0011779905

Project Title: Renovate Building No. 460 w ith demolition of six (6) Quonset buildings, Camp Casey Project No.: 267235

a. This is a Non-Work Plan Task Order Request for Proposal (RFP) for Multiple Aw ard task Order Contract (MATOC) Local Contractors Only.

Only proposals for this requirement are being solicited from the MATOC local Contractors for the follow ing MATOC contracts issued by the 411th Contracting support Brigade (CSB) , Korea. Proposals from offerors other than these MATOC local Contractors w ill not be considered for aw ard.

MATOC Number: W91QVN-18-D-0027, 0028, 0042, 0044, 0046 and 0050.

b. Site Visit: Offerors w ho intend to propose on this solicitation are strongly encouraged to attend site visit. See site visit clause FAR 52.236-27 in Section L.

c. Submission of Proposals: See Section L for details.

The proposals shall be submitted by 1300 hours (Korean Standard Time) on the closing date of the RFP via Email to kw ison.pak.ln@army.mil and tondra.r.madison.civ@army.mil If the Contractor is unable to submit the proposal in response to this RFP, the Contractor shall submit the “No-offer letter” by closing date and time specif ied in the solicitation via Email.

MS. PAK, KWI-SON 315-755-3369

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS

NEGOTIATED

08-Jul-2022

(RFP)

(IFB)

X

CALL:

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

See Item 7

2. TYPE OF SOLICITATION

SEALED BID

3. DATE ISSUED

9. FOR INFORMATION A. NAME

SOLICITATION

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA

FAR (48 CFR) 53.236-1(e)

11. The Contractor shall begin performance w ithin _______10 calendar days and complete it w ithin ________210 calendar days after receiving aw ard, X notice to proceed. This performance period is X mandatory, negotiable. (See _________________________ Section F

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

YES X NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specified in Item 8 by ___________ local time ______________21 Jul 2022 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.

shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An offer guarantee is, X is not required.

C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Offers providing less than _______210 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO.

7. ISSUED BY CODE

411TH CONTRACTING SUPPORT BRIGADE, KOREA

HUMPHREYS CONTRACTING DIVISION

UNIT 15289

APO AP 96271-5584

UNITED STATES

W91QVN

PAGE OF PAGES

1 OF

CODE

(Title, identifying no., date):

12B. CALENDAR DAYS

01:00 PM (hour)

Sealed envelopes containing offers

5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

8. ADDRESS OFFER TO (If Other Than Item 7)

FAX:TEL: TEL: FAX:

W91QVN22R0131 39

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W91QVN22R0131

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 1 Job

Repair "K" Work

FFP

Renovate Building No. 460 with Demolition of six (6) Quonset Buildings, Camp Casey. The contractor shall provide all labor, tools, equipment, supplies and any other resources necessary to accomplish the scope of work contained herein as indicated in the drawings and in accordance with the specifications FOB: Destination

PURCHASE REQUEST NUMBER: 0011779905

PSC CD: Z2EA

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0002 1 Job

Construction "L" Work

FFP

Renovate Building No. 460 with Demolition of six (6) Quonset Buildings, Camp Casey. The contractor shall provide all labor, tools, equipment, supplies and any other resources necessary to accomplish the scope of work contained herein as indicated in the drawings and in accordance with the specifications.

FOB: Destination

PURCHASE REQUEST NUMBER: 0011779905

PSC CD: Z2EA

NET AMT

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

War Hazard

FFP

War Hazard Expected Losses from War Hazard are Zero (0).

FOB: Destination

PSC CD: Z2EA

NET AMT

Section C - Descriptions and Specifications

NON‐WORK PLAN TASK ORDER OF W91QVN‐22‐R‐0131

Renovate Building No. 460 With Demolition of six (6) Quonset Buildings

Camp Casey, Korea

TECHNICAL PROVISIONS - I

STATEMENT OF WORK

PROJECT NO TITLE LOCATION

267235 Renovate building No. 460 Camp Casey with demolition of six (6) Quonset buildings

1. DESCRIPTION: The work to be performed to renovate building No. 460 with demolition of six (6) Quonset buildings is described below and executed by one or more of the groups.

1.1. Work by Contractor: The contractor shall provide all labor, tools, equipment, supplies and any other resources necessary to accomplish the scope of work contained herein as indicated in the drawings and in accordance with the specifications.

1.2. Work by In-House Labor: Not applicable to this project.

1.3. Work by Troop Labor: Not applicable to this project.

2. PRINCIPAL FEATURES: This project includes the following principal features:

2.1. Schedule #I, Repair (K): All work shall be in accordance with the attached drawings and specifications.

2.1.1. Civil Work

2.1.1.1. Replace concrete sidewalk.

2.1.1.2. Replace and regrade Asphalt Concrete (AC) pavement.

2.1.1.3. Replace concrete curb with 0.2m width granite curb.

2.1.1.4. Replace one (1) 8.0m x 6.0m open shed with four (4) movable picnic tables.

2.1.1.5. Paint road edge line and parking line with 150mm thickness reflective white.

2.1.1.6. Replace chain link fence and one (1) single gate.

2.1.1.7. Replace basketball court, line marking, basketball goal post, and sloping for surface drainage.

2.1.1.8. Restore carpet sodding with top soil.

2.1.1.9. Replace 0.3m w steel grating cover ditch.

2.1.1.10. Replace steel grating ditch with 500mm diameter Reinforced Concrete Pipe (RCP) and one

(1) surface inlet (0.7m x 0.7m).

2.1.1.11. Replace 150mm diameter Polyvinyl Chloride (PVC) sewer line and concrete encasement.

2.1.1.12. Upgrade drainage system with 300mm diameter RCP, five (5) surface inlet (0.5m x 0.5m) and one (1) 1.2m x 1.2m drain manhole.

2.1.1.13. Connect existing water line to the building.

2.1.1.14. Plant Zelkova tree.

2.1.1.15. Plant cherry blossom.

2.2. Schedule #II, New Construction (L): All work shall be in accordance with the attached drawings and specifications.

2.2.1. Civil Work

2.2.1.1. Install 0.2m width granite curb.

2.2.1.2. Construct one (1) 4.6m width concrete step with handrail.

2.2.1.3. Construct one (1) 1.5m width concrete step with handrail.

2.2.1.4. Construct high land free standing wall block (Inoblock or approved equal).

2.2.1.5. Construct 3.6m x 2.4m trash bin.

2.2.1.6. Connect existing water line to the building for sprinkler system.

2.2.1.7. Install water line marking on sodding, pavement area, and curved spot.

2.2.2. Architectural Work

2.2.2.1. Floor work

2.2.2.1.1. Install new Polyvinyl Chloride Tile (PVCT) including Vinyl Cove Base (VCB) and Wood Base (WB) as shown on new floor plan and interior finish schedule.

2.2.2.1.2. Install new marble tile as shown on floor plans and interior finish schedule.

2.2.2.1.3. Install Floor Ceramic Tile (FCT) including cement bond coat, waterproof membrane, and mortar bed as shown on floor plans, section, and details drawings.

2.2.2.1.4. Apply epoxy coating with non-slip grits on existing floors as shown on floor plan and interior finish schedule.

2.2.2.2. Interior and exterior wall work

2.2.2.2.1. Install new Gypsum Wall Board (GWB) wall (Normal, water resistant or 'X' type) including metal studs as shown on floor plans, sections, and detail drawings.

2.2.2.2.2. Paint and texture coat for all existing interior walls including as shown on floor plan, detail drawings interior finish schedule.

2.2.2.2.3. Install new Exterior Insulation and Finish System (EIFS) and face bricks as shown on floor plan, elevations, sections, and detail drawings.

2.2.2.2.4. Install new Sound Absorption Wall Panel (SAWP) at mechanical room as shown on floor plan and interior finish schedule.

2.2.2.2.5. Install new Glazed Ceramic Wall Tile (GCWT) including cement bond coats, waterproof membrane, plastering with metal lath and waterproof GWB as shown on floor plans and sections.

2.2.2.2.6. Install new wooden panel and Solid Surface Material Wall (SSMW) as shown on floor plan and interior finish schedule.

2.2.2.2.7. Install new Marble Composition Panel (MCP) at Vest-1 as shown on floor plan and interior finish schedule.

2.2.2.3. Interior and exterior ceiling and roof work

2.2.2.3.1. Install new acoustical ceiling tiles including metal suspension systems as shown on floor plans and interior finish schedule.

2.2.2.3.2. Install new GWB (Normal, water resistant or 'X' type) ceiling including ceiling suspension system as shown on floor plans and finish schedule.

2.2.2.3.3. Paint all interior ceiling surfaces as shown on interior finish schedule and section.

2.2.2.3.4. Install new standing seam metal roof as shown on floor plan, roof plan, elevations, and details.

2.2.2.3.5. Install new rain gutters and downspouts as shown on floor plans and elevations.

2.1.2.4. Miscellaneous work

2.2.2.4.1. Install doors and door frames including new hardware sets as shown on new floor plan and door schedule.

2.2.2.4.2. Install new aluminum thermal breaker, blast type windows including insect screen including glass as shown on floor plans, elevations, and window schedule.

2.2.2.4.3. Install new window horizontal mini blinds, fireproof type.

2.2.2.4.4. Install new wooden head, jam and sill for all windows as shown on door/window schedule.

(Natural color, oak)

2.2.2.4.5. Install new aluminum louver as shown on floor plans and louver schedule.

2.2.2.4.6. Install new Fire Extinguishers Cabinets (FEC) as shown on floor plans and detail drawing.

2.2.2.4.7. Install all new toilet accessories as shown on floor plans and detail drawings.

2.2.2.4.8. Install new interior and exterior signages as shown on floor plan, elevations, and signage schedule.

2.2.2.4.9. Install new metal shelf with mop rack with new in janitor room.

2.2.2.4.10. Install new aluminum grating, Stainless Steel (SST) handrail and SST boot scraper as shown on floor plan and detail drawing.

2.2.2.4.11. Install TA-50 lockers (2 tier) including lockset as shown on floor plan and detail drawing.

2.2.2.4.12. Install new 100mm deep gravel bed including granite curb around building as shown on floor plan and detail drawing.

2.2.2.4.13. Install new bulletin board as shown on floor plan, detail drawing and signage schedule.

2.2.2.4.14. Install new wooden chair rails, wooden wall rails and ceiling molding at conference as shown on floor plans and detail drawings.

2.2.2.4.15. Install new concrete stoops and concrete steps as shown on floor plan.

2.2.2.4.16. Install woven wires and frame including gates and lockset as shown on floor plan and detail drawings.

2.2.2.4.17. Install new projection screen and projector mount new as shown on floor plans, detail drawings and interior finish schedule.

2.2.2.4.18. Install new access doors on wall and ceiling as required.

2.2.3. Mechanical Work

2.2.3.1. Install heating and cooling system by installing new Variable Refrigerant Flow (VRF) duct-free split heat pump indoor and outdoor units, DX type air handling unit, split air conditioning outdoor and indoor unit, electric unit heaters, electric wall heaters, pipes, valves, controller, insulations, controls, access doors, equipment support (concrete pad) and all associated accessories for heating and cooling system as shown on drawings. Remote controller indicators and labels shall be in English.

2.2.3.2. Install ventilation system by installing new exhaust fans, energy recovery ventilators, dehumidifier, controller, CO2 sensor, Heating, Ventilating, and Air Conditioning (HVAC) emergency shutdown switch, controls, diffusers, grilles, louvers, dampers, ducts, insulations, access doors, equipment support, and all associated accessories for ventilation system as shown on drawings.

2.2.3.3. Perform Duct Air Leakage Test (DALT) and Testing, Adjusting, and Balancing (T.A.B) after construction to verify that the HVAC system works properly.

2.2.3.4. Install plumbing system by installing new domestic cold and hot water piping system, sewer and vent piping system including plumbing fixtures, instantaneous water heaters, electric water cooler, valves, water hammer arresters, control, access doors, and all associated accessories as shown on drawings.

2.2.3.5. Install sprinkler system by installing new automatic fire protection wet sprinkler system, spare sprinkler head cabinet with spare sprinkler head (6ea) as shown on drawings.

2.2.3.6. The contractor shall inspect and test the fire protection system. The work inspection and test shall be performed by the Fire Protection Professional Engineer (FPE).

2.2.4. Electrical Work

2.2.4.1. Install new interior and exterior lighting fixtures, exit lights, toggle switches, 3-way switches, dimming switch, lighting contactors, photocell, wires and conduit.

2.2.4.2. Install new watt-hour meter, panelboards, receptacles with cover plates associated wiring and conduit.

2.2.4.3. Install new safety switches, motor controllers, junction boxes, control/power wires and conduit for mechanical systems.

2.2.4.4. Install new addressable fire alarm control and mass notification system panel, manual pull station, smoke detector and relay module, antenna, visual/signal strobes (15 or 75 candela), microphone, speaker device, fire alarm building transmitter, and associated wiring and conduit.

2.2.4.5. Install new telecommunication system including telephone terminal board, telephone/data outlets with cover plates, terminal blocks, equipment rack, and associated wire and conduit.

2.2.4.6. Install CATV distribution cabinet, pull boxes, CATV outlets, and associated wiring and conduit.

2.2.4.7. Install new exterior underground telecommunication line and accessories.

2.2.4.8. Install new exterior power distribution system including pad mounted transformer.

2.2.5. Structural Work

2.2.5.1. Construct new concrete spread footing.

2.2.5.2. Construct 150mm thickness concrete slab.

2.2.5.3. Construct 200mm thickness concrete wall and foundation.

2.2.5.4. Construct steel column and foundation and roof framing.

2.2.5.5. Construct concrete stoop and canopy.

TECHNICAL PROVISIONS - II

TECHNICAL DETAIL SPECIFICATIONS

with demolition of six (6) Quonset buildings

GENERAL: The specification sections listed below are applicable to this project. The specifications are from the “Standard Technical Specifications for O&MA Projects, Korea, Revision 1” (2014 OMA SPECS, REVISION 1), dated 20151030, located on the http://www.usfk.mil/Portals/105/Documents/Contracting/NewContract/2014-OMA-SPECS_REVISION- 1.pdf. The electronic version of the specifications is Acrobat® PDF format and can be read with the Acrobat Reader® software.

The Standard Technical Detail Specifications:

The work shall conform to the most current version of the listed standards/specifications below.

DIVISION 01 – GENERAL REQUIREMENTS

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 45 00.00 10 QUALITY CONTROL

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 58 00 PROJECT IDENTIFICATION

01 78 00 CLOSEOUT SUBMITTALS

01 78 23 OPERATION AND MAINTENANCE DATA

DIVISION 02 - EXISTING CONDITIONS

02 41 00 DEMOLITION AND DECONSTRUCTION

02 61 13 EXCAVATION AND HANDLING OF CONTAMINATED

MATERIAL

02 65 00 UNDERGROUND STORAGE TANK REMOVAL

02 81 00 TRANSPORTATION AND DISPOSAL OF HAZARDOUS

MATERIALS

02 82 14.00 10 ASBESTOS HAZARD CONTROL ACTIVITIES

02 83 19.00 10 LEAD BASED PAINT HAZARD ABATEMENT, TARGET

HOUSING & CHILD OCCUPIED FACILITIES

DIVISION 03 – CONCRETE

03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING

03 15 00.00 10 CONCRETE ACCESSORIES

03 20 00.00 10 CONCRETE REINFORCING

03 30 00 CAST-IN-PLACE CONCRETE

DIVISION 05 – METALS

05 05 23 WELDING, STRUCTURAL

05 12 00 STRUCTURAL STEEL

05 50 13 MISCELLANEOUS METAL FABRICATIONS

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 10 00 ROUGH CARPENTRY

06 20 00 FINISH CARPENTRY

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 24 00 EXTERIOR INSULATION AND FINISH SYSTEMS

07 60 00 FLASHING AND SHEET METAL

07 92 00 JOINT SEALANTS

DIVISION 08 – OPENINGS

08 11 13 STEEL DOORS AND FRAMES

08 14 00 WOOD DOORS

08 51 13 ALUMINUM WINDOWS

08 71 00 DOOR HARDWARE

08 81 00 GLAZING

08 91 00 METAL WALL AND DOOR LOUVERS

DIVISION 09 – FINISHES

09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD

09 22 36 LATH

09 29 00 GYPSUM BOARD

09 30 00 CERAMIC TILE, QUARRY TILE, AND PAVER TILE

09 51 00 ACOUSTICAL CEILINGS

09 65 00 RESILIENT FLOORING

09 90 00 PAINTS AND COATINGS

DIVISION 10 – SPECIALTIES

10 14 01 EXTERIOR SIGNAGE

10 14 02 INTERIOR SIGNAGE

10 21 13 TOILET COMPARTMENTS

10 28 13 TOILET ACCESSORIES

DIVISION 12 – FURNISHINGS

12 21 00 WINDOW BLINDS

12 32 00 MANUFACTURED WOOD CASEWORK

12 36 00 COUNTERTOPS

DIVISION 21 - FIRE SUPPRESSION

21 13 13.00 10 WET PIPE SPRINKLER SYSTEM, FIRE PROTECTION

DIVISION 22 – PLUMBING

22 00 00 PLUMBING, GENERAL PURPOSE

DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING

23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS

23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC

23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS

23 09 53.00 20 SPACE TEMPERATURE CONTROL SYSTEMS

23 82 02.00 10 UNITARY HEATING AND COOLING EQUIPMENT

DIVISION 26 – ELECTRICAL

26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS

26 08 00 APPARATUS INSPECTION AND TESTING

26 20 00 INTERIOR DISTRIBUTION SYSTEM

26 51 00 INTERIOR LIGHTING

26 56 00 EXTERIOR LIGHTING

DIVISION 27 – COMMUNICATIONS

27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM

27 54 00.00 20 COMMUNITY ANTENNA TELEVISION (CATV) SYSTEMS

DIVISION 28 - ELECTRONIC SAFETY AND SECURITY

28 31 33.00 10 FIRE ALARM REPORTING SYSTEM, RADIO TYPE

28 31 64.00 10 FIRE DETECTION AND ALARM SYSTEM, ADDRESSABLE

28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM

DIVISION 31 – EARTHWORK

31 00 00 EARTHWORK

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 05 33 LANDSCAPE ESTABLISHMENT

32 11 16.16 BASE COURSE FOR RIGID AND SUBBASE COURSE FOR

PERVIOUS PAVING

32 11 16 SUBBASES FOR FLEXIBLE PAVING

32 12 10 BITUMINOUS TACK AND PRIME COATS

32 13 17 COMPRESSION JOINT SEAL FOR CONCRETE PAVEMENTS

32 16 13 CONCRETE SIDEWALK AND CURBS AND GUTTERS

32 31 13 CHAIN LINK FENCES AND GATES

32 92 23 SODDING

DIVISION 33 - UTILITIES

33 11 00 WATER DISTRIBUTION

33 30 00 SANITARY SEWERS

33 70 02.00 10 ELECTRICAL DISTRIBUTION SYSTEM, UNDERGROUND

33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)

TECHNICAL PROVISIONS - III

SPECIAL CONDITIONS

with demolition of six (6) Quonset buildings

1. Material Approval Submittal:

(1) The contractor shall submit a shop drawing submittal schedule and the material approval request with all supporting documents to the COR within 7 days after receipt of NTP.

(2) Attached list of materials in Appendix “B” shall be included in the shop drawing submittal schedule and material approval request.

2. Extended warranty - FAR 52.246-21

2.1. Extended warranty list

No. Warranty Item Description Warranty

Period (Yrs) Certification (Yes / No)

Warranty Tag (Yes / No)

Repair Time after call

1 High land stone free standing Product 5

2 Metal roof panel Installer 10

3 VRF Heat Pump Outdoor Unit Product 3 Y Y 24 Hrs

VRF Heat Pump Indoor Unit, various capacity Product 3 Y Y 24 Hrs

5 Air Handling Unit Product 3 Y Y 24 Hrs

6 Energy Recovery Ventilator Product 3 Y Y 24 Hrs

Split Air Conditioning Outdoor

& Indoor Unit Product 3 Y Y 24 Hrs

8 LED light Product 10 Y Y 7 Days

2.2. Contractor shall submit to COR the Warranty Certification with 4025 for the listed items.

2.3. Contractor shall submit to COR Warranty management plan and approve it before 30 days of pre-warranty conference. (OMA Sec 01 78 00)

2.4. Contractor shall have the Pre-Warranty Conference before Contract Close Date. (OMA Sec 01 78)

2.5. Warranty Information and Data

2.5.1. Contractor shall submit Warranty tag design, COR shall review and approve it for the listed and shall install it for the listed items. (OMA Sec 01 78 00)

2.5.2. Submit the O&M Manual with Manufacturer’s instruction for DPW training. (OMA Sec 01 78 00)

3. The contractor shall have personnel on site for the sprinkler work and the fire alarm work upon Government's direction, who are certified by the National Institute for Certification in Engineering Technologies (NICET) Level III or equivalent. Equivalent Certificates in Korea are the followings which are issued by the Human Resource Development Service of Korea. If the contractor does not have personnel who are certified by NICET, the contractor shall have two personnel that one is certified for (1) and the other for (2) below.

(1) Engineer Fire Fighting Facilities - Electrical (소방설비기사 -전기)

(2) Engineer Fire Fighting Facilities - Mechanical (소방설비기사 -기계)

4. Environmental Requirements in Contract

The Contractor shall perform work consistent with the relevant policy and objectives identified in Installation’s Environmental Management System (EMS). The Contractor shall perform work in a manner that conforms to all appropriate Environmental Management Programs and Operational Controls identified by Installation’s EMS, including pollution prevention, waste reduction, energy use, and natural resource protection. The Contractor shall provide monitoring and measurement information as necessary for the organization to address environmental performance relative to the environmental, energy, and transportation management goals. In addition, the Contractor shall advise their employees of their roles and responsibilities identified by the EMS and how these requirements affect their work performed under this contract. The Contractor is responsible for ensuring that the Contractor and any persons involved in the supervision or performance of the contract complete all required Environmental training.

In the event of any environmental nonconformance or noncompliance associated with the contracted services, the contractor shall take corrective and/or preventative actions. In the event of any noncompliance with any federal, state, or local environmental law, regulation or requirement, the Contractor shall immediately respond by taking all appropriate corrective actions and notifying the Contracting Officer’s Representative (COR) and the Environmental Office. For any nonconformance with the EMS, the Contractor shall take corrective action and initiate further preventative action, as required by the Environmental Office.

All on-site contractor personnel shall complete necessary safety and environmental training specified for the type of work conducted on-site. Upon contract award, the COR will notify the EMS Manager to arrange Environmental training for appropriate staff.

Additionally, when ordering supplies for use on Installation, all contractor personnel must favor energy-efficient, recycled or reclaimed material whenever practicable.

The responsibilities of all contractor personnel include:

(1) Comply with all applicable environmental laws, regulations and installation environmental policies.

(2) Control and prevent spills or hazardous substances releases IAW installation Spill Prevention Plan.

(3) Ensure dust, debris, materials, trash, etc., do not become air borne and travel off the project site.

(4) Do not remove, cut, deface, injure, or destroy land resources including trees, shrubs, vines, topsoil and land forms without approval, except in areas indicated on the drawings or specified to be cleared.

(5) Monitor all water areas affected by construction activities to prevent pollution of surface and ground waters. Do not apply toxic or hazardous chemicals to soil or vegetation unless otherwise indicated.

(6) Open burning is prohibited on the Government premises IAW installation environmental policy.

(7) Participate in installation’s recycling program.

(8) Reducing the amount of hazardous material and/or solvent used by purchasing fewer hazardous materials and by increasing the use of products with recycled content. Spills of hazardous or toxic materials must be immediately reported to the Contracting Officer and the Environmental Office.

Storage, describing, packaging, labeling, marking and placarding of hazardous waste and hazardous material IAW applicable environmental laws, regulations and local environmental policies. Transport hazardous waste off Government property and dispose of it in compliance with National, Provincial, and/or Local requirements for solid waste disposal.

(9) Reducing the amount of solid waste from construction and demolition debris, and scrap metal sent to municipal and rubble landfills by reducing, reusing, and recycling. Handling, storage, and disposal of solid waste must be conducted to prevent contamination. Transport solid waste off Government property and dispose of it in compliance with National, Provincial, and/or Local requirements for solid waste disposal.

(10) Conserving energy and water usage by turning off lights and equipment when not in use and using only the necessary amount of water needed to complete the required tasks. Continuous conservation of our natural resources is a must.

(11) When potential cultural or historic items are inadvertently found during construction activities, immediately cease activities in the vicinity of the discovery and report the findings to the Environmental Office.

(12) Participate in installation’s Integrated Pest Management (IPM) program whenever practicable.

(13) Minimize interference with disturbance to, and damage to fish, wildlife, and plants including their habitat.

3. CONTRACT REQUIREMENTS PACKAGE ANTITERRORISM/OPERATIONS SECURITY REVIEW

COVER SHEET

After Notice to process is issued, COR shall take following action, Section IV. Standard Contract Language/Contract Clause Applicability and/or Additional SOW Language.

A. AT Level I training. This standard language is for contractor employees with an area of performance within as Army controlled installation, facility or area. All contractor employees, including subcontractor employees, requiring access to Army installations, facilities, and controlled-access areas shall complete AT Level I awareness training within 30 calendar days after the contract start date or effective date of incorporation of this requirement into the contract, whichever is applicable. The contractor shall submit certificates of completion for each affected contractor employee and subcontractor employee, to the COR or to the contracting officer, if a COR is not assigned, within 05 calendar days after completion of training by all employees and subcontractor personnel. AT Level I awareness training is available at the following website: http://jko.jten.mil

B. Access and general protection/security policy and procedures. This standard language is for contractor employees with an area of performance within Army controlled installation, facility, or area.

Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes.

B-a. For contractors that do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05/AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

C. iWATCH Training. The contractor and all associated sub-contractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within 30 calendar days of contract award and within 05 calendar days of new employees commencing performance with the results reported to the COR NLT 30 calendar days after contract award.

D. For contracts that require OPSEC Training. Per AR 530-1 Operations Security, the contractor employees must complete Level I OPSEC Awareness training. New employees must be trained within 30 calendar days of their reporting for duty and annually thereafter.

APPENDIX "A"

LIST OF APPLICABLE CONTRACT DRAWINGS

See Section J ‐ List of Documents, Exhibits and Other Attachments

APPENDIX "B"

List of materials for Material Approval Submittal with demolition of six (6) quonset buildings

Submittal Identification

Description of Submittal

LC-1 Ready mixed concrete, S/12cm, 240 kg/cm2

LC-2 Hot mixed Asphalt Concrete #67

LC-3 Gravel for Base Course

LC-4 Sand for Subbase Course

LC-5 Prime Coat MC-1

LC-6 Tack Coat RC-3

LC-7 Form lumber

LC-8 Reinforcing steel bar

LC-9 Expansion joint

LC-10 Wire mesh

LC-11 Granite Curb 200x300

LC-12 Post fence steel pipe galv. 3" dia x 10' w/ conc. footing

LC-13 Brace rail, steel pipe galv. 1 5/8" dia x 10' w/ cap

LC-14 Top rail steel pipe galv. 1 5/8" dia x 20' w/ coupling

LC-15 Chain link #9-2"x2"

LC-16 Coat Basketball court including labor cost

LC-17 Basketball Goal post

LC-18 ZELKOVA TREE (4.0H X 12.0R)

LC-19 CHERRY BLOSSOM (4.0H X 12.0B)

LC-20 Steel grating 300mm x 995mm w/ angle

LC-21 500mm DIA RCP

LC-22 300mm DIA RCP

LC-23 PVC Pipe 50mm dia for Water Line

LC-24 50mm 1/4 Bend

LC-25 Carpet Sodding

LC-26 0.5m X 0.5m Surface inlet w/ steel grating cover

LC-27 Manhole w/ Cover

LC-28 Shade shelter (8.0M x 6.0M)

Description of Submittal

LC-29 PVC Pipe 150mm dia for Water Line

LC-30 150mm 1/4 Bend

LC-31 38mm steel pipe for handrail

LC-32 Water line marking including labor cost

LC-33 High land stone free standing (W150~450, H150, D225)

LC-34 Trash bin

OC-1 50MM TAPPING SADDLE

OC-2 50MM GATE VALVE W/ BOX

OC-3 150MM TAPPING VALVE

OC-4 150X150X150MM TAPPING SLEVE

LS-1 Ready Mixed Conc. 280kg/cm2

LS-2 FORM

LS-3 #8-150x150 WWF

LS-4 REBAR D13

LS-5 REBAR D16

LS-6 REBAR D19

LS-7 H-346x174x6x9

LS-8 H-350x175x7x11

LS-9 H-150x150x7x10

LS-10 H-344x348x10x16

LS-11 L-50x50x6

LS-12 Purlin-200x75x25x4.5

LS-13 L-150x90x9

LS-14 VAPOR BARRIER(P.E. FILM, 0.1MM, 2PLY)

LS-15 M20 A.B.(350LG)

LS-16 M12 BOLT

LS-17 16DIA ROD BAR

LS-18 TURN BUCKLE

LA-1 Granite curb stone, 200Wx300Dx1,000L

LA-2 Ready mixed concrete, 210kg/CM, slump 12

LA-3 Wooven Wire welding fabric, 150x150, #8 x #8 incl. gate

LA-4 Vapor barrier, 0.1mm

LA-5

EIFS, PB System incl. meshes, EPS board, base/finish coat and control joint

LA-6 Waterproofing (bath room floor)

LA-7 Anodized AL blast door w/ AL frame & glasses, HDW, 1900 x 2150

LA-8 Anodized AL door w/ AL frame & glasses, HDW, 1900 x 2150

Description of Submittal

LA-9

Steel thermal insulated blast double door w/steel frame door size: 1,714 W X 2150 H X

44.5 Thk.

LA-10

Steel insulated thermal blast door with steel frame door size; 915W. X 2133H. X 44.5 Thk. 100 X 600 insulated glass

LA-11 Steel thermal insulated door w/steel frame door size: 915W X 2133 H X 44.5 Thk.

LA-12

Steel thermal double door w/steel frame door size: 1,714 W X 2133 H X 44.5 Thk., 1hrs fire rated

LA-13 Steel hollow core single door w/frame door size; 915W X 2133H. X 44.5 Thk.

LA-14 Wood solid door w/frame door size; 915W. X 2133H. X 44.5 Thk.

LA-15 Door closer, C02021

LA-16 Door closer, C02011

LA-17 Hinge, butt, A5111, 114 x 114 (NRP)

LA-18 Hinge, butt, A5112, 114 x 114 (NRP)

LA-19 Door stop and holder, Exterior type w/Conc, H9", 3"x3"

LA-20 Door stop , L02161

LA-21 Door stop , L02141

LA-22 Push plate, J302

LA-23 Pull plate, J405

LA-24 Kick plate, J102

LA-25 Threshold, aluminum, 150W, SGL, J39150

LA-26 Threshold, aluminum, 150W, SGL, J32100

LA-27 Marble SSM threshold 150mm W

LA-28 Key box, E8351

LA-29

Aluminum blast window thermal break type, fixed & tilting window, 1600x900, 26.75thk Low-e insulated glass, insect screen

LA-30 AL louver 500 X 400 with Insect Screen & Bird Screen

LA-31 Metal stud, 0.8 mm x 45 mm x200 mm W/expansion bolt

LA-32 Metal stud, 0.8 mm x 45 mm x90 mm W/expansion bolt

LA-33 Metal runner, 0.8 mm x 45 mm x202 mm W/expansion bolt

LA-34 Metal runner, 0.8 mm x 45 mm x92 mm W/expansion bolt

LA-35 Metal ceiling suspension system for GWB

LA-36 Acoustical ceiling suspension system, aluminum

LA-37 Gypsum board, 15mm thk x1,200 x2,400, normal

LA-38 Gypsum board, 15mm thk x1,200 x2,400, water resistant or X

LA-39 Gypsum board, 15mm thk x1,200 x2,400, fire resistant or X

LA-40 Acoustical tile, 600x600x16mm thk.

LA-41 Cement board with nail and adhesive, 12THK

LA-42 Floor ceramic tile

Description of Submittal

LA-43 Epoxy joint grout motor for 300 x 300 CMT

LA-44 Glazed ceramic wall tile with accessories

LA-45 Epoxy joint grout motor for 300 x 600 GCWT

LA-46 Marble tile with mortar bed

LA-47 PVC tile, KCC Neo Sense, 450 x 450 x 3Thk

LA-48 Vinyl cove base w/adhesive

LA-49 Paint, Anti-mold and mildew, latex, interior, KCC Supro home & wellbeing, EX8816

LA-50 Paint, MPI 54, latex, interior

LA-51 Paint, MPI 47, enamel, interior

LA-52 Paint, MPI 94, enamel, exterior

LA-53 Paint, MPI 79, primer for metal

LA-54 Texture coat, terracotta 25kg w/finish coat

LA-55

Noroo Paint, MPI 77, Epoxy Epoxy Paint Include Surface Preparation Base, Cleanpoxy3100, MPI77, 0.175L/M2 Mid, Cleanpoxy3100, MPI77,0.15L/M2 Top, Cleanpoxy3100, MPI77,0.15L/M2

LA-56 Toilet partition 1600 x 900

LA-57 Grab bar 915mm x 30D toilet

LA-58 Urinal partition, 1200 x 430

LA-59 Toilet tissue dispenser, Double Roll, Horizontal Type

LA-60 Paper towel dispenser with receptacle

LA-61 Mirror, 1050 x 850 with plywood back board

LA-62 Soap dispenser, liquid, wall type, SST

LA-63 Mop rack with STS shelf

LA-64 Signage, interior room, Misc BB3

LA-65 Toilet signage

LA-66 Signage, exterior

LA-67 Building identification, exterior, brass with back light

LA-68 Bulletin board, 1200 x 900, oak trim, tan nucork

LA-69 Vanity cabinet, 700x650MM size, laminated counter top

LA-70 Window trim, oak, 110W x 90W x 18Thk

LA-71 Wooden hanging rail, oak, 100W x 40Thk

LA-72 Wooden chair rail, oak, 90W x 20Thk

LA-73 Wood base board, oak, 100W x 20Thk

LA-74 Solid sufrace material (SSM) 12T W/plywood, sub-panel

LA-75 Marble composition panel W/plywood, sub-panel

LA-76 Locker, 2 tier, 600 x 750 x 1800H x 100H base, Coated steel locker

Description of Submittal

LA-77 Handrail, sst

LA-78 Boots Scraper

LA-79 Fire extinguish cabinet

LA-80 Access door, 450x450

LA-81 Projector electric screen, Grand Veiw GEC-180HI, 4,474(W) x 2,621(H)

LA-82 Projector bracket

LA-83 STL Plate Trench Cover with welding type hinge, 13 mm Thk

LA-84 SSMR roof panel only with ridge & hip

LA-85 Fiber glass, blanket w/VB. FG. 24K. 205mmThk

LA-86 Vapor retarder 1.8m x 45m 0.15mm Thk

LA-87 Protected metal liner panel #28GA

LA-88 Rain gutter, protect MET, 150 x 100H, 24GA W/accessories

LA-89 Downspout, protect MET, 100 x 75, 24GA W/accessories

LA-90

Metal canopy w/protected metal roof, lining, rain gutter w/flashing.

Wall hung type (C-100x50x20x3.2, GALV. STL & EXP. Bolt 12DIA)

OA-1 GSA class 5-A armory door, door size 78"H x 40"W w/ mechanical dial lock FF-L- 2937

OA-2 Exit device, type 1, F-01, lever type

OA-3 Exit device, type 1, F-08

OA-4 Lockset, 1000-1, F-01, lever type

OA-5 Lockset, 1000-1, F-07, lever type

OA-6 Lockset, 1000-1, F-08, lever type

OA-7 Lockset, 4000-1, F-76

OA-8 Lockset, 4000-1, F-82

OA-9 Floor Closer, C06041 with offset pivot

OA-10 Flush bolt, L04081

OA-11 Adjustable astragal R0Y824

OA-12 Weather proof seal R0Y165 for head and jamb.

OA-13 Sound absorption wall panel

LM-1 VRF Heat Pump Outdoor Unit, various size

LM-2 VRF Heat Pump Indoor Unit, various size

LM-3 Air Handling Unit

LM-4 Energy Recovery Ventilator

LM-5 Split Air Conditioning Outdoor & Indoor Unit

LM-6 Y-joint, various size

LM-7 Diffusers, various size

LM-8 Registers, various size

LM-9 Duct w/accessories, various sizes

Description of Submittal

LM-10 Duct insulation w/accessories, various size

LM-11 Pipe flexible connector

LM-12 Water closets

LM-13 Lavatories w/ faucet

LM-14 Water hammer arrester, various size

LM-15 Galvanized steel pipe with fittings & hangers, various size

LM-16 Copper tube water line, including fittings & pipe hangers, various size

LM-17 Vent thru roof

LM-18 Cast iron soil pipe with coupling incl accessories, various size

LM-19 P-trap, cast iron soil pipe, various size

LM-20 Floor cleanouts, various size

LM-21 Floor drains

OM-1 Dehumidifier

OM-2 Electric Unit Heater

OM-3 Electric Wall Heater

OM-4 Wall Exhaust Fan

OM-5 Roof Exhaust Fan, various size

OM-6 Water Meter

OM-7 Electric Water Cooler

OM-8 Instantaneous Water Heater, various size

OM-9 HVAC Emergency Shutdown Switch

OM-10 Backflow Preventer

OM-11 Pressure Reducing Valve

OM-12 Non-freeze WALL Hydrant

OM-13 Trap Primer

OM-14 Service Sink

OM-15 Alarm check valve

OM-16 Backflow preventer

OM-17 OS & Y valves, various size

OM-18 Tamper switch

OM-19 Ball valve switch

OM-20 Pressure switch

OM-21 Water motor alarm bell

OM-22 Check valve

OM-23 Fire department connection

OM-24 Ball drip valve

OM-25 Test header

Description of Submittal

OM-26 Hose valve w/cap & chain

OM-27 Test valve

OM-28 Water flow switch

OM-29 Sight glass

OM-30 Smooth bore corrosion resistant

OM-31 Spare sprinkler head cabinet

OM-32 Quick response pendent sprinkler head, various size

OM-33 Quick response up-right sprinkler head, various size

OM-34 Quick response dry sidewall sprinkler head

LE-1

LED lighting fixture, 1/25 Watt w/lamp, recessed mounted, type "NS-4b", power unit (AC to DC) and emergency power pack

LE-2

LED lighting fixture, 1/45 Watt w/lamp, recessed mounted, type "NS-5a", power unit (AC to DC)

LE-3

LED lighting fixture, 1/45 Watt w/lamp, recessed mounted ,type "NS-5b", power unit (AC to DC) and emergency power pack

LE-4

LED lighting fixture, 1/50 Watt w/lamp, recessed mounted ,type "NS-6a", power unit (AC to DC)

LE-5

LED lighting fixture, 1/50 Watt w/lamp, recessed mounted, type "NS-6b", power unit (AC to DC) and emergency power pack

LE-6

LED lighting fixture, 1/45 Watt w/lamp, surface mounted, type "NS-7a", power unit (AC to DC)

LE-7

LED lighting fixture, 1/45 Watt w/lamp, surface mounted, type "NS-7b", power unit (AC to DC) and emergency power pack

LE-8 LED lighting fixture, 18 Watt ,wall mounted, Mirror top "NS-8"

LE-9

LED lighting fixture, 18 Watt ,Surface mounted, type "NS-9",power unit (AC to DC), wet location

LE-10 LED lighting fixture, wall mount, 22 Watts, wet location, Type "NS-10"

LE-11 LED lighting fixture, wall mount,15 Watts, arm room, Type "NS-11"

LE-12 Lighting fixture, exit sign stencil face, LED, red Lamp, type "NS-3"

LE-13 Parking lot Lighting pole, 100W, LED, concrete foundation

LE-14 Sports lighting pole, 4-300W, LED, concrete foundation

LE-15 Pad mounted transformer, oil filled radial type. 150KVA, Pri: 22.9KV, Sec.:120/208V.

LE-16 Termination kits for 24KV cable

LE-17 Termination kits for 600V cable

LE-18 Fuse cut-out switch, 18KV

LE-19 Lightning arrester, 18KV

LE-20 Fiber optic cable, 12 core

LE-21 Telephone cable, 25 pair

Description of Submittal

LE-22 Dual Jack Outlet for "Telephone/LAN" system

LE-23 Quad Jack Outlet for "Telephone/LAN" system

LE-24 UTP telephone cable, CAT6

LE-25 Cable tray

LE-26 Coaxial Cable, RG11/U

LE-27 Coaxial Cable, RG6/U

LE-28 Pullbox w/ 8-way tap off and locking device

LE-29 Junction box

LE-30 Elec wire (various size)

LE-31 Conduit (various size)

LE-32 Shop drawing fire alarm system

OE-1 Toggle switch, w/plate, 1P-20A-120VAC

OE-2 3-way toggle switch, w/plate, 1P-20A-120VAC

OE-3 Dimming switch

OE-4 Photoelectric control , 1P-120V, 2000 Watt max.

OE-5 Lighting contactor "LC1"

OE-6 Lighting contactor "LC2"

OE-7 Duplex receptacle, w/plate, 2P-20A-125 VAC, gnd. Type

OE-8 Quadplex receptacle, w/plate, 2P-20A-125 VAC, gnd. Type

OE-9 Duplex receptacle, w/plate, 2P-20A-125 VAC, GFCI Type

OE-10 Duplex receptacle, w/plate, 2P-20A-125 VAC, GFCI Type "WP"

OE-11 Single receptacle, w/plate, 2P-20A-4W-250 VAC, gnd. Type

OE-12 TRANSIENT VOLTAGE SURGE SUPPRESSOR

OE-13 Safety switch-A, 3PST-200A-240V, with non-fusible, NEMA 3R, Encl

OE-14 Safety switch-B, 3PST- 60A-240V, with non-fusible, NEMA 3R, Encl

OE-15 Safety switch-C,E DPST-30A-240V, with non-fusible, NEMA 1, Encl

OE-16 Safety switch-D, DPST- 30A-240V, Non-fusible, NEMA 3R, Encl

OE-17 Combination type magnetic motor starter-MA

OE-18 Magnetic motor starter-a

OE-19 Panelboard "P1"

OE-20 Panelboard "P2"

OE-21 Panelboard "C"

OE-22 Panelboard "MDP"

OE-23 Smart watt hour meter w/ current transformer (CT's 400:5A)

OE-24 Addressable fire alarm/mass notification control panel

OE-25 Fire alarm building transmitter, BT-XM

OE-26 Combination fire alarm & MNS Speaker/Strobe

Description of Submittal

OE-27 Combination fire alarm & MNS Speaker "WP"

OE-28 Addressable smoke detector

OE-29 Addressable module

OE-30 Addressable manual pull station

OE-31 VHF-FM Antenna, BSA-1 type, Coaxial cable, w/connector, type 1 &ii, lightning arrester

OE-32 Equipment rack

OE-33 Wall MTD Telephone terminal Board

OE-34 Splice kits

OE-35 Fabric inner duct, 3"X4

Section F - Deliveries or Performance

DELIVERY INFORMATION

CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

0001 210 dys. ANP 1 W1FD USA GARRISON RED CLOUD

W1FD USA GARRISON RED CLOUD

CAMP RED CLOUD

UIJEONGBU 11770

011-82-53-470-65

W582LE

0002 210 dys. ANP 1 (SAME AS PREVIOUS LOCATION)

W582LE

0003 N/A N/A N/A N/A

CLAUSES INCORPORATED BY FULL TEXT

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 210 calendar days including 150 days for procurement of US origin material after Notice to Proceed is issued.

The time stated for completion shall include final cleanup of the premises.

(End of clause)

Section G - Contract Administration Data

Section I - Contract Clauses

CLAUSES INCORPORATED BY REFERENCE

52.232-18 Availability Of Funds APR 1984 52.229-12 Tax on Certain Foreign Procurements FEB 2021

Section J - List of Documents, Exhibits and Other Attachments

LIST OF APPLICABLE CONTRACT DRAWINGS

with demolition of six (6) Quonset buildings

GENERAL: The work shall conform to the following contract drawings and OMA standard detail drawings, 2014 (dated 30 November 2015), issued by the Department of the Army, Installation Management Agency, Korea Region Office and located on http://www.usfk.mil/Portals/105/Documents/Contracting/NewContract/STANDARD-DETAIL-DRAWINGS- FOR-OMA-PROJECTS-KOREA_20151130.pdf, all of which form a part of the specifications.

Ring No. Sheet No. Description Date

1 T-1 TITLE SHEET-1 11 APR 22

2 T-2 TITLE SHEET-2 11 APR 22

CIVIL

3 C-1 LOCATION PLAN 11 APR 22

4 C-2 REMOVAL PLAN 11 APR 22

5 C-3 SITE LAYOUT PLAN AND SCOPE OF WORK 11 APR 22

6 C-4 UTILITY PLAN 11 APR 22

7 C-5 PLANT TREE PLAN 11 APR 22

8 C-6 GRADING SECTION 11 APR 22

9 C-7 BASKETBALL COURT PLAN 11 APR 22

10 C-8 BASKETBALL GOAL POST DETAIL 11 APR 22

11 C-9 OPEN SHED TYPICAL SECTION AND DETAILS - 1 11 APR 22

12 C-10 OPEN SHED TYPICAL SECTION AND DETAILS 2 11 APR 22

13 C-11 OPEN SHED FOUNDATION, RAMP AND FLOOR

DETAIL

11 APR 22

14 C-12 MISC. DETAILS - 1 11 APR 22

15 C-13 MISC. DETAILS - 2 11 APR 22

16 C-14 MISC. DETAILS - 3 11 APR 22

17 C-15 MISC. DETAILS - 4 11 APR 22

18 C-16 MISC. DETAILS - 5 11 APR 22

19 C-17 TRASH BIN - 1 11 APR 22

20 C-18 TRASH BIN - 2 11 APR 22

21 C-19 TRASH BIN - 3 11 APR 22

22 C-20 TRASH BIN - 4 11 APR 22

23 C-21 CHAIN LINK FABRIC FENCE - 1 11 APR 22

24 C-22 CHAIN LINK FABRIC FENCE - 2 11 APR 22

STRUCTURAL

25 S-1 GENERAL NOTES, DESIGN DATA & TYPICAL DETAILS 11 APR 22

26 S-2 FOUNDATION/GROUND FLOOR PLAN 11 APR 22

27 S-3 ROOF FRAMING PLAN 11 APR 22

28 S-4 WALL SECTION 11 APR 22

29 S-5 DETAILS 11 APR 22

ARCHITECTURAL

30 A-1 GENERAL NOTES, SCOPE OF WORKS & ACM NOTES 11 APR 22

31 A-2 NEW GROUND FLOOR PLAN 11 APR 22

32 A-3 NEW ROOF PLAN 11 APR 22

33 A-4 ELEVATIONS-1 11 APR 22

34 A-5 ELEVATIONS-2 11 APR 22

35 A-6 GENERAL SECTIONS AN DETAIL 11 APR 22

36 A-7 EXTERIOR WALL SECTIONS-1 11 APR 22

37 A-8 EXTERIOR WALL SECTIONS-1 11 APR 22

38 A-9 TYP EXTERIOR WALL DETAILS 11 APR 22

39 A-10 ENLARGED PARTIAL FLOOR PLAN-1 11 APR 22

40 A-11 ENLARGED PARTIAL FLOOR PLAN-2 11 APR 22

41 A-12 ENLARGED FLOOR PLANS AND TYPICAL

ELEAVATIONS

11 APR 22

42 A-13 INTERIOR WALL SECTION - 1 11 APR 22

43 A-14 INTERIOR WALL SECTION - 2 11 APR 22

44 A-15 ROOF DETAILS 11 APR 22

45 A-16 MISC DETAILS - 1 11 APR 22

46 A-17 MISC DETAILS - 2 11 APR 22

47 A-18 MISC DETAILS - 3 11 APR 22

48 A-19 MISC DETAILS - 4 11 APR 22

49 A-20 MISC DETAILS - 5 11 APR 22

50 A-21 MISC DETAILS - 6 11 APR 22

51 A-22 INTERIOR, EXTERIOR FINISH SCHEDULE & FINISH

SCHEDULE NOTES

11 APR 22

52 A-23 MATERIAL & COLOR SCHEDULE 11 APR 22

53 A-24 DOOR / WINDOW SCHEDULE, ELEVATIONS AND

DETAIL

11 APR 22

54 A-25 HARDWARE SCHEDULE & DOOR / WINDOW NOTE 11 APR 22

55 A-26 SIGNAGE PLAN, SCHEDULE & DETAILS 11 APR 22

MECHANICAL

56 M-1 LEGEND & ABBREVIATION 11 APR 22

57 M-2 GENERAL NOTES & SCOPE OF WORK 11 APR 22

58 M-3 EQUIPMENT SCHEDULE - 1 11 APR 22

59 M-4 EQUIPMENT SCHEDULE - 2 11 APR 22

60 M-5 NEW H.V.A.C PIPING ENLARGED PLAN (SECTOR “A”) 11 APR 22

61 M-6 NEW H.V.A.C PIPING ENLARGED PLAN (SECTOR “B”) 11 APR 22

62 M-7 NEW H.V.A.C ENLARGED PLAN, SECTION AND

DETAIL (SECTOR “A”)

11 APR 22

63 M-8 NEW H.V.A.C ENLARGED PLAN (SECTOR “B”) 11 APR 22

64 M-9 NEW DOMESTIC WATER PIPING ENLARGED PLAN

(SECTOR “A”)

11 APR 22

65 M-10 NEW DOMESTIC WATER PIPING ENLARGED PLAN

(SECTOR “B”)

11 APR 22

66 M-11 NEW SEWER & VENT PIPING ENLARGED PLAN

(SECTOR “B”)

11 APR 22

67 M-12 AUTOMATIC FIRE SUPPRESSION(S) GENERAL NOTE,

SPRINKLER Q'TY LIST AND FIRE PROTECTION

REQUIREMENTS

11 APR 22

68 M-13 NEW FIRE PROTECTION PIPING ENLARGED PLAN

(SECTOR “A”)

11 APR 22

69 M-14 NEW FIRE PROTECTION PIPING ENLARGED PLAN

(SECTOR “B”)

11 APR 22

70 M-15 CONTROL DIAGRAMS 11 APR 22

71 M-16 MECH. DETAILS - 1 11 APR 22

72 M-17 MECH. DETAILS - 2 11 APR 22

73 M-18 MECH. DETAILS - 3 11 APR 22

74 M-19 FIRE DETAILS - 1 11 APR 22

75 M-20 FIRE DETAILS - 2 11 APR 22

ELECTRICAL

76 E-1 LEGEND, GENERAL NOTES AND SCOPE OF WORK 11 APR 22

77 E-2 NEW GROUND FL LIGHTING PLAN & LIGHTING

CONTACTOR "LC" DIAGRAM

11 APR 22

78 E-3 LIGHTING FIXTURE DETAILS 11 APR 22

79 E-4 LIGHT FIXTURE SCHEDULE 11 APR 22

80 E-5 NEW GROUND FL POWER PLAN 11 APR 22

81 E-6 NEW GROUND FL POWER/CONTROL PLAN FOR

MECHANICAL SYSTEM

11 APR 22

82 E-7 EXIST/NEW POWER ONE-LINE DIAGRAM & NEW

PANELBOARD "MDP" LOAD SCHEDULE

11 APR 22

83 E-8 NEW PANELBOARD "P1", "P2" &"C" LOAD SCHEDULE 11 APR 22

84 E-9 NEW GROUND FL FIRE ALARM AND MASS

NOTIFICATION SYSTEM PLAN

11 APR 22

85 E-10 NEW FIRE ALARM/MASS NOTIFICATION SYSTEM

DIAGRAM

11 APR 22

86 E-11 NEW…

This is the start of the file's text. The full file is on GovTribe.