Bid Documents (30).pdf

PDF 9 MB Posted

Attached to
Sila, Section 11 Reinforced Concrete Paving
Solicitation number
13287-10
Issued by
Travis County, Texas

About this file

Summary

This is a bid documents package for construction of reinforced concrete paving prepared by Lennar Homes of Texas Land and Construction, Ltd. on behalf of Harris County Municipal Utility District No. 514 in Harris County, Texas. The project, titled "Sila, Section 11 Reinforced Concrete Paving," encompasses approximately 13,808 square yards of 6-inch subgrade preparation, 12,220 square yards of 6-inch reinforced concrete pavement, and 7,004 linear feet of reinforced concrete curb, with additional work including site preparation, storm water pollution control, signage, mailbox pads, and wheelchair ramps. Sealed bids in duplicate are due by 10:30 AM Local Time on Tuesday, August 4, 2026, at the office of BGE, Inc., 10777 Westheimer, Suite 500, Houston, Texas 77042, or electronically through www.civcastusa.com. A non-mandatory pre-bid conference is scheduled for Tuesday, July 28, 2026, at 10:30 AM via Microsoft Teams. Bidders must demonstrate qualifications including successful completion of four similar projects in the Houston area within the last three years under the same firm's direction. The contract award will be made to the responsible bidder submitting the lowest responsive bid, with execution of contract documents and provision of required bonds and insurance certificates due within seven days of the Notice of Award.

Bid security of five percent of the total bid amount is required in the form of a certified check, cashier's check, or bid bond. The project owner is exempt from Texas sales and use taxes as a political subdivision, and all contractors and subcontractors must issue Texas Sales and Use Tax Exemption Certifications for applicable purchases. Prevailing wage requirements apply to this project pursuant to Texas Government Code Chapter 2258, with wage rates established according to United States Department of Labor Davis-Bacon Act determinations for Harris County Heavy Construction Projects, Highway Construction Projects, and Building Construction Projects. The contract includes liquidated damages of $1,500.00 per calendar day for failure to complete work within the specified contract time, and contractors must comply with Subchapter J, Chapter 552, Texas Government Code, regarding preservation and provision of contracting information. All bids must include a completed, signed, and notarized Texas Ethics Commission Form 1295 with an assigned certificate number.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Lennar Homes of Texas Land and Construction, Ltd.

on behalf of

Harris County Municipal Utility District No. 514

Contract Documents and Specifications for Construction of

Sila, Section 11 Reinforced Concrete Paving

Harris County, Texas

July 2026

TBPE Registration No. F-1046

10777 Westheimer, Suite 500 Houston, Texas 77042

281-558-8700

07/23/2026

DEV (OBO)

\\bgeinc\data2\00013287-10\LD-Single_Phase\03_Constr\01_Bid_Phase\03_Paving\02_Bid_Docs\01_Front_Ends\Cover and TOC.docx

Contract Documents and Specifications for Construction of

Sila, Section 11 Reinforced Concrete Paving

Harris County, Texas

CONTENTS

I. INVITATION TO BIDDERS

II. INSTRUCTIONS TO BIDDERS

III. BID

IV. STANDARD FORM OF AGREEMENT

V. PERFORMANCE BOND

VI. PAYMENT BOND

VII. MAINTENANCE BOND

VIII. GENERAL CONDITIONS OF THE AGREEMENT

IX. SUPPLEMENTARY CONDITIONS

X. CONTRACTOR’S CONSTRUCTION FORMS

• X(A) TEXAS – CONDITIONAL WAIVER ON PROGRESS PAYMENT

• X(B) TEXAS – UNCONDITIONAL WAIVER AND RELEASE ON PROGRESS PAYMENT

• X(C) TEXAS – CONDITIONAL WAIVER ON FINAL PAYMENT

• X(D) TEXAS – UNCONDITIONAL WAIVER ON FINAL PAYMENT

• X(E) - AFFIDAVIT OF BILLS PAID

XI. STANDARD SPECIFICATIONS

XII. SPECIAL SPECIFICATIONS

XIII. STORM WATER POLLUTION PREVENTION PLAN

DEV (OBO) I - 1/2

Date: July 17, 2026

INVITATION TO BIDDERS

Sealed Bids, in duplicate, addressed to Lennar Homes of Texas Land and Construction, Ltd., a Texas limited partnership, dba Friendswood Development Company on behalf of Harris County Municipal Utility District No. 514, will be received at the office of BGE, Inc., 10777 Westheimer, Suite 500; Houston, Texas, 77042 (Phone: 281-558-8700) OR electronically through www.civcastusa.com, until 10:30 AM Local Time, Tuesday, August 4, 2026, and then publicly opened and read at the office of BGE, Inc. for the furnishing of all material, equipment, labor and supervision necessary or incidental to “Construction of Sila, Section 11 Reinforced Concrete Paving, Harris County, Texas.”

In addition to the opening of sealed Bids at the address above, you may view the public opening of sealed Bids via Microsoft Teams. To join via Microsoft Teams the Call-in number is (832) 680-2579 and the Conference ID is 450 220 562#.

Scope of Work of the Contract includes the following:

1. Approx. 13,808 SY of 6-inch Subgrade Preparation

2. Approx. 12,220 SY of 6-inch Reinforced Concrete Pavement

3. Approx. 7,004 LF of Reinforced Concrete Curb

Bids received after closing time will not be considered.

A non-mandatory pre-bid conference will be held on Tuesday, July 28, 2026, at 10:30 AM Local Time, remotely through Microsoft Teams. To join via Microsoft Teams the Call-in number is

(832) 680-2579 and the Conference ID is 746 900 486#

Each Bid must be accompanied by a Bid Bond or a certified or cashier’s check, acceptable to the Owner, in an amount not less than five percent (5%) of the total amount Bid, as a guarantee that the successful bidder will enter into the Contract and execute the Bonds on the forms provided and provide the required insurance certificates within seven (7) days after the date Contract Documents are received by the Contractor. If a certified or cashier’s check is provided, the successful bidder shall deliver, at the bid opening address, the original certified or cashier’s check within twenty-four (24) hours of receipt of the bid opening.

Copies of the bidding documents may be obtained from www.civcastusa.com, search: 13287-10.

Bidders must register on this website to view and/or download specifications, plans, soils report and environmental reports for this project. There is NO charge to view or download documents.

A bidder submitting electronic Bids must submit its Bid and Bid Securities in compliance with Owner’s Order Adopting Section 49.2731 Electronic Bidding Rules and all electronic Bids and Bid Securities must be submitted through www.civcastusa.com. Bidder must register on this website in order to submit a Bid and Bid Security and there is no charge to submit Bids and Bid Securities on this website.

The Owner reserves the right to reject any or all Bids and to waive all defects and irregularities in bidding or bidding process except time of submitting a Bid. The successful bidder, if any, will be the responsible bidder which in the Board’s judgment will be most advantageous to the District and result in the best and most economical completion of the Project.

http://www.civcastusa.com/ http://www.civcastusa.com/

DEV (OBO) I - 2/2

The requirements of Subchapter J, Chapter 552, Government Code, may apply to this Bid and/or Contract and the Contractor agrees that the Contract can be terminated if the Contractor knowingly or intentionally fails to comply with a requirement of that subchapter.

LENNAR HOMES OF TEXAS LAND AND CONSTRUCTION, LTD.

ON BEHALF OF HARRIS COUNTY MUNICIPAL UTILITY DISTRICT NO. 514

Dev (OBO) II - 1

INSTRUCTIONS TO BIDDERS

ARTICLE 1 – DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:

A. Issuing Office – The office from which the Bidding Documents are to be issued.

B. Owner - the Owner is understood to be Lennar Homes of Texas Land and

Construction, Ltd., a Texas limited partnership, dba Friendswood Development Company on behalf of Harris County Municipal Utility District No. 514. Funding for the project will be provided in accordance with the terms and conditions described in the Agreement or the Special Conditions of Agreement.

ARTICLE 2 – COPIES OF BIDDING DOCUMENTS

2.01 Complete sets of the Bidding Documents may be viewed at the Issuing Office or obtained at www.civcastusa.com.

2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.

2.03 Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not authorize or confer a license for any other use.

ARTICLE 3 – QUALIFICATIONS OF BIDDERS

3.01 To demonstrate Bidder’s qualifications to perform the Work, responsible bidder must submit to Owner with its Bid, (a) written evidence establishing its qualifications such as financial data, previous experience, and present commitments, and (b) the following additional information:

A. Evidence of Bidder’s authority to do business in the state of Texas.

B. Bidder’s state or other contractor license number, if applicable.

C. Subcontractor and Supplier qualification information; coordinate with provisions of

Article 12 of these Instructions, “Subcontractors, Suppliers, and Others.”

D. Evidence that Bidder has successfully completed 4 similar projects under the direction of the same firm. Successfully completed projects shall be located in the Houston area, completed within the last 3 years and shall be similar to this Work in scope and in magnitude of cost.

3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.

Dev (OBO) II - 2

3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.

3.04 Bidder is advised to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications.

ARTICLE 4 – SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF

SITE; OWNER’S SAFETY PROGRAM; OTHER WORK AT THE SITE

4.01 Site and Other Areas

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor.

Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

4.02 Existing Site Conditions

A. Subsurface and Physical Conditions; Hazardous Environmental Conditions

1. The Supplementary Conditions identify:

a. those reports known to Owner of explorations and tests of subsurface conditions at or adjacent to the Site.

b. those drawings known to Owner of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities).

c. reports and drawings known to Owner relating to Hazardous Environmental

Conditions that have been identified at or adjacent to the Site.

d. Technical Data contained in such reports and drawings.

2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.

B. Underground Facilities: Information and data shown or indicated in the Bidding

Documents with respect to existing Underground Facilities at or adjacent to the Site are set forth in the Contract Documents and are based upon information and data

Dev (OBO) II - 3 furnished to Owner and Engineer by owners of such Underground Facilities, including Owner, or others.

C. Adequacy of Data: Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to subsurface conditions, other physical conditions, and Underground Facilities, and possible changes in the Bidding Documents due to differing or unanticipated subsurface or physical conditions appear in Paragraphs 5.03, 5.04, and 5.05 of the General Conditions. Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work, appear in Paragraph 5.06 of the General Conditions.

4.03 Site Visit and Testing by Bidders

A. Bidder shall conduct the required Site visit during normal working hours, and shall not disturb any ongoing operations at the Site.

B. Bidder is not required to conduct any subsurface testing, or exhaustive investigations of Site conditions.

C. Bidder shall contact Engineer for information regarding access to the Site.

D. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site.

E. Bidder shall comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.

F. Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.

4.04 Owner’s Safety Program

A. Site visits and work at the Site may be governed by an Owner safety program. As the

General Conditions indicate, if an Owner safety program exists, it will be noted in the Supplementary Conditions.

Dev (OBO) II - 4

4.05 Other Work at the Site

A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.

ARTICLE 5 – BIDDER’S REPRESENTATIONS

5.01 It is the responsibility of each Bidder before submitting a Bid to:

A. examine and carefully study the Bidding Documents, and any data and reference items identified in the Bidding Documents;

B. visit the Site, conduct a thorough, alert visual examination of the Site and adjacent areas, and become familiar with and satisfy itself as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work;

become familiar with and satisfy itself as to all Laws and Regulations that may affect cost, progress, and performance of the Work;

C. consider the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder; and (3) Bidder’s safety precautions and programs;

D. agree, based on the information and observations referred to in the preceding paragraph, that at the time of submitting its Bid no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents;

E. become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents;

F. promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder;

G. determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance and furnishing of the Work; and

Dev (OBO) II - 5

H. agree that the submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article, that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.

ARTICLE 6 – PRE-BID CONFERENCE

6.01 A non-mandatory pre-bid conference will be held at the time and location stated in the

Invitation or advertisement to bid. Representatives of Owner and Engineer will be present to discuss the Project. Bidders are encouraged to attend and participate in the conference.

Engineer will transmit to all prospective Bidders of record such Addenda as Engineer considers necessary in response to questions arising at the conference. Oral statements may not be relied upon and will not be binding or legally effective.

ARTICLE 7 – INTERPRETATIONS AND ADDENDA

7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted to Engineer through www.civcastusa.com. Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda to all parties recorded as being a plan holder. Questions received less than seventy two (72) hours prior to the date for opening of Bids may not be answered. Only questions answered by Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.

7.02 Addenda may be issued to clarify, correct, supplement, or change the Bidding Documents.

ARTICLE 8 – BID SECURITY

8.01 Each Bid must be accompanied by Bid security made payable to Owner in an amount of five percent (5%) of Bidder’s total amount bid and in the form of a certified check, bank money order, or a Bid bond issued by a surety meeting the requirements of Paragraph

6.01 of the General Conditions.

8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract Documents, furnished the required contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract Documents and furnish the required contract security within 7 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited. Such forfeiture shall be Owner’s exclusive remedy if Bidder defaults.

8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the Effective Date of the Contract or sixty-first (61st) days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.

8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.

Dev (OBO) II - 6

ARTICLE 9 – CONTRACT TIMES

9.01 The number of days within which, or the dates by which, the Work is to be completed and ready for final payment, are set forth in the Agreement.

ARTICLE 10 – LIQUIDATED DAMAGES

10.01 Provisions for liquidated damages, if any, are set forth in the Agreement.

ARTICLE 11 – SUBSTITUTE AND “OR-EQUAL” ITEMS

11.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents, and those “or-equal” or substitute of materials and equipment subsequently approved by Engineer prior to submittal of Bids and identified by Addendum. No item of material or equipment will be considered by Engineer as an “or-equal” or substitute unless written request for approval has been submitted by Bidder and has been received 72 hours prior to date for receipt of Bids. Each such request shall comply with the requirements of Paragraphs 7.04 and 7.05 of the General Conditions. The burden of proof of merit of the proposed item is upon Bidder.

Engineer’s decision of approval or disapproval of a proposed item will be final. If Engineer approves any such proposed item, such approval will be set forth in an Addendum issued to all prospective Bidders. Bidders shall not rely upon approvals made in any other manner.

11.02 All prices that Bidder sets forth in its Bid shall be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.

ARTICLE 12 – SUBCONTRACTORS, SUPPLIERS, AND OTHERS

12.01 A Bidder shall be prepared to retain specific Subcontractors, Suppliers, or other individuals or entities for the performance of the Work if required by the Bidding Documents (most commonly in the Specifications) to do so. If a prospective Bidder objects to retaining any such Subcontractor, Supplier, or other individual or entity, and the concern is not relieved by an Addendum, then the prospective Bidder should refrain from submitting a Bid.

12.02 Subsequent to the submittal of the Bid, Owner may not require the Successful Bidder or

Contractor to retain any Subcontractor, Supplier, or other individual or entity against which Contractor has reasonable objection.

12.03 Bidders are required to disclose their list of the Subcontractors or Suppliers proposed for any part of the work.

12.04 If requested by Owner, Successful Bidder shall provide experience with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, or other individual or entity. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, individual, or entity, Owner may request apparent Successful Bidder to submit an acceptable substitute without an increase in price.

Dev (OBO) II - 7

12.05 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next most qualified, responsible, and responsive Bidder that proposes to use acceptable Subcontractors, Suppliers, or other individuals or entities. Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor, Supplier, individual, or entity so listed and against which Owner or Engineer makes no written objection prior to the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.06 of the General Conditions.

ARTICLE 13 – PREPARATION OF BID

13.01 The Bid Form is included with the Bidding Documents.

A. All blanks on the Bid Form shall be completed in ink and the Bid Form signed in ink.

Erasures or alterations shall be initialed in ink by the person signing the Bid Form. A Bid price shall be indicated for each section, bid item, alternate, adjustment unit price item, and unit price item listed therein.

B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”

13.02 A Bid by a corporation shall be executed in the corporate name by a corporate officer

(whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation shall be shown.

13.03 A Bid by a partnership shall be executed in the partnership name and signed by a partner

(whose title must appear under the signature), accompanied by evidence of authority to sign. The partnership’s address for receiving notices shall be shown.

13.04 A Bid by a limited liability company shall be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the firm’s address for receiving notices shall be shown.

13.05 A Bid by an individual shall show the Bidder’s name and address for receiving notices.

13.06 A Bid by a joint venture shall be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture’s address for receiving notices shall be shown.

13.07 All names shall be printed in ink below the signatures.

13.08 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form.

13.09 Postal and e-mail addresses and telephone number for communications regarding the Bid shall be shown.

13.10 The Bid shall contain evidence of Bidder’s authority and qualification to do business in the

State of Texas, or Bidder shall covenant in writing to obtain such authority and qualification

Dev (OBO) II - 8 prior to award of the Contract and attach such covenant to the Bid. Bidder’s state contractor license number, if any, shall also be shown on the Bid Form.

ARTICLE 14 – BASIS OF BID

14.01 Lump Sum

A. Bidders shall submit a Bid on a lump sum basis as set forth in the Bid Form.

14.02 Unit Price

A. Bidders shall submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form.

B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity” (which Owner or its representative has set forth in the Bid Form) for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.

C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

14.03 Allowances

A. For cash allowances, the Bid price shall include such amounts as the Bidder deems proper for Contractor's overhead, costs, profit, and other expenses on account of cash allowances, if any, named in the Contract Documents, in accordance with Paragraph 13.02.B of the General Conditions.

ARTICLE 15 – SUBMITTAL OF BID

15.01 A Bid shall be received no later than the date and time prescribed and at the place indicated in the advertisement or invitation to bid and shall be enclosed in a plainly marked package with the Project title (and, if applicable, the designated portion of the Project for which the Bid is submitted), the name and address of Bidder, and shall be accompanied by the Bid security and other required documents. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate package plainly marked on the outside with the notation “BID ENCLOSED.”

15.02 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the Bidder unopened.

Dev (OBO) II - 9

ARTICLE 16 – MODIFICATION AND WITHDRAWAL OF BID

16.01 A Bid may be withdrawn by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids. Upon receipt of such notice, the unopened Bid will be returned to the Bidder.

16.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 16.01 and submit a new Bid prior to the date and time for the opening of Bids.

16.03 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with

Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, that Bidder will be disqualified from further bidding on the Work.

ARTICLE 17 – OPENING OF BIDS

17.01 Bids will be opened at the time and place indicated in the advertisement or invitation to bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.

ARTICLE 18 – BIDS TO REMAIN SUBJECT TO ACCEPTANCE

18.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but

Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

ARTICLE 19 – EVALUATION OF BIDS AND AWARD OF CONTRACT

19.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible. If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, then the Owner will reject the Bid as nonresponsive.

Owner also reserves the right to waive all minor informalities not involving price, time, or changes in the Work.

19.02 If Owner awards the contract for the Work, such award shall be to the responsible Bidder submitting the lowest responsive Bid.

19.03 In evaluating Bids, Owner will consider whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.

19.04 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the

Bidder and may consider the qualifications and experience of Subcontractors and

Dev (OBO) II - 10

Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.

19.05 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.

ARTICLE 20 – BONDS AND INSURANCE

20.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance, payment, and maintenance bonds as well as insurance requirements. When the Successful Bidder delivers the Agreement (executed by Successful Bidder) to Owner, it shall be accompanied by the required original bonds, as well as original insurance documents.

ARTICLE 21 – SIGNING OF AGREEMENT

21.01 When Owner issues a Notice of Award to the Successful Bidder, it shall be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 7 days thereafter, Successful Bidder shall execute and deliver the required number of counterparts of the Agreement (and any bonds and insurance documentation required to be delivered by the Contract Documents) to Owner.

ARTICLE 22 – SALES AND USE TAXES

22.01 Owner is exempt from Texas sales and use taxes pursuant to Texas Tax Code § 151.309 as a political subdivision of the State of Texas. Owner shall provide Contractor with a completed Texas Sales and Use Tax Exemptions Certification as evidence of the applicability of such exemption and, accordingly, Contractor shall not collect Texas sales and use taxes from Owner with respect to this contract. Contractor and all subcontractors to Contractor shall issue a Texas Sales and Use Tax Exemption Certification with respect to, and shall not pay Texas sales and use taxes on, all purchases of the following items that are exempt from Texas sales and use taxes pursuant to Texas Tax Code § 151.311:

(i) tangible personal property that will be incorporated into Owner’s realty; (ii) tangible personal property that is necessary and essential for the performance of this contract and is consumed entirely on the job site; and (IV) taxable services for use in the performance of this contract that are performed at the job site and are either integral to the performance of this contract or expressly required to be provided by this contract. In addition, Contractor and all subcontractors to Contractor (i) shall not include any provision for Texas sales and use taxes with respect to such exempt items in any bid or contract amount, and (ii) shall pass on to the Owner cost savings due to the exempt status of such exempt items.

Contractor’s contracts with all subcontractors to Contractor shall include the foregoing provision regarding the exemption from Texas Sales and use taxes.

ARTICLE 23 - LABOR CLASSIFICATION AND MINIMUM WAGE SCALE

23.01 Chapter 2258 of the Texas Government Code provides that any political subdivision of the

State of Texas shall determine the general prevailing wage rate received by the classes of workers employed on projects similar to this project and shall specify in the call for bids

Dev (OBO) II - 11 and in the Contract the applicable minimum wage rates. The statute further provides that the Contractor of Subcontractors shall pay, as a penalty, to the Owner Sixty Dollars ($60.00) for each worker employed for each calendar day or part of the day that the worker is paid less that the wage rates stipulated in the Contract. The Owner is authorized to withhold from the Contractor the amount due under Contract.

The Statute likewise requires that the Contractor and Subcontractors keep an accurate record of the name and occupations of all persons employed by them in the construction of the Project and to show the actual per diem wages paid to each worker. These records are open to the inspection of the Owner.

23.02 The minimum wage rates that apply to this Contract are specified in the attachment hereto.

Contractor and Subcontractors shall review and ascertain such wage rates and pay at least such minimum rates.

ARTICLE 24 – ADDITIONAL REQUIREMENTS

24.01 House Bill 1295 Implementation

Provision of Texas Ethics Commission Form 1295 (“TEC Form 1295”) by Bidders: Effective January 1, 2016, pursuant to Texas Government Code 2252.908 (the “Interested Party Disclosure Act” or the “Act”), the District may not award the contract to a bidder unless the bidder has provided to the District a completed, signed and notarized TEC Form 1295 which has been assigned a certificate number by the Texas Ethics Commission (the “TEC”). Pursuant to the rules prescribed by the TEC, the TEC Form 1295 must be completed online through the TEC’s website at https://www.ethics.state.tx.us, assigned a certificate number, printed, signed and provided to the district. The TEC Form 1295 must be submitted with the contractor’s bid. Neither the District nor its consultants have the ability to verify the information included in a TEC Form 1295, and neither have an obligation nor undertake responsibility for advising any Bidder with respect to the proper completion of the TEC Form 1295.

24.02 Senate Bill 943: Large Contracts - New Requirements for Bids and Contracts at least

$1,000,000

A. The requirements of Subchapter J, Chapter 552, Government Code, may apply to this bid or Contract and contractor agrees that the Contract can be terminated if contractor knowingly or intentionally fails to comply with a requirement of that subchapter.* Accordingly, contractor shall: (1) preserve all Contracting Information (defined below) in contractor’s possession related to this Contract as provided by the District’s Records Control Schedule for the duration of the Contract; (2) promptly provide to the District on the District’s request any Contracting Information in contractor’s custody or possession; and (3) on completion of the Contract, either provide at no cost to the District all Contracting Information related to the Contract in contractor’s possession, or preserve such Contracting Information as provided by the District’s Records Control Schedule. For purposes of this Contract, Contracting Information means information related to the Contract in contractor’s custody or possession, including:

a) information in a voucher or the Contract relating to the receipt or expenditure of public funds by the District;

https://www.ethics.state.tx.us/

Dev (OBO) II - 12

b) solicitation or bid documents relating to the Contract with the District;

c) communications sent between the District and contractor during the solicitation, evaluation, or negotiation of the Contract;

d) documents, including bid tabulations, showing the criteria by which the

District evaluated contractor or potential contractors responding to a solicitation and, if applicable, an explanation of why contractor was selected; and

e) communications and other information sent between the District and contractor related to the performance of the Contract or work performed thereunder on behalf of the District.

B. Contractor declares that it has not received from a governmental body a notice of noncompliance with a provision of Subchapter J, Chapter 552, Texas Government Code, or, if such a notice has been received, Contractor has taken adequate steps to ensure future compliance with such subchapter and has provided or upon request will provide documentation of same

WHEREAS, Chapter 2258 applies to construction projects paid for in whole or in part from funds of the District, regardless of whether the work is done under the District's supervision or direction; and

WHEREAS, Chapter 2258 provides that a contractor which is awarded a construction contract for the District, or a subcontractor of the contractor, shall pay not less than the rates determined as set forth above to a worker employed in the execution of such contract for a construction project; and

Section 2: The District hereby adopts the Prevailing Wage Rate Scale for Construction Projects attached hereto as Exhibit A, which establishes minimum rates for each project type that shall be used by all contractors and their subcontractors on construction projects by or on behalf of the District.

WHEREAS, Chapter 2258 provides that a worker employed on a construction project by or on behalf of the District shall be paid not less than said general prevailing rates, as applicable;

and

WHEREAS, the Board of Directors of the District (the "Board") has determined the general prevailing rate of per diem wages by using the prevailing wage rate as determined by the United States Department of Labor in accordance with the Davis-Bacon Act (40 U.S.C. Section 276a et seq.), as amended, and has determined to adopt a Prevailing Wage Rate Scale for Construction Projects for the District. Now, Therefore, WHEREAS, Chapter 2258, Texas Government Code ("Chapter 2258"), requires the District to determine the general prevailing rate of per diem wages for each craft or type of worker in the locality in which a construction project for the District is to be performed and the general prevailing rate of per diem wages for legal holiday and overtime work; and

WHEREAS, Harris County Municipal Utility District No. 514 (the "District") has been heretofore duly created and organized; and

RESOLUTION ADOPTING PREVAILING WAGE RATE SCALE

FOR CONSTRUCTION PROJECTS

BE IT RESOLVED BY THE BOARD OF DIRECTORS OF HARRIS COUNTY

MUNICIPAL UTILITY DISTRICT NO. 514, THAT:

Section 1: The Board has determined the general prevailing rate of per diem wages for each craft or type of worker in the locality in which a construction project for the District is to be performed and the general prevailing rate of per diem wages for legal holiday and overtime work by using the prevailing wage rate as determined by the United States Department of Labor in accordance with the Davis-Bacon Act (40 U.S.C. Section 276a et seq.), as amended, and further, the Board has determined that the wage rates in the Prevailing Wage Rate Scale for Construction Projects (comprised of one or more United States Department of Labor wage determination scales for each project type) attached hereto as Exhibit A are the general prevailing wage rates for construction projects by or on behalf of the District.

[REMAINDER OF PAGE INTENTIONALLY LEFT BLANK]

765966v4

Section 3: A contractor or subcontractor on a construction project by or on behalf of the District shall maintain records as required by Chapter 2258 and shall be subject to the penalties, forfeitures, and withholding of money for failure to comply with this Resolution and/or pending a final determination of an alleged violation, as provided in Chapter 2258.

Section 4: The District engineer is hereby directed and authorized to specify the wage rates adopted hereunder for each project type in all specifications for bids and contracts for construction projects by or on behalf of the District.

Section 5: Any prior Resolution Adopting Prevailing Wage Rate Scale for Construction Projects previously adopted by the Board is hereby revoked.

PASSED and ADOPTED this 17th day of March, 2026.

ATTEST:

(SEAL)

765966v4

Secre ary, Br ard of 0

President, Board of Directors

EXHIBIT A

PREVAILING WAGE RATE SCALE FOR CONSTRUCTION PROJECTS

765966v4

705412v8

United States Department of Labor

Wage Determination Scale TX 31

Construction Type: Heavy Construction Projects Including

Water and Sewer Lines (Includes Flood Control)

Counties: Harris

"General Decision Number: TX20260031 01/02/2026

Superseded General Decision Number: TX20250031

State: Texas

Construction Type: Heavy

County: Harris County in Texas.

HEAVY CONSTRUCTION PROJECTS Including Water and Sewer Lines

(Does Not Include Flood Control).

Modification Number Publication Date

0 01/02/2026

SFTX0669-001 01/01/2025

Rates Fringes

SPRINKLER FITTER (Fire

Sprinklers)......................$ 36.15 24.47

SUTX2005-019 08/16/2005

CARPENTER........................$ 14.04 0.00

CEMENT MASON/CONCRETE FINISHER...$ 12.50 1.17

ELECTRICIAN......................$ 17.00 0.04

Formbuilder/Formsetter...........$ 13.84 1.17

IRONWORKER, REINFORCING..........$ 11.28 0.00

Laborers:

Common......................$ 8.94 0.00

Landscape...................$ 7.35 0.00

Mason Tender Cement.........$ 9.94 0.00

Pipelayer...................$ 10.14 0.00

PIPEFITTER.......................$ 17.00 0.04

POWER EQUIPMENT OPERATOR:

Backhoe.....................$ 13.47 0.00

Bulldozer...................$ 12.58 0.00

Crane.......................$ 15.33 0.57

Excavator...................$ 16.37 0.00

Front End Loader............$ 12.16 0.00

Grader......................$ 12.20 1.48

Tractor.....................$ 15.00 0.00

TRUCK DRIVER.....................$ 12.02 1.02

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the

Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.

Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between

January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive

Order 13658 does not apply to contracts subject only to the

Davis-Bacon Related Acts regardless of when they were awarded.

If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.30 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in 2025. The applicable Executive Order minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses

(29CFR 5.5 (a) (1) (iii)).

The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.

Union Rate Identifiers

A four-letter identifier beginning with characters other than

""SU"", ""UAVG"", ?SA?, or ?SC? denotes that a union rate was prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.

0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.

Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.

Union Average Rate Identifiers

The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:

UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.

The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.

A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.

Survey Rate Identifiers

The ""SU"" identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007

6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.

?SU? wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).

State Adopted Rate Identifiers

The ""SA"" identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007

01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.

The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the ?SA? identifier took effect under state law in the state from which the rates were adopted.

WAGE DETERMINATION APPEALS PROCESS

1) Has there been an initial decision in the matter? This can be:

a) a survey underlying a wage determination

b) an existing published wage determination

c) an initial WHD letter setting forth a position on a wage determination matter

d) an initial conformance (additional classification and rate) determination

On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:

Branch of Wage Surveys

Wage and Hour Division

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.

Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:

Branch of Construction Wage Determinations

Wage and Hour Division

U.S. Department of Labor

2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).

Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:

Wage and Hour Administrator

The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative

Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board

Washington, DC 20210.

END OF GENERAL DECISION

705418v8

Wage Determination Scale TX 299

Construction Type: Highway Construction Projects

County: Austin, Brazoria, Chambers, Fort Bend, Galveston, Hardin,…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .