This document is a solicitation (RFP) for a construction project at Lowell National Historical Park in Lowell, Massachusetts. The project involves replacing an existing 10-ton air handler, with work requiring furnishing labor, materials, tools, and professional services to remove the current unit and install a new one. The contractor will need to confirm the condition of existing piping, connecting ducts, and electrical systems, and tie into the existing heating loop to effectively heat and cool the space.
The estimated project value ranges between $250,000 and $500,000, with a scheduled site visit on June 3, 2025, at 8:00 am ET. The location for the site visit is 246 Market Street, Lowell, MA. Important notes include that funds are not currently available but are expected to become available, and the government reserves the right to cancel the solicitation. Attachments include a Scope of Work, Specifications, Floor Plans, Davis-Bacon Wage Rates, Contract Administration documents, and other supporting materials. The solicitation is issued by the Department of the Interior National Park Service Northeast Region.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P4325R0021_Amd_0002.pdf | ||
| Sol_140P4325R0021_Amd_0001.pdf | ||
| B08_Solicitation_Attachment_4_DOL_Wage_Determination.pdf | ||
| B08_Solicitation_Attachment_1_SOW.pdf | ||
| B08_Solicitation_Attachment_3_Floor_Plan.pdf | ||
| B08_Solicitation_Attachment_6__Limitations_on_Subcontracting_Report_Template.xlsx | XLSX spreadsheet | |
| B08_Solicitation_Attachment_7_JOFOC_Brand_Name_Justification.pdf | ||
| Sol_140P4325R0021.pdf | ||
| B08_Solicitation_Attachment_5_Construction_Contract_Administration_Provision.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Lowell National Historical Park Lowell, MA
SOLICITATION #
Replace Air Handler and Upgrade Controls at LTC
LOWE 328040
PERFORMANCE SPECIFICATIONS
NATIONAL PARK SERVICE (NPS)
DENVER SERVICE CENTER (DSC)
Replace Air Handler and Upgrade Controls at LTC TOC-1
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work
01 26 01 Contract Modification Procedures
01 35 23 Safety Requirements
01 40 00 Quality Requirements
01 50 00 Temporary Facilities and Controls
01 67 00 Product Requirements
01 73 29 Cutting and Patching
01 73 40 Execution
01 74 19 Construction Waste Management and Disposal
01 77 00 Closeout Procedures
01 91 14 Total Building Commissioning
DIVISION 23 – MECHANICAL SYSTEMS
23 05 13 Common Motor Requirements for HVAC Equipment
23 05 17 Sleeves and Sleeve Seals for HVAC Piping
23 05 18 Escutcheons for HVAC Piping
23 05 19 Meters and Gages for HVAC Piping
23 05 23 General-Duty Valves for HVAC Piping
23 05 29 Hangers and Supports for HVAC Piping and Equipment
23 05 48 Vibration Controls for HVAC
23 05 53 Identification for HVAC Piping and Equipment
23 05 93 Testing, Adjusting and Balancing for HVAC
23 07 13 HVAC Duct Insulation
23 07 19 HVAC Piping Insulation
23 09 23 Direct Digital Control (DDC) System for HVAC
23 09 93.11 Sequence of Operations for HVAC DDC
23 23 00 Refrigerant Piping
23 31 13 Metal Ducts
23 33 00 Air Duct Accessories
23 34 16 Centrifugal HVAC Fans
23 37 13.13 Air Diffusers
23 63 13 Air-Cooled Refrigerant Condensers
23 73 13.13 Indoor, Basic Air Handling Units
DIVISION 26 – ELECTRICAL SYSTEMS
26 05 19 Low-Voltage Electrical Power Conductors and Cables
26 05 26 Grounding and Bonding for Electrical Systems
26 05 29 Hangers and Supports for Electrical Systems
26 05 33 Raceways and Boxes for Electrical Systems
26 05 44 Sleeves and Sleeve Seals for Electrical Raceways and Cabling
26 05 53 Identification for Electrical Systems
26 24 17 Existing Panelboards
26 27 26 Wiring Devices
26 28 13 Fuses
26 28 16 Enclosed Switches and Circuit Breakers
Replace Air Handler and Upgrade Controls at LTC TOC-2
26 29 23 Variable - Frequency Motor Controllers …………………………………………………….
Replace Air Handler and Upgrade Controls at LTC 01 11 00 - 1
091015 SUMMARY OF WORK
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work phases.
3. Work under other contracts.
4. Government Furnished Materials.
5. Contractor use of premises.
6. Public use of site.
7. Occupancy requirements for buildings.
8. Work Restrictions.
9. Special Construction Requirements.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Peabody Properties (Market Mills), Lowell, MA.
B. The Work consists of the following:
1. The Work includes replacement of the identified air handling unit system at the Lowell
Telemedia Center (LTC), including minisplit with outside condenser, air handling unit with all necessary connections. Ductwork adjustments are included, along with associated electrical work.
C. Project will be constructed under a single prime design build contract.
1.3 WORK PHASES
A. The Work shall be conducted in one phase.
1.4 WORK UNDER OTHER CONTRACTS
A. General: Cooperate fully with separate contractors (cleaning maid service).
1. If interior restrooms are utilized, that cleaning service contract does not remove responsibility from the contractor to maintain the restroom in good condition.
Replace Air Handler and Upgrade Controls at LTC 01 11 00 - 2
1.5 CONTRACTOR USE OF SITE
A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine constructions operations to designated staging and access areas, mechanical room, control room and adjacent room, and access pathway, elevator, interior halls.
2. Limit site disturbance, including fencing and staging areas, to 40 feet beyond building perimeter; 10 feet beyond surface walkways, patios, surface parking, and utilities less than
12 inches in diameter; 15 feet beyond primary roadway curbs and main utility branch trenches; and 25 feet beyond constructed areas with permeable surfaces (such as pervious paving areas, storm water detention facilities, and fields) that require additional staging areas in order to limit compaction in the constructed area.
B. Access to the construction site is limited.
1. Construction personnel and deliveries will be permitted to enter the courtyard via south entrance.
2. Deliveries from market street entrance is limited. Contractor will coordinate access with
NPS, Peabody Properties, and the city of Lowell.
C. Storage of Materials: Confine storage of materials to designated staging and storage areas, to be identified during a site visit.
D. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with
Contracting Officer and remove agreed-on roots and branches that interfere with construction.
4. Carefully supervise construction operations near trees to prevent damage.
E. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to
Owner, residential tenants, Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
F. All vehicles operating on paved areas will comply with the following requirements:
1. All vehicles are required to use pneumatic tires.
2. The contractor will be held responsible for the protection of all paving and will be held accountable for any damage that occurs as a direct result of the work. Any vehicles that exceed a gross weight of 10,000 pounds must use the protection described below. Using
Replace Air Handler and Upgrade Controls at LTC 01 11 00 - 3 this method does not relieve the contractor of responsibility to protect the paving surfaces or to repair any damage.
a. Two layers of ¾” plywood, with a layer of 2” Styrofoam panels in between, laid in such a manner the surface of the paved area is fully covered.
b. When it becomes apparent that the Styrofoam has become compressed to a height that is less than half its original thickness, or to an extent that the Styrofoam is not protecting the paving, it is to be replaced as described above.
3. Paving protection will be installed under dumpsters placed in the courtyard.
G. Construction Camp: Establishment of a camp within the park will not be permitted.
H. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials.
1.6 PUBLIC USE OF SITE
A. The Brush Gallery will be open to the public during construction.
1. The courtyard between the Visitor Center and Market Mills and the arcade connecting the courtyard and Market Street will remain open and accessible to the public, visitors, and residents/tenants of adjacent buildings.
2. The contractor is to coordinate access with NPS and adjacent tenant representatives concerning access to courtyard via east parking lot steps and ramp and Market Street entrance to breezeway.
B. Contractor shall at all times conduct his operations to ensure the least inconvenience to the public.
Site closures will be permitted, when required, upon specific approval of Contracting Officer in writing for a maximum of three days.
1. No loud radios or other forms of music will be permitted
2. Loud noise will be kept to a minimum. Active recording studios are adjacent the work, and notice to be given before noise is permitted.
1.7 OCCUPANCY REQUIRMENTS FOR BUILIDINGS
A. Existing Buildings
1. Partial Government Occupancy: Government and residential tenants will occupy the premises during entire construction period, with the exception of areas under construction.
Cooperate with Government during construction operations to minimize conflicts and facilitate Government and other tenant usage. Perform the Work so as not to interfere with
Government’s or other tenant’s operations. Maintain existing exits and pedestrian access through the site for the duration of the contract.
a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.
b. All ADA accessible ramps, all emergency exists and fire lanes must remain open at all times.
c. The Government will have limited escorted access to storage areas and lockers for the duration of the contract.
Replace Air Handler and Upgrade Controls at LTC 01 11 00 - 4
d. The Government restroom service contractor will have limited access to the construction site to maintain first and second floor restrooms for the duration of the contract.
B. Existing Fire Detection System: The existing fire detection system, including all smoke detectors, heat detectors and pull stations shall be kept operational throughout the construction period.
1. Smoke detectors within the areas of construction may be temporarily disabled during periods of active construction work, but they shall be made operational at the end of each day or active work period.
2. Fire detection devices shall not be removed at any time unless specifically approved in advance by the Contracting Officer.
C. Existing Security System: All existing interior motion sensing security devices are to remain operational throughout the construction period.
1. Motion sensors shall not be removed or temporarily disabled except as specifically approved in advance by the Contracting Officer. If removed, all existing device wiring shall be marked and fitted with wire nuts to prevent cross connections.
1.8 CONDUCT OF OPERATIONS
A. At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by the Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed without prior consent from the Contracting Officer. Submit requests 48 hours in advance of the work to the
Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.9 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be performed during normal business working hours of 7:30 a.m. to 4:30 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: Weekend hours must be approved by the Contracting Officer a minimum of 1 week in advance.
2. Early Morning Hours: Limit noise in the courtyard before 8:30 am.
3. Hours for Core Drilling and other noise-producing activities, and work in duct shafts: will be performed after 9:00 am.
4. Notify Contracting Officer not less than 24 hours in advance prior to core drilling and other noise-producing activities.
5. Prior to start of work on Market Street building occupied floors above Visitor Center, coordinate work with building owners and occupants
B. Existing Utilities
Replace Air Handler and Upgrade Controls at LTC 01 11 00 - 5
1. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
2. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.
3. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than seven days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Hours for Utility Shutdowns: Only between 9 am and 5 pm weekdays.
D. Nonsmoking Building: Smoking is not permitted within the building or within 25 feet of entrances, operable windows, or outdoor air intakes.
E. Interruptions to Existing Fire Protection and Fire Alarm Systems: Maintain an operational fire alarm protection system and fire alarm system in the Market Mills Visitor Center at all times during construction.
1. Notify the Contracting Officer not less than 72 hours in advance of proposed interruption.
2. The existing fire protection system, including all smoke detectors, heat detectors, and pull stations will be kept operational during all phases of construction. All smoke detectors in the construction area are to be covered with plastic bags during work hours and removed after each day's work. At no time will any smoke detector be covered during evening hours.
Fire detection devices are not to be removed unless the Contracting Officer is notified in advance and the device can be disabled.
1.10 SPECIAL CONSTRUCTION REQUIREMENTS
A. No on-site construction work will be allowed during courtyard activities. Coordinate activity schedules with NPS.
B. Park Operations & Management:
1. The Galleries and Studios have active artists using the spaces, and care shall be given to protect artwork from damage. A pre-construction meeting shall involve the COR and contractor to discuss issues related to working in artist and gallery areas.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
Replace Air Handler and Upgrade Controls at LTC 01 26 01 - 1
031414 CONTRACT MODIFICATION PROCEDURES
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. The work of this section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Those costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with the preparation of modifications will not be allowed. The costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager, Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
Replace Air Handler and Upgrade Controls at LTC 01 26 01 - 2
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: These are costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate. The following items, if applicable, are considered allowable costs for calculating
General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on the project site. Modification costs for salaried workers are only allowed within the structure of a 40 hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: This is the hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens, this includes insurance and taxes that the business must pay on behalf of the worker to government entities and educational forums, such as:
1) Social Security
2) Medicare
3) Workers Compensation– Policy and company calculation to be made available.
4) FUTA– Cap Rate and percentage to be proportionally allocated over one year.
5) SUTA– Cap Rate and percentage to be proportionally allocated over one year.
Replace Air Handler and Upgrade Controls at LTC 01 26 01 - 3
6) Union agreement costs – Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects the contractor from claims resulting from bodily injury or property damage to a third party. Include this as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees that the contractor will pay the labor and material costs they have incurred. Banks and Insurance companies charge a premium for each individual project based on a sliding scale which relates to the size of the project. Include this as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: This covers the contractor’s loss due to fire, high winds, or other natural forces. This is not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Your proposal must be received in the format and within the time frame specified in the Request for Proposal letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. The proposal must be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed that that they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may utilize the government provided Contractor Estimate http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank http://www.nps.gov/dscw/publicforms.htm#ct
Replace Air Handler and Upgrade Controls at LTC 01 26 01 - 4
Form, or their own form, provided that it contains the same information and level of detail as the Gov’t provided form.
3. Requests for extensions of contract time as a result of this change must be justified with a Time Impact Analysis (TIA). Refer to Division 01 Specification, “Construction
Schedule”, for time impact analysis requirements. TIA and associated costs must be received with the proposal by the date shown within the Request for Proposal letter.
Contractor’s failure to submit within the specified time frame will be construed as the
Contractor waiving the right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer upon request.
5. Contractor must review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to the NPS.
All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate the cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing the hours required for each craft that will be directly engaged in modification work.
Any work proposed that will require overtime work or premium pay shall be itemized separately. All rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, FICA, FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. The labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. The estimated cost for materials shall include quotes from multiple sources. Material prices must include all applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by the NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for the work being performed.
2. Do not include costs for “miscellaneous tools and equipment”, in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 must be broken out separately.
3. Regardless of ownership, the rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. U.S. Army Corps of Engineers , Ownership and Operating Expense Schedule (use latest edition and applicable region) http://www.nps.gov/dscw/publicforms.htm#ct
Replace Air Handler and Upgrade Controls at LTC 01 26 01 - 5
b. Construction Blue Book
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. The estimated equipment rates shall include the operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires & tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per FAR 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate the full rate for equipment only for the duration that the equipment will be utilized to accomplish the work of the modification.
6. Standby unit rates used are to be in accordance with paragraph 1.3, D, 2, above. If the
US Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then ½ of the equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, the established standby rate shall apply from the first day of the delay.
8. Equipment that is not used and on the jobsite for up to five consecutive days may be classified at standby rates, provided that the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work. Equipment that is still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
1. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit.
Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead………………8%
Profit…………………..10%
2. Total aggregate limit of markup (OH&P) for contractor and subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
3. If contractors form a partnership, than the partnership may only receive home office overhead and profit in the same amount as an individual contractor (refer to par
1.3,E,1 above). It is the responsibility of the partners to decide on the division of revenue.
4. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, the overhead and profit mark-ups are required on the net increases and deducted on net decreases.
Replace Air Handler and Upgrade Controls at LTC 01 26 01 - 6
5. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
Replace Air Handler and Upgrade Controls at LTC 01 35 23 - 1
SAFETY REQUIREMENTS
SECTION 01 35 23 - SAFETY REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. This section includes establishing an effective accident prevention program and providing a safe working environment for all personnel and visitors.
1.2 SUBMITTALS
A. Accident Prevention Plan (APP): After contract award and before the Pre-Construction conference, submit for review, an Accident Prevention Plan. The Contracting Officer will review the proposed Plan. If the plan requires any revisions or corrections, the Contractor shall resubmit the Plan within 10 days. No progress payments will be made until the Plan is accepted.
1.3 QUALITY ASSURANCE
A. Comply with contract clauses entitled "Accident Prevention" and "Permits and
Responsibilities". In case of conflicts between Federal, State, and local safety and health requirements, the most stringent shall apply. Equipment or tools not meeting OSHA requirements will not be allowed on the project sites. Failure to comply with the requirements of this section and related sections may result in suspension of work.
B. Qualifications of Employees:
1. All employees must be physically and able to perform their assigned duties in a safe manner.
2. Do not allow employees to perform work whose ability or alertness is impaired because of prescription or illegal drug use, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.
3. Operators of vehicles, hoisting equipment, and hazardous plant equipment shall be able to understand signs, signals, and operating instructions, and be fully capable of operating such equipment. Provide operating instructions for all equipment. Newly hired operators shall be individually tested by an experienced operator or supervisor to determine if they are capable of safely operating equipment. Retain copies of all operators’ licenses and/or certifications onsite.
1.4 ACCIDENT REPORTING
A. Reportable Accidents (per OSHA 29CFR 1904): A project reportable accident is defined as death, occupational disease, traumatic injury to employees or the public, fires, and property damage by accident in excess of $100. Notify Contracting Officer immediately in the event of a reportable accident. Within 7 days of a reportable accident, fill out and forward to Contracting
Replace Air Handler and Upgrade Controls at LTC 01 35 23 - 2
Officer an Accident/Property Damage Report (Form CM-22). Form may be obtained from the
Contracting Officer.
PART 2 - PRODUCTS
2.1 ACCIDENT PREVENTION PLAN (APP)
A. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:
1. Name of responsible supervisor to carry out the program.
2. Weekly and monthly safety meetings shall be documented with topic and attendees.
3. First aid and rescue procedures.
4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National
Park Service personnel, and Contractor's employees. Identify the work included under each phase, with an Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc.
5. Training, both initial and continuing.
6. Planning for possible emergency situations, such as cave-ins, earthquake, explosions,, fires, floods, power outages, slides, and wind storms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.
7. Blasting Plan Requirements: See Division 01 Specification Section, “Explosives”.
2.2 FIRST AID FACILITIES
A. Provide adequate facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.
2.3 PERSONNEL PROTECTIVE EQUIPMENT
A. Meet requirements of applicable ANSI standards. Selection shall conform to OSHA 29CFR
1926.95 Subpart E.
PART 3 - EXECUTION
3.1 EMERGENCY INSTRUCTIONS
A. Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.
3.2 FIRE AND LIFE SAFETY
A. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations).
Replace Air Handler and Upgrade Controls at LTC 01 35 23 - 3
B. Store hazardous materials in accordance with manufacturer’s and OSHA 29CFR1926 Subpart D requirements. Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.
1. Immediately report all spills of hazardous materials to the park.
2. Maintain a spill emergency response kit.
3. Train employees how to respond to a spill and use the emergency response kit.
3.3 PROTECTIVE EQUIPMENT
A. Inspect personal protective equipment daily and maintain in a serviceable condition. Clean, sanitize, and repair personal items, as appropriate, before issuing them to another individual.
B. Inspect, maintain, and document other protective equipment and devices before use and on a periodic basis to ensure safe operation. Retain inspection documentation onsite.
3.4 SAFETY MEETINGS
A. As a minimum, conduct one weekly 15-minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the Contracting Officer within one day after the meeting.
B. Conduct monthly safety meetings for all levels of supervision. Meetings shall be attended by all contractors and subcontractors performing work on the site. Notify the Contracting Officer of meeting dates and times. These meetings shall be used to review the effectiveness of the
Contractor's safety effort, to resolve current health and safety problems, to provide a forum for planning safe construction activities, and for updating the Accident Prevention Plan. The
Contracting Officers Representative will attend the meeting and enter the results of the meetings into the daily log.
3.5 HARD HATS AND PROTECTIVE EQUIPMENT AREAS
A. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.
B. It is the Contractor's responsibility to require all those working on or visiting the site to wear hard hats and other necessary personal protective equipment in good repair at all times. As a minimum, maintain six hard hats and all other APP required equipment.
3.6 TRAINING
A. First Aid: Provide adequate training to an adequate number of personnel to ensure prompt and efficient first aid.
B. Hazardous Material: Train and instruct each employee exposed to hazardous material in safe and approved methods of handling and storage. Hazardous materials are defined as explosive, Replace Air Handler and Upgrade Controls at LTC 01 35 23 - 4 flammable, poisonous, corrosive, oxidizing, irritating, or otherwise harmful substances that could cause death or injury.
END OF SECTION 01 35 23
Replace Air Handler and Upgrade Controls at LTC 01 40 00 - 1
QUALITY REQUIREMENTS
SECTION 01 40 00 - QUALITY REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for quality assurance and quality control.
B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the
Contract Document requirements. The quality of all work shall be the responsibility of the
Contractor.
1. Specified tests, inspections, and related actions do not limit Contractor's other quality assurance and control procedures that facilitate compliance with the Contract Document requirements.
C. See Divisions 02 through 49 Sections for specific test and inspection requirements.
1.2 DEFINITIONS
A. Quality Assurance Services: Activities, actions, and procedures performed before and during execution of the work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.
B. Quality Control Services: Tests, inspections, procedures, and related actions during and after execution of the work to evaluate that actual products incorporated into the work and completed construction comply with requirements.
C. Mockups: Full-size physical assemblies that are constructed on-site. Mockups are constructed to verify selections made under Sample submittals; to demonstrate aesthetic effects and, where indicated, qualities of materials and execution; to review coordination, testing, or operation; to show interface between dissimilar materials; and to demonstrate compliance with specified installation tolerances. Mockups are not Samples. Unless otherwise indicated, approved mockups establish the standard by which the Work will be judged.
D. Preconstruction Testing: Tests and inspections that are performed specifically for the project before products and materials are incorporated into the work to verify performance or compliance with specified criteria.
E. Product Testing: Tests and inspections that are performed by a Nationally Recognized Testing
Laboratory (NRTL), a National Voluntary Laboratory Accreditation Program (NVLAP), or a testing agency qualified to conduct product testing, to establish product performance and compliance with industry standards.
F. Source Quality Control Testing: Tests and inspections that are performed at the source, i.e., plant, mill, factory, or shop.
G. Field Quality Control Testing: Tests and inspections that are performed on-site for installation of the work and for completed work.
Replace Air Handler and Upgrade Controls at LTC 01 40 00 - 2
H. Testing Agency or Laboratory: An entity engaged to perform specific tests, inspections, or both. Testing laboratory shall mean the same as testing agency.
I. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application, and similar operations.
1. Using a term such as “carpentry” does not imply that certain construction activities must be performed by accredited or unionized individuals of a corresponding generic name, such as “carpenter.” It also does not imply that requirements specified apply exclusively to trades people of the corresponding generic name.
1.3 CONFLICTING REQUIREMENTS
A. Reference Standards: If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different, but apparently equal, to Contracting Officer for a decision before proceeding.
B. Minimum Quality Levels: The quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Contracting Officer for a decision before proceeding.
1.4 SUBMITTALS
A. Quality Control Plan:
1. After contract award and before the Pre-Construction conference, submit for approval a written Contractor Quality Control (CQC) plan.
2. If the plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.
3. The Government reserves the right to require changes in the plan during the contract period as necessary to obtain the quality specified.
4. No change in the approved plan may be made without written concurrence by the
Contracting Officer.
B. Qualification Data: For testing agencies specified in “Quality Assurance” Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.
C. Contractor's Quality Control Daily Reports: Submit showing all inspections and tests on the first workday following the date covered by the report. Quality Control Supervisor shall utilize the DSC forms available by accessing the DSC Workflows website, http://www.nps.gov/dscw/publicforms.htm.
1. Review CMR Dailies and reconcile any differences prior to posting CQC Dailies on the
SharePoint Project Website.
D. Test Reports
1. Test reports shall be completed by the person performing the test.
http://www.nps.gov/dscw/publicforms.htm
Replace Air Handler and Upgrade Controls at LTC 01 40 00 - 3
2. Submit Daily Test Information Sheets with Quality Control Daily Reports.
3. Submit failing test results and proposed remedial actions within four hours of noted deficiency.
4. Submit three copies of complete test results no later than one calendar day after the test was performed.
E. Accessibility Inspection Report:
1. Fill out the applicable sections of the Accessibility Inspection Report and attach to the
Quality Control Daily Report.
2. Utilize the attached Accessibility Inspection form to document compliance with the
Architectural Barriers Act Accessibility Standards (ABAAS).
3. Inspect at various stages of construction as needed to insure the finished product meets the standards.
4. Submit report not later than one calendar day after the inspection was performed.
F. Off-Site Inspection Reports: Submit prior to shipment.
G. If the CQC plan and Quality Control Daily Reports are not submitted as specified, the
Contracting Officer may retain all payments until such time a plan is accepted and implemented, or may retain payments for work completed on days there are no Quality Control
Daily Reports.
H. Permits, Licenses, and Certificates: For NPS records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the work.
1.5 QUALITY ASSURANCE
A. General: Qualifications paragraphs in this Article establish the minimum qualification levels required; individual Specification Sections specify additional requirements.
B. Contractors Quality Control Staff:
1. The Contractor's Quality Control Supervisor may also perform other duties.
2. The Contractor's designated Quality Control Supervisor shall be on the project site whenever contract work is in progress.
3. The Contractor's job supervisory staff may be used to assist the Quality Control
Supervisor supplemented, as necessary, by additional certified testing technicians.
C. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.
D. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.
E. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.
Replace Air Handler and Upgrade Controls at LTC 01 40 00 - 4
F. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in the commonwealth of Massachusetts and who is experienced in providing engineering services of the kind indicated (including Structural Tests and Special Inspections
(STSI). Engineering services are defined as those performed for installations of the system, assembly, or products that are similar to those indicated for this Project in material, design, and extent.
G. Specialists: Certain sections of the Specifications require that specific construction activities shall be performed by entities who are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated.
1. Requirement for specialists shall not supersede building codes and regulations governing the work.
H. Testing Agency Qualifications: An NRTL, an NVLAP, or an independent agency with the experience and capability to conduct testing and inspecting indicated, as documented according to ASTM E 329; and with additional qualifications specified in individual Sections; and where required by Contract, is acceptable to the Contracting Officer.
1. NRTL: A nationally recognized testing laboratory according to 29 CFR 1910.7.
2. NVLAP: A testing agency accredited according to NIST's National Voluntary
Laboratory Accreditation Program.
3. All measuring devices, laboratory equipment, and instruments shall be calibrated at established intervals against certified standards in accordance with NIST requirements.
Upon request, measuring and testing devices shall be made available for use by the
Government for verification tests.
I. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this
Project.
J. Mockups: Before installing portions of the work requiring mockups, build mockups for each form of construction and finish required to comply with the following requirements, using materials indicated for the completed work:
1. Build mockups in location and of size indicated or, if not indicated, as directed by
Contracting Officer.
2. Notify Contracting Officer seven days in advance of dates and times when mockups will be constructed.
3. Demonstrate the proposed range of aesthetic effects and workmanship.
4. Obtain Contracting Officer’s approval of mockups before starting work, fabrication, or construction.
5. Maintain mockups during construction in an undisturbed condition as a standard for judging the completed work.
6. Demolish and remove mockups when directed, unless otherwise indicated.
K. Laboratory Mockups: Comply with requirements of preconstruction testing and those specified in individual Sections in Divisions 02 through 49.
1.6 QUALITY CONTROL
A. The Contractor is responsible for all testing and inspections, including Structural Tests and
Special Inspections (STSI), as identified in the attached STSI. Inspect and test work as needed
Replace Air Handler and Upgrade Controls at LTC 01 40 00 - 5 to ensure that the quality of materials, workmanship, construction, finish, and functional performance are in compliance with applicable specifications, drawings, and those required by the Building Code.
1. Engage a qualified testing agency to perform these quality-control services.
2. Submit the appropriate report, for each quality-control service.
3. Testing and inspecting requested by Contractor and not required by the Contract
Documents are Contractor's responsibility.
4. The Contracting Officer may designate test locations.
B. Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to inspect field-assembled components and equipment installation, including service connections. Report results in writing.
C. Re-testing/Re-inspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality-control services, including retesting and re-inspecting, for construction that replaced work that failed to comply with the Contract Documents.
D. Testing Agency Responsibilities: Cooperate with NPS and Contractor in performance of duties.
Provide qualified personnel to perform required tests and inspections.
1. Notify Contracting Officer and Contractor promptly of irregularities or deficiencies observed in the work during performance of its services.
2. Determine the location from which test samples will be taken and in which in-situ tests are conducted.
3. Conduct and interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from requirements.
4. Submit 3 copies of the certified written report of each test, inspection, and similar quality-control service through Contractor.
5. Do not release, revoke, alter, or increase the Contract Document requirements or approve or accept any portion of the work.
E. Associated Services: Cooperate with agencies performing required tests, inspections, and similar quality-control services, and provide reasonable auxiliary services as requested. Notify agency sufficiently in advance of operations to permit assignment of personnel. Provide the following:
1. Access to the work.
2. Incidental labor and facilities necessary to facilitate tests and inspections.
3. Adequate quantities of representative samples of materials that require testing and inspecting. Assist agency in obtaining samples.
4. Facilities for storage and field curing of test samples.
5. Delivery of samples to testing agencies.
6. Preliminary design mix proposed for use for material mixes that require control by testing agency.
7. Security and protection for samples and for testing and inspecting equipment at Project site.
F. Coordination: Coordinate sequence of activities to accommodate required quality assurance and control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspecting.
1. Schedule times for tests, inspections, obtaining samples, and similar activities.
Replace Air Handler and Upgrade Controls at LTC 01 40 00 - 6
PART 2 - PRODUCTS
2.1 QUALITY CONTROL PLAN
A. The Quality Control Plan shall include:
1. A list of personnel responsible for quality control and assigned duties. Include each person's qualifications.
2. A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.
3. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.
4. Methods of performing, documenting, and enforcing quality control of all work.
5. Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.
PART 3 - EXECUTION
3.1 OFF-SITE CONTROL
A. Items that are fabricated or assembled off-site shall be inspected for quality control at the place of fabrication.
3.2 ON-SITE CONTROL
A. Notification:
1. Notify the Contracting Officer at least 48 hours in advance of the preparatory phase meeting.
2. Notify the Contracting Officer at least 24 hours in advance of the initial and follow-up phases.
B. Preparatory Phase: Perform before beginning each feature of work.
1. Review control submittal requirements with personnel directly responsible for quality assurance and…