US Army Corps of Engineers Fort Worth District Building Strong
Invitation For Bid W9126G21B0052
Benbrook Project Office Security Fence, Benbrook, Texas
100% SMALL BUSINESS SET-ASIDE
10 August 2021
TR_ Benbrook Off ice Security Fence Upgrade
Set Aside: 100% Small Buiness
Firm-Fixed Price
NAICS: 238990, Size Standard: $16.5M
FAR 36.204(c) Magnitude of Construction is betw een $100,000 and $250,000
POC: Samuela Adams, samuela.y.adams@usace.army.mil
If the contractor fails to provide adequate and acceptable bond documents and insurance certif icates w ithin ten days after contract aw ard, such failure shall constitute ground for termination for default w ithout the equirements for the Contracting Officer to first issue a "show cause" letter. The Government w ill not allow the contractor to w ork on the project unless the bond documents and insurance certif icate have been accepted by the Contracting Officer and a signed Notice to Proceed has been issued to the contractor.
X
SAMUELA Y ADAMS 817-886-1168
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
10-Aug-2021
(RFP)
(IFB)
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______1 calendar days and complete it w ithin ________60 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, X negotiable. (See _________________________52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________ (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee X is, is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______90 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
US ARMY CORPS OF ENGINEERS FORT WORTH
819 TAYLOR ST, CT OFC RM 2A17
FORT WORTH TX 76102-0300
W9126G
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
(hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
(817) 886-6403FAX:TEL: TEL: FAX:
W9126G21B0052 73
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
Section 00 10 00 - Solicitation
CONTRACTING OFFICER STATEMENT
Only a warranted Contracting Officer (either a Procuring Contracting Officer (PCO), or an Administrative Contracting Officer (ACO)), acting within their delegated limits, has the authority to issue modifications or otherwise change the terms and conditions of this contract. If an individual other than the Contracting Officer attempts to make changes to the terms and conditions of this contract you shall not proceed with the change and shall immediately notify the Contracting Officer.
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job
Benbrook Project Office Security Fence
FFP
Removing approximately 1,252 linear feet of existing chain link and barbed wire security fence, removing two double swing gates two 10ft sections, removing one 20 linear feet cantilever gate. Installing approximately 1,252 linear feet of new chain link and barbed wire FE8 security fence, installing three FE8 Double swing gates, installing one FE8 pedestrian gate, installing one 8ft 20 linear feet cantilever gate and installing approximately 1,252 linear feet of concrete mow strip on the outside of the existing fences mow strip at Benbrook lake project office. See Attachment for projectoverview map, map of new fence lines, and fencing specifications).
FOB: Destination
PSC CD: Y1PZ
NET AMT
CLIN SCHEDULE
CESWF-OPT-B Recreation Work, Ben Brook Project Office Security fence
Ben Brook Lake BID
SCHEDULE
Unit price shall include all associated costs for each item. Reference 01 11 00 Summary of Work and Appendices.
Item No. Description Quantity Unit U/Price Amount
BASE
0001 Ben Brook Project Office security fence
1 Job $ $
Total $
Base Period of Performance shall be 90 calendar days from issuance of Notice to Proceed. Additional options which are awarded would increase the Period of Performance by the days indicated in the SOW.
Prices must be valid for 90 calendar days for Base, and additional days for options, as indicated in the SOW, after submission of the proposal.
CLIN SCHEDULE
Section 00 11 00 Page 1
NOTES:
1. Offerors must bid on all items.
2. Costs attributable to Division 01 - General Requirements are assumed to be prorated among bid items listed.
3. The Offeror shall propose a total integrated contract duration in number of calendar days after the Notice to Proceed (NTP) is received by the Contractor, whether via electronic means or hard copy, whichever is the earliest method of delivery. The total number of proposed calendar days for design and construction through completion, ready for turnover shall not exceed the number of calendar days specified in Section 00 73 00 Supplementary Conditions. The proposed duration shall be come the required contract duration. The Government may issue the NTP via e-mail or Facsimile (FAX) or by other means. Day number 1 is the day after the date of receipt of the NTP.
4. Any proposal that is materially unbalanced as to prices for the Base CLIN Schedule may be rejected. An unbalanced proposal is one that is based on prices significantly less than the cost for some work and prices that are significantly overstated for other work and can also exist where only overpricing or underpricing exists.
5. AVAILABILITY OF FUNDS (APR 1984) (FAR 52.232-18)
Funds are not presently available for this contract. The Government's obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Office.
END OF CLIN SCHEDULE
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 N/A N/A N/A Government
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 N/A N/A N/A N/A
INSTRUCTIONS TO OFFERORS
SEALED BIDDING INSTRUCTIONS
1. INQUIRIES
OFFEROR'S QUESTIONS AND COMMENTS
All questions and/or comments are to be submitted via ProjNet. Bidder Inquiry in ProjNet at http://www.projnet.org/projnet To submit and review bid inquiry items, bidders will need to be a current registered user or self-register into system. To self-register go to web page, click BID tab select Bidder Inquiry, select agency USACE, enter Key for this solicitation listed below, and your e-mail address, click login. Fill in all required information and click create user. Verify that information on next screen is correct and click continue.
From this page you may view all bidder inquiries or add inquiry.
Bidders will receive an acknowledgement of their question via email, followed by an answer to their question after it has been processed by our technical team.
The Solicitation Number is: W9126G21B0052 The Bidder Inquiry Key is: 2V94GS-AI5TEE
Last day to submit ProjNet questions is five (5) calendar days prior to bid closure date in order to ensure adequate time is allotted to form an appropriate response and amend the solicitation, if necessary.
Offerors are requested to review the specification in its entirety, review the Bidder Inquiry System for answers to questions prior to submission of a new inquiry.
The call center operates weekdays from 8AM to 5PM U.S. Central Standard Time Zone (Chicago). The telephone number for the Call Center is 800-428-HELP.
2. INSTRUCTIONS TO OFFERORS
SPECIAL INSTRUCTIONS PERTAINING TO ELECTRONIC BIDS SUBMISSION (FAR 14.302 & 14.304)
a. All bids and a copy of the SF24 Bid Bond MUST be received electronically via email to samuela.y.adams@usace.army.mil no later than 10 Sep 2021 at 10:00AM (CT). No bids, amendments or bid bonds in Original will be accepted.
b. Electronically submitted offers must be in Adobe PDF format and include a completed SF 1442 (in accordance with FAR 52.214-18), Acknowledgement of all amendments, completed CLIN schedule, and Bid Bond.
c. Offers received will be publicly opened at the following location:
US Army Engineer District, Fort Worth, 819 Taylor St, Room, Fort Worth, TX 76102 10 Sep 2021, Time: 2:00PM (CT) Teleconference Number: (844) 800-2712 Access Code: 43375062 Security Code: 8286
d. Please note, oral explanations or instructions are not binding. Any information given to an Offeror which impacts the solicitation and/or offer will be given in the form of a written amendment to the solicitation.
e. Original copies of the Bid Bond shall be submitted to the following point of contact two (2) calendar days after the bid due date.
US Army Engineer District, Fort Worth ATTN: Samuela Adams 819 Taylor St, Room 2A17 Fort Worth, TX 76102-0300
f. OFFERS BY TELEGRAPH. Offers received by telegraph, modifications thereto, or cancellations of offers WILL NOT be accepted.
g. FACSIMILE OFFERS. Facsimile offers, modifications thereto, or cancellations of offers WILL NOT be accepted.
h. EMAIL. Modifications and cancellations of offers WILL NOT be accepted. Only the electronically submitted bid will be accepted by the Government.
i. RESPONSIBILITY. Award will be made to the lowest, responsible bidder whose bid, conforming to the invitation for bids, will be the most advantageous to the Government. To be determined responsible, the apparent low bidder shall:
(1) Have adequate financial resources to perform the contract, or the ability to obtain them. The contractor will be required to provide the Name of the Financial Institution, POC, and phone number.
(2) Ensure the representations and certifications have been completed in the Online Representation and Certification Application (ORCA) within the System for Award Management (SAM) website, in accordance with FAR 52.204-8. The representations and certifications submitted under this tab and online will be reviewed to ensure the Offeror’s representations are consistent, accurate and in accordance with regulation.
(3) Have a satisfactory performance record. The contractor shall have no performance annotated with an individual rating of less than SATISFACTORY on any Final Evaluation within five (5) years from the bid opening date.
(4) Have a satisfactory record of integrity and business ethics. Awardee will be required to provide at least three (3) references for like work, to include Business Name, Point of Contact, and telephone number.
(5) Have the necessary organization, experience, accounting and operational controls, and technical skills, or the ability to obtain them (including, as appropriate, such elements as production control procedures, property control systems, quality assurance measures, and safety programs applicable to materials to be produced or services to be performed by the prospective contractor and subcontractors).
Per FAR 9.104-3, acceptable evidence normally consists of a commitment or explicit arrangement that will be in existence at the time of the contract to acquire the needed facilities, equipment, other resources or personnel.
(6) Have the necessary production, construction, and technical equipment and facilities, or the ability to obtain them; and W9126G21B0052
(7) Be otherwise qualified and eligible to receive an award under applicable laws and regulations
j. NOTIFICATION OF UNSUCCESSFUL BIDDERS. All contract award information for this solicitation will be published electronically on SAM.gov at www.sam.gov , Solicitation Number W9126G21B0052.
Written unsuccessful bidder letters will NOT be issued.
PWS
Benbrook Project Office Security Fence
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION
31 00 00
31 - EARTHWORK
EARTHWORK
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 32 13 CHAIN LINK FENCES AND GATES
APPENDICES
1.4.1.2 PROJECT OFFICE MAPS AND DRAWINGS
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 31 19.00 44 PROJECT MEETINGS
01 32 01.00 10 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 CONTRACTOR QUALITY CONTROL
01 57 23 TEMPORARY STORM WATER POLLUTION CONTROL
01 78 00 CLOSEOUT SUBMITTALS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements
Manual
1.2 SUBMITTALS
SD-01 Preconstruction Submittals
Bonding; G Safety and Health Plan; G
AHA; G
Quality Control Plan; G Work Plan; G Work Schedule; G
1.3 GENERAL REQUIREMENTS
1.3.1 Liquidated Damages (L&D's)
Liquidated damages shall be charged in the amount of $220.66 per day if Contractor exceeds Period of Performance and there are no modifications to justify time extensions.
1.3.2 Security Requirements
1.3.2.1 AT Level 1 Training
All contractor employees, to include subcontractor employees, requiring access to Army installations, facilities, controlled access areas, or require network access, shall complete AT Level 1 awareness training within 30 calendar days after contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. Upon request, the contractor shall submit certificates of completion for each affected employee and subcontractor employee, to the COR or to the contracting officers (if a COR is not assigned), within 5 calendar days after completion of training by all employees and subcontractor personnel. AT Level 1 awareness training is available at the following website: http://jko.jten.mil/courses/atl1/launch.html;
or it can be provided by the RA ATO in presentation form which will be documented via memorandum."
1.3.2.2 Access and General Protection
All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also
SECTION 01 11 00 Page 2 http://jko.jten.mil/courses/atl1/launch.html%3B provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.
Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.
1.3.2.3 iWatch and/or CorpsWatch Training
The contractor and all associated sub-contractors shall receive a brief/ training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.
1.3.2.4 Key Control
No keys will be issues under this task order
1.3.2.5 E-Verify Program
The Contractor shall pre-screen Candidates using the E-verify Program https://www.e-verify.gov website to meet the established employment eligibility requirements. The Vendor shall ensure the Candidate has two valid forms of identification prior to ensure the correct information is entered into E-Verify System. An initial list of verified/eligible Candidates shall be provided to the Contracting Officer's Representative no later than 3 business days after the initial contract award.
1.3.2.6 Escorts
All contract employees, including subcontractor employees who are not in possession of the appropriate security clearance or access privileges, will be escorted in areas where they may be exposed to classified and/or sensitive materials and/or sensitive or restricted areas.
1.4 WORK COVERED BY CONTRACT DOCUMENTS
Provide all labor, tools, equipment, material, supplies and management to perform the following work at Benbrook Lake Project Office, Benbrook, Texas:
1.4.1 BASE - Period of Performance 60 Calendar Days
1.4.1.1 This Contract shall consist of constructing a Security Fence at Benbrook Lake project office, Benbrook Lake, Benbrook, Texas.
http://www.dhs.gov/E-Verify
1.4.1.2 Benbrook Lake P r o j e c t O f fi c e Security Fence (See Appendix 1.4.1.2)
This contract consists of removing approximately 1,252 linear feet of existing chain link and barbed wire security fence, removing two double swing gates two 10ft sections, removing one 20 linear feet cantilever gate. Installing approximately 1,252 linear feet of new chain link and barbed wire FE8 security fence, installing three FE8 Double swing gates, installing one FE8 pedestrian gate, installing one 8ft 20 linear feet cantilever gate and installing approximately 1,252 linear feet of concrete mow strip on the outside of the existing fences mow strip at Benbrook lake project office. See Attachment for project overview map, map of new fence lines, and fencing specifications).
The Contractor shall provide all labor, materials, tools, transportation, supplies, and equipment necessary to remove existing chain link and barbed wire security fence, Gates. Install new chain link and barbed wire security fence, gates, and mow strip.
The west side of the project office is approximately 168 linear feet of existing chain link fence, remove chain link fence, barbed wire and post. Install approximately 148 Linear foot of FE8 fenceand components, install one FE8 20ft double swing gate consisting of two 10ft sections and components. Install approximately 168 linear feet of concrete mow strip.
North end of the project office is approximately 505 linear foot of existing chain link fence, remove existing chain link fence, barbed wire and post, one approximately 20 linear feet cantilever gate and one double swing gate with approximately two 6ft gate sections.
Install approximately 505 Linear foot of FE8 fence and components.
Install one FE8 double swing gate 20ft total consisting of two 10ft sections, one FE8 pedestrian gate approximately 5ft, one 8ft approximately 20 linear feet cantilever gate and approximately 409 linear feet of concrete mow strip.
South end of the project office is approximately 442 linear foot of existing chain link fence remove chain link fence, barbed wire, and post. Install Approximately 422 linear foot of FE8 fence and components, install one FE8 20 linear foot double swing gate consisting of two 10ft sections and approximately 442 linear feet on concrete mow strip.
The East end of the compound is approximately 177 linear foot of existing chain link fence. Remove existing fence and components, install approximately 177 linear foot of FE8 fence and Approximately 177 linear feet of mow strip.
FENCE REMOVAL STANDARD
All identified chain link, barbed wire will be removed to include all wire, ties, chain link, barbed wire, rails, stanchions, caps, and any other associated materials. posts shall be cut flush with the existing mow strip and filled with concrete. All materials will be properly disposed of off USACE property in accordance with all local, state, and federal laws and regulations.
Before beginning any fence removal work, carefully survey the existing compound fencing and examine the drawings and specifications to determine the extent of the work. Take all necessary precautions to insure against damage to existing concrete or other structures to remain in place as approved by the Contracting Officer at no additional cost to the Government.
The contractor will be responsible for securing the project office compound during the contract period. No section of fence shall be removed that cannot be repaired within the same working day. At no point during construction will the area be left unattended, while gaps in the fencing remain no larger than four inches.
The project office compound must be secure at the end of every day.
If a temporary security fence is used, it shall be installed on the inside of the existing fence to provide ease of access to the contractor during construction. Fence must be of chain link or welded wire, at least 6 feet high, with a heavy concrete base, and individual panels bolted together. Another method that is acceptable is to temporarily secure the “old” chain-link fence material at the end of the day. This would reduce the cost of temporary security fence
All demolished materials will be removed from Government property in accordance with all local, state, and federal regulations.
FENCE INSTALLATION
Perform complete installation conforming to ASTM F567.
FENCE CONSTRUCTION STANDARD
Chain-link fence (See Attachment). Fence must be constructed of 8-foot wide wire-mesh fabric material, excluding the top guard. Chain-link fences must be constructed with 9-gauge or heavier wire. They must be galvanized with mesh openings not larger than 2 inches per side and have twisted and barbed selvages at the top and the bottom. The wire must be taut and securely fastened to rigid 2.875” OD metal posts set in concrete. The bottom must be flush with the concrete footer and supported by the stitched tension wire along the bottom of the fence (See Attachment). The fence is topped with a top guard which consists of a 45-degree diagonal support front and back, 6 strands of barbed wire with concertina wire attached between the strands of barbed wire.
Materials and construction must meet with the US Army Corps of Engineers (USACE) guide specifications shown in the USACE Standard (STD) 872-90 series (See Attachment 1.3)
a. Top rail (Barbed wire). Standard barbed wire is twisted, double-strand, 13.5-gauge wire, with four- point barbs spaced an equal distance apart. Top rail should consist of 6 strands at an approximately 45- degree angle front and back as shown in Attachment.
b. Top rail (Concertina Wire). Steel Banded type, 2 coils spiraled in opposite directions, set between both 45- degree out riggers, affixed to barbed wire with 16- gage stainless steel tie wire as shown in attachment.
c. Posts. All posts must be removed and replaced. Replacement posts must be 2.875” OD metal posts set in appropriate concrete footers.
d. New Gates. New pipe, chain link, and barbed wire gates will be installed at the north, west and south ends of the compound. All gates will be compliant with the requirements in Attachment.
e. Grounding. Grounding is required at each corner post at a minimum according to specifications in Attachment.
MOW STRIP REMOVALE STANDARD
The existing concrete mow strip is to be left in place.
MOW STRIP CONSTRUCTION STANDARD
Concrete mow strip will be constructed under the entire length of the perimeter fence on the outside of the existing mow strip. Concrete mow strip will extend two (2) inches above ground level. Concrete mow strip will not be less than ten (10) inches wide and eight (8) inches below ground level. Concrete mow strip will not be placed in the gate openings where concrete or asphalt exist nor where the fence is in asphalt already. Mow strip shall be reinforced with #4 rebar and placed according to federal standards and specifications. Provide concrete conforming to ASTM C 94/C 94M and obtaining a minimum 28-day compressive strength of 3,000 psi. Specific to the Headquarters area, the mow strip will extend two (2) inches above the internal ground level. A two (2) inch deep by four (4) inch wide inverted triangular slots shall be cut across the width of the mow strip, centered between every other fence post to allow for drainage.
REMEDIATION
Site remediation shall include backfilling any excavated areas and damaged areas and reseeding with grass seed as noted in paragraph
1.5 WORK RESCHEDULING
Normal duty hours for work shall be from 8:00 a.m. to 4:30 p.m., Monday through Friday. Requests for additional work shall require written approval from the Contracting Officer's Representative 3 days in advance of the proposed work period.
1.6 OCCUPANCY OF PREMISES
The Benbrook Lake project office will be occupied during performance of work under this Contract. Before work is started, the Contractor shall arrange with the Contracting Officer's Representative a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches. The project office fenced in area may be used for equipment or lay down, but coordination is required to ensure the lake staff can continue with their operations.
1.7 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer's Representative. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
1.8 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT
The Government will not furnish any materials or equipment.
1.9 REGULATORY REQUIREMENTS
In addition to the detailed requirements included in the provisions of this contract, comply with the most recent addition of USACE EM 385-1-1, and federal, state, and local laws, ordinances, criteria, rules and regulations.
PART 2 PRODUCTS
2.1 Sustainability
2.1.1 MATERIALS
2.1.2 Materials shall be new.
2.1.3 The Contractor must meet the recycled content requirements set forth by the EPA for specified products. The following web site contains a list of EPA designated products:
http://www.ssc.nasa.gov/environmental/pdf/AffirPro.pdf. Contractor will ensure compliance with the EPA guidelines under the categories of: non-paper office products, paper and paper products.
The Contractor must meet the Bio Preferred Program requirements set forth by USDA. The following is a link to USDA-designated product categories:
https://www.biopreferred.gov/BioPreferred/faces/pages/ ProductCategories.xhtml. Contractor will ensure compliance under the categories of: Metal Cleaners and Corrosion Removers –Corrosion Removers, Paint Removers.
2.1.4 REFERENCES
FAR Provision 52.223-1 - Biobased Product Certification
FAR Clause 52.223-2 - Affirmative Procurement of Biobased Products Under Service and Construction Contracts
FAR Provision 52.223-4 - Recovered Material Certification
FAR Clause 52.223-9 - Estimate of Percentage of Recovered Material Content for EPA-Designated Items
FAR Clause 52.223-17 - Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts
PART 3 EXECUTION
3.1 WORKING HOURS
Normal working hours for the Contractor shall be between the hours of 8:00 a.m. to 4:30 p.m., Monday through Friday, except as specifically approved in advance by the Contracting Officer or Contracting Officer's Representative. Major Federal holidays during the peak season shall be observed by the Contractor and no work on site shall be permitted except in extreme cases and after written permission by Contracting Officer or Contracting Officer's Representative.
3.2 PERIOD OF PERFORMANCE
Period of Performance shall be based on base and option awarded as identified in item description. Period of Performance shall be in calendar days from Notice to Proceed.
Example: Base Period of Performance is 60 calendars days from Notice to proceed and additional options which are awarded would increase the http://www.ssc.nasa.gov/environmental/pdf/AffirPro.pdf http://www.biopreferred.gov/BioPreferred/faces/pages/ProductCatego http://www.biopreferred.gov/BioPreferred/faces/pages/ProductCatego
Period of Performance by the days indicated in the option lines above.
3.3 RESTORATION OF SITE
The Contractor shall return the sites and surrounding areas to as near original condition as possible. The Contractor shall remove all debris resulting from work in this contract and it shall be removed from Government property. Where the ground is disturbed, the Contractor shall repair damage and then seed or turf the area. The Contractor shall provide state certification of the latest season’s crop delivered in sealed packages, bearing the producer’s guaranteed analysis for percentages of mixtures, purity, germination, weed and seed content, and inert material.
Label in conformance with AMS Seed Act and applicable state seed laws. Wet, moldy, or otherwise damaged seed will be rejected. Seed to be broadcast shall be of a 30/70 blend of perennial rye grass (Lolium perenne) and Buffalo grass (Bouteloua dactyloides). Although, there are other distributors, both seed types can be purchased at the following sites:
Turner Seed Company https://www.turnerseed.com Native American Seed https://www.seedsource.com
Field mixes will be acceptable when field mix is performed on site in the presence of the COR or Quality Assurance Representative.
-- End of Section --http://www.turnerseed.com/ http://www.seedsource.com/
SECTION 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
1.1 DEFINITIONS
1.1.1 Government or Corps of Engineers
“Government" or "Corps of Engineers" when used in reference to of the United States.
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel; G
Personnel List; G
Vehicle List; G
Statement of Acknowledgement Form SF 1413; G
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic, and security regulations. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.3.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct, and change the information contained in previous lists.
Not Used
SECTION 01 30 00 Page 1
SECTION 01 30 00
ADMINISTRATIVE REQUIREMENTS
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
15 CFR 772 Definition of Terms
15 CFR 773 Special Licensing Procedures submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTALPROCEDURES:
List of contact personnel; G,
1.3 MINIMUM INSURANCE REQUIREMENTS (SEE FAR. REQUIREMENTS)
1.4 CONTRACTOR PERSONNEL REQUIREMENTS
1.4.1 Subcontractors and Personnel
Furnish a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. Provide licensing information as required for drilling well (15 CFR 772 and 15 CFR 773). As changes occur and additional information becomes available, correct, and change the information contained in previous lists.
1.5 Not Used
1.6 SUPERVISION
Provide at least one (1) qualified Project Manager and/or one (1) on-site Project Superintendent. Both shall comply with the English-speaking requirements. The Project Manager must have experience as a Project Manager or Superintendent on projects like this contract or similar in size and complexity. The Project Superintendent must have experience as a Superintendent on projects similar in size and complexity.
The Project Manager in this context shall mean the individual with the responsibility for the overall management of the project and the Project
SECTION 01 30 00 Page 2
Superintendent shall mean the individual with the responsibility for quality and production. Both the Project Manager and Project Superintendent are subject to removal by the Contracting Officer for Non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders shall be made the subject of claim for extension of time for excess costs or damages by the Contractor.
Approval of Project Manager and on-site Project Superintendent is required prior to start of construction. Provide resumes for the proposed Project Manager and on-site Project Superintendent describing their experience with references and qualifications to the Contracting Officer for approval.
On-site Project Superintendent must have a minimum of 5 years’ experience with similar type projects. The Contracting Officer reserves the right to interview the proposed Project Manager and on-site Project Superintendent at any time in order to verify the submitted qualifications.
1.7 MEETINGS OR CONFERENCES
The Contractor will attend meetings or conferences as specified in Section 01 31 00.00 44 PROJECT MEETINGS. After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer Representative (COR) to discuss and develop a mutual understanding relative to the administration of the safety program, preparation of the schedule prices, shop drawings, and other submittals, scheduling programming, and prosecution of the work. Major subcontractors who will engage in the work shall also attend.
1.8 ELECTRONIC MAIL (E-MAIL) ADDRESS
The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats. Within 10 days after contract award, the Contractor shall provide the COR a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. Multiple e-mail addresses will not be allowed.
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to this e-mail address.
PART 2 PRODUCTS Not Used
PART 3 EXECUTION Not Used
SECTION 131 00 00 44 Page 1
SECTION 01 31 00 00 44
PROJECT MEETINGS
1.1 PRECONSTRUCTION CONFERENCE
Approximately three weeks after award of the contract and prior to the start of any construction work an authorized representative of the Contracting Officer's Representative will schedule and conduct a preconstruction conference. The Contractor's Project Manager, Superintendent, and Quality Control Manager will attend this meeting. The Contractor is encouraged to have an officer of his company and representation from his sub-contractors at this conference. This conference will be held at the location specified by the Contracting Officer's Representative. Minutes of the meeting will be prepared by the Government and signed by both the Contractor and the Contracting Officer's Representative. The minutes shall become a part of the contract file.
1.1.1 Start of Construction Work
If the Contractor has submitted the Accident Prevention (Safety) Plan, Quality Control Plan, Environmental Protection Plan for review prior to this meeting, these may be accepted in total or accepted with comments at the conference. Construction work will not proceed until after this meeting has been held, the plans noted above have been accepted, and the Notice to Proceed has been received and acknowledged by the Contractor.
1.2 OTHER MEETINGS
Construction Quality Control meetings and conferences are specified in Section 01 45 04.30 44 CONTRACTOR QUALITY CONTROL. Other meetings are specified in various Division 1 and technical sections.
SECTION 01 32 01 01 10 Page 1
SECTION 01 32 01 01 10
PROJECT SCHEDULE
ER 1-1-11 (1995) Progress, Schedules, and Network
Analysis Systems used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Project Schedule; G
1.3 QUALITY ASSURANCE
Designate an authorized representative to be responsible for the preparation of the schedule and all required updating (activity status) and preparation of reports. The authorized representative shall be experienced in scheduling projects similar in nature to this project.
1.4 SCHEDULE OF WORK
Commence, prosecute, and complete the work under this contract in accordance with the following schedule and Contract Clauses Commencement, Prosecution and Completion of Work and Liquidated Damages.
Work will commence within 10 days (calendar) after the Notice to Proceed (NTP).
Liquidated Damages will be accessed at $220.66 per calendar day.
1.4.1 Time Extensions for Unusually or Severe Weather:
a. This provision specifies the procedure for determination of time extensions for unusually severe weather in accordance with the contract clause entitled "Default: (Fixed Price Construction)." In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
SECTION 01 32 01 01 10 Page 2
(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
b. The following schedule of monthly anticipated adverse weather delays due to precipitation and temperature is based on National Oceanic and Atmospheric Administration (NOAA) or similar data for the project location and will constitute the base line for monthly weather time evaluations.
The Contractor's progress schedule must reflect these anticipated adverse weather delays in all-weather dependent activities. Wind is not considered in the Monthly Anticipated Adverse Weather Calendar Day Schedule.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAY WORK DAYS BASED ON (5) DAY WORK
WEEK.
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
4 5 4 5 5 3 3 2 3 3 4 5
c. Upon acknowledgment of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor will record on the daily Contractor Quality Control (CQC) report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous month), be calculated chronologically from the first to the last day of each month, and be recorded as full days. If the number of actual adverse weather delay days exceeds the number of days anticipated in paragraph "b", above, the Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a modification in accordance with the contract clause entitled "Default (Fixed Price Construction).
PART 2 PRODUCTS Not Used
3.1 GENERAL REQUIREMENTS
Prepare for approval a Project Schedule, as specified herein, pursuant to the Contract Clause, SCHEDULE FOR CONSTRUCTION CONTRACTS. Show in the schedule the sequence in which the Contractor proposes to perform the work and dates on which the Contractor contemplates starting and completing all schedule activities. The scheduling of the entire project, including the design and construction sequences, is required. The scheduling of construction is the responsibility of the Contractor. Contractor management personnel shall actively participate in its development.
Subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. Provide a schedule that is a forward planning as well as a project monitoring tool.
3.1.1 Approved Project Schedule
Use the approved Project Schedule to measure the progress of the work and to aid in evaluating time extensions. Make the schedule cost loaded and activity coded. The schedule will provide the basis for all progress payments. If the Contractor fails to submit any schedule within the time prescribed, the Contracting Officer or Contracting Officer's Representative may withhold approval of progress payments until the Contractor submits the required schedule.
SECTION 01 32 01 01 10 Page 3
3.1.2 Schedule Status Reports
Provide a Schedule Status Report on at least a monthly basis. If, in the opinion of the Contracting Officer or the Contracting Officer's Representative, the Contractor falls behind the approved schedule, the Contractor shall take steps necessary to improve its progress including those that may be required by the Contracting Officer, without additional cost to the Government. In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or the amount of construction plant, and to submit for approval any supplementary schedule or schedules as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
3.1.3 Default Terms
Failure of the Contractor to comply with the requirements of the Contracting Officer shall be grounds for a determination, by the Contracting Officer, that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the contract. Upon making this determination, the Contracting Officer may terminate the Contractor's right to proceed with the work, or any separable part of it, in accordance with the default terms of the contract.
3.2 BASIS FOR PAYMENT
Use the schedule as the basis for determining contract earnings during each update period and therefore the amount of each progress payment. Lack of an approved schedule update, or qualified scheduling personnel, will result in the inability of the COR to evaluate contract earned value for the purposes of payment. Failure of the Contractor to provide all required information will result in the disapproval of the preliminary, initial and subsequent schedule updates. In the event schedule revisions are directed by the COR and those revisions have not been included in subsequent revisions or updates, the COR may hold retainage up to the maximum allowed by contract, each payment period, until such revisions to the Project Schedule have been made. Activity cost loading shall be reasonable, as determined by the COR. The aggregate value of all activities coded to a contract CLIN shall equal the value of the CLIN on the Schedule.
3.3 PROJECT SCHEDULE DETAILED REQUIREMENTS
The computer software system utilized to produce and update the Project Schedule shall be capable of meeting all requirements of this specification. Failure of the Contractor to meet the requirements of this specification will result in the disapproval of the schedule.
3.3.1 Critical Path Method
Use the Critical Path Method (CPM) of network calculation to generate the Project Schedule.
3.3.2 Level of Detail Required
Develop the Project Schedule to an appropriate level of detail to address major milestones and to allow for satisfactory project planning and execution. Failure to develop the Project Schedule to an appropriate level of detail, as determined by the Contracting Officer or Contracting Officer's Representative, will result in its disapproval. The Contracting Officer will consider, but is not limited to, the following characteristics and requirements to determine appropriate level of detail:
3.3.3 NOT USED
SECTION 01 32 01 01 10 Page 4
3.3.4 NOT USED
3.3.5 Mandatory Tasks
The following tasks must be included and properly scheduled:
a. Contractor's pre-final inspection.
b. Correction of punch list from Contractor's pre-final inspection.
c. Government's pre-final inspection.
d. Correction of punch list from Government's pre-final inspection.
e. Final inspection.
3.3.5.1 Activity Responsibility Coding (RESP)
Assign responsibility Code for all activities to the Prime Contractor, Subcontractor or Government agency responsible for performing the activity.
3.3.6 Contract Line Item (CLIN) Coding (BIDI)
Code all activities to the CLIN on the Contract Line Item Schedule to which the activity belongs. An activity shall not contain more than one CLIN Item Code.