B97 Generator Install SOW_R1.docx
DOCX document 73 KB Posted
- Solicitation number
- 70Z08121QPEC129
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF18_70Z08121QPEC129.pdf | ||
| SF18_70Z08121QPEC129.pdf | ||
| Wage Rates 15-4405_NC.txt | TXT text file | |
| B97 Electrical Drawings_reference b.pdf | ||
| Map Location and Photos_B97 Generator_reference a.pdf | ||
| Commercial Supplies and Services Clauses and Provisions FAC 2021-04.doc | DOC document | |
| FY21 Soliciation verbiage for FBO PEC129.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work & Specifications
Building #97 Generator & Quick Disconnect Install
Located at U.S. Coast Guard Base Elizabeth City, N.C.
MAY 2021
Commanding Officer United States Coast Guard BASE Elizabeth City Facilities Engineering Department Elizabeth City, NC 27909
Austin T. McPherson Facilities Engineering Department
1) SCOPE: The Contractor shall provide all necessary transportation, labor, equipment, materials, weights, measures, and testing materials to supply a portable generator and a cam-lock style generator tap box to provide emergency power to the Facilities Engineering Department (FED) shops of building #97.
2) GOVERNMENT FACILITIES AND UTILITIES:
a) Electrical power and water are available within close proximity. The Contractor will be permitted to utilize these utilities in performing the work, provided that the existing systems are not overloaded.
b) Telephone services will not be available for use by the contractor.
c) Building restroom facilities are available for use.
3) MATERIALS AND LOCATIONS:
a) The Contractor will furnish all materials, equipment, instruments, tools, safety lines and harnesses, and other items necessary for accomplishment of these services.
b) Materials shall be delivered to the jobsite in their original unopened packages, clearly marked with the manufacturer’s name, brand name, and description of contents. Storage shall be in accordance with manufacturer’s recommendations in a clean, dry, well-ventilated area. Stored materials shall be protected from sunlight, and kept away from excessive heat. Insulation board shall not be exposed to flame or other ignition sources. The contractor shall not store any highly flammable materials in the work area. Sufficient area for staging is available on site; storage areas will be pre-approved by the Contracting Officers Representative (COR) and Environmental Compliance Office (ECO). Laydown areas and parking should be on non-vegetated areas when possible. Special precautions shall be taken to ensure construction materials and debris does not enter the airfield, runways, or taxiways.
c) The Contractor is required to comply with local VOC laws and regulations. All applicable Safety Data Sheets shall be available upon request.
4) SCHEDULE OF WORK: The Contractor shall perform all work during normal base work hours. The base normal working hours are 8:00 am to 4:30 pm, Monday through Friday, but the contractor is not limited to these hours. If the contractor is going to work outside normal working hours, permission must be obtained from the Contracting Officers Representative (COR).
5) EXISTING CONDITIONS: The contractor is expected to satisfy himself as to the existing conditions and the work to be performed. The contractor shall verify all dimensions and equipment data prior to ordering materials and commencement of work. Any site visit will be arranged by the Contracting Officers Representative (COR). The Contractor shall wear the appropriate personal protective equipment (PPE) when visiting the site in accordance with OSHA, State, and Federal regulations.
6) LIABILITY OF CONTRACTOR: Any damage to government property caused by the contractor shall be repaired or replaced by the contractor at no cost to the government. The contractor shall not disconnect any service without approval from the Contracting Officers Representative (COR).
7) INSPECTION AND ACCEPTANCE: The Contracting Officers Representative (COR) will accomplish inspection and acceptance of the work.
8) LABOR LAWS: The Service Contract Act applies to the procurement.
9) SAFETY: The Contractor is wholly responsible for work site safety. The Contractor shall implement a safety program that protects the lives and health of personnel in the construction area, prevents damage to property, and avoids work interruptions. To accomplish this end, the Contractor shall provide appropriate safety barricades, signs, signal lights, etc. as well as complying with and abiding by all federal safety regulations as published by the Occupational Health and Safety Administration, 29 CFR 1910 (series), 29 CFR 1926 (series), State and Local safety laws, rules and regulations. Any operation defined as “Hot Work” as per OSHA/NFPA requires a permit to be issued by Base Elizabeth City Fire Department by contacting 252-335-6257. This includes welding, cutting, brazing, grinding or any work that could produce sparks or heat and may initiate a fire.
a. FIRE SAFETY: The contractor will ensure that the Fire Alarm panels located in Building #97 are connected to the emergency generator circuit. This will ensure the buildings have an operating fire alarm notification system in place if power loads are transferred to the emergency generators.
10) ENVIRONMENTAL COMPLIANCE: Any waste generated as a result of the project shall either be recycled IAW CIM 16455.10 and the BASE Pollution Prevention Plan or be disposed of IAW the Resource Conservation and Recovery Act (RCRA). Any Hazardous Waste shall be manifested off site with Base listed as the Generator and signatory. Any hazardous waste shall be analyzed, characterized, stored and disposed of IAW the RCRA and all applicable federal, state (i.e. DOT) and local laws and ordinances. All solid waste/trash shall be removed from site and not disposed of in onsite dumpsters. BASE recycling areas are reserved for BASE Tenants and shall not be used by Contractors at anytime. All work will be performed IAW the BASE Spill Prevention Control and Countermeasures Plan, Clean Water Act (CWA) 40 CFR 112 and the BASE Stormwater Pollution Prevention Plan (SWPPP). All chemicals required for this project shall be preapproved by the Base ECO. Safety Data Sheets (SDS) shall be provided to both the BASE ECO and Safety offices and proper storage shall be provided IAW 29 CFR 1910.1200. All installation related solid waste shall be removed from the BASE after each working day. All extra chemicals and products shall be removed from the site upon work completion, as the Emergency Planning and Community Right-To-Know Act requires Coast Guard maintains an inventory of all Hazardous Materials located at the site. A laydown area as required and an Erosion and Sediment Control Plan, shall be preapproved by BASE ECO IAW the SWPPP. No parking is allowed on vegetated areas if non-vegetated areas are within reasonable distance of worksite. Laydown areas will be approved on a case-by-case basis by the Contracting Officers Representative and Base Environmental Compliance Office on non-vegetative areas only. Any damage to vegetated areas shall be repaired and reseeded by the Contractor. Nothing shall be discharged to a storm drain at any time during the project. All storm drains within range of a potential discharge shall be covered/sealed during installation and kept covered until the work has been completed and the system has been deemed fully operational and compliant with all applicable CG policies/plans/permits/laws/ordinances. All storm drains and waterways within range of a potential discharge shall be covered/sealed or protected by silt fence. Any spills shall be reported to BASE ECO (Chris Dunn) at (252)267-9789 after containing and dialing (252)335-6257 for Base Spill Response. Draining of chemicals/fluids/petroleum shall not be allowed onsite unless preapproved by ECO.
11) SITE RESTORATION & CLEAN UP: The work site shall be cleaned up at the completion of each workday. Upon completion of the job, the Contractor shall clean up the job site, returning it to a state of cleanliness equal to or exceeding that in which it was found. The Contractor shall properly dispose of any trash, extra materials, dirt, debris, or other litter that remains, off-site. There will be no final acceptance of the contract until the Contracting Officers Representative (COR) approves the appearance of the job site.
12) GOVERNMENT FACILITIES AND REGULATIONS: The Contractor, their employees, and any sub-contractors shall become familiar with and obey all Base/ Unit regulations. All personnel employed on the project shall keep within the limits of the work area, and shall not enter any other area outside of the work site unless to do so in the performance of their duties. There shall be No Smoking in any Coast Guard Building. All smoking must be done in the designated smoking area.
13) CONTRACT TIMELINE: The Contractor shall provide all required information and complete this contract within this time schedule, unless approved by the Contracting Officer.
a) Provide all required submittals to the Contracting Officer within 14 calendar days after contract award.
b) The U.S. Coast Guard will have 7 calendar days to review the submittals and respond to Contractor.
c) Contractor shall provide projected delivery schedule during proposal and provide a firm delivery date within 14 calendar days after the contract has been awarded.
d) The Contractor, upon receiving notification that the U.S. Coast Guard has approved the submittals and having received the Contractors firm delivery date schedule, will have 14 Calendar days to begin work on the project & 30 Calendar days to complete. The Contractor shall notify the Contracting Officer of any long lead time delivery of equipment, so that the Contracting Officer can modify the delivery date of the contract.
14) SUBMITTALS:
a. Once awarded, the following list of submittals required for approval defines the specific minimum requirements for this contract. The submittal shall contain sufficient information that can be used to determine compliance of the material with these specifications and referenced specifications.
i. Detailed work schedule
ii. Equipment/data sheet submittals for each component
iii. O&M for each component installed (i.e., engines, generators, generator controllers, generator tap box, automatic transfer switches, quick disconnects etc.)
15) TECHNICAL REQUIREMENTS:
General: The Contractor shall provide all necessary transportation, labor, equipment, materials, weights, measures, and testing materials to install a cam-lock style generator tap box, an emergency service disconnect and a portable generator IAW NFPA 70 (NEC), NFPA 99, NFPA 110 and specifications provided. Attachments have been provided including map location, floor plan, and equipment photos.
a) The contractor shall complete the following tasks:
I. Install a cam-lock style generator tap box and must have the following specifications:
· NEMA 4X rated wall mounted enclosure
· Interlocked utility service disconnect sized appropriately based on current demands.
· Voltage rating: 208V (3 Phase)
· Plugs, connectors and contacts shall be sized appropriately based on current demands at panel LD1
· Generator tap box will need to feed/power the 208/120V main panel “LD1”. Panel LD1 is rated for 208/120V, 600A.
II. Generator tap box shall feed/power the 208/120V main panel “LD1”. Panel LD1 has the following specifications:
Electrical Panel LD1 Panel CAT# APB2775S Manufacturer: GE (Spectra Series) Volts: 208Y/120V (3 Phase, 4 Wire) Main circuit breaker: 600A (Cat #: SQHA36AT0600)
III. Evaluate existing electrical distribution system, properly size, electrically spec, and install a portable generator capable of supplying emergency power to all 208/120VAC circuits in the Facilities Engineering Department (FED) portion of building #97 (see reference b). Portable generator must have the following specifications:
· Fuel source: Diesel
· Capable of providing 208/120V (3 Phase).
· IP56 rated weather proof, sound attenuated enclosure
· Capable of running 24 hours at 100% load
· Trailer mounted portable generator
· Contractor must provide generator start-up service
· 2-year warranty (cover parts, labor & travel)
b) It is HIGHLY recommended that the Contractor make a site visit to properly evaluate the location of building #97(FED) and verify all aspects and/or specifications to the existing electrical distribution equipment.
c) The Contractor shall dispose of all oil and absorbent materials utilized IAW Section 10 (Environmental Compliance).
d) The Contractor shall schedule all work with the Contracting Officers Representative (COR). The Contractor shall understand the importance to schedule and complete all work in a timely fashion. The Contractor shall minimize the impact for the command and/or mission of the personnel located at building #97.
e) The Contractor shall perform all work IAW all Federal, EPA, OSHA, and State of North Carolina laws and regulations.
16) EXECUTION: Installation, workmanship, fabrication, assembly, erection, examination, inspection and testing shall be in accordance with appropriate sections of 29 CFR 1910, 1926.
17) REFERENCE DOCUMENTS:
a) Map Locations & Photos
b) B97 Electrical Drawings image1.png