sizes as shown on the plans
2.12 Valve Boxes and Lids
A. Backflow Prevention Device:
1. Above Grade – GS-3 Hinged Enclosure manufactured by Guardshack with green color and installed with a lock shield bracket or approved equal.
2. Below Grade
a. 2” and under Jumbo Carson Box - #2436 with flush cover, green, bolted closed.
b. 2” and above Carson Valve Box - #2436 with flush cover, green, bolted closed.
B. Electric remote-control and Isolation valves (2” and under), Electric master valve, Flow sensor:
Carson jumbo box Spec grade box - 1220, Green, bolted closed AND Carson jumbo box extension PN:1220-6 for bottom box.
C. Isolation valves (over 2”) Carson #910 with T-Cover, green, bolted closed with 4” Minimum Size, Class 160 PVC sleeve down to valve.
D. Quick Coupler – Carson #910-10 with T-Cover, green, bolted closed.
E. Drain Valve – Carson #910-10 with T-Cover, green, bolted closed
F. In traffic bearing situations use traffic bearing concrete or polymer concrete boxes and lids rated for AASHTO H-20 highway loading. Sizes equivalent to above.
September 16, 2026 Page 19 of 48
2.13 Irrigation Wire
A. Control wire must be insulated; single strand copper designed for 24 volt or higher. It shall be 14 gauge underground approved copper wire.
B. Copper conductors must meet or exceed ASTMB-2 specifications.
C. Control wire must be U.L. approved as type U.F. (underground feeder).
D. Red and white colors are required.
Valve wires to be red
Common wire to be white
E. Sufficient quantities must be supplied to meet splice and extra wire requirements listed under control wire installation.
F. All control wires shall be labeled at each end as to initial connection at controller and respective valve, in a permanent fashion.
2.14 Wire Connectors – 3M “DBRY” or approved equal.
2.15 Detectable Marking Tape – Use detectable marking tape consisting of inert polyethylene plastic that is impervious to all know alkalis, acids, chemical agents and solvents likely to be encountered in the soil with metallic foil core to provide the most positive detection by pipeline locators. Furnish color-coded tape with the type of line buried below and the word “Caution” imprinted continuously over its entire length in permanent black ink. Provide tape of the width recommended by manufacturer for the depth of installation used.
2.16 Tracer Wire – Copper #18 AWG minimum, UL listed, Blue
2.17 Sprinkler Heads – Makes and models shown on Plans.
2.18 Automatic Controller Cabinet – Provide one or more of the following, as specified on the Plans:
a. Baseline SS-Series Pedestal for BaseStation 3200
September 16, 2026 Page 20 of 48
b. V.I.T. Products, Inc. “SB24SS/LMLC”, all doors and access panels to be lockable with padlock.
2.19 Conduit and Fittings
A. Under ground: Sch. 40 grey PVC, Class III, conforming to UL Standard 651.
B. Above ground: Rigid Conduit, conforming to UL Standard 6A.
C. Conduits through walls shall be LB conduits.
D. Sweep ells shall be minimum 24” radius.
2.20 Grounding Equipment
A. Ground Rods: UL listed 5/8” x 8’ copper clad ground rod, with ground rod wire clamps as required per NEC.
B. Ground Wire: #6 AWG solid, soft-annealed uncoated copper, conforming to UL standard 719 per NEC.
2.21 Bedding and Backfill Materials
A. Mainline and Lateral Lines: Native on-site soil, free of rock and other deleterious materials. If rock or other deleterious materials are encountered, notify Owner’s Representative, and use clean fill sand if directed.
PART 3 QUALITY ASSURANCE
A. Comply with requirements of utility supplying water for prevention of backflow and back siphonage. Comply with appropriate water rights.
B. Installer Qualifications: Engage an experienced Installer with a minimum of five years of experience who has completed irrigation systems similar in material, design, and extent to that indicated Projects that…