This is a Bid Notice and associated contract documents issued by the City of Pittsburg, California for Project No. 3040, the Buchanan Park Pond Loop Replacement. The project involves demolition and replacement of existing deteriorated concrete pedestrian pathways within Buchanan Park located at 4150 Harbor St, Pittsburg, CA 94565. Work includes clearing and grubbing, selective tree removal, concrete and asphalt demolition, construction of new concrete walkways, installation of Class II riprap with geotextile fabric for bank stabilization, erosion and sediment control measures, traffic and pedestrian control, protection and reinstallation of existing park amenities, and restoration of disturbed areas. Sealed bids are due by Thursday, September 24, 2026, at 11:00 a.m. at City Hall, 65 Civic Avenue, Pittsburg, California. A non-mandatory pre-bid meeting will be held at the project site on Thursday, September 17, 2026, at 11:00 a.m. The City anticipates work will begin on or about Monday, November 16, 2026, with a completion requirement of 60 calendar days from the start date. The contract will be awarded within 60 days after bid opening to the responsible bidder submitting the lowest responsive bid. The base bid schedule includes eight line items covering mobilization, clearing and grubbing, erosion and sediment control, concrete removal, concrete sidewalk installation (4,200 SF), tree removal (2 each), Class II riprap (50 cubic yards), and geotextile fabric (132 square yards), with two additive alternates for additional sidewalk and riprap work.
The estimated construction cost is $181,500. Bidders must be registered with the California Department of Industrial Relations (DIR) and possess either a Class A General Engineering or C-8 Concrete Contractor license. Bid security of ten percent of the maximum bid amount is required in the form of a cashier's check, certified check, or bid bond. The successful bidder must submit performance and payment bonds for 100% of the contract price within ten days of receiving the Notice of Potential Award. This project is subject to California prevailing wage requirements under Labor Code Section 1720 et seq., with rates available at http://www.dir.ca.gov/DLSR. The prime contractor must perform at least 50% of the work with its own forces, except for work designated as Specialty Work. All subcontractors performing work in excess of one-half of 1% of the base bid price must be listed with DIR registration numbers. Liquidated damages are assessed at $1,500 per day for each day of unexcused delay beyond the 60-calendar-day completion period. The contract incorporates City of Pittsburg standard details and specifications (dated 2022) and California Department of Transportation standards (dated 2025).
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project No. 3040 Buchanan Park Pond Loop Replacement
3040 final plans.pdf
City of Pittsburg, California logo
Notice inviting bids, bid proposal, contract documents, general and special conditions and technical specifications
For the construction of
Project No. 3040
BUCHANAN PARK POND LOOP REPLACEMENT
In Pittsburg, California
To be used in conjunction with:
City of Pittsburg standard details and specifications (dated 2022 and current updates), standard specifications and plans issued by the State of California, Department of Transportation (dated 2025 and current updates)
August 2026
Accepted for use:
Blue signature above a line for John Samuelson, PE C-67734, Public Works Director/City Engineer
John Samuelson, PE C-67734 Public Works Director/City Engineer
EL Buchanan Park Pond Loop - Title sheet - G1
SM plan Buchanan Park Pond Loop - 8.19.26 - G-2
SM plan Buchanan Park Pond Loop - 8.19.26 - C-1
SM plan Buchanan Park Pond Loop - 8.19.26 - C-2
SM plan Buchanan Park Pond Loop - 8.19.26 - C-3
Table of contents
Notice Inviting Bids 1
Instructions to Bidders 3
Bid Proposal 10
Bid Schedule 13
9/9/26, 6:03 PM Project No. 3040 Buchanan Park Pond Loop Replacement https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F6392343… 1/293
Subcontractor List 15
Noncollusion Declaration 16
Bid Bond 17
Bidder's Questionnaire 19
Contract 22
Payment Bond 27
Performance Bond 29
General Conditions 31
Article 1 - Definitions 31
Definitions 31
Article 2 - Roles and Responsibilities 33
2.1 City 33
2.2 Contractor 34
2.3 Subcontractors 37
2.4 Coordination of Work 37
2.5 Submittals 38
2.6 Shop Drawings 39
Article 3 - Contract Documents 39
3.1 Interpretation of Contract Documents 39
3.2 Order of Precedence 40
3.3 Caltrans Standard Specifications 41
3.4 For Reference Only 41
3.5 Current Versions 41
3.6 Conformed Copies 41
Article 4 - Bonds, Indemnity, and Insurance 42
4.1 Payment and Performance Bonds 42
4.2 Indemnity 42
4.3 Insurance 42
Article 5 - Contract Time 44
5.1 Time is of the Essence 44
5.2 Schedule Requirements 45
5.3 Delay and Extensions of Contract Time 47
5.4 Liquidated Damages 50
https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F6392343… 2/293
Article 6 - Contract Modification 50
6.1 Contract Modification 50
6.2 Contractor Change Order Requests 52
6.3 Adjustments to Contract Price 52
6.4 Unilateral Change Order 53
6.5 Non-Compliance Deemed Waiver 53
6.6 Post-Bid Cost Increases 53
Article 7 - General Construction Provisions 53
7.1 Permits, Fees, Business License, and Taxes 53
7.2 Temporary Facilities 54
7.3 Noninterference and Site Management 54
7.4 Signs 55
7.5 Project Site and Nearby Property Protections 55
7.6 Materials and Equipment 56
7.7 Substitutions 57
7.8 Testing and Inspection 57
7.9 Project Site Conditions and Maintenance 58
7.10 Instructions and Manuals 60
7.11 As-built Drawings 60
7.12 Existing Utilities 60
7.13 Notice of Excavation 61
7.14 Trenching and Excavations of Four Feet or More 61
7.15 Trenching of Five Feet or More 62
7.16 New Utility Connections 62
7.17 Lines and Grades 62
7.18 Historic or Archeological Items 62
7.19 Environmental Control 62
7.20 Noise Control 63
7.21 Mined Materials 63
Article 8 - Payment 63
8.1 Schedule of Values 63
8.2 Progress Payments 63
https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F6392343… 3/293
8.3 Adjustment of Payment Application 64
8.4 Early Occupancy 65
8.5 Retention 65
8.6 Payment to Subcontractors and Suppliers 65
8.7 Final Payment 66
8.8 Release of Claims 66
8.9 Warranty of Title 66
Article 9 - Labor Provisions 66
9.1 Discrimination Prohibited 66
9.2 Labor Code Requirements 66
9.3 Prevailing Wages 67
9.4 Payroll Records 67
9.5 Labor Compliance 68
Article 10 - Safety Provisions 68
10.1 Safety Precautions and Programs 68
10.2 Hazardous Materials 68
10.3 Material Safety 69
10.4 Hazardous Condition 69
10.5 Emergencies 69
Article 11 - Completion and Warranty Provisions 69
11.1 Final Completion 69
11.2 Warranty 70
11.3 Use Prior to Final Completion 71
11.4 Substantial Completion 71
Article 12 - Dispute Resolution 72
12.1 Claims 72
12.2 Claims Submission 72
12.3 City’s Response 74
12.4 Meet and Confer 74
12.5 Mediation and Government Code Claims 74
12.6 Tort Claims 75
12.7 Arbitration 75
12.8 Burden of Proof and Limitations 75
https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F6392343… 4/293
12.9 Legal Proceedings 75
12.10 Other Disputes 75
Article 13 - Suspension and Termination 76
13.1 Suspension for Cause 76
13.2 Suspension for Convenience 76
13.3 Termination for Default 76
Table of contents
13.4 Termination for Convenience 78
13.5 Actions Upon Termination for Default or Convenience 78
Article 14 - Miscellaneous Provisions 79
14.1 Assignment of Unfair Business Practice Claims 79
14.2 Provisions Deemed Inserted 79
14.3 Waiver 80
14.4 Titles, Headings, and Groupings 80
14.5 Statutory and Regulatory References 80
14.6 Survival 80
Special Conditions 81
Technical specifications
Section 011000 Summary Section 012200 Unit Prices Section 012300 Alternates Section 012500 Substitution Procedures Section 012600 Contract Modification Procedures Section 012613 Requests for Interpretation Section 012900 Payment Procedures Section 013100 Project Management and Coordination Section 013200 Construction Progress Documentation Section 013216 Construction Progress Schedule Section 013300 Submittal Procedures Section 014100 Regulatory Requirements Section 014200 References Section 014213 Abbreviations Section 014300 Quality Assurance Section 014500 Quality Control Section 015000 Temporary Facilities and Controls https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F6392343… 5/293
Section 015526 Temporary Traffic Control Section 015610 Protection of Property Section 015723 Storm Water Pollution Protection Plan Section 016000 Product Requirements Section 017000 Execution Section 017113 Mobilization Section 017123 Construction Surveying Section 017329 Cutting and Patching Section 017419 Construction Waste Management and Disposal Section 017700 Closeout Requirements Section 017700 Closeout Submittal Section 022113 Survey Monuments Section 023219 Exploratory Excavations Section 024100 Demolition Section 310513 Clearing & Grubbing, Excavation, and Earthwork Section 310514 Subgrade Enhancement Geosynthetic Section 321123 Aggregate Base Courses Section 321313 Concrete Surface Improvements
Appendices
APPENDIX A - RESOLUTION 93-8022
APPENDIX B - CONTRACT PLANS
APPENDIX C - WATER METER APPLICATION
Notice Inviting Bids
1. Bid Submission. City of Pittsburg (“City”) will accept sealed bids for its Buchanan Park Pond Loop Replacement (“Project”), by or before Thursday, September 24, 2026, at 11:00 a.m., at its City Hall office, located at 65 Civic Avenue, First Floor, Pittsburg, California, at which time the bids will be publicly opened and read aloud.
2. Project Information.
2.1 Location and Description. The Project is located at Buchanan Park, 4150 Harbor St, Pittsburg, CA 94565 and is described as follows: The work generally consists of demolition and replacement of existing deteriorated concrete pedestrian pathways within Buchanan Park, including associated site improvements to restore safe and compliant pedestrian access around the pond. Work includes clearing and grubbing, selective tree removal, concrete and asphalt demolition, construction of new concrete walkways, installation of Class II riprap with geotextile fabric for bank stabilization, erosion and sediment control measures, traffic and pedestrian control, protection and reinstallation of existing park amenities, restoration of disturbed areas, and all incidental work necessary to complete the project in accordance with the Plans and Specifications.
https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F6392343… 6/293
2.2 Time for Final Completion. The Project must be fully completed within 60 calendar days from the start date set forth in the Notice to Proceed. City anticipates that the Work will begin on or about Monday, November 16, 2026, but the anticipated start date is provided solely for convenience and is neither certain nor binding.
2.3 Estimated Cost for Base Bid: The estimated construction cost is $181,500.
3. License and Registration Requirements.
3.1 License. This Project requires a valid California contractor’s license for the following classification(s): Class A General Engineering or C-8 Concrete Contractor.
3.2 DIR Registration. City may not accept a Bid Proposal from or enter into the Contract with a bidder, without proof that the bidder is registered with the California Department of Industrial Relations (“DIR”) to perform public work pursuant to Labor Code § 1725.5, subject to limited legal exceptions.
4. Contract Documents. The plans, specifications, bid forms and contract documents for the Project, and any addenda thereto (“Contract Documents”) may be downloaded from City’s website located at: http://www.pittsburgca.gov/business/current-bidding-opportunities. A printed copy of the Contract Documents is not available.
5. Bid Security. The Bid Proposal must be accompanied by bid security of ten percent of the maximum bid amount, in the form of a cashier’s or certified check made payable to City, or a bid bond executed by a surety licensed to do business in the State of California on the Bid Bond form included with the Contract Documents. The bid security must guarantee that within ten days after City issues the Notice of Potential Award, the successful bidder will execute the Contract and submit the payment and performance bonds, insurance certificates and endorsements, valid Certificates of Reported Compliance as required under the California Air Resources Board’s In-Use Off-Road Diesel- Fueled Fleets Regulation (13 CCR § 2449 et seq.) (“Off-Road Regulation”), if applicable, and any other submittals required by the Contract Documents and as specified in the Notice of Potential Award.
Buchanan Park Pond Loop Replacement Project 3040 2026 Form NOTICE INVITING BIDS
6. Prevailing wage requirements.
6.1 General. Pursuant to California Labor Code § 1720 et seq., this Project is subject to the prevailing wage requirements applicable to the locality in which the Work is to be performed for each craft, classification or type of worker needed to perform the Work, including employer payments for health and welfare, pension, vacation, apprenticeship and similar purposes.
6.2 Rates. The prevailing rates are on file with the City and are available online at http://www.dir.ca.gov/DLSR. Each Contractor and Subcontractor must pay no less than the specified rates to all workers employed to work on the Project. The schedule of per diem wages is based upon a working day of eight hours. The rate for holiday and overtime work must be at least time and one-half.
6.3 Compliance. The Contract will be subject to compliance monitoring and enforcement by the DIR, under Labor Code § 1771.4.
7. Performance and payment bonds. The successful bidder will be required to provide performance and payment bonds, each for 100% of the Contract Price, as further specified in the Contract
9/9/26, 6:03 PM Project No. 3040 Buchanan Park Pond Loop Replacement https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F6392343… 7/293 http://www.pittsburgca.gov/business/current-bidding-opportunities http://www.dir.ca.gov/DLSR
Documents.
8. Substitution of securities. Substitution of appropriate securities in lieu of retention amounts from progress payments is permitted under Public Contract Code § 22300.
9. Subcontractor list. Each Subcontractor must be registered with the DIR to perform work on public projects. Each bidder must submit a completed Subcontractor List form with its Bid Proposal, including the name, location of the place of business, California contractor license number, DIR registration number, and portion of the Work to be performed for each Subcontractor that will perform Work or service, or fabricate and install Work, for the prime contractor in excess of one-half of 1% of the total bid price, using the Subcontractor List form included with the Contract Documents.
10. Instructions to bidders. All bidders should carefully review the Instructions to Bidders for more detailed information before submitting a Bid Proposal. The definitions provided in Article 1 of the General Conditions apply to all of the Contract Documents, as defined therein, including this Notice Inviting Bids.
By: John Samuelson signature Date: 8/26/26
John Samuelson, Public Works Director/City Engineer
Publication Date: August 28, 2026
End of notice inviting bids
Buchanan Park Pond Loop Replacement Project 3040 2026 Form Notice Inviting Bids
Instructions to Bidders
Each Bid Proposal submitted to City of Pittsburg (“City”) for its Buchanan Park Pond Loop Replacement (“Project”) must be submitted in accordance with the following instructions and requirements:
1. Bid Submission.
1.1 General. Each Bid Proposal must be completed, using the form provided in the Contract Documents, signed, and submitted to City in a sealed envelope, with all required forms and attachments, by or before the date and time set forth in Section 1 of the Notice Inviting Bids, or as amended by subsequent addendum. Faxed or emailed Bid Proposals will not be accepted, unless otherwise specified. Late submissions will be returned unopened. City reserves the right to postpone the date or time for receiving or opening bids. Each bidder is solely responsible for all of its costs to prepare and submit its bid and by submitting a bid waives any right to recover those costs from City. The bid price(s) must include all costs to perform the Work as specified, including all labor, materials, supplies, and equipment and all other direct or indirect costs such as applicable taxes, insurance and overhead.
1.2 Bid Envelope. The sealed envelope containing the Bid Proposal and all required forms and attachments must be clearly labeled and addressed as follows:
BID PROPOSAL:
Buchanan Park Pond Loop Replacement Project Contract No. 3040 https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F6392343… 8/293
City Clerk 65 Civic Avenue Pittsburg, CA 94565 Attn: Alice E. Evenson
The envelope must also be clearly labeled, as follows, with the bidder’s name, address, and its registration number with the California Department of Industrial Relations (“DIR”) for bidding on public works contracts (Labor Code §§ 1725.5 and 1771.1):
[Contractor company name] [street address] [city, state, zip code] DIR Registration No: ____________________
1.3 DIR Registration. Subject to limited legal exceptions for joint venture bids and federally-funded projects, City may not accept a Bid Proposal from a bidder without proof that the bidder is registered with the DIR to perform public work under Labor Code § 1725.5. If City is unable to confirm that the bidder is currently registered with the DIR, City may disqualify the bidder and return its bid unopened. (Labor Code §§ 1725.5 and 1771.1(a).)
2. Bid Proposal Form and Enclosures. Each Bid Proposal must be completed in ink using the Bid Proposal form included with the Contract Documents. The Bid Proposal form must be fully completed without interlineations, alterations, or erasures. Any necessary corrections must be clear and legible, and must be initialed by the bidder’s authorized representative. A Bid Proposal submitted with exceptions or terms such as “negotiable,”
Buchanan Park Pond Loop Replacement Project 3040 2026 Form INSTRUCTIONS TO BIDDERS
“will negotiate,” or similar, will be considered nonresponsive. Each Bid Proposal must be accompanied by bid security, as set forth in Section 4 below, and by a completed Subcontractor List and Noncollusion Declaration using the forms included with the Contract Documents, and any other required enclosures, as applicable.
3. Authorization and Execution. Each Bid Proposal must be signed by the bidder’s authorized representative. A Bid Proposal submitted by a partnership must be signed in the partnership name by a general partner with authority to bind the partnership. A Bid Proposal submitted by a corporation must be signed with the legal name of the corporation, followed by the signature and title of two officers of the corporation with full authority to bind the corporation to the terms of the Bid Proposal, under California Corporations Code § 313.
4. Bid Security. Each Bid Proposal must be accompanied by bid security of ten percent of the maximum bid amount, in the form of a cashier’s check or certified check, made payable to the City, or bid bond using the form included in the Contract Documents and executed by a surety licensed to do business in the State of California. The bid security must guarantee that, within ten days after issuance of the Notice of Potential Award, the bidder will: execute and submit the enclosed Contract for the bid price; submit payment and performance bonds for 100% of the maximum Contract Price; submit the insurance certificates and endorsements; and submit valid Certificates of Reported Compliance as required by the Off-Road Regulation, if applicable, and any other submittals, if any, required by the Contract Documents or the Notice of Potential https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F6392343… 9/293
Award. A Bid Proposal may not be withdrawn for a period of 60 days after the bid opening without forfeiture of the bid security, except as authorized for material error under Public Contract Code § 5100 et seq.
5. Requests for Information. Questions or requests for clarifications regarding the Project, the bid procedures, or any of the Contract Documents must be submitted in writing to SM Saklaen, Senior Civil Engineer at ssaklaen@pittsburgca.gov. Oral responses are not authorized and are not binding on the City. Bidders should submit any such written inquiries at least five Working Days before the scheduled bid opening. Questions received any later might not be addressed before the bid deadline. An interpretation or clarification by City in response to a written inquiry will be issued in an addendum.
6. Pre-Bid Investigation.
6.1 General. Each bidder is solely responsible at its sole expense for diligent and thorough review of the Contract Documents, examination of the Project site, and reasonable and prudent inquiry concerning known and potential site and area conditions prior to submitting a Bid Proposal. Each bidder is responsible for knowledge of conditions and requirements which reasonable review and investigation would have disclosed. However, except for any areas that are open to the public at large, bidders may not enter property owned or leased by the City or the Project site without prior written authorization from City.
A “non-mandatory” pre-bid meeting shall be held at the Project site at 4150 Harbor St, Pittsburg, CA 94565, on Thursday September 17th, 2026 at 11:00 AM.
6.2 Document Review. Each bidder is responsible for review of the Contract Documents and any informational documents provided “For Reference Only,” e.g., as-builts, technical reports, test data, and the like. A bidder is responsible for notifying City of any errors, omissions, inconsistencies, or conflicts it discovers in the Contract Documents, acting solely in its capacity as a contractor and subject to the limitations of Public Contract Code § 1104. Notification of any such errors, omissions, inconsistencies, or conflicts must be submitted in writing to the City no
Buchanan Park Pond Loop Replacement Project 3040 2026 Form INSTRUCTIONS TO BIDDERS Page 4 later than five Working Days before the scheduled bid opening. (See Section 5, above.) City expressly disclaims responsibility for assumptions a bidder might draw from the presence or absence of information provided by City.
6.3 Project Site. Questions regarding the availability of soil test data, water table elevations, and the like should be submitted to the City in writing, as specified in Section 5, above. Any subsurface exploration at the Project site must be done at the bidder's expense, but only with prior written authorization from City. All soil data and analyses available for inspection or provided in the Contract Documents apply only to the test hole locations. Any water table elevation indicated by a soil test report existed on the date the test hole was drilled. The bidder is responsible for determining and allowing for any differing soil or water table conditions during construction. Because groundwater levels may fluctuate, difference(s) in elevation between ground water shown in soil boring logs and ground water actually encountered during construction will not be considered changed Project site conditions. Actual locations and depths must be determined by bidder's field investigation. The bidder may request access to underlying or background information on the Project site in City's
9/9/26, 6:03 PM Project No. 3040 Buchanan Park Pond Loop Replacement https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F639234… 10/293 mailto:ssaklaen@pittsburgca.gov possession that is necessary for the bidder to form its own conclusions, including, if available, record drawings or other documents indicating the location of subsurface lines, utilities, or other structures.
6.4 Utility Company Standards. The Project must be completed in a manner that satisfies the standards and requirements of any affected utility companies or agencies (collectively, “utility owners”). The successful bidder may be required by the third party utility owners to provide detailed plans prepared by a California registered civil engineer showing the necessary temporary support of the utilities during coordinated construction work. Bidders are directed to contact the affected third party utility owners about their requirements before submitting a Bid Proposal.
7. Bidders Interested in More Than One Bid. No person, firm, or corporation may submit or be a party to more than one Bid Proposal unless alternate bids are specifically called for. However, a person, firm, or corporation that has submitted a subcontract proposal or quote to a bidder may submit subcontract proposals or quotes to other bidders.
8. Addenda. Subject to the limitations of Public Contract Code § 4104.5, City reserves the right to issue addenda prior to bid time. Any addenda issued prior to the bid opening are part of the Contract Documents. Each bidder is solely responsible for ensuring it has received and reviewed all addenda prior to submitting its bid. Bidders should check City's website periodically for any addenda or updates on the Project at: https://www.pittsburgca.gov/business/current-bidding-opportunities.
9. Brand Designations and “Or Equal” Substitutions. Any specification designating a material, product, thing, or service by specific brand or trade name, followed by the words “or equal,” is intended only to indicate quality and type of item desired, and bidders may request use of any equal material, product, thing, or service. All data substantiating the proposed substitute as an equal item must be submitted with the written request for substitution. A request for substitution must be submitted within 35 days after Notice of Potential Award unless otherwise provided in the Contract Documents. This provision does not apply to materials, products, things, or services that may lawfully be designated by a specific brand or trade name under Public Contract Code § 3400(c).
10. Bid Protest. Any bid protest against another bidder must be submitted in writing and received by City at 65 Civic Avenue, Pittsburg, CA or sent via email at ssaklaen@pittsburgca.gov before 5:00 p.m.
no later than two Working Days following bid opening (“Bid Protest Deadline”) and must comply with the following requirements:
Buchanan Park Pond Loop Replacement Project 3040 2026 Form INSTRUCTIONS TO BIDDERS
10.1 General. Only a bidder who has actually submitted a Bid Proposal is eligible to submit a bid protest against another bidder. Subcontractors are not eligible to submit bid protests. A bidder may not rely on the bid protest submitted by another bidder, but must timely pursue its own protest. For purposes of this Section 10, a “Working Day” means a day that City is open for normal business, and excludes weekends and holidays observed by City. Pursuant to Public Contract Code § 4104, inadvertent omission of a Subcontractor’s DIR registration number on the Subcontractor List form is not grounds for a bid protest, provided it is corrected within 24 hours of the bid opening or as otherwise provided under Labor Code § 1771.1(b).
10.2 Protest Contents. The bid protest must contain a complete statement of the basis for the protest and must include all supporting documentation. Material submitted after the Bid Protest Deadline will not be considered. The protest must refer to the specific portion or portions of the Contract Documents upon which the protest is based. The protest must include the name, address, email
9/9/26, 6:03 PM Project No. 3040 Buchanan Park Pond Loop Replacement https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F6392343… 11/293 https://www.pittsburgca.gov/business/current-bidding-opportunities address, and telephone number of the protesting bidder and any person submitting the protest on behalf of or as an authorized representative of the protesting bidder.
10.3 Copy to Protested Bidder. Upon submission of its bid protest to City, the protesting bidder must also concurrently transmit the protest and all supporting documents to the protested bidder, and to any other bidder who has a reasonable prospect of receiving an award depending upon the outcome of the protest, by email or hand delivery to ensure delivery before the Bid Protest Deadline.
10.4 Response to Protest. The protested bidder may submit a written response to the protest, provided the response is received by City before 5:00 p.m., within two Working Days after the Bid Protest Deadline or after actual receipt of the bid protest, whichever is sooner (the “Response Deadline”). The response must attach all supporting documentation. Material submitted after the Response Deadline will not be considered. The response must include the name, address, email address, and telephone number of the person responding on behalf of or representing the protested bidder if different from the protested bidder.
10.5 Copy to Protesting Bidder. Upon submission of its response to the bid protest to the City, the protested bidder must also concurrently transmit by email or hand delivery, by or before the Response Deadline, a copy of its response and all supporting documents to the protesting bidder and to any other bidder who has a reasonable prospect of receiving an award depending upon the outcome of the protest.
10.6 Exclusive Remedy. The procedure and time limits set forth in this Section are mandatory and are the bidder’s sole and exclusive remedy in the event of a bid protest. A bidder’s failure to comply with these procedures will constitute a waiver of any right to further pursue a bid protest, including filing a Government Code Claim or initiation of legal proceedings.
10.7 Right to Award. City reserves the right, acting in its sole discretion, to reject any bid protest that it determines lacks merit, to award the Contract to the bidder it has determined to be the responsible bidder submitting the lowest responsive bid, and to issue a Notice to Proceed with the Work notwithstanding any pending or continuing challenge to its determination.
Buchanan Park Pond Loop Replacement Project 3040 2026 Form INSTRUCTIONS TO BIDDERS Page 6
11. Reservation of Rights. City reserves the unfettered right, acting in its sole discretion, to waive or to decline to waive any immaterial bid irregularities; to accept or reject any or all bids; to cancel or reschedule the bid; to postpone or abandon the Project entirely; or to perform all or part of the Work with its own forces. The Contract will be awarded, if at all, within 60 days after opening of bids or as otherwise specified in the Special Conditions, to the responsible bidder that submitted the lowest responsive bid. Any planned start date for the Project represents the City’s expectations at the time the Notice Inviting Bids was first issued. City is not bound to issue a Notice to Proceed by or before such planned start date, and it reserves the right to issue the Notice to Proceed when the City determines, in its sole discretion, the appropriate time for commencing the Work. The City expressly disclaims responsibility for any assumptions a bidder might draw from the presence or absence of information provided by the City in any form. Each bidder is solely responsible for its costs to prepare and submit a bid, including site investigation costs.
12. Bonds. Within ten calendar days following City’s issuance of the Notice of Potential Award to the successful bidder, the bidder must submit payment and performance bonds to City as specified in the Contract Documents using the bond forms included in the Contract Documents. All required bonds https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F639234… 12/293 must be calculated on the maximum total Contract Price as awarded, including additive alternates, if applicable.
13. License(s). The successful bidder and its Subcontractor(s) must possess the California contractor’s license(s) in the classification(s) required by law to perform the Work. The successful bidder must also obtain a City business license within 10 days following City’s issuance of the Notice of Potential Award. Subcontractors must also obtain a City business license before performing any Work.
14. Ineligible subcontractor. Any Subcontractor who is ineligible to perform work on a public works project under Labor Code §§ 1777.1 or 1777.7 is prohibited from performing work on the Project.
15. Safety orders. If the Project includes construction of a pipeline, sewer, sewage disposal system, boring and jacking pits, or similar trenches or open excavations, which are five feet or deeper, each bid must include a bid item for adequate sheeting, shoring, and bracing, or equivalent method, for the protection of life or limb, which comply with safety orders as required by Labor Code § 6707.
16. In-use off-road diesel-fueled fleets. If the Project involves the use of vehicles subject to the California Air Resources Board’s In-Use Off-Road Diesel-Fueled Fleets Regulation (13 CCR § 2449 et seq.) (“Off-Road Regulation”), then within ten calendar days following City’s issuance of the Notice of Potential Award to the successful bidder, the bidder must submit to City valid Certificates of Reported Compliance for its fleet and its listed Subcontractors, if applicable, in accordance with the Off-Road Regulation, unless exempt under the Off-Road Regulation.
17. Bid Schedule. Each bidder must complete the Bid Schedule form with unit prices as indicated, and submit the completed Bid Schedule with its Bid Proposal.
17.1 Incorrect Totals. In the event a computational error for any bid item (base bid or alternate) results in an incorrect extended total for that item, the submitted base bid or bid alternate total will be adjusted to reflect the corrected amount as the product of the estimated quantity and the unit cost. In the event of a discrepancy between the actual total of the itemized or unit prices shown on the Bid Schedule for the base bid, and the amount entered as the base bid on the Bid Proposal form, the actual total of the itemized or unit prices shown on the Bid Schedule for the base bid will be deemed the base bid price. Likewise, in the event of a discrepancy
Buchanan Park Pond Loop Replacement Project 3040 2026 Form INSTRUCTIONS TO BIDDERS Page 7 between the actual total of the itemized or unit prices shown on the Bid Schedule for any bid alternate, and the amount entered for the alternate on the Bid Proposal form, the actual total of the itemized prices shown on the Bid Schedule for that alternate will be deemed the alternate price.
Nothing in this provision is intended to prevent a bidder from requesting to withdraw its bid for material error under Public Contract Code § 5100 et seq.
17.2 Estimated quantities. Unless identified as a “Final Pay Quantity,” the quantities shown on the Bid Schedule are estimated and the actual quantities required to perform the Work may be greater or less than the estimated amount. The Contract Price will be adjusted to reflect the actual quantities required for the Work based on the itemized or unit prices provided in the Bid Schedule, with no allowance for anticipated profit for quantities that are deleted or decreased, and no increase in the unit price, and without regard to the percentage increase or decrease of the estimated quantity and the actual quantity.
https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F639234… 13/293
18. Bidder’s questionnaire. A completed, signed Bidder’s Questionnaire using the form provided with the Contract Documents and including all required attachments must be submitted within 48 hours following a request by City. A bid that does not fully comply with this requirement may be rejected as nonresponsive. A bidder who submits a Bidder’s Questionnaire which is subsequently determined to contain false or misleading information, or material omissions, may be disqualified as non-responsive.
19. Subcontractor work limits. The prime contractor must perform at least 50% of the Work on the Project, calculated as a percentage of the base bid price, with its own forces, except for any Work identified as “Specialty Work” in the Contract Documents. The total bid amount for any such Specialty Work, as shown on the Bid Schedule, may be deducted from the base bid price before computing the 50% self-performance requirement. The remaining Work may be performed by qualified Subcontractor(s).
20. Additive or deductive bid alternates. As required by Public Contract Code § 20103.8, if this bid solicitation includes additive or deductive bid alternates, the method checked below will be used to determine the lowest bid. If no method is checked, subparagraph (A) will be used to determine the lowest bid. City retains the right to add to or deduct from the Contract any of the additive or deductive bid alternates included in the Bid Proposal, based on the bid price provided for each such alternate. In addition, following award and execution of the Contract, City reserves the right to incorporate one or more of the bid alternates that were not included in the Contract as awarded. Any such post-award addition(s) and/or deduction(s) will be incorporated by Change Order and based on the bid price provided for each such alternate.
___ X ___ (A) The lowest bid will be the lowest bid price on the base contract without consideration of the prices on the additive or deductive items.
_____ (B) The lowest bid will be the lowest total of the bid prices on the base contract and those additive or deductive items that were specifically identified in the bid solicitation or Bid Proposal as being used for the purpose of determining the lowest bid price. The following alternate items will be used for the purpose of determining the lowest bid price.
_____ (C) The lowest bid will be the lowest total of the bid prices on the base contract and those additive or deductive items taken in order from a specifically identified list of those items that, when in the solicitation, and added to, or subtracted from, the base contract, are less than, or equal to, a funding amount publicly disclosed by City before the first bid is opened.
_____ (D) The lowest bid will be determined in a manner that prevents any information that
Buchanan Park Pond Loop Replacement 2026 Form INSTRUCTIONS TO BIDDERS Project 3040 Page 8 would identify any of the bidders or the proposed subcontractors or suppliers from being revealed to City before the ranking of all bidders from lowest to highest has been determined.
END OF INSTRUCTIONS TO BIDDERS
Buchanan Park Pond Loop Replacement Project 3040 2026 Form INSTRUCTIONS TO BIDDERS https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F639234… 14/293
Note about transcribed forms: this format exists to remove accessibility barriers, but some recipients prefer the original printed format. If you'd like help moving your entries into the original form, please use the live assistance options in the sidebar or contact the author.
Bid Proposal
Buchanan Park Pond Loop Replacement
Enter bidder name (“Bidder”) hereby submits this Bid Proposal to the City of Pittsburg (“City”) for the above-referenced project (“Project”) in response to the Notice Inviting Bids and in accordance with the Contract Documents referenced in the Notice.
1. Base Bid.
Bidder proposes to perform and fully complete the Work for the Project as specified in the Contract Documents, within the time required for full completion of the Work, including all labor, materials, supplies, and equipment and all other direct or indirect costs including, but not limited to, taxes, insurance and all overhead, for the following price (“Base Bid”):
Base Bid amount $ 0.00
2. Bid Alternates.
Bidder submits the following prices for the specified bid alternates:
Alternate #1: Additional Sidewalk Add amount $ 0.00
Alternate #2: Additional Riprap Add amount $ 0.00
3. Addenda.
Bidder agrees that it has confirmed receipt of or access to, and reviewed, all addenda issued for this bid. Bidder waives any claims it might have against the City based on its failure to receive, access, or review any addenda for any reason. Bidder specifically acknowledges receipt of the following addenda:
Addendum acknowledgements Addendum #01 date received mm/dd/yyyy Addendum #02 date received mm/dd/yyyy Addendum #03 date received mm/dd/yyyy
Addendum acknowledgements continued Addendum #05 date received mm/dd/yyyy Addendum #06 date received mm/dd/yyyy Addendum #07 date received mm/dd/yyyy https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F639234… 15/293
Addendum #04 date received mm/dd/yyyy
Addendum #08 date received mm/dd/yyyy4. Bidder’s Certifications and Warranties.
By signing and submitting this Bid Proposal, Bidder certifies and warrants the following:
4.1 Examination of Contract Documents.
Bidder has thoroughly examined the Contract Documents and represents that, to the best of Bidder’s knowledge, there are no errors, omissions, or discrepancies in the Contract Documents, subject to the limitations of Public Contract Code § 1104.
4.2 Examination of Worksite.
Bidder has had the opportunity to examine the Worksite and local conditions at the Project location.
4.3 Bidder Responsibility.
Bidder is a responsible bidder, with the necessary ability, capacity, experience, skill, qualifications, workforce, equipment, and resources to perform or cause the Work to be performed in accordance with the Contract Documents and within the Contract Time.
4.4 Responsibility for Bid.
Bidder has carefully reviewed this Bid Proposal and is solely responsible for any errors or omissions contained in its completed bid. All statements and information provided in this Bid Proposal and enclosures are true and correct to the best of Bidder's knowledge.
Buchanan Park Pond Loop Replacement Project 3040
2026 Form
Bid Proposal
4.5 Nondiscrimination. In preparing this bid, the Bidder has not engaged in discrimination against any prospective or present employee or Subcontractor on grounds of race, color, ancestry, national origin, ethnicity, religion, sex, sexual orientation, age, disability, or marital status.
4.6 Iran Contracting Act. If the Contract Price exceeds $1,000,000, Bidder is not identified on a list created under the Iran Contracting Act, Public Contract Code § 2200 et seq. (the “Act”), as a person engaging in investment activities in Iran, as defined in the Act, or is otherwise expressly exempt under the Act.
5. Award of Contract. By signing and submitting this Bid Proposal, Bidder agrees that, if City issues the Notice of Potential Award to Bidder, then within ten days following issuance of the Notice of Potential Award to Bidder, Bidder will do all of the following:
https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F639234… 16/293
5.1 Execute Contract. Enter into the Contract with City in accordance with the terms of this Bid Proposal, by signing and submitting to City the Contract prepared by City using the form included with the Contract Documents;
5.2 Submit Required Bonds. Submit to City a payment bond and a performance bond, each for 100% of the Contract Price, using the bond forms provided and in accordance with the requirements of the Contract Documents;
5.3 Insurance Requirements. Submit to City the insurance certificate(s) and endorsement(s) as required by the Contract Documents; and
5.4 Certificates of Reported Compliance. Submit to City valid Certificates of Reported Compliance for its fleet and its listed Subcontractors, if applicable, if the Project involves the use of vehicles subject to the Off-Road Regulation. (See Section 16 of the Instructions to Bidders.)
6. Bid Security. As a guarantee that, if awarded the Contract, Bidder will perform its obligations under Section 4 above, Bidder is enclosing bid security in the amount of ten percent of its maximum bid amount in one of the following forms (check one):
Bid security A cashier’s check or certified check payable to City and issued by
Bank name Enter bank name
Amount 0.00
A bid bond, using the Bid Bond form included with the Contract Documents, payable to City and executed by a surety licensed to do business in the State of California.
Bid submission and signatures This Bid Proposal is hereby submitted on
Date mm/dd/yyyy
Year 20__
Signature s/
Name and Title Enter name and title
Signature s/ [See Section 3 of Instructions to Bidders]
Name and Title Enter name and title
Company Name Enter company name
License #, Expiration Date, and Classification License number, expiration date, classification
Buchanan Park Pond Loop Replacement Project 3040
2026 Form Bid proposal
Address Street address
DIR Registration # Registration number
City, State, Zip City, State ZIP
Phone
(555) 555-5555 https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F639234… 17/293
Contact Name Full name
Contact Email name@example.com
End of bid proposal
Buchanan Park Pond Loop Replacement Project 3040
2026 Form Bid proposal
Bid Schedule
Bid schedule form Bidder name:
This Bid Schedule must be completed in ink and included with the sealed Bid Proposal. Pricing must be provided for each item as indicated. Items marked “(SW)” are Specialty Work that must be performed by a qualified subcontractor. The lump sum or unit cost for each item must be inclusive of all costs, whether direct or indirect, including profit and overhead.
AL = Allowance CY = Cubic Yard SY = Square Yard
EA = Each LB = Pounds LF = Linear Foot
LS = Lump Sum SF = Square Feet TON = Ton (2000 lbs)
Base bid
Bid item no. Item description Est. qty. Unit Unit cost Extended total amount
1 Mobilization 1 LS
2 Clearing and Grubbing 1 LS
Erosion & Sediment Control
1 LS
4 Concrete Removal 4200 SF
Concrete Sidewalk (4”
PCC)
4200 SF
https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F639234… 18/293
Bid item no. Item description Est. qty. Unit Unit cost Extended total amount
6 Tree Removal 2 EA
7 Class II Riprap 50 CY
8 Geotextile Fabric 132 SY
* Final Pay Quantity
Total base bid:
Items 1 through 8 inclusive: $
Note: The amount entered as the “Total Base Bid” should be identical to the base bid amount entered in Section 1 of the Bid Proposal form.
Bid alternate(s)
Add alternate #1: Additional sidewalk
Item no. Item description Est. qty. Unit Unit cost Extended total amount
A10 Concrete Removal 1200 SF
A11 Concrete Sidewalk (4”
PCC)
1200 SF
Total for add alternate #1:
Items A10 through A11 inclusive: $
Note: The amount entered as the total for this alternate should be identical to the amount entered for this alternate in the Bid Proposal form.
Buchanan Park Pond Loop Replacement Project 3040
2026 Form Bid schedule
Add alternate #2: Additional riprap
Item no. Item description Est. qty. Unit Unit cost Extended total amount
A20 Class II Riprap 65 CY https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F639234… 19/293
Add alternate #2: Additional riprap
Item no. Item description Est. qty. Unit Unit cost Extended total amount
A21 Geotextile Fabric 180 SY
Total for add alternate #2
Items A20 through A21 inclusive:
Total amount
Note: The amount entered as the total for this alternate should be identical to the amount entered for this alternate in the Bid Proposal form.
End of bid schedule
Buchanan Park Pond Loop Replacement Project 3040
2026 Form Bid schedule
Subcontractor List
For each Subcontractor that will perform Work in an amount in excess of one-half of 1% of the
Bidder’s total Base Bid,1 the bidder must list a description of the Work, the name of the Subcontractor, its California contractor license number, the location of its place of business, and its DIR registration number. If the Instructions to Bidders include a provision on “Subcontractor Work Limits,” the bidder must also list the percentage of Work to be performed by the Subcontractor (based on a percentage of the Base Bid price) in the “Percent of Work” column.
DESCRIPTIO
N OF WORK
SUBCONTRA
CTOR NAME
CALIFORNIA
CONTRACTO
R LICENSE
NO.
LOCATION
OF
BUSINESS
DIR REG. NO. PERCENT OF
WORK
https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F639234… 20/293
DESCRIPTIO
N OF WORK
SUBCONTRA
CTOR NAME
CALIFORNIA
CONTRACTO
R LICENSE
NO.
LOCATION
OF
BUSINESS
DIR REG. NO. PERCENT OF
WORK
END OF SUBCONTRACTOR LIST
1 For street or highway construction, this requirement applies to any subcontract of $10,000 or more.
Buchanan Park Pond Loop Replacement Project 3040
2026 Form https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F639234… 21/293
Subcontractor List
Noncollusion Declaration
To Be Executed by Bidder and Submitted with Bid
The undersigned declares:
Bidder information Title Business name
I am the above-named title holder of the above business name, the party making the foregoing bid.
The bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation. The bid is genuine and not collusive or sham. The bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or to refrain from bidding. The bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder. All statements contained in the bid are true. The bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company, association, organization, bid depository, or to any member or agent thereof, to effectuate a collusive or sham bid, and has not paid and will not pay any person or entity for such purpose.
Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability company, limited liability partnership, or any other entity, hereby represents that he or she has full power to execute, and does execute, this declaration on behalf of the bidder.
This declaration is intended to comply with California Public Contract Code § 7106 and Title 23 U.S.C. § 112.
I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is executed on the date and at the location entered below.
Execution details Date mm/dd/yyyy
City
State
Signature s/ Signature Name (print)
End of Noncollusion Declaration https://docaccess.com/docviewer.html?url=https%3A%2F%2Fwww.pittsburgca.gov%2Fhome%2Fshowpublisheddocument%2F18700%2F639234… 22/293
Buchanan Park Pond Loop Replacement 2026 Form Noncollusion Declaration Project 3040
Bid Bond
Bidder name
(“Bidder”) has submitted a bid, dated mm/dd/yyyy , 20 (“Bid”), to City of Pittsburg (“City”) for work on the Buchanan Park Pond Loop Replacement (“Project”). Under this duly executed bid bond (“Bid Bond”), Bidder as Principal and Surety name
, its surety (“Surety”), are bound to City as obligee in the penal sum of ten percent of the maximum amount of the Bid (the “Bond Sum”). Bidder and Surety bind themselves and their respective heirs, executors, administrators, successors and assigns, jointly and severally, as follows:
1. General. If Bidder is awarded the Contract for the Project, Bidder will enter into the Contract with City in accordance with the terms of the Bid.
2. Submittals. Within ten days following issuance of the Notice of Potential Award to Bidder, Bidder must submit to City the following:
1. Contract. The executed Contract,…