This solicitation is for the construction of a temporary community housing site in Terrebonne Parish, Louisiana. Work includes constructing gravel roads, manufactured home pads, parking areas, utilities, fencing, and site amenities to develop approximately 138 manufactured home unit pads for operational status. The project magnitude is $10-25 million. The NAICS code is 238910 and product service code is Z1QA. The solicitation is set aside for service-disabled veteran owned small businesses. Responses are due by April 26, 2022 to the Army Corps of Engineers Memphis District. Pricing will be on a firm fixed price basis.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Title: 2097 West Park, Terrebonne Parish, Louisiana
The general description of the w ork is to furnish all materials, equipment, labor, layouts of w ork features, and supervision needed to construct a temporary community housing site consisting of approximately 138 MHU site pads. The site shall be developed to operational status so that manufactured homes may be placed on site pads. Work shall include constructing gravel roads, manufactured home gravel pads, gravel parking pads, concrete parking pads at UFAS (handicap accessible) site pads, positive storm w ater drainage, potable w ater and sew er lines, on site w astew ater treatment plant, electric pow er service, site lighting, fencing, and other miscellaneous site amenities. Each residential lot w ill have one MHU pad constructed on that site.
Magnitude of Construction : $10,000,000.00 - $25,000,000.00 NAICS Code: 238910
PSC: Z1QA
Set-Aside: Service Disabled Veteran Ow ned
X
SEQUORIA L WILSON 8178861111
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS
NEGOTIATED
18-Apr-2022
(RFP)
(IFB)
CALL:
B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
See Item 7
2. TYPE OF SOLICITATION
SEALED BID
3. DATE ISSUED
9. FOR INFORMATION A. NAME
SOLICITATION
NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)
Prescribed by GSA
FAR (48 CFR) 53.236-1(e)
11. The Contractor shall begin performance w ithin _______2 calendar days and complete it w ithin ________60 calendar days after receiving aw ard, X notice to proceed. This performance period is mandatory, negotiable. (See _________________________52.211-10
12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES," indicate within how many calendar days after award in Item 12B.)
X YES NO
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A. Sealed offers in original and __________1 copies to perform the w ork required are due at the place specif ied in Item 8 by ___________ local time ______________26 Apr 2022 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time.
shall be marked to show the offeror's name and address, the solicitation number, and the date and time of fers are due.
B. An offer guarantee is, X is not required.
C. All offers are subject to the (1) w ork requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D. Offers providing less than _______60 calendar days for Government acceptance after the date offers are due w ill not be considered and w ill be rejected.
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
7. ISSUED BY CODE
US ARMY ENGINEER DISTRICT, MEMPHIS
167 N. MAIN STREET
MEMPHIS TN 38103-1894
W912EQ
PAGE OF PAGES
1 OF
CODE
(Title, identifying no., date):
12B. CALENDAR DAYS
01:00 PM (hour)
Sealed envelopes containing offers
5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.
8. ADDRESS OFFER TO (If Other Than Item 7)
FAX:TEL: TEL: FAX:
W912EQ22B0005 226
2097 West Park Page 1 of 226 W912EQ22B0005
20B. SIGNATURE
(REV. 4-85)STANDARD FORM 1442 BACK
TO SIGN
NSN 7540-01-155-3212
SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)
CODE FACILITY CODE
17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.
the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)
AMOUNTS SEE SCHEDULE OF PRICES
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT NO.
DATE
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN
OFFER (Type or print)
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
(4 copies unless otherwise specified)
CODE
(Insert any number equal to or greater than
20C. OFFER DATE
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
10 U.S.C. 2304(c) 41 U.S.C. 253(c)
CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY
(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)
See Item 14
(Include only if different than Item 14)16. REMITTANCE ADDRESS
30B. SIGNATURE
29. AWARD (Contractor is not required to sign this document.)
document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .
gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)
30C. DATE
(Type or print)
TEL: EMAIL:
31B. UNITED STATES OF AMERICA 31C. AWARD DATE
BY
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
(Contractor is required to sign this28. NEGOTIATED AGREEMENT
(M ust be fully completed by offeror)OFFER
2097 West Park Page 2 of 226 W912EQ22B0005
Item # Item Quantity Unit of Measure Price Amount
WATER SERVICE
1 Yard Hydrant 1 EA $___________ $_______________
2 Fire Hydrant, Dry Barrel 36" Bury Depth 12 EA $___________ $_______________
3 3/4"-1" Water Service Pipe 5,275 LF $___________ $_______________
4 Water Service Connection for MHU, Inc. Shutoff Valves 205 EA $___________ $_______________
5 Water Service Fees (Tap & Water Meter Installed by Utility ) 1 EA $___________ $_______________
6 4" Water Main Pipe 3,900 LF $___________ $_______________
7 4" Gate Valve w/ Cast Iron Box 2 EA $___________ $_______________
8 6" Water Main Pipe (Inc. Long FH Legs) 4,050 LF $___________ $_______________
9 6" Gate Valve w/ Cast Iron Box (Inc FH Valves) 17 EA $___________ $_______________
10 6" Double Check Valve Backflow Preventer Assembly 1 EA $___________ $_______________
SEWER SERVICE
11 8" Gravity Sewer Pipe 6,590 LF $___________ $_______________
12 4"-6" Gravity Sewer Service Pipe 5,275 LF $___________ $_______________
13 3" Force Main Pipe 4,800 LF $___________ $_______________
14 Cleanout - Main Line 4 EA $___________ $_______________
15 MHU Gravity Sewer Service Connection, Inc. CO 205 EA $___________ $_______________
16 Manhole (Typical) 16 EA $___________ $_______________
17 Wastewater Pump Station - Complete Install 2 LS $___________ $_______________
18 Wastewater Treatment Plant Equipment - Complete Install of GFE 1 LS $___________ $_______________
Wastewater Treatment Plant Site - Complete (less electric service, and concrete pads quantified elsewhere) 1 LS $___________ $_______________
ELECTRICAL SERVICE
20 Connect to Electric Utility (All Costs Upstream of Metering Structure) 1 LS $___________ $_______________
21 30 KVA Pole Mounted Transformer 1 EA $___________ $_______________
22 75 KVA Pole Mounted Transformer 18 EA $___________ $_______________
23 112.5 KVA Pole Mounted Transformer 18 EA $___________ $_______________
24 Primary Power Pole 19 EA $___________ $_______________
25 Primary Overhead Circuit 7,075 LF $___________ $_______________
26 Primary Metering Structure 1 LS $___________ $_______________
27 Secondary Overhead Circuit 7,400 LF $___________ $_______________
28 Below Grade Secondary Circuit (Conduit & Conductors) 5,740 LF $___________ $_______________
29 Secondary Power Pole 38 EA $___________ $_______________
30 Site Lighting - Lamp Assembly 17 EA $___________ $_______________
31 MHU Service / Power Disconnect 82 EA $___________ $_______________
32 Wastewater Treatment Plant Service, Complete 1 EA $___________ $_______________
33 Wastewater Pump Station Service, Complete 2 EA $___________ $_______________
2097 West Park Page 3 of 226 W912EQ22B0005
MISC. SITE SERVICE
34 Fencing 7,180 LF $___________ $_______________
35 Fencing Gates (Various Sizes) 1 EA $___________ $_______________
36 Post Mounted Street Sign (Loc. TBD) 5 EA $___________ $_______________
37 Pet Waste Station 3 EA $___________ $_______________
38 Bus Stop (Including Concrete, Loc TBD) 2 EA $___________ $_______________
39 Mail Box Assembly (Including concrete) 2 EA $___________ $_______________
40 Dumpster Pad (not including concrete) 2 EA $___________ $_______________
41 Concrete - UFAS Pads 71,280 SF $___________ $_______________
42 Concrete - WWTP Equipment Pads 5,940 SF $___________ $_______________
43 Concrete - Misc. 2,200 SF $___________ $_______________
44 Concrete - DOTD Driveway Apron 1 EA $___________ $_______________
45 Aggregate Site & Parking Pad, Complete - MHU 516,295 SF $___________ $_______________
46 Aggregate Site Pads, Complete - UFAS 68,400 SF $___________ $_______________
47 Streets & Misc Aggregate surfaces, Complete 241,675 SF $___________ $_______________
48 Culvert - On site drainage 3 EA $___________ $_______________
49 Culvert - Bayou Blue 36", complete inc. fill to final grade 1 EA $___________ $_______________
GENERAL
50 Overhead, Incidentals, and Other Costs Not Otherwise Specified 1 LS $___________ $_______________
51 Mobilization 1 LS $___________ $_______________
52 Demobilization 1 LS $___________ $_______________
53 Bonding 1 LS $___________ $_______________
2097 West Park Page 4 of 226 W912EQ22B0005
CONDITIONS AND NOTICES TO BIDDERS
A. BIDDING MATERIAL – Copies of the Solicitation, Specifications, and drawings forms are available by INTERNET ACCESS ONLY. Prospective bidder should submit technical questions concerning this Invitation for Bid via Bidder Inquiry in ProjNet at www.projnet.org/projnet. (See Paragraph M Below). All other inquiries should be emailed to the
Contract Specialist, sequoria.l.wilson@usace.army.mil
B. BID DOCUMENTS: The following documents must be submitted with a bid:
1. SF 1442, Solicitation, Offer and Award
2. Schedule of bidder prices
3. Representations and Certifications (Section 00600)
4. All amendments must be acknowledged
5. Financials
6. Equipment list
C. SITE VISITS – Bidders should inspect the job site prior to submitting a bid. A site visit can be scheduled by contacting Mr. Randy J Persica at randy.j.persica@usace.army.mil or (504)-628-
5100. See Section 00100, clause 52.236-27 Alt I, entitled “Site Visit (Construction)”.
D. CONDITIONS AFFECTING THE WORK – Bidders should visit the site and take such other steps as may be reasonably necessary to ascertain the nature and location of the work and the general and local conditions that can affect the work or the cost thereof. Failure to do so will not relieve offeror from the responsibility for estimating properly the difficulty or cost of successfully performing the work. The Government will assume no responsibility for any understanding or representations concerning conditions made by any of its officers or agents prior to the execution of the contract, unless included in the Request for Proposal, the specifications or related documents. See Section 00700, clause 52.236-3, entitled “Site
Investigation and Conditions Affecting the Work”.
E. BID SUBMISSION INSTRUCTIONS - Due to the COVID-19 Global Pandemic, the
Government is taking precautions to ensure the safety and health of all Contractors and
Government employees. All submissions to this bid announcement shall be submitted electronically through DoD Safe. Bids will be opened at the time set for opening in the Invitation for Bids. Their content will be made public for the information of bidders and others interested.
As soon as practicable after bid opening, an abstract of bids will be available through our web page at: https://beta.sam.gov Contract Opportunities under attachment Abstract.
(1) NO paper copies, CD-ROMs or facsimile submissions will be accepted. Electronic Proposal
Submission is required through the Army’s Electronic File Sharing Service, DoD SAFE
(https://safe.apps.mil).
(2) The DoD SAFE Application is used to send large files to individuals that would normally be too large to send via email. There are no user accounts for SAFE. Authentication is handled via email. Anyone has access to DoD SAFE, and the application is available for use
2097 West Park Page 5 of 226 W912EQ22B0005 http://www.projnet.org/projnet http://www.projnet.org/projnet mailto:sequoria.l.wilson@usace.army.mil mailto:randy.j.persica@usace.army.mil https://safe.apps.mil/ by anyone. See the attached SAFE “Getting Started Guide” has information on how to utilize the system (https://safe.apps.mil/about.php).
F. INSTRUCTIONS FOR UPLOADING FILES -
(1.) Send an email to the Contracting Officer and Contract Specialist to receive the link to drop off your proposal. This will need to be completed five (5) business days prior to proposal due date.
a. Sequoria Wilson, Contract Specialist at: sequoria.l.wilson@usace.army.mil
b. Priscilla Sweeney, Contracting Officer at: priscilla.g.sweeney@usace.army.mil
(2.) You will receive an email with the link to submit your drop-off. The link will be provided no later than two (2) business days prior to the proposal due date.
(3.) Short Note to the Recipients: Click the Add Files or Drag and Drop your files. For file description, enter W912EQ22B0005-FIRMNAME.
(4.) Click Upload button to send documents.
(5.) Guest users will need to check their email to verify their email address before the recipients will be notified. (Government-issued Common Access Cards ((CACs)) are not required).
File Size Limitations: Bidders are advised to follow the DoD SAFE instructions for uploading files. DoD SAFE supports delivery up to 8GB. If needed, Bidders are advised to break the files down into smaller sections to upload it to the system. In such cases, please divide the sections as logically as possible and be sure to clearly name the files as specified below.
File Naming Convention: To ensure your submission is received and processed appropriately, it is important that interested parties CAREFULLY ensure their electronic files adhere to the following naming convention:
• W912EQ22B0005-FIRMNAME-VOLUME I
• W912EQ22B0005-FIRMNAME-VOLUME II
Each file name shall begin with the solicitation number followed by the firm’s name and a brief file description. Please see examples above.
File Organization: Although hard copies are not accepted, each submittal shall be clearly indexed and logically assembled. Font size shall be 10 or larger. Pages shall be letter sized (larger page sizes (such as 11x17 foldouts, etc.) will be counted as two (2) pages.
Upload Completion & Deadline: Interested parties shall submit responses no later than the date specified on the solicitation document. The time & date of proposal receipt will be the upload completion / delivery time & date recorded within DoD SAFE site. Do not assume that electronic submission will occur instantaneously. Large files (i.e. 10MB or more) will take some time to
2097 West Park Page 6 of 226 W912EQ22B0005 upload. Bidders should time their upload effort with prudence by not waiting until the last few minutes—this will allow for unexpected delays in the transmittal process. Bidders are encouraged to keep a copy of the upload confirmation for their record. Submissions after the deadline will be considered late and will be processed in accordance with FAR 52.214-7.
Electronic Files: Files shall be in their native format (i.e. doc, xls, ppt, etc.), or if in pdf format, shall be in searchable text. Text and graphics portfolios of the electronic copies shall be in a format readable by Microsoft Office or Adobe applications. Data submitted in a spreadsheet format shall be readable by MS Excel (all cells and formulas should be unlocked).
As another precaution, the Federal building is closed to the public for viewing. In lieu of this, there will be a conference phone line available for all who are interested in attending the bid opening. Bid opening call-in information:
USA Toll-Free: 844-800-2712
Meeting Number: 2761 757 0411
Password: tVHQpFF*894
G. BIDDER’S ADDRESS – Prospective bidders should indicate in the bid, the address to which payment and/or correspondence should be mailed, if such address is different from that shown for the bidder on Standard Form 1442 Block 14.
H. AMENDMENTS PRIOR TO DATE SET FOR OPENING BIDS - The right is reserved as the interest of the Government may require, to revise or modify the specifications or drawings or both prior to the date set for receiving Request for Proposal. Such revisions and amendments, if any, will be announced by an amendment or modifications to this Request for Proposal. If the revisions and modifications are of a nature which requires material changes in quantities or prices or both, the date set for Invitation for Bid may be postponed by such number of days as in the opinion of the issuing officer will enable bidders to revise their proposal. In such cases, the amendment will include an announcement of the new date for proposals.
I. NOTICE TO BIDDERS - NINETY DAY OFFER GUARANTEE (See SF 1442 Block 13d)
Bidders are advised to review CLASS DEVIATION REVISIONS-FAR 52.219-14-
Limitations on Subcontracting (DEVIATION 2019-O0003) and 52.291-27 Notice of Service-
Disabled-Veteran-Owned Small Business Set-Aside (DEVIATION 2019-O0003) implemented by the Small Business Administration in accordance with FAR part 19.
J. EXPLANATION OF PROVISION/CLAUSE NUMBERS UTILIZED IN THIS
SOLICITATION –
1. Federal Acquisition Regulation (FAR) provisions/clauses are numbered as follows:
52.252-1.
2097 West Park Page 7 of 226 W912EQ22B0005
2. Defense Acquisition Regulation Supplement (DFARS) provisions/clauses are numbered as follows: 252.204-7000.
3. Army Federal Acquisition Regulation Supplement (AFARS), provisions/clauses are numbered as follows: 5152.237-9000.
4. USACE Acquisition Instruction (UAI) provisions/clauses are numbered as follows:
5152.232-9001.
K. REQUIRED SYSTEM FOR AWARD MANAGEMENT REGISTRATION - By submission of a bid, the bidders acknowledges the requirement that prospective awardees must be registered in the System for Award Management (SAM) database prior to award, during performance, and through final payment of any contract resulting from this quote. Lack of registration in the SAM database will make an bidder ineligible for award. Contractors may obtain information on registration and annual confirmation requirements by calling 1-888-227-
2423, or at: http://www.sam.gov.
L. BIDDER’S QUALIFICATIONS - To establish its responsibility, bidders may be requested by the Government to submit a statement regarding his previous experience in performing comparable work, his business and technical organization, financial resources (including recent financial statements or audits), plant available to be used in performing the work and, if applicable, an approved sub-contracting plan in accordance with FAR 9.104-1. All documents relevant to establish a bidder’s responsibility shall be made available as soon as practicable after receiving proposal; but, not later than 3 days after request by the Contracting Officer or the authorized Representative of the Contracting Officer.
The Government may perform a price realism analysis as a part of its fair and reasonable price determination. A price realism analysis may also be used for the purpose of measuring a
Bidder’s understanding of the requirements, to evaluate whether the Bidder can realistically perform the requirements at the fixed price proposed, and to assess the risk to the Government inherent in the bid.
M. NOTICE OF BONDS AND INSURANCE - The following proposal/contract information is applicable only if the proposal/contract is over one hundred fifty thousand dollars ($150,000):
1. PERFORMANCE BONDS. The penal amount of the performance bond shall equal one hundred percent (100%) of the contract price. Bonds shall be received within ten (10) days after receipt of contract award. See Section 00700, clause 52.228-15, entitled
“Performance and Payment Bonds – Construction”.
2. PAYMENT BONDS: Within ten (10) days after receipt of contract award to the bidder whom award is made, one (1) bond, with good and sufficient surety or sureties acceptable to the Government, shall be furnished; namely a Payment Bond (Standard Form 25A). The penal amount of such bonds shall equal one hundred percent (100%) of the contract price. See Section 00700, clause 52.228-15, entitled “Performance and Payment Bonds –
Construction”.
2097 West Park Page 8 of 226 W912EQ22B0005 http://www.sam.gov/
3. INSURANCE: The accepted bidder shall provide adequate insurance, within ten (10) days after receipt of contract award. See Section 00800, entitled Insurance
Requirements and Section 00 80 00.00 11, Special Contract Requirements --- Additional
Insurance References.
N. POST AWARD SUBMITTAL REQUIREMENTS - Within ten (10) days after receipt of contract award, the contractor shall submit an acceptable performance bond, payment bond and certificate of insurance. Within fifteen (15) days after receipt of notice of award, the contractor shall provide an approved Accident Prevention Plan, Environmental Protection Plan and Quality Control Plan. (See Sections 00 80 00.00 11, 01 57 20.00 11, and 01 45 04.00 11)
Within ten (10) days prior to commencement of work under this contract, the contractor shall submit to the Contracting Officer’s Chief of Security, a list of all Personnel, Vehicles and
Equipment that may be used during the construction work under this contract. (See Sections
00800)
O. BIDDER INQUIRY
1. Prospective Bidders should submit questions concerning this Invitation for Bid via email to sequoria.l.wilson@usace.army.mil and priscilla.g.sweeney@usace.army.mil.
P. BUSINESS INTEGRITY- The apparent successful bidder as a condition for award of any contract resulting from this solicitation may be required to execute a certificate related to
Business Integrity.
Q. AVAILABLILITY OF FUNDS -Funds are not presently available for this contract. The
Government’s obligation under this contract is contingent upon the availability of appropriated funds from which payment for contract purposes can be made. No legal liability on the part of the Government for any payment may arise until funds are made available to the Contracting
Officer for this contract and until the Contractor receives notice of such availability, to be confirmed in writing by the Contracting Officer IAW FAR Part 52.232-18 – Availability of
Funds.
2097 West Park Page 9 of 226 W912EQ22B0005 mailto:sequoria.l.wilson@usace.army.mil mailto:priscilla.g.sweeney@usace.army.mil
Section 00100 - INSTRUCTIONS TO BIDDERS
52.204-7 System for Award Management OCT 2018
52.204-18 Commercial and Government Entity Code Maintenance AUG 2020
52.214-3 Amendments To Invitations For Bids DEC 2016
52.214-5 Submission Of Bids DEC 2016
52.214-6 Explanation To Prospective Bidders APR 1984
52.214-7 Late Submissions, Modifications, and Withdrawals of Bids NOV 1999
52.214-18 Preparation of Bids-Construction APR 1984
52.214-19 Contract Award-Sealed Bidding-Construction AUG 1996
52.214-34 Submission Of Offers In The English Language APR 1991
52.214-35 Submission Of Offers In U.S. Currency APR 1991
52.216-1 Type Of Contract APR 1984
52.222-5 Construction Wage Rate Requirements--Secondary Site of the MAY 2014
Work
52.222-12 Contract Termination-Debarment MAY 2014
52.222-23 Notice of Requirement for Affirmative Action to Ensure FEB 1999
Equal Employment Opportunity for Construction
52.233-2 Service Of Protest SEP 2006
52.236-27 Alt I Site Visit (Construction) (Feb 1995) - Alternate I FEB 1995
252.204-7004 Antiterrorism Awareness Training for Contractors. FEB 2019
252.204-7008 Compliance With Safeguarding Covered Defense Information OCT 2016
Controls
252.204-7019 Notice of NIST SP 800-171 DoD Assessment Requirements NOV 2020
2097 West Park Page 10 of 226 W912EQ22B0005
52.204-7 SYSTEM FOR AWARD MANAGEMENT (OCT 2018)
(a) Definitions. As used in this provision--
Electronic Funds Transfer (EFT) indicator means a four-character suffix to the unique entity identifier. The suffix is assigned at the discretion of the commercial, nonprofit, or Government entity to establish additional System for
Award Management records for identifying alternative EFT accounts (see subpart 32.11) for the same entity.
Registered in the System for Award Management (SAM) means that--
(1) The Offeror has entered all mandatory information, including the unique entity identifier and the EFT indicator, if applicable, the Commercial and Government Entity (CAGE) code, as well as data required by the Federal Funding
Accountability and Transparency Act of 2006 (see subpart 4.14) into SAM;
(2) The offeror has completed the Core, Assertions, and Representations and Certifications, and Points of Contact sections of the registration in SAM;
(3) The Government has validated all mandatory data fields, to include validation of the Taxpayer Identification
Number (TIN) with the Internal Revenue Service (IRS). The offeror will be required to provide consent for TIN validation to the Government as a part of the SAM registration process; and
(4) The Government has marked the record ``Active''.
Unique entity identifier means a number or other identifier used to identify a specific commercial, nonprofit, or
Government entity. See www.sam.gov for the designated entity for establishing unique entity identifiers.
(b)(1) An Offeror is required to be registered in SAM when submitting an offer or quotation, and shall continue to be registered until time of award, during performance, and through final payment of any contract, basic agreement, basic ordering agreement, or blanket purchasing agreement resulting from this solicitation.
(2) The Offeror shall enter, in the block with its name and address on the cover page of its offer, the annotation
``Unique Entity Identifier'' followed by the unique entity identifier that identifies the Offeror's name and address exactly as stated in the offer. The Offeror also shall enter its EFT indicator, if applicable. The unique entity identifier will be used by the Contracting Officer to verify that the Offeror is registered in SAM.
(c) If the Offeror does not have a unique entity identifier, it should contact the entity designated at www.sam.gov for establishment of the unique entity identifier directly to obtain one. The Offeror should be prepared to provide the following information:
(1) Company legal business name.
(2) Tradestyle, doing business, or other name by which your entity is commonly recognized.
(3) Company physical street address, city, state, and Zip Code.
(4) Company mailing address, city, state and Zip Code (if separate from physical).
(5) Company telephone number.
(6) Date the company was started.
(7) Number of employees at your location.
2097 West Park Page 11 of 226 W912EQ22B0005
(8) Chief executive officer/key manager.
(9) Line of business (industry).
(10) Company headquarters name and address (reporting relationship within your entity).
(d) Processing time should be taken into consideration when registering. Offerors who are not registered in SAM should consider applying for registration immediately upon receipt of this solicitation. See https://www.sam.gov for information on registration.
(End of Provision)
52.204-18 COMMERCIAL AND GOVERNMENT ENTITY CODE MAINTENANCE (AUG 2020)
(a) Definition. As used in this clause--
Commercial and Government Entity (CAGE) code means--
(1) An identifier assigned to entities located in the United States or its outlying areas by the Defense Logistics
Agency (DLA) Commercial and Government Entity (CAGE) Branch to identify a commercial or government entity by unique location; or
(2) An identifier assigned by a member of the North Atlantic Treaty Organization (NATO) or by the NATO Support and Procurement Agency (NSPA) to entities located outside the United States and its outlying areas that the DLA
Commercial and Government Entity (CAGE) Branch records and maintains in the CAGE master file. This type of code is known as a NATO CAGE (NCAGE) code.
(b) Contractors shall ensure that the CAGE code is maintained throughout the life of the contract for each location of contract, including subcontract, performance. For contractors registered in the System for Award Management
(SAM), the DLA Commercial and Government Entity (CAGE) Branch shall only modify data received from SAM in the CAGE master file if the contractor initiates those changes via update of its SAM registration. Contractors undergoing a novation or change-of-name agreement shall notify the contracting officer in accordance with subpart
42.12. The contractor shall communicate any change to the CAGE code to the contracting officer within 30 days after the change, so that a modification can be issued to update the CAGE code on the contract.
(c) Contractors located in the United States or its outlying areas that are not registered in SAM shall submit written change requests to the DLA Commercial and Government Entity (CAGE) Branch. Requests for changes shall be provided at https://cage.dla.mil. Change requests to the CAGE master file are accepted from the entity identified by the code.
(d) Contractors located outside the United States and its outlying areas that are not registered in SAM shall contact the appropriate National Codification Bureau (points of contact available at http://www.nato.int/structur/AC/135/main/links/contacts.htm) or NSPA at https://eportal.nspa.nato.int/AC135Public/scage/CageList.aspx to request CAGE changes.
(e) Additional guidance for maintaining CAGE codes is available at https://cage.dla.mil.
(f) If the contract includes Federal Acquisition Regulation clause 52.204-2, Security Requirements, the contractor shall ensure that subcontractors maintain their CAGE code(s) throughout the life of the contract.
(End of Clause)
2097 West Park Page 12 of 226 W912EQ22B0005 https://www.sam.gov/ https://cage.dla.mil/ http://www.nato.int/structur/AC/135/main/links/contacts.htm https://eportal.nspa.nato.int/AC135Public/scage/CageList.aspx https://cage.dla.mil/
52.214-3 AMENDMENTS TO INVITATIONS FOR BIDS (DEC 2016)
(a) If this solicitation is amended, then all terms and conditions which are not modified remain unchanged.
(b) (1) Bidders shall acknowledge receipt of any amendment to this solicitation--
(i) By signing and returning the amendment;
(ii) By identifying the amendment number and date in space provided for this purpose on the form for submitting a bid;
(iii) By letter;
(iv) By facsimile, if facsimile bids are authorized in the solicitation; or
(v) By email, if email bids are authorized in the solicitation.
(2) The Government must receive the acknowledgement by the time and at the place specified for receipt of bids.
(End of provision)
52.214-5 SUBMISSION OF BIDS (DEC 2016)
(a) Bids and bid modifications shall be submitted in sealed envelopes or packages (unless submitted by electronic means) (1) addressed to the office specified in the solicitation, and (2) showing the time and date specified for receipt, the solicitation number, and the name and address of the bidder.
(b) Bidders using commercial carrier services shall ensure that the bid is addressed and marked on the outermost envelope or wrapper as prescribed in subparagraphs (a)(1) and (2) of this provision when delivered to the office specified in the solicitation.
(c) Facsimile bids, modifications, or withdrawals, will not be considered unless authorized by the solicitation.
(d) Bids submitted by electronic commerce shall be considered only if the electronic commerce method was specifically stipulated or permitted by the solicitation.
52.214-6 EXPLANATION TO PROSPECTIVE BIDDERS (APR 1984)
Any prospective bidder desiring an explanation or interpretation of the solicitation, drawings, specifications, etc., must request it in writing soon enough to allow a reply to reach all prospective bidders before the submission of their bids. Oral explanations or instructions given before the award of a contract will not be binding. Any information given a prospective bidder concerning a solicitation will be furnished promptly to all other prospective bidders as an amendment to the solicitation, if that information is necessary in submitting bids or if the lack of it would be prejudicial to other prospective bidders.
2097 West Park Page 13 of 226 W912EQ22B0005
52.214-7 LATE SUBMISSIONS, MODIFICATIONS, AND WITHDRAWALS OF BIDS (NOV 1999)
(a) Bidders are responsible for submitting bids, and any modifications or withdrawals, so as to reach the
Government office designated in the invitation for bids (IFB) by the time specified in the IFB. If no time is specified in the IFB, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that bids are due.
(b)(1) Any bid, modification, or withdrawal received at the Government office designated in the IFB after the exact time specified for receipt of bids is “late” and will not be considered unless it is received before award is made, the
Contracting Officer determines that accepting the late bid would not unduly delay the acquisition; and--
(i) If it was transmitted through an electronic commerce method authorized by the IFB, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of bids; or
(ii) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of bids and was under the Government's control prior to the time set for receipt of bids.
(2) However, a late modification of an otherwise successful bid that makes its terms more favorable to the
Government, will be considered at any time it is received and may be accepted.
(c) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the bid wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.
(d) If an emergency or unanticipated event interrupts normal Government processes so that bids cannot be received at the Government office designated for receipt of bids by the exact time specified in the IFB and urgent
Government requirements preclude amendment of the IFB, the time specified for receipt of bids will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(e) Bids may be withdrawn by written notice received at any time before the exact time set for receipt of bids. If the
IFB authorizes facsimile bids, bids may be withdrawn via facsimile received at any time before the exact time set for receipt of bids, subject to the conditions specified in the provision at 52.214-31, Facsimile Bids. A bid may be withdrawn in person by a bidder or its authorized representative if, before the exact time set for receipt of bids, the identity of the person requesting withdrawal is established and the person signs a receipt for the bid.
52.214-18 PREPARATION OF BIDS--CONSTRUCTION (APR 1984)
(a) Bids must be (1) submitted on the forms furnished by the Government or on copies of those forms, and (2) manually signed. The person signing a bid must initial each erasure or change appearing on any bid form.
(b) The bid form may require bidders to submit bid prices for one or more items on various bases, including--
(1) Lump sum bidding;
(2) Alternate prices;
(3) Units of construction; or
(4) Any combination of subparagraphs (1) through (3) above.
(c) If the solicitation requires bidding on all items, failure to do so will disqualify the bid. If bidding on all items is
2097 West Park Page 14 of 226 W912EQ22B0005 not required, bidders should insert the words "no bid" in the space provided for any item on which no price is submitted.
(d) Alternate bids will not be considered unless this solicitation authorizes their submission.
52.214-19 CONTRACT AWARD--SEALED BIDDING--CONSTRUCTION (AUG 1996)
(a) The Government will evaluate bids in response to this solicitation without discussions and will award a contract to the responsible bidder whose bid, conforming to the solicitation, will be most advantageous to the Government, considering only price and the price-related factors specified elsewhere in the solicitation.
(b) The Government may reject any or all bids, and waive informalities or minor irregularities in bids received.
(c) The Government may accept any item or combination of items, unless doing so is precluded by a restrictive limitation in the solicitation or the bid.
(d) The Government may reject a bid as nonresponsive if the prices bid are materially unbalanced between line items or subline items. A bid is materially unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated in relation to cost for other work, and if there is a reasonable doubt that the bid will result in the lowest overall cost to the Government even though it may be the low evaluated bid, or if it is so unbalanced as to be tantamount to allowing an advance payment.
(End of provison)
52.214-34 SUBMISSION OF OFFERS IN THE ENGLISH LANGUAGE (APR 1991)
Offers submitted in response to this solicitation shall be in the English language. Offers received in other than
English shall be rejected.
52.214-35 SUBMISSION OF OFFERS IN U.S. CURRENCY (APR 1991)
Offers submitted in response to this solicitation shall be in terms of U.S. dollars. Offers received in other than U.S.
dollars shall be rejected.
52.216-1 TYPE OF CONTRACT (APR 1984)
The Government contemplates award of a firm-fixed price contract resulting from this solicitation.
2097 West Park Page 15 of 226 W912EQ22B0005
52.222-5 CONSTRUCTION WAGE RATE REQUIREMENTS--SECONDARY SITE OF THE WORK (MAY
2014)
(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements,of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting
Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
52.222-12 CONTRACT TERMINATION--DEBARMENT (MAY 2014)
A breach of the contract clauses entitled Construction Wage Rate Requirements, Contract Work Hours and Safety
Standards--Overtime Compensation, Apprentices and Trainees, Payrolls and Basic Records, Compliance with
Copeland Act Requirements, Subcontracts (Labor Standards), Compliance with Construction Wage Rate
Requirements and Related Regulations, or Certification of Eligibility may be grounds for termination of the contract, and for debarment as a Contractor and subcontractor as provided in 29 CFR 5.12.
(End of clause)
52.222-23 NOTICE OF REQUIREMENT FOR AFFIRMATIVE ACTION TO ENSURE EQUAL
EMPLOYMENT OPPORTUNITY FOR CONSTRUCTION (FEB 1999)
(a) The offeror's attention is called to the Equal Opportunity clause and the Affirmative Action Compliance
Requirements for Construction clause of this solicitation.
(b) The goals for minority and female participation, expressed in percentage terms for the Contractor's aggregate workforce in each trade on all construction work in the covered area, are as follows:
Goals for minority participation for each trade
Goals for female participation for each trade
SMSA Counties 31.0
Non-SMSA Counties 27.7
6.9
These goals are applicable to all the Contractor's construction work performed in the covered area. If the Contractor performs construction work in a geographical area located outside of the covered area, the Contractor shall apply the goals established for the geographical area where the work is actually performed. Goals are published periodically in the Federal Register in notice form, and these notices may be obtained from any Office of Federal Contract
Compliance Programs office.
(c) The Contractor's compliance with Executive Order 11246, as amended, and the regulations in 41 CFR 60-4 shall be based on (1) its implementation of the Equal Opportunity clause, (2) specific affirmative action obligations required by the clause entitled "Affirmative Action Compliance Requirements for Construction,'' and (3) its efforts
2097 West Park Page 16 of 226 W912EQ22B0005 to meet the goals. The hours of minority and female employment and training must be substantially uniform throughout the length of the contract, and in each trade. The Contractor shall make a good faith effort to employ minorities and women evenly on each of its projects. The transfer of minority or female employees or trainees from
Contractor to Contractor, or from project to project, for the sole purpose of meeting the Contractor's goals shall be a violation of the contract, Executive Order 11246, as amended, and the regulations in 41 CFR 60-4. Compliance with the goals will be measured against the total work hours performed.
(d) The Contractor shall provide written notification to the Deputy Assistant Secretary for Federal Contract
Compliance, U.S. Department of Labor, within 10 working days following award of any construction subcontract in excess of $10,000 at any tier for construction work under the contract resulting from this solicitation. The notification shall list the --
(1) Name, address, and telephone number of the subcontractor;
(2) Employer's identification number of the subcontractor;
(3) Estimated dollar amount of the subcontract;
(4) Estimated starting and completion dates of the subcontract; and
(5) Geographical area in which the subcontract is to be performed.
(e) As used in this Notice, and in any contract resulting from this solicitation, the "covered area" is Economic Area 113 New Orleans, LA:
SMSA Counties:
0920 Biloxi-Gulfport, MS 19.2
MS Hancock; MS Harrison; MS Stone.
5560 New Orleans, LA 31.0
LA Jefferson; LA Orleans; LA St. Bernard; LA St. Tammany.
Non-SMSA Counties 27.7
LA Assumption; LA Lafourche; LA Plaquemines; LA St. Charles; LA St. James;
LA St. John the Baptist; LA Tangipahoa; LA Terrebonne; LA Washington;
MS Forrest; MS Lamar; MS Marion; MS Pearl River; MS Perry; MS Pike;
MS Walthall.
52.233-2 SERVICE OF PROTEST (SEP 2006)
(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from
Chief, Construction A/E Contracting Division ATTN:
CEMVM-CT, Room 681 U.S. Army Corps of Engineers, Memphis District 167 N. Main Street, B-202 Memphis, TN 38103-1894
(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.
2097 West Park Page 17 of 226 W912EQ22B0005
52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995) – ALTERNATE I (FEB 1995)
(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.
(b) Site visits may be arranged during normal duty hours by contacting:
NAME: Mr. Randy J. Persica
EMAIL: randy.j.persica@usace.army.mil
TELEPHONE: (504)-268-5100
252.204-7004 LEVEL I ANTITERRORISM AWARENESS TRAINING FOR CONTRACTORS (FEB 2019)
(a) Definition. As used in this clause--
Military installation means a base, camp, post, station, yard, center, or other activity under the jurisdiction of the
Secretary of a military department or, in the case of an activity in a foreign country, under the operational control of the Secretary of a military department or the Secretary of Defense (see 10 U.S.C. 2801(c)(4)).
(b) Training. Contractor personnel who require routine physical access to a Federally-controlled facility or military installation shall complete Level I antiterrorism awareness training within 30 days of requiring access and annually thereafter. In accordance with Department of Defense Instruction O-2000.16 Volume 1, DoD Antiterrorism (AT)
Program Implementation: DoD AT Standards, Level I antiterrorism awareness training shall be completed--
(1) Through a DoD-sponsored and certified computer or web-based distance learning instruction for Level I antiterrorism awareness; or
(2) Under the instruction of a Level I antiterrorism awareness instructor.
(c) Additional information. Information and guidance pertaining to DoD antiterrorism awareness training is available at https://jko.jten.mil/ or as otherwise identified in the performance work statement.
(d) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (d), in subcontracts, including subcontracts for commercial items, when subcontractor performance requires routine physical access to a Federally-controlled facility or military installation.
(End of clause)
252.204-7008 COMPLIANCE WITH SAFEGUARDING COVERED DEFENSE INFORMATION CONTROLS
(OCT 2016)
Controlled technical information, covered contractor information system, covered defense information, cyber incident, information system, and technical information are defined in clause 252.204-7012, Safeguarding Covered
Defense Information and Cyber Incident Reporting.
(b) The security requirements required by contract clause 252.204-7012 shall be implemented for all covered defense information on all covered contractor information systems that support the performance of this contract.
2097 West Park Page 18 of 226 W912EQ22B0005 mailto:randy.j.persica@usace.army.mil https://jko.jten.mil/
(c) For covered contractor information systems that are not part of an information technology service or system operated on behalf of the Government (see 252.204-7012(b)(2))--
(1) By submission of this offer, the Offeror represents that it will implement the security requirements specified by
National Institute of Standards and Technology (NIST) Special Publication (SP) 800-171, ``Protecting Controlled
Unclassified Information in Nonfederal Information Systems and Organizations'' (see http://dx.doi.org/10.6028/NIST.SP.800-171) that are in effect at the time the solicitation is issued or as authorized by the contracting officer not later than December 31, 2017.
(2)(i) If the Offeror proposes to vary from any of the security requirements specified by NIST SP 800-171 that are in effect at the time the solicitation is issued or as authorized by the Contracting Officer, the Offeror shall submit to the Contracting Officer, for consideration by the DoD Chief Information Officer (CIO), a written explanation of—
(A) Why a particular security requirement is not applicable; or
(B) How an alternative but equally effective, security measure is used to compensate for the inability to satisfy a particular requirement and achieve equivalent protection.
(ii) An authorized representative of the DoD CIO will adjudicate offeror requests to vary from NIST SP 800-171 requirements in writing prior to contract award. Any accepted variance from NIST SP 800-171 shall be incorporated into the resulting contract.
252.204-7019 NOTICE OF NIST SP 800-171 DOD ASSESSMENT REQUIREMENTS (NOV 2020)
(a) Definitions.
Basic Assessment, Medium Assessment, and High Assessment have the meaning given in the clause 252.204-7020, NIST SP 800-171 DoD Assessments.
Covered contractor information system has the meaning given in the clause 252.204-7012, Safeguarding Covered
Defense Information and Cyber Incident Reporting, of this solicitation.
(b) Requirement. In order to be considered for award, if the Offeror is required to implement NIST SP 800-171, the
Offeror shall have a current assessment (i.e., not more than 3 years old unless a lesser time is specified in the solicitation) (see 252.204-7020) for each covered contractor information system that is relevant to the offer, contract, task order, or delivery order. The Basic, Medium, and High NIST SP 800-171 DoD Assessments are described in the NIST SP 800-171 DoD Assessment Methodology located at https://www.acq.osd.mil/dpap/pdi/cyber/strategically_assessing_contractor_implementation_of_NIST_SP_800-
171.html.
(c) Procedures.
(1) The Offeror shall verify that summary level scores of a current NIST SP 800-171 DoD Assessment (i.e., not more than 3 years old unless a lesser time is specified in the solicitation) are posted in the Supplier Performance
Risk System (SPRS) (https://www.sprs.csd.disa.mil/) for all covered contractor information systems relevant to the offer.
(2) If the Offeror does not have summary level scores of a current NIST SP 800-171 DoD Assessment (i.e., not more than 3 years old unless a lesser time is specified in the solicitation) posted in SPRS, the Offeror may conduct and submit a Basic Assessment to webptsmh@navy.mil for posting to SPRS in the format identified in paragraph (d) of this provision.
2097 West Park Page 19 of 226 W912EQ22B0005 http://dx.doi.org/10.6028/NIST.SP.800-171 https://www.acq.osd.mil/dpap/pdi/cyber/strategically_assessing_contractor_implementation_of_NIST_SP_800-171.html…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .