This bid document package is for Fort Bend County Municipal Utility District No. 275 and concerns the construction of Texas Heritage Parkway Extension Section 2B in Fulshear Ranch, Fort Bend County, Texas. The project involves construction of approximately 0.98 mile of concrete pavement boulevard featuring an illuminated roundabout intersection, pedestrian tunnels, storm sewer, water line, and wastewater line. The scope includes extensive roadway work, drainage infrastructure, illumination, signing, pavement markings, and utility installations (water, sanitary sewer, and stormwater pollution prevention). A non-mandatory pre-bid conference was scheduled for Friday, July 10, 2026, at 10:30 AM via Microsoft Teams. Sealed bids were due by 10:30 AM Local Time on Friday, July 17, 2026, submitted either physically to BGE, Inc. at 10777 Westheimer, Suite 500, Houston, Texas 77042, or electronically through www.civcastusa.com. The contractor must achieve Substantial Completion within 243 calendar days and Final Completion within 303 calendar days from the Notice to Proceed, with a required start date within seven days of written notice. The bid documents include detailed unit price items across nine major work categories, with bidders required to submit bids for all listed items.

The contract price is subject to economic incentives and disincentives: the contractor receives a $5,000 per day increase for each day Substantial Completion is achieved prior to the established deadline, with a maximum increase of $150,000, and incurs a $5,000 per day deduction for each day of delay beyond the Substantial Completion date with no limit. Bidders must provide a bid security of 5 percent of the total bid amount in the form of a certified check, bank money order, or bid bond. Successful bidders must provide Performance Bonds, Payment Bonds, and Maintenance Bonds each in the amount of 100 percent of the initial Contract Price (if thresholds are met). Prevailing wage rates for Fort Bend County apply, and the contractor must comply with Texas Government Code requirements including submission of Texas Ethics Commission Form 1295 and Subchapter J, Chapter 552 requirements for contracts exceeding $1,000,000. Hines Texas Heritage Investors LP serves as the developer and is designated as the "Owner" for payment purposes, meaning the contractor shall look to the developer for payment rather than the District directly, though the District retains approval authority. The project is developer-financed, and bidders must demonstrate qualifications including successful completion of four similar projects in the Houston area within the last three years.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Fort Bend County Municipal Utility District No. 275

Contract Documents and Specifications for Construction of

Texas Heritage Parkway Extension Section 2B Fulshear Ranch

Fort Bend County, Texas

June 2026

TBPE Registration No. F-1046

10777 Westheimer, Suite 500 Houston, Texas 77042

281-558-8700

\\bgeinc\data2\00014571-00\TS\03_Constr\01_Bid_Phase\Section 2B\02_Bid_Docs (THP Extension Bid Book)\Cover and TOC.docx

Contract Documents and Specifications for Construction of

Texas Heritage Parkway Extension Section 2B Fulshear Ranch

Fort Bend County, Texas

CONTENTS

I. INVITATION TO BIDDERS

II. INSTRUCTIONS TO BIDDERS

III. BID

IV. DEVELOPER FINANCED CONTRACT

V. PERFORMANCE BOND

VI. PAYMENT BOND

VII. MAINTENANCE BOND

VIII. SUPPLEMENTARY CONDITIONS

IX. CONTRACTOR CONSTRUCTION FORMS

• IX(A) - AFFIDAVIT FOR PARTIAL PAYMENT

• IX(B) - AFFIDAVIT FOR FINAL PAYMENT AND BILLS PAID

• IX(C) - CERTIFICATE OF SUBSTANTIAL COMPLETION

• IX(D) - CERTIFICATE OF COMPLETION

X. STANDARD SPECIFICATIONS

XI. SPECIAL SPECIFICATIONS

XII. STORM WATER POLLUTION PREVENTION PLAN

(Physical Bids Only) I - 1/2

Attention: Pursuant to Texas Government Code § 2252.908, unless you are a publicly traded entity or a wholly owned subsidiary of same, you must be able to provide Fort Bend County Municipal Utility District No. 275 (the "District") with printed and signed copies of a completed disclosure of interested parties form (Form 1295) and a certificate of filling at the time of the District's execution of the contract. Failure to do so will result in the District's inability to execute the contract. To complete the disclosure of interested parties form, or for further information, please visit the Texas Ethics Commission's website at https://www.ethics.state.tx.us

Date: June 26, 2026

INVITATION TO BIDDERS

Sealed Bids, in duplicate, addressed to Board of Directors, Fort Bend County Municipal Utility District No. 275, will be received at the office of BGE, Inc., 10777 Westheimer, Suite 500;

Houston, Texas, 77042 (Phone: 281-558-8700) OR electronically through www.civcastusa.com, until 10:30 AM Local Time, Friday, July 17, 2026, and then publicly opened and read for the furnishing of all material, equipment, labor and supervision necessary or incidental to “Construction of Texas Heritage Parkway Extension Section 2B Fulshear Ranch for Fort Bend County MUD No. 275, Fort Bend County, Texas.”

In addition to the opening of sealed Bids at the address above, you may view the public opening of sealed Bids via Microsoft Teams. To join via Microsoft Teams the Call-in number is (832) 680-2579 and the Conference ID is 651 511 433#.

Scope of Work of the Contract includes the following:

• Construction of approximately 0.98 mile long concrete pavement boulevard with illuminated roundabout intersection and pedestrian tunnels, storm sewer, water line, and wastewater line.

Bids received after closing time will not be considered and be returned unopened.

Anon-mandatory pre-bid conference will be held on Friday, July 10, 2026, at 10:30 AM Local Time, remotely through Microsoft Teams. To join via Microsoft Teams the Call-in number is

(832) 680-2579 and the Conference ID is 554 572 63#.

Each Bid must be accompanied by a Bid Bond or a certified or cashier’s check, acceptable to the Owner, in an amount not less than five percent (5%) of the total amount Bid, as a guarantee that the successful bidder will enter into the Contract and execute the Bonds on the forms provided and provide the required insurance certificates within seven (7) days after the date Contract Documents are received by the Contractor. If a certified or cashier’s check is provided, the successful bidder shall deliver, at the bid opening address, the original certified or cashier’s check within twenty-four (24) hours of receipt of the bid opening.

Copies of the bidding documents may be reviewed and obtained from www.civcastusa.com, search: 14571-00(2B). Bidders must register on this website in order to view and/or download specifications, plans, soils report, and environmental reports for this Project. There is NO charge to view or download documents.

https://www.ethics.state.tx.us/ http://www.civcastusa.com/

(Physical Bids Only) I - 2/2

A bidder submitting electronic Bids must submit its Bid and Bid Securities in compliance with Owner’s Order Adopting Section 49.2731 Electronic Bidding Rules and all electronic Bids and Bid Securities must be submitted through www.civcastusa.com. Bidder must register on this website in order to submit a Bid and Bid Security and there is no charge to submit Bids and Bid Securities on this website.

By submitting a Bid, bidder acknowledges and agrees that the Contract Documents may be accepted, executed or agreed to through the use of an Electronic Signature, as defined by and in accordance with Owner’s Electronic Signature Rules for Construction Contracts.

The Owner reserves the right to reject any or all Bids and to waive all defects and irregularities in bidding or bidding process except time of submitting a Bid. The Successful Bidder, if any, will be the responsible Bidder which in the Board’s judgment will be most advantageous to the District and result in the best and most economical completion of the Project.

The requirements of Subchapter J, Chapter 552, Government Code, may apply to this Bid and/or Contract and the Contractor agrees that the Contract can be terminated if the Contractor knowingly or intentionally fails to comply with a requirement of that subchapter.

FORT BEND COUNTY MUD NO. 275

II - 1

INSTRUCTIONS TO BIDDERS

ARTICLE 1 – DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions. Additional terms used in these Instructions to Bidders have the meanings indicated below:

A. Issuing Office – The office from which the Bidding Documents are to be issued.

B. Owner - the Owner is understood to be Fort Bend County Municipal Utility District

No. 275. Funding for the project will be provided in accordance with the terms and conditions described in the Agreement or the Special Conditions of Agreement.

ARTICLE 2 – COPIES OF BIDDING DOCUMENTS

2.01 Complete sets of the Bidding Documents may be viewed at the Issuing Office or obtained at www.civcastusa.com.

2.02 Complete sets of Bidding Documents shall be used in preparing Bids; neither Owner nor Engineer assumes any responsibility for errors or misinterpretations resulting from the use of incomplete sets of Bidding Documents.

2.03 Owner and Engineer, in making copies of Bidding Documents available on the above terms, do so only for the purpose of obtaining Bids for the Work and do not authorize or confer a license for any other use.

ARTICLE 3 – QUALIFICATIONS OF BIDDERS

3.01 To demonstrate Bidder’s qualifications to perform the Work, responsible bidder must submit to Owner, within five (5) calendar days of notification, (a) written evidence establishing its qualifications such as financial data, previous experience, and present commitments, and (b) the following additional information:

A. Evidence of Bidder’s authority to do business in the state of Texas.

B. Bidder’s state or other contractor license number, if applicable.

C. Subcontractor and Supplier qualification information; coordinate with provisions of

Article 12 of these Instructions, “Subcontractors, Suppliers, and Others.”

D. Evidence that Bidder has successfully completed 4 similar projects under the direction of the same firm. Successfully completed projects shall be located in the Houston area, completed within the last 3 years and shall be similar to this Work in scope and in magnitude of cost.

3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.

II - 2

3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.

3.04 Bidder is advised to carefully review those portions of the Bid Form requiring Bidder’s representations and certifications.

ARTICLE 4 – SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF

SITE; OWNER’S SAFETY PROGRAM; OTHER WORK AT THE SITE

4.01 Site and Other Areas

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor.

Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

4.02 Existing Site Conditions

A. Subsurface and Physical Conditions; Hazardous Environmental Conditions

1. The Supplementary Conditions identify:

a. those reports known to Owner of explorations and tests of subsurface conditions at or adjacent to the Site.

b. those drawings known to Owner of physical conditions relating to existing surface or subsurface structures at the Site (except Underground Facilities).

c. reports and drawings known to Owner relating to Hazardous Environmental

Conditions that have been identified at or adjacent to the Site.

d. Technical Data contained in such reports and drawings.

2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.

B. Underground Facilities: Information and data shown or indicated in the Bidding

Documents with respect to existing Underground Facilities at or adjacent to the Site are set forth in the Contract Documents and are based upon information and data

II - 3

furnished to Owner and Engineer by owners of such Underground Facilities, including Owner, or others.

C. Adequacy of Data: Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to subsurface conditions, other physical conditions, and Underground Facilities, and possible changes in the Bidding Documents due to differing or unanticipated subsurface or physical conditions appear in Paragraphs 5.03, 5.04, and 5.05 of the General Conditions. Provisions concerning responsibilities for the adequacy of data furnished to prospective Bidders with respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at the Site which was not shown or indicated in the Drawings or Specifications or identified in the Contract Documents to be within the scope of the Work, appear in Paragraph 5.06 of the General Conditions.

4.03 Site Visit and Testing by Bidders

A. Bidder shall conduct the required Site visit during normal working hours, and shall not disturb any ongoing operations at the Site.

B. Bidder is not required to conduct any subsurface testing, or exhaustive investigations of Site conditions.

C. Bidder shall contact Engineer for information regarding access to the Site.

D. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder access to the Site to conduct such additional examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site.

E. Bidder shall comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.

F. Bidder shall fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.

4.04 Owner’s Safety Program

A. Site visits and work at the Site may be governed by an Owner safety program. As the

General Conditions indicate, if an Owner safety program exists, it will be noted in the Supplementary Conditions.

II - 4

4.05 Other Work at the Site

A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.

ARTICLE 5 – BIDDER’S REPRESENTATIONS

5.01 It is the responsibility of each Bidder before submitting a Bid to:

A. examine and carefully study the Bidding Documents, and any data and reference items identified in the Bidding Documents;

B. visit the Site, conduct a thorough, alert visual examination of the Site and adjacent areas, and become familiar with and satisfy itself as to the general, local, and Site conditions that may affect cost, progress, and performance of the Work;

become familiar with and satisfy itself as to all Laws and Regulations that may affect cost, progress, and performance of the Work;

C. consider the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Site-related reports and drawings identified in the Bidding Documents, with respect to the effect of such information, observations, and documents on (1) the cost, progress, and performance of the Work; (2) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder; and (3) Bidder’s safety precautions and programs;

D. agree, based on the information and observations referred to in the preceding paragraph, that at the time of submitting its Bid no further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of its Bid for performance of the Work at the price bid and within the times required, and in accordance with the other terms and conditions of the Bidding Documents;

E. become aware of the general nature of the work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents;

F. promptly give Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder discovers in the Bidding Documents and confirm that the written resolution thereof by Engineer is acceptable to Bidder;

G. determine that the Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance and furnishing of the Work; and

II - 5

H. agree that the submission of a Bid will constitute an incontrovertible representation by Bidder that Bidder has complied with every requirement of this Article, that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.

ARTICLE 6 – PRE-BID CONFERENCE

6.01 A non-mandatory pre-bid conference will be held at the time and location stated in the

Invitation or advertisement to bid. Representatives of Owner and Engineer will be present to discuss the Project. Bidders are encouraged to attend and participate in the conference.

Engineer will transmit to all prospective Bidders of record such Addenda as Engineer considers necessary in response to questions arising at the conference. Oral statements may not be relied upon and will not be binding or legally effective.

ARTICLE 7 – INTERPRETATIONS AND ADDENDA

7.01 All questions about the meaning or intent of the Bidding Documents are to be submitted to Engineer through www.civcastusa.com. Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda to all parties recorded as being a plan holder. Questions received less than 72 hours prior to the date for opening of Bids may not be answered. Only questions answered by Addenda will be binding. Oral and other interpretations or clarifications will be without legal effect.

7.02 Addenda may be issued to clarify, correct, supplement, or change the Bidding Documents.

ARTICLE 8 – BID SECURITY

8.01 Each Bid must be accompanied by Bid security made payable to Owner in an amount of five percent (5%) of Bidder’s total amount bid and in the form of a certified check, bank money order, or a Bid bond issued by a surety meeting the requirements of Paragraph

6.01 of the General Conditions.

8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract Documents, furnished the required contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract Documents and furnish the required contract security within 7 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited. Such forfeiture shall be Owner’s exclusive remedy if Bidder defaults.

8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the Effective Date of the Contract or sixty-first (61st) days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.

8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.

II - 6

ARTICLE 9 – CONTRACT TIMES

9.01 The number of days (calendar days) within which, or the dates by which, the Work is to be completed and ready for final payment, are set forth in the Agreement (or incorporated therein by reference to the attached Bid Form).

ARTICLE 10 – LIQUIDATED DAMAGES

10.01 Provisions for liquidated damages, if any, are set forth in the Agreement.

ARTICLE 11 – SUBSTITUTE AND “OR-EQUAL” ITEMS

11.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents, and those “or-equal” or substitute of materials and equipment subsequently approved by Engineer prior to submittal of Bids and identified by Addendum. No item of material or equipment will be considered by Engineer as an “or-equal” or substitute unless written request for approval has been submitted by Bidder and has been received 72 hours prior to date for receipt of Bids. Each such request shall comply with the requirements of Paragraphs 7.04 and 7.05 of the General Conditions. The burden of proof of merit of the proposed item is upon Bidder.

Engineer’s decision of approval or disapproval of a proposed item will be final. If Engineer approves any such proposed item, such approval will be set forth in an Addendum issued to all prospective Bidders. Bidders shall not rely upon approvals made in any other manner.

11.02 All prices that Bidder sets forth in its Bid shall be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.

ARTICLE 12 – SUBCONTRACTORS, SUPPLIERS, AND OTHERS

12.01 A Bidder shall be prepared to retain specific Subcontractors, Suppliers, or other individuals or entities for the performance of the Work if required by the Bidding Documents (most commonly in the Specifications) to do so. If a prospective Bidder objects to retaining any such Subcontractor, Supplier, or other individual or entity, and the concern is not relieved by an Addendum, then the prospective Bidder should refrain from submitting a Bid.

12.02 Subsequent to the submittal of the Bid, Owner may not require the Successful Bidder or

Contractor to retain any Subcontractor, Supplier, or other individual or entity against which Contractor has reasonable objection.

12.03 Bidders are required to disclose their list of the Subcontractors or Suppliers proposed for any part of the work.

12.04 If requested by Owner, Successful Bidder shall provide experience with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor, Supplier, or other individual or entity. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor, Supplier, II - 7 individual, or entity, Owner may request apparent Successful Bidder to submit an acceptable substitute without an increase in price.

12.05 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next most qualified, responsible, and responsive Bidder that proposes to use acceptable Subcontractors, Suppliers, or other individuals or entities. Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor, Supplier, individual, or entity so listed and against which Owner or Engineer makes no written objection prior to the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.06 of the General Conditions.

ARTICLE 13 – PREPARATION OF BID

13.01 The Bid Form is included with the Bidding Documents.

A. All blanks on the Bid Form shall be completed in ink and the Bid Form signed in ink.

Erasures or alterations shall be initialed in ink by the person signing the Bid Form. A Bid price shall be indicated for each section, bid item, alternate, adjustment unit price item, and unit price item listed therein.

B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”

13.02 A Bid by a corporation shall be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation shall be shown.

13.03 A Bid by a partnership shall be executed in the partnership name and signed by a partner

(whose title must appear under the signature), accompanied by evidence of authority to sign. The partnership’s address for receiving notices shall be shown.

13.04 A Bid by a limited liability company shall be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the firm’s address for receiving notices shall be shown.

13.05 A Bid by an individual shall show the Bidder’s name and address for receiving notices.

13.06 A Bid by a joint venture shall be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture’s address for receiving notices shall be shown.

13.07 All names shall be printed in ink below the signatures.

13.08 The Bid shall contain an acknowledgment of receipt of all Addenda, the numbers of which shall be filled in on the Bid Form.

13.09 Postal and e-mail addresses and telephone number for communications regarding the Bid shall be shown.

II - 8

13.10 The Bid shall contain evidence of Bidder’s authority and qualification to do business in the State of Texas, or Bidder shall covenant in writing to obtain such authority and qualification prior to award of the Contract and attach such covenant to the Bid. Bidder’s state contractor license number, if any, shall also be shown on the Bid Form.

ARTICLE 14 – BASIS OF BID

14.01 Lump Sum

A. Bidders shall submit a Bid on a lump sum basis as set forth in the Bid Form.

14.02 Unit Price

A. Bidders shall submit a Bid on a unit price basis for each item of Work listed in the unit price section of the Bid Form.

B. The “Bid Price” (sometimes referred to as the extended price) for each unit price Bid item will be the product of the “Estimated Quantity” (which Owner or its representative has set forth in the Bid Form) for the item and the corresponding “Bid Unit Price” offered by the Bidder. The total of all unit price Bid items will be the sum of these “Bid Prices”; such total will be used by Owner for Bid comparison purposes. The final quantities and Contract Price will be determined in accordance with Paragraph 13.03 of the General Conditions.

C. Discrepancies between the multiplication of units of Work and unit prices will be resolved in favor of the unit prices. Discrepancies between the indicated sum of any column of figures and the correct sum thereof will be resolved in favor of the correct sum.

14.03 Allowances

A. For cash allowances, the Bid price shall include such amounts as the Bidder deems proper for Contractor's overhead, costs, profit, and other expenses on account of cash allowances, if any, named in the Contract Documents, in accordance with Paragraph 13.02.B of the General Conditions.

ARTICLE 15 – SUBMITTAL OF BID

15.01 A Bid shall be received no later than the date and time prescribed and at the place indicated in the advertisement or invitation to bid and shall be enclosed in a plainly marked package with the Project title (and, if applicable, the designated portion of the Project for which the Bid is submitted), the name and address of Bidder, and shall be accompanied by the Bid security and other required documents. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid shall be enclosed in a separate package plainly marked on the outside with the notation “BID ENCLOSED.”

15.02 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the Bidder unopened.

II - 9

ARTICLE 16 – MODIFICATION AND WITHDRAWAL OF BID

16.01 A Bid may be withdrawn by an appropriate document duly executed in the same manner that a Bid must be executed and delivered to the place where Bids are to be submitted prior to the date and time for the opening of Bids. Upon receipt of such notice, the unopened Bid will be returned to the Bidder.

16.02 If a Bidder wishes to modify its Bid prior to Bid opening, Bidder must withdraw its initial Bid in the manner specified in Paragraph 16.01 and submit a new Bid prior to the date and time for the opening of Bids.

16.03 If within 24 hours after Bids are opened any Bidder files a duly signed written notice with

Owner and promptly thereafter demonstrates to the reasonable satisfaction of Owner that there was a material and substantial mistake in the preparation of its Bid, that Bidder may withdraw its Bid, and the Bid security will be returned. Thereafter, if the Work is rebid, that Bidder will be disqualified from further bidding on the Work.

ARTICLE 17 – OPENING OF BIDS

17.01 Bids will be opened at the time and place indicated in the advertisement or invitation to bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.

ARTICLE 18 – BIDS TO REMAIN SUBJECT TO ACCEPTANCE

18.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but

Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

ARTICLE 19 – EVALUATION OF BIDS AND AWARD OF CONTRACT

19.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible. If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, then the Owner will reject the Bid as nonresponsive.

Owner also reserves the right to waive all minor informalities not involving price, time, or changes in the Work.

19.02 If Owner awards the contract for the Work, such award shall be to the responsible Bidder submitting the lowest responsive Bid.

19.03 In evaluating Bids, Owner will consider whether or not the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.

19.04 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the

Bidder and may consider the qualifications and experience of Subcontractors and

II - 10

Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.

19.05 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.

ARTICLE 20 – BONDS AND INSURANCE

20.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance, payment, and maintenance bonds as well as insurance requirements. When the Successful Bidder delivers the Agreement (executed by Successful Bidder) to Owner, it shall be accompanied by the required original bonds, as well as original insurance documents.

ARTICLE 21 – SIGNING OF AGREEMENT

21.01 When Owner issues a Notice of Award to the Successful Bidder, it shall be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within seven (7) days thereafter, Successful Bidder shall execute and deliver the required number of counterparts of the Agreement (and any bonds and insurance documentation required to be delivered by the Contract Documents) to Owner.

ARTICLE 22 – SALES AND USE TAXES

22.01 Owner is exempt from Texas sales and use taxes pursuant to Texas Tax Code § 151.309 as a political subdivision of the State of Texas. Owner shall provide Contractor with a completed Texas Sales and Use Tax Exemptions Certification as evidence of the applicability of such exemption and, accordingly, Contractor shall not collect Texas sales and use taxes from Owner with respect to this contract. Contractor and all subcontractors to Contractor shall issue a Texas Sales and Use Tax Exemption Certification with respect to, and shall not pay Texas sales and use taxes on, all purchases of the following items that are exempt from Texas sales and use taxes pursuant to Texas Tax Code § 151.311:

(i) tangible personal property that will be incorporated into Owner’s realty; (ii) tangible personal property that is necessary and essential for the performance of this contract and is consumed entirely on the job site; and (IV) taxable services for use in the performance of this contract that are performed at the job site and are either integral to the performance of this contract or expressly required to be provided by this contract. In addition, Contractor and all subcontractors to Contractor (i) shall not include any provision for Texas sales and use taxes with respect to such exempt items in any bid or contract amount, and (ii) shall pass on to the Owner cost savings due to the exempt status of such exempt items.

Contractor’s contracts with all subcontractors to Contractor shall include the foregoing provision regarding the exemption from Texas Sales and use taxes.

II - 11

ARTICLE 23 - LABOR CLASSIFICATION AND MINIMUM WAGE SCALE

23.01 Chapter 2258 of the Texas Government Code provides that any political subdivision of the State of Texas shall determine the general prevailing wage rate received by the classes of workers employed on projects similar to this project and shall specify in the call for bids and in the Contract the applicable minimum wage rates. The statute further provides that the Contractor of Subcontractors shall pay, as a penalty, to the Owner Sixty Dollars ($60.00) for each worker employed for each calendar day or part of the day that the worker is paid less that the wage rates stipulated in the Contract. The Owner is authorized to withhold from the Contractor the amount due under Contract.

The Statute likewise requires that the Contractor and Subcontractors keep an accurate record of the name and occupations of all persons employed by them in the construction of the Project and to show the actual per diem wages paid to each worker. These records are open to the inspection of the Owner.

23.02 The minimum wage rates that apply to this Contract are specified in the attachment hereto.

Contractor and Subcontractors shall review and ascertain such wage rates and pay at least such minimum rates.

ARTICLE 24 – ADDITIONAL REQUIREMENTS

24.01 House Bill 1295 Implementation

Provision of Texas Ethics Commission Form 1295 (“TEC Form 1295”) by Bidders: Effective January 1, 2016, pursuant to Texas Government Code 2252.908 (the “Interested Party Disclosure Act” or the “Act”), the District may not award the contract to a bidder unless the bidder has provided to the District a completed, signed and notarized TEC Form 1295 which has been assigned a certificate number by the Texas Ethics Commission (the “TEC”). Pursuant to the rules prescribed by the TEC, the TEC Form 1295 must be completed online through the TEC’s website at https://www.ethics.state.tx.us, assigned a certificate number, printed, signed and provided to the district. The TEC Form 1295 must be submitted with the contractor’s bid. Neither the District nor its consultants have the ability to verify the information included in a TEC Form 1295, and neither have an obligation nor undertake responsibility for advising any Bidder with respect to the proper completion of the TEC Form 1295.

24.02 Senate Bill 943: Large Contracts - New Requirements for Bids and Contracts at least

$1,000,000

A. The requirements of Subchapter J, Chapter 552, Government Code, may apply to this bid or Contract and contractor agrees that the Contract can be terminated if contractor knowingly or intentionally fails to comply with a requirement of that subchapter.* Accordingly, contractor shall: (1) preserve all Contracting Information (defined below) in contractor’s possession related to this Contract as provided by the District’s Records Control Schedule for the duration of the Contract; (2) promptly provide to the District on the District’s request any Contracting Information in contractor’s custody or possession; and (3) on completion of the Contract, either provide at no cost to the District all Contracting Information related to the Contract in contractor’s possession, or preserve such Contracting https://www.ethics.state.tx.us/

II - 12

Information as provided by the District’s Records Control Schedule. For purposes of this Contract, Contracting Information means information related to the Contract in contractor’s custody or possession, including:

a) information in a voucher or the Contract relating to the receipt or expenditure of public funds by the District;

b) solicitation or bid documents relating to the Contract with the District;

c) communications sent between the District and contractor during the solicitation, evaluation, or negotiation of the Contract;

d) documents, including bid tabulations, showing the criteria by which the

District evaluated contractor or potential contractors responding to a solicitation and, if applicable, an explanation of why contractor was selected; and

e) communications and other information sent between the District and contractor related to the performance of the Contract or work performed thereunder on behalf of the District.

B. Contractor declares that it has not received from a governmental body a notice of noncompliance with a provision of Subchapter J, Chapter 552, Texas Government Code, or, if such a notice has been received, Contractor has taken adequate steps to ensure future compliance with such subchapter and has provided or upon request will provide documentation of same

RESOLUTION ADOPTING PREVAILING WAGE RATES

Fort Bend County Municipal Utility District No. 275 and body politic and corporate of the State of Texas Created pursuant to Chapters 49 and 54, Texas Water Code, as amended, to accomplish the purposes provided by Section 59, Article XVI, Texas Constitution.

Chapter 2258 public body to determine the general prevailing wage rate for classes of workers in the locality in which a public work project is to be performed.

wage rates establishing minimum rates to be paid by all contractors and subcontractors in connection with all District construction projects.

Because the District is located in Fort Bend County, Section 49.279, Texas Water Code, allows ling wage rates of

Fort Bend County.

The Board concurs that it is in the best interests of the District to adopt the prevailing wage rates of Fort Bend County;

NOW, THEREFORE, BE IT RESOLVED BY THE BOARD OF DIRECTORS OF FORT

BEND COUNTY MUNICIPAL UTILITY DISTRICT NO. 275 THAT:

Section 1: The Board hereby adopts the prevailing wage rates previously adopted and utilized by Fort Bend County for Fort Bend County public work projects. When, and to the extent, Fort Bend County amends its prevailing wage rates, such amended rates shall be considered the prevailing wage rates of the District effective upon such amendment by Fort Bend County. Nothing in this Resolution Adopting Prevailing Wage Rates in any way prohibits the payment to workers of amounts greater than the prevailing wage rates adopted by the District.

Section 2: Contractors and subcontractors on District construction projects shall be responsible to ascertain the then-current prevailing wage rates adopted and utilized by Fort Bend County, obtain a copy of same from Fort Bend County, and to pay at least such minimum wage rates for the classes of workers described therein.

Section 3: and authorized to include this Resolution Adopting Prevailing Wage Rates in: 1) the call for the bids for District construction contracts, and 2) in the District construction contracts themselves.

PASSED AND APPROVED ON April 10, 2025.

{{ *Signature1_es_:signer1:signature:email=example@email.com}} President, Board of Directors

III - 1

BID

Bid for “Construction of Texas Heritage Parkway Extension Section 2B Fulshear Ranch for Fort Bend County MUD No. 275, Fort Bend County, Texas.”

Fort Bend County Municipal Utility District No. 275 c/o BGE, Inc.

10777 Westheimer, Suite 500 Houston, Texas 77042

CONTRACTOR:

(Legal Name of Company)

ADDRESS:

County:

TELEPHONE:

FAX:

EMAIL:

The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an agreement with Owner in the form included in the Contract Documents to perform and furnish all Work as specified or indicated in the Contract Documents for the Bid Price and within the Bid Times indicated in this Bid and in accordance with the terms and conditions of the contract Documents.

Bidder accepts all of the terms and conditions of the Invitation to Bidders and Instructions to Bidders, including without limitation those dealing with the disposition of Bid security. This Bid will remain subject to acceptance for sixty (60) days after the day of Bid opening. Bidder will sign and deliver the required number of counterparts of the Agreement with the Bonds and other documents required by the Bidding Requirements within seven (7) days after the date of Owner’s Notice of Award.

In submitting this Bid, Bidder represents, as more fully set forth in the Agreement, that:

Bidder has examined, carefully studied, and understands all the terms and conditions set forth in the Bidding Documents and the following Addenda receipt of all which are hereby acknowledged:

Addendum No. Date Received Acknowledgement

This Bid is genuine and not made in the interest of or on behalf of any undisclosed person, firm or corporation and is not submitted in conformity with any agreement or rules of any group, association, organization or corporation; Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid; Bidder has not solicited or induced any person, firm or corporation to refrain from bidding; and Bidder has not sought by collusion to obtain for itself any advantage over any other Bidder or over Owner.

Bidder will complete the Work in accordance with the Contract Documents for the following prices:

(see attached bid form)

UNIT ITEM

ITEM COST TOTAL

PART I: SECTION 2B

Unit A: Site Prep

1 Preparing Right-Of-Way STA 52 $ $

Subtotal of A $

Unit B: Roadway

1 Roadway Excavation (to be spread and compacted within ROW and on future residential lots up to 1/2-mile haul or used as roadway embankment)

CY 22027 $ $

2 Embank (FNL) (OC) (TY A) (For Retaining Wall) CY 2129 $ $

3 Lime Treatment (8" Depth) SY 21351 $ $

4 Hydrated Lime (8% by Dry Weight) TON 529 $ $

5 Cement TRT (Exist Matrl) (8" Depth) SY 21351 $ $

6 Cement for Subgrade Stabilization (6% by Dry Weight) TON 396 $ $

7 Concrete Pavement (8") SY 35727 $ $

8 Exposed Aggregate Median (3''-6'' Stone Cobbles; 4'' Concrete)

SY 728 $ $

9 Exposed Aggregate Median (3''-6'' Stone Cobbles; 10'' Concrete;

10'' Subgrade)

SY 466 $ $

10 PVC (SCH 40) (6IN)

LF 756 $ $

11 PVC (SCH 40) (10IN) LF 233 $ $

12 Mountable Curb (4"X18") LF 410 $ $

13 Concrete Curb (6") LF 23656 $ $

14 Constructing Detours(2" HMA & 6" Black Base)(Temporary Base)

SY 1296 $ $

Subtotal of B $

QUANTITY

& UNIT

Fort Bend County Municipal Utility District No. 275

Texas Heritage Parkway Extension Section 2B Fulshear Ranch

Bid Form

\\bgeinc\data2\00014571-00\TS\03_Constr\01_Bid_Phase\Section 2B\[2B_Blank Bid Form.xlsx]Bid Form

III - 2 Vendor to Initial Here:______

QUANTITY

& UNIT

Fort Bend County Municipal Utility District No. 275

Texas Heritage Parkway Extension Section 2B Fulshear Ranch

Bid Form

\\bgeinc\data2\00014571-00\TS\03_Constr\01_Bid_Phase\Section 2B\[2B_Blank Bid Form.xlsx]Bid Form

UNIT C: Drainage

1 Trench Safety System (5 to 10 ft) LF 5335 $ $

2 Trench Safety System (10 to 15 ft) LF 2774 $ $

3 Trench Safety System (15 to 20 ft) LF 1712 $ $

4 Trench Safety System (Greater than 20 ft) LF 418 $ $

5 Retaining Walls (Spread Footing) SF 13677 $ $

6 CL C (Cast-In-Place) (12 ft x 8 ft Pedestrian Tunnel) CY 529 $ $

7 Reinforced Concrete Pipe, C76, Class III, Rubber Gasket (24") LF 5653 $ $

8 Reinforced Concrete Pipe, C76, Class III, Rubber Gasket (30") LF 538 $ $

9 Reinforced Concrete Pipe, C76, Class III, Rubber Gasket (36") LF 828 $ $

10 Reinforced Concrete Pipe, C76, Class III, Rubber Gasket (42") LF 1292 $ $

11 Reinforced Concrete Pipe, C76, Class III, Rubber Gasket (48") LF 934 $ $

12 Reinforced Concrete Pipe, C76, Class III, Rubber Gasket (54")

LF 569 $ $

13 Precast Concrete Standard Manhole (Depth 5 ft to 10 ft) EA 8 $ $

14 Precast Concrete Standard Manhole (Depth > 10 ft) EA 30 $ $

15 Type "C" Inlet (Standard Depth) EA 38 $ $

16 Type "C" Inlet (Additional Depth) EA 3 $ $

17 Type "C-2" Inlet (w/ 1 Ext each Side) (Standard Depth)

EA 15 $ $

18 Type "C-2" Inlet (w/ 1 Ext each Side) (Additional Depth) EA 3 $ $

19 Type A Inlet (Standard Depth) EA 3 $ $

20 Type A Inlet (Additional Depth) EA 1 $ $

Subtotal of C $

III - 3 Vendor to Initial Here:______

QUANTITY

& UNIT

Fort Bend County Municipal Utility District No. 275

Texas Heritage Parkway Extension Section 2B Fulshear Ranch

Bid Form

\\bgeinc\data2\00014571-00\TS\03_Constr\01_Bid_Phase\Section 2B\[2B_Blank Bid Form.xlsx]Bid Form

UNIT D: Illumination

1 DRILL SHAFT (RDWY ILL POLE) (30 IN) LF 64 $ $

2 IN RD IL (TY SA) 30S-2.5 (250W EQ) LED EA 8 $ $

3 IN RD IL (U/P) (TY 1)(150W EQ)LED EA 18 $ $

4 CONDT (PVC) (SCH 40) (1") LF 412 $ $

5 CONDT (PVC) (SCH 40) (2") LF 1252 $ $

6 ELEC CONDR (NO. 8) BARE LF 2027 $ $

7 ELEC CONDR (NO. 8) INSULATED LF 9760 $ $

8 ELC SRV TY A 240/480 60(SS)SS(E)GC(U)* EA 1 $ $

Subtotal of D $

UNIT E: Signing and Pavement Markings

1 Aluminum Signs (Ground Mounted)- Furnish & Install

EA 54 $ $

2 Painted Curb (Yellow) LF 2612 $ $

3 Reflectorized Pavement Markings Type I (Thermoplastic) 6" White/BRK - Furnish & Applied LF 2317 $ $

4 Reflectorized Pavement Markings Type I (Thermoplastic) 6" White/SLD - Furnish & Applied LF 162 $ $

5 Reflectorized Pavement Markings Type I (Thermoplastic) 8" White/BRK - Furnish & Applied

LF 509 $ $

6 Reflectorized Pavement Markings Type I (Thermoplastic) 8" White/Solid - Furnish & Applied LF 2584 $ $

7 Reflectorized Pavement Markings Type I (Thermoplastic) 8" Yellow/Solid - Furnish & Applied

LF 407 $ $

III - 4 Vendor to Initial Here:______

QUANTITY

& UNIT

Fort Bend County Municipal Utility District No. 275

Texas Heritage Parkway Extension Section 2B Fulshear Ranch

Bid Form

\\bgeinc\data2\00014571-00\TS\03_Constr\01_Bid_Phase\Section 2B\[2B_Blank Bid Form.xlsx]Bid Form

8 Reflectorized Pavement Markings Type I (Thermoplastic) 24" White/SLD - Furnish & Applied

LF 64 $ $

9 Reflectorized Pavement Markings Type I (Thermoplastic) 24" White/BRK - Furnish & Applied (3' Dash 2' Gap) LF 207 $ $

10 Reflectorized Pavement Markings Type I (W) (36") (Yld Tri) EA 84 $ $

11 Reflectorized Pavement Markings Type I (Thermoplastic) Arrow - Furnish & Applied

EA 10 $ $

12 Reflectorized Pavement Markings Type I (Thermoplastic) Double Arrow - Furnish & Applied

EA 14 $ $

13 Reflectorized Pavement Markings Type I (Thermoplastic) Word "Only" - Furnish & Applied EA 10 $ $

14 Reflectorized Pavement Markings Type I (Thermoplastic) Word "Yield" - Furnish & Applied

EA 8 $ $

15 Reflectorized Pavement Markers 4" Type II-C-R - Furnish & Install

EA 310 $ $

Subtotal of E $

UNIT F: SW3P

1 Sodding For Erosion Control (Various Widths)

SY 3644 $ $

2 Hydro-Mulch Seeding AC 16 $ $

3 Reinforced Filter Fabric Barrier LF 9842 $ $

4 Inlet Protection Barrier (For Stage I Inlets, Gravel Bags )

LF 2142 $ $

III - 5 Vendor to Initial Here:______

QUANTITY

& UNIT

Fort Bend County Municipal Utility District No. 275

Texas Heritage Parkway Extension Section 2B Fulshear Ranch

Bid Form

\\bgeinc\data2\00014571-00\TS\03_Constr\01_Bid_Phase\Section 2B\[2B_Blank Bid Form.xlsx]Bid Form

5 Inlet Protection Barrier (For Stage II Inlets, Gravel Bags ) EA 63 $ $

6 Construction Exits SY 220 $ $

7 Concrete Truck Washout LS 4 $ $

8 SWPPP Monitoring And Documentation MO 6 $ $

Subtotal of F $

UNIT G: Extra Work Items

1 Mobilization LS 1 $ $

2 Project Site Documentation (Before & After Construction) LS 1 $ $

Subtotal of G $

UNIT H: Ret.Wall Items

1 CEM STABIL BKFL CY 2530 $ $

2 Stone Veneer Masonry SF 5758 $ $

Subtotal of H $

UNIT I: Water Items

1 16" C900 DR-18 PVC CL 150 Water Line (Incld. Pipe & Fittings)

LF 5069 $ $

2 16" C900 DR-18 PVC CL 150 - Restrained Joint Water Line (Incld. Pipe & Fittings)

LF 562 $ $

3 12" C900 DR-18 PVC CL 150 Water Line (Incld. Pipe & Fittings)

LF 454 $ $

4 12" C900 DR-18 PVC CL 150 - Restrained Joint Water Line (Incld. Pipe & Fittings)

LF 258 $ $

8" C900 DR-18 PVC CL 150 WATER LINE (INCLD.PIPE &

FITTINGS)

LF 87 $ $

III - 6 Vendor to Initial Here:______

QUANTITY

& UNIT

Fort Bend County Municipal Utility District No. 275

Texas Heritage Parkway Extension Section 2B Fulshear Ranch

Bid Form

\\bgeinc\data2\00014571-00\TS\03_Constr\01_Bid_Phase\Section 2B\[2B_Blank Bid Form.xlsx]Bid Form

8" C900 DR-18 PVC CL 150 - RESTRAINED JOINT WATER

LINE (INCLD. PIPE & FITTINGS) LF 312 $ $

7 Fire Hydrant Assembly, Includes 6" Gate Valve & Box, 6" PVC and All Appurtenances (All Depths)

EA 7 $ $

8 16" Gate Valve & Box EA 7 $ $

9 8" Gate Valve & Box EA 2 $ $

10 12" Gate Valve & Box EA 2 $ $

11 2" Blow-Off Valve & Box EA 7 $ $

12 16" Plug and Clamp EA 3 $ $

13 12" Plug and Clamp EA 2 $ $

14 8" Plug and Clamp EA 2 $ $

15 16" Wet Connect EA 1 $ $

16 30" Steel Casing LF 335 $ $

17 24" Steel Casing LF 349 $ $

18 Spread and Compact Utility Spoils Onsite Per Grading Plan (to be spread and compacted within ROW and on future residential lots up to 1/2-mile haul or used as roadway embankment)

CY 2962 $ $

19 OSHA Trench Safety System LF 6742 $ $

Subtotal of I $

III - 7 Vendor to Initial Here:______

QUANTITY

& UNIT

Fort Bend County Municipal Utility District No. 275

Texas Heritage Parkway Extension Section 2B Fulshear Ranch

Bid Form

\\bgeinc\data2\00014571-00\TS\03_Constr\01_Bid_Phase\Section 2B\[2B_Blank Bid Form.xlsx]Bid Form

UNIT J: Sanitary Sewer Items

1 27" SDR26 D3034 PS115 PVC Sanitary Sewer, Incl. Pipe & Fittings (All Depths) (Cememt Stabilized Sand to be a minimum 2 Sack/CY and/or 200 PSI and installed to a minimum of 11' from proposed natural ground)

LF 4076 $ $

2 24" SDR26 D3034 PS115 PVC Sanitary Sewer, Incl. Pipe & Fittings (All Depths) (Cememt Stabilized Sand to be a minimum 2 Sack/CY and/or 200 PSI and installed to a minimum of 11' from proposed natural ground)

LF 949 $ $

3 21" SDR26 D3034 PS115 PVC Sanitary Sewer, Incl. Pipe & Fittings (All Depths) (Cememt Stabilized Sand to be a minimum 2 Sack/CY and/or 200 PSI and installed to a minimum of 11' from proposed natural ground)

LF 508 $ $

4 8" SDR26 D3034 PS115 PVC Sanitary Sewer, Incl. Pipe & Fittings (All Depths) (Cememt Stabilized Sand to be a minimum 2 Sack/CY and/or 200 PSI and installed to a minimum of 11' from…

This is the start of the file's text. The full file is on GovTribe.