B08_Solicitation_attach_3_Specifications_Submittal_List.pdf
PDF 70 KB Posted
- Attached to
- PARKING GARAGE DRAINAGE / ABA RENOVATION Federal contract opportunity
- Solicitation number
- 140P6323B0006
About this file
This submittal list and review estimate template specifies submittals required for a construction services task order to renovate parking garages at Mount Rushmore National Monument. Required submittals include an accident prevention plan, proofs of insurance and bonds, construction schedules, demolition plans, shop drawings, material data, test results, calculations, product samples, and manufacturer instructions for items like concrete mixes, anchors, and waterproofing membranes. The template assigns estimated review hours for each submittal to project managers, engineers, and architects.
The related federal contract opportunity is an invitation for bid to provide construction services for drainage and accessibility renovations to the parking garages. The solicitation is issued by the National Park Service Midwest Region of the Department of the Interior.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140P6323B0006_Amd_0003.pdf | ||
| Questions_and_Answers_6_20_23_0002.pdf | ||
| Sol_140P6323B0006_Amd_0002.pdf | ||
| Sol_140P6323B0006_Amd_0001.pdf | ||
| B08_Solicitation_attach_2__Drawings.pdf | ||
| B08_Solicitation_attach_4_Limitations_on_Subcontracting_Report.xlsx | XLSX spreadsheet | |
| B08_Solicitation_attach_1__Specifications.pdf | ||
| B08_Solicitation_attach_5__Wage_Determintation_SD20230032.pdf | ||
| Sol_140P6323B0006.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittal List with Review Estimate Template National Park Service (NPS) - Denver Service Center (DSC) | 1-27-21
SUBMITTAL LIST ACTION SUBMITTAL
REVIEW ESTIMATE
Park Acronym/Project Management Information System (PMIS) Number: MORU/314109 (Complete this portion for Architect / Engineer (A/E)
Project Title:
construction service task order negotiation.)
SUBMITTAL REQUIREMENTS ARCHITECT / ENGINEER REVIEW TIME
(Indicate with X) (Indicate in whole or partial hours.)
INFORMATIONAL ACTION
S P
E C
IF
IC
A T
IO
N
S E
C T
IO
N
P A
R A
G R
A P
H N
U M
B E
R
DESCRIPTION
C E
R T
IF
IC
A T
IO
N
S O
R
L A
B O
R A
T O
R Y
T E
S T
S
R E
P O
R T
S O
R C
A L C
U L A
T
IO
N S
O R
P L A
N
M A
N U
F A
C T
U R
E R
D A
T A
A N
D I N
S T
R U
C T
IO
N
S
O T
H E
R
S A
M P
L E
S
S H
O P
D R
A W
IN
G
S
M A
N U
F A
C T
U R
E R
D A
T A
A N
D I N
S T
R U
C T
IO
N
S
O T
H E
R
A R
C H
IT
E
C T
C
IV
IL
E
N G
IN
E
E R
S T
R U
C T
U R
A L E
N G
IN
E
E R
M E
C H
A N
IC
A
L E
N G
IN
E
E R
E L E
C T
R
IC
A L E
N G
IN
E
E R
P R
O J E
C T
M A
N A
G E
C
O R
D
IN
A T
IO
N
L A
N D
S C
A P
E A
R C
H
IT
E C
T
011000 7.2 Accident Prevention Plan (APP) X
011000 9.1.C Preconstruction Conference Submittals
Proof of Insurance and Bonds X
Letter Designating Project Superintendent X
Construction Schedule X
Schedule of Values X
Accident Prevention (Safety) Plan X
List of Subcontractors X
Subcontractor Certification of Labor Compliance X
Quality Control Plan X
Waste Management Plan X
024100 1.4 Demolition and Removal Plan including schedule with start date X X
321313 1.3 Shop Drawings, Test Results, Jointing Plan, Material Information X X X X
321623 1.3 Shop Drawings, Test Results, Jointing Plan, Material Information X X X X
Sheet S0.1 Chemical Anchors X X
Anchor Bolts X X
Concrete Mix Design and Test Results X X
Shop Drawings X
GPR Survey Results X X
Stamped Shoring Plans X X
Renovate Existing Lincoln & Washington Garages Water Intrusion & Accessibility
Deficiencies
Submittal List with Review Estimate Template | National Park Service (NPS) - Denver Service Center (DSC) page 1 of 2
SUBMITTAL LIST ACTION SUBMITTAL
REVIEW ESTIMATE
Park Acronym/Project Management Information System (PMIS) Number: MORU/314109 (Complete this portion for Architect / Engineer (A/E)
Project Title:
construction service task order negotiation.)
SUBMITTAL REQUIREMENTS ARCHITECT / ENGINEER REVIEW TIME
(Indicate with X) (Indicate in whole or partial hours.)
INFORMATIONAL ACTION
S P
E C
IF
IC
A T
IO
N
S E
C T
IO
N
P A
R A
G R
A P
H N
U M
B E
R
DESCRIPTION
C E
R T
IF
IC
A T
IO
N
S
L A
B O
R A
T O
R Y
T E
S T
S
R E
P O
R T
S O
R C
A L C
U L A
T
IO
N S
O R
P L A
N
M A
N U
F A
C T
U R
E R
D A
T A
A N
D I N
S T
R U
C T
IO
N
S
O T
H E
R
S A
M P
L E
S
S H
O P
D R
A W
IN
G
S
M A
N U
F A
C T
U R
E R
D A
T A
A N
D I N
S T
R U
C T
IO
N
S
O T
H E
R
A R
C H
IT
E
C T
C
IV
IL
E
N G
IN
E
E R
S T
R U
C T
U R
A L E
N G
IN
E
E R
M E
C H
A N
IC
A
L E
N G
IN
E
E R
E L E
C T
R
IC
A L E
N G
IN
E
E R
P R
O J E
C T
M A
N A
G E
C
O R
D
IN
A T
IO
N
L A
N D
S C
A P
E A
R C
H
IT
E C
T
Renovate Existing Lincoln & Washington Garages Water Intrusion & Accessibility
Deficiencies
Total: 0 0 0 0 0 0 0