This document is a Statement of Work (SOW) for a federal contract opportunity to repair electrical RV site hook-ups at the South Rim Campground in Black Canyon of the Gunnison National Park.

The project scope includes replacing three 200-amp panelboards and 23 individual RV electrical pedestals, as well as adding lighting and infrared heaters to the two Loop B restrooms. Work must be completed within 120 calendar days after the Notice to Proceed is issued. The contract will have two base bid items: 1) Replacing the panelboards and RV pedestals, and 2) Providing lighting and heaters for the Loop B restrooms. Submittals, quality control, and project closeout requirements are also detailed. The related federal contract opportunity is Solicitation #140P6324Q0033 issued by the National Park Service Midwest Region.

View the file

Other files for this federal contract opportunity

Other files attached to BLCA-REPAIR ELECTRICAL RV HOOK-UPS, newest first.
File Type Posted
B09_Solicitation_amendment_1_attach_Q_and_A_0001.docx DOCX document
Sol_140P6324Q0033_Amd_0001.pdf PDF
B08_Solicitation_Attach_1_SPEC_.pdf PDF
B08_Solicitation_Attach_4_Spec_Photos__-_Loop_B_existing_electrical_.pdf PDF
B08_Solicitation_attach_6_Experience_Questionaire.xls XLS spreadsheet
B08_Solicitation_Attach_3_Drawings_.pdf PDF
B08_Solicitation_Attach_5__Submittal_List_-.pdf PDF
Sol_140P6324Q0033.pdf PDF
B08_Solicitation_Attach_7_Wage_Determination.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BLACK CANYON OF THE GUNNISON

NATIONAL PARK

MONTROSE, CO

REPAIR ELECTRICAL RV SITE HOOK-UPS

AT SOUTH RIM CAMPGROUND

BLCA 249319

PROJECT SCOPE

NATIONAL PARK SERVICE

INTERMOUNTAIN REGION

Table of Contents

1.0 PROJECT INTRODUCTION

1.1 Scope

1.2 Location

1.3 Background and Description

1.4 Schedule

1.5 Information

1.6 Data and Materials to be provided by the NPS

2.0 PROJECT REQUIREMENTS

2.1 General Requirements

2.1.1 Scope of Work and Project Summary/Requirements

2.1.2 Definition of Contract Line Items

2.1.3 Progress Payments

2.1.4 Project Meetings

2.1.5 Project Schedule

2.2 Design Requirements

2.2.1 Deliverables

2.3 Construction Requirements

2.3.1 Environmental and Sustainability Requirements

2.3.2 Schedule of Values

2.3.3 Construction Support

2.3.4 Submittals During Construction

2.3.5 Quality Control

2.3.6 Working Hour Restrictions

2.3.7 Temporary Services

2.3.8 Access

2.3.9 Existing Utilities

2.3.10 Accident Prevention

2.3.10 Temporary Controls

2.3.11 Project Close-out

2.3.12 Substantial Completion and Final Inspection

2.4 Forms

3.0 PERFORMANCE REQUIREMENTS

3.1 Facility Performance

3.2 Elements and Products

4.0 TECHNICAL REQUIREMENTS

5.0 ATTACHMENTS

• PROJECT INTRODUCTION

Park Alpha and PMIS Number: BLCA 249319

Project Title: Repair Electrical RV Site Hook-ups at South Rim Campground

See Section 2 for a detailed description of the Scope of Work and Project Summary

Requirements.

1.1 Scope

In accordance with the terms and conditions of the Contract, the Contractor shall perform the work for the National Park Service (NPS) as described below.

1.2 Location

This project is in Black Canyon of the Gunnison National Park. The individual areas/buildings at the site involved in this project are the:

1. South Rim Campground Loop B

2. South Rim Campground Restrooms

1.3 Background and Description

This project upgrades the electrical distribution feeding the 23 camp sites in the South Rim

Campground as well as adds lighting and an infrared heater in the two campground restrooms.

Currently the campsites each have a 30-amp electrical capacity even though the electrical pedestals at each of the camp sites are rated at 50 amps.

1.4 Schedule

The work in this RFQ shall be completed in accordance with the following schedule:

Construction:

Construction shall not begin until the Contracting Officer has issued the Notice to

Proceed.

Construction shall be completed no later than 120 calendar days after the Notice to

Proceed is issued.

1.5 Information

NPS Points of Contact:

Contracting:

Contracting Specialist/ Contracting Officer (CO):

Joseph Kirk TBD Phone:605.574.0510 Email:Joseph_Kirk@nps.gov

1.6 Data and Materials to be provided by the NPS

The following data and materials will be provided to the Contractor and are included in Section

5 of this RFQ:

• Construction Drawings and Specifications

• Campground photos of existing electrical equipment

• Campground electrical load data mailto:casey_hagaman@nps.gov mailto:david_covington@nps.gov

• PROJECT REQUIREMENTS

2.1 General Requirements

2.1.1 Scope of Work and Project Summary/Requirements

The project consists of replacing three (3) existing 200 Amp panelboards and 23 individual

Recreational Vehicle hook up pedestals that currently include one 50-Amp, one 30-Amp and one

20-Amp breakers and associated plugs. Additionally, the two restrooms in Loop B campground will be provided with interior lighting and an electric infrared heater.

The contractor shall install the new systems in accordance with the requirements outlined in this Project Scope document, construction drawings and specifications.

The buildings included for this project are:

1. Loop B restrooms 1 and 2

For the campsites, the project will include, but not be limited to, the following for each campsite in the scope:

• Remove the existing electric RV distribution pedestals at the 23 campsites. Remove any abandoned mounting concrete/piers related to the former RV pedestals.

Concrete pedestal mounting bases may be reused if in good condition and suitable.

Dispose of unused pedestal bases in accordance with state, local, and NPS requirements.

• Provide and install 23 new electrical pedestals in accordance with manufacturer’s instructions and NFPA 70 National Electric Code 2023 edition. Include any required installation hardware and material and a concrete base. Pedestal shall be

UL listed. Concrete pedestal bases may be reused if in good condition and suitable for the application.

• Remove three (3) existing 200 Amp panelboards and associated wiring/conduit that feeds the existing 23 individual Recreational Vehicle hook up pedestals.

• Provide and install 3 new 200-amp panelboards and associated wiring, conduit, and circuit breakers. Provide manufacturer’s cutsheet for review and approval. Provide as-built drawings of the installation. New panelboards are to be installed in the same locations.

• Provide new trenching and underground wire and connections from the 3 new panelboards to the new RV pedestals. Provide as-built drawings of the installation showing the underground feeder routing on the site plan.

• Test and verify the system’s operations and repair as needed.

For the restrooms, the project will include the following for each building in the scope:

• Provide and install new lighting and infrared heaters in the two Loop B restrooms including associated wiring, trenching, conduit, and circuit breakers.

• Provide cutsheets for review and approval by NPS official for the heater and lighting. Provide as-built drawings of building work provided.

2.1.2 Definition of Contract Line Items

The intent of this section is to explain, in general, what is included in each contract line item, limits or cut-off points where one item ends, and another begins. If no item exists for a portion of the work, include the costs in a related line item.

CONTRACT BASE BID ITEM NO. 1 – REPLACE 3EXISTING 200 AMP

PANELBOARDS/CIRCUIT BREAKERS AND 23 RV ELECTRICAL PEDESTALS: This

Contract Line Item consists of the demolition and replacement of the 3 each 200-amp panelboards at the Loop B restroom. It also includes replacing the existing pedestals at the campsites on Loop B and trenching and installation of new underground wiring to the 23 electrical pedestals at the campsites from the panelboards. This item is for the components associated with a portion of the Loop B campground electrical distribution system.

CONTRACT BASE BID ITEM 2 – PROVIDE LIGHTING AND HEATERS FOR THE

LOOP B RESTROOMS – This Contract Line item consists of trenching, underground wiring, conduit, circuit breakers, material, and labor to install heat and lighting to the two

Loop B restrooms.

2.1.3 Progress Payments

Construction Phase - Progress payments during construction will be based on the percentage of work completed on items listed on the approved schedule of values. Actual construction completed and in place will form the basis for payment. Verification of the percent complete shall be initiated by the Contractor in coordination with the field representative of the Contracting Officer. The Contractor shall make the computations for payment based on the government’s verification of work completed and in place for any periods for which progress payments are requested.

2.1.4 Project Meetings

Preconstruction Meeting

The following deliverables shall be submitted a minimum of one week prior to the

Preconstruction Meeting.

• Letter designating Project Superintendent

• Project Schedule and Schedule of Values

• Accident Prevention Program

• List of subcontractors (must be same as in the proposal)

• Written statements from subcontractors certifying compliance with applicable labor standard clauses

• Evidence of liability insurance coverage and workmen’s compensation for the contractor and all subcontractors

• Waste Management Plan

• Quality Control Plan

After the contract award and prior to the start of construction, the CO will arrange an on-site

Preconstruction meeting with the Contractor. The meeting agenda will include the following as a minimum:

• Correspondence procedures

• Jobsite safety

• Roles and responsibilities

• Lines of Authority

• Coordination of subcontractors

• Acceptance/rejection of work

• Progress meetings

• Progress Payments

• Submittal process

• Construction schedule

• Notice to proceed

• Labor standards

• Payroll reports

• Modifications

• Accident reporting

• Project close-out requirements

• As-construction drawings and operation and maintenance (O&M) manuals

• Park Rules and Regulations

• Medical emergency processes, availability, emergency numbers, and contacts.

• Areas available for use by the Contractor

• Site Constraints and Access requirements of the Park

• Saturdays, Sundays, holidays, and night work.

Progress Meetings

The Contractor shall participate in weekly, or as appropriate, telephone conference calls with the

Contracting Officer, and other project team members to update them on the following meeting agenda items:

• Approval of minutes of previous meetings

• Submittal status

• Review of off-site fabrication and delivery

• Requests for Information (RFI’s) and issues

• Modifications

• Work in progress and projected

• Schedule update

• Status of Project Record Drawings and O&M Manuals

• Other business relating to work

2.1.5 Project Schedule

Purpose: The purpose of the project schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of design and construction activities of the

Contractor. The project schedule will assist the Contractor and the Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the

Contractor's monthly progress payment requests.

Schedule Development: The project schedule shall cover the entire contract period. The late finish date of the project schedule shall be no later than the date as the established completion date of the contract.

The project schedule, as developed, shall show the sequence and interdependence of activities required for complete performance of the work. The Contractor shall be responsible for ensuring all work sequences are logical and the project schedule shows a coordinated work plan. Proposed durations assigned to each activity shall be the Contractor's best estimate of time required to complete the activity considering the scope and resources planned for the activity. Include permit requirements and constraints. Seasonal weather conditions shall be considered and included in the planning and scheduling of all work influenced by high or low ambient temperatures, wind and/or precipitation to ensure completion of all work within the contract time.

Project Schedule Updates

Monthly updates: The monthly updating of the project schedule shall be an integral part and basic element of the estimate upon which progress payments shall be made under this contract.

2.2 Design Requirements

The Contractor shall investigate and/or evaluate the park’s existing Loop B campground electrical distribution and utilize the construction drawings and specifications found in section 5 for equipment locations, construction information and wiring. The contractor shall provide detailed drawings for all proposed cabling routes and penetration details to be submitted for approval. The Design shall consist of, but is not limited to, wiring diagrams, site plans, details, specifications, cut sheets, material data sheets, etc., to the extent they clearly convey the systems being proposed for installation. The submittals must be approved by the Park before the purchase and/or installation of the new systems.

Design Criteria: Replace/upgrade existing electrical distribution with new equipment complying with all applicable codes, as well as the International Building Code, National Fire

Protection Association (NFPA) codes/requirements, government standards, and other applicable codes, requirements and/or guidelines. Systems shall be compatible in design and function with simplicity an important factor. Requirements include, but are not limited to, the following:

General Criteria:

• The new electrical equipment must be readily available to ensure that it can be serviced and upgraded as needed.

• Adequate surge protection shall be provided in the panelboards.

• All new underground direct buried wiring is planned for the installation.

• The local utility is aware of the transformer size currently feeding the campground and is monitoring the transformer in real time as additional electrical loads are added. The local utility will upgrade the transformer size in the future as needed.

2.2.1 Deliverables

The following documents are required for NPS review (refer to Section 1.6 for schedule):

• Submit 3 hard copies and 3 electronic copies of the Design Documents for review:

o Shop Drawings/sketch indicating underground electrical distribution for approval.

o Design Data if any

• Submit in native and PDF formats electronic copies of the above design documents.

• Submit design installation details, if any.

2.3 Construction Requirements

2.3.1 Environmental and Sustainability Requirements

Specific sustainability requirements generated in design will dictate more stringent environmental requirements for this project. Refer to part 3, Performance Requirements, of this document. The following are general requirements:

• Site Disturbance: Minimize the construction limits of the project to reduce the project’s impact on the site.

• Waste Management: Employ processes that ensure the generation of as little waste as possible. Waste disposal in landfills shall be minimized. All material unsuitable for recycling must be disposed of, in a legal manner, at public or private dumping areas outside the park.

2.3.2 Schedule of Values

After contract award and before the Pre-Construction Meeting, submit a schedule of values based on the Contract Price Schedule. Breakdown each lump-sum item into component parts of design deliverables or construction work for which progress payments may be requested. The total costs for the component parts of work shall equal the contract line-item amount for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. Include mobilization, general condition costs, overhead and profit in the total dollar value of unit price items and in the component parts of work for each lump-sum item, as described below. Do not include mobilization, general condition costs, overhead or profit as a separate item.

Do not break down unit price items. Use only the contract line-item amount for unit price items.

The total cost of all items shall equal the contract sum. The Schedule of Values will form the basis for progress payments.

An acceptable Schedule of Values shall be agreed upon by the Contractor and Contracting

Officer before the first progress payment is processed.

2.3.3 Construction Support

Special Construction Requirements - N/A

Parking of Construction Vehicles

Parking of vehicles shall be limited to existing roads, in legally designated areas, and within approved staging area(s).

2.3.4 Submittals During Construction

Construction Submittals:

Construction Submittal Types

Action Submittals: Written, graphic information, and physical samples that require

Government’s responsive action.

• Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

• Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

• Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.

Informational Submittals: Written information that does not require Government’s responsive action. Submittals may be rejected for not complying with requirements.

• General: Prepare and submit Informational Submittals required by individual

Specification Sections.

• Informational submittals include but are not limited to Coordination Drawings, Certificates, Test reports, Manufacturer’s instructions, Division 01 Management

Plans, etc.

Contractors Review

Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions.

General Submittal Procedures

Prepare and submit submittals using Transmittal Form CM-16 for products and materials shown in Part 4.0, Technical Requirements. Details on the specific requirements for each can be found in the individual technical sections.

Contracting Officer reserves the right to require submittals in addition to those called for in individual sections.

Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Review them for legibility, accuracy, completeness, and compliance with Contract Documents.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Partial submittals are not acceptable, will be considered non-responsive, and will be returned without review.

Processing Time: Allow enough time for submittal review, including time for re-submittals.

No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals.

1. Action Submittals: Allow 15 calendar days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.

2. Informational submittals: Allow 10 calendar days for review of each submittal.

Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:

1. Transmittal Form: All submittals shall be transmitted using National Park Service form CM-16, which can be obtained from the CO.

a. Complete the general information at the top of the form.

b. Provide all required information based on the submittal type.

c. Attach all related documents.

d. Sign the CM-16 form in the contractor section at the bottom of the form.

2. Physical samples: Complete the CM-16 as described above. Deliver the physical sample to the CO (or designee) on site for processing.

Contracting Officer's Review

Action Submittals: Contracting Officer will review each submittal, generate comments on corrections or modifications required, and indicate the appropriate action on the Transmittal

Form. The submittal will be marked in one of three ways as defined below:

1. Approved: Acceptable with no corrections.

2. Approved with Notations: Minor corrections or clarifications required. All comments are clear, and no further review is required. The Contractor shall address all review comments when proceeding with the work.

3. Disapproved – Resubmit: Rejected as not in accordance with the contract or as requiring major corrections or clarifications. The Contracting Officer will identify the reasons for disapproval. The Contractor shall revise and resubmit with changes clearly identified.

Informational Submittals: Contracting Officer will review each submittal and will either accept or reject them.

Submittal List

An example of a Submittal List is included at the end of this section. The intent is to provide an overall summary of submittal requirements and not a comprehensive list. The technical requirements indicate the type and specify submittal requirements. The terms and conditions of the Contract still apply regardless of what is shown on the submittal list.

Use for Construction

Use only final submittals with mark indicating “Approved” or “Approved with notations”.

Ensure all notations have been incorporated and, at a minimum, keep one copy of the final approved submittal on site for use during construction.

2.3.5 Quality Control

General

The quality of all work shall be the responsibility of the Contractor. Testing shall be the responsibility of an independent testing laboratory. Inspect and test all work as needed to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable specifications and drawings.

Quality Control Daily Reports shall be completed by the Quality Control Supervisor. Test reports shall be completed by person performing the test.

Quality Control Staff

The Contractor's Quality Control Supervisor may also perform the duties of Project

Superintendent. The Contractor's designated Quality Control Supervisor shall be on the project site whenever contract work is in progress.

The Contractor's job supervisory staff may be used to assist the Quality Control Supervisor supplemented, as necessary, by additional certified testing technicians.

Submittals

Quality Control Plan: Prior to the Preconstruction meeting, submit for approval a written

Contractor Quality Control (CQC) plan. If the plan requires any revisions or corrections, the

Contractor shall resubmit the plan within 10 days. The Government reserves the right to require changes in the plan during the contract period as necessary to obtain the quality specified. No change in the approved plan may be made without written concurrence by the Contracting

Officer.

The plan shall include:

• A list of personnel responsible for quality control and assigned duties. Include each person's qualifications.

• A copy of a letter of direction to the Contractor's Quality Control Supervisor outlining assigned duties.

• Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms where applicable.

• Methods of performing, documenting, and enforcing quality control of all work.

• Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.

Daily Reports: Submit showing all inspections, critical construction tasks, and tests on the first workday following the date covered by the report. Utilize the Daily Test Information Report

Sheet and CQC Daily Report forms, https://www.nps.gov/dscw/con_cqcdiaries29.htm, or similar forms as approved by CO.

Test Reports: Submit Daily Test Information Sheets with Quality Control Daily Reports.

Submit complete test results not later than one calendar days after the test was performed. Failed test results shall include proposed remedial actions to address the noted deficiency.

If the CQC plan and Quality Control Daily Reports are not submitted as specified, the

Contracting Officer may retain all payments until such time a plan is accepted and implemented or may retain payments for work completed on days there are no Quality Control daily reports.

Enforcement

The Contractor shall stop work on any item or feature pending satisfactory correction of any deficiency noted by the quality control staff or the Contracting Officer.

https://www.nps.gov/dscw/con_cqcdiaries29.htm

2.3.6 Working Hour Restrictions

All work and deliveries shall be limited to the weekday hours of 8:30 am to 4:30 pm unless otherwise approved by the Contracting Officer. No work shall occur on National Park Service holidays or weekends without prior approval.

2.3.7 Temporary Services

Temporary materials may be new or used but must be adequate in capacity for the required usage, must not create unsafe conditions, and must not violate requirements of applicable codes and standards.

Fire Protection: Observe and enforce standards of fire prevention. No open fires shall be allowed.

Hazard Control: Take all necessary precautions to prevent fire during construction. Do not store flammable or combustible liquids in existing structures. Provide adequate ventilation during use of volatile or noxious substances.

Spark Arresters: Equip all gasoline or diesel-powered equipment used in potential forest or grass fire locations with spark arresters approved by the U. S. Forest Service. Written determinations of areas and periods of potential fire hazard will be issued by Contracting Officer.

Locate internal combustion equipment so that exhausts discharge well away from combustible materials. Locate service areas a minimum of 50 feet from buildings. Shut down equipment before refueling.

Smoking: Smoking within buildings or temporary storage sheds is prohibited. Use designated smoking areas only.

Welding: No welding is anticipated nor permitted for this project.

Electricity and Lighting: Use of existing electrical power service will be permitted, as long as equipment is maintained in a condition acceptable to the NPS.

Sanitary Facilities: Contractor shall have use of the park restroom facilities.

2.3.8 Access

Coordinate construction efforts with the Contracting Officer such that there is minimal impact to the work of the National Park Service personnel and the visiting public.

During construction of the scheduled facilities, the Contractor shall have continuous access to the site.

2.3.9 Existing Utilities

Disruptions of services shall be kept to a minimum. The contractor shall coordinate with the local utility companies. All disruptions shall be arranged at least 48 hours in advance with

National Park Service and must be approved by Contracting Officer.

Construction procedures will prevent accidental disruptions to facilities outside the project limits by investigation of existing utilities and protection during construction: accidental disruptions shall be remedied at no cost to National Park Service.

2.3.10 Accident Prevention

Accident Prevention Program: Prior to the Preconstruction Meeting submit an accident prevention program. The program must be accepted by the NPS before any on site work can begin. The program shall comply with OSHA and project requirements. Include the following:

Name of responsible supervisor to carry out the program; monthly safety meetings; first aid procedures; outline of each phase of work, hazards associated with each phase and methods proposed to ensure property protection, and safety of the public, National Park Service staff and Contractor employees; training; planning for possible emergency situations;

housekeeping and fire protection.

Accident Reporting: Reportable accidents, defined as death, occupational disease, traumatic injury to contractor’s personnel, NPS employees or the public, property damage of any accident in excess of $100 and fires, must be reported within seven days. Complete the CM-22 DSC

Contractor Accident/Property Damage Report template, http://www.nps.gov/dscw/publicforms.htm#ct, and forward to the Contracting Officer.

Quality Assurance: Ensure that all employees are physically qualified to perform their assigned duties in a safe manner. Do not allow employees to work if their abilities are impaired. Operators of all equipment shall be able to understand signs, signals and operating instructions, and be capable of operating such equipment.

Accident Prevention Products: Provide the following:

• First aid facilities.

• Personnel protective equipment: Meet requirements of NIOSH and MSHA.

• Emergency instructions, including telephone numbers and reporting instruction for ambulance, physician, hospital, fire department and park police. Place in conspicuous locations at the worksite.

• Adequate egress at all times in accordance with the Standard for Safeguarding

Construction, Alteration, and Demolition Operations (NFPA 241).

• Hard hats for all employees and for up to 2 visitors.

• Designate and post signs in all hardhat areas.

Training: Provide training for first aid and hazardous material handling and storage.

2.3.10 Temporary Controls

http://www.nps.gov/dscw/publicforms.htm#ct

Housekeeping: Keep project neat, orderly, and in a safe condition at all times.

2.3.11 Project Close-out

Project Record Drawings: Maintain one complete full-size set of contract drawings and one full-size set of vendor-supplied drawings. Clearly mark changes, deletions, and additions using

National Park Service standards to show actual constructed conditions, https://www.nps.gov/policy/DOrders/DO10A.html. Keep record drawings current. Certification of accuracy and completeness will be required for monthly payment requisitions. On completion of the total project, submit complete record drawings.

Cleaning: Before scheduling the final inspection, remove all tools, equipment, surplus materials, and rubbish. Restore or refinish surfaces that are damaged due to work of this contract to original condition. Remove grease, dirt, stains, foreign materials, and labels from finished surfaces.

Thoroughly clean all work and staging areas. Pick up and remove all construction debris from the site. At time of final inspection, project shall be thoroughly clean and ready for use.

Before submitting a request for final inspection, submit the following:

• Project Record Drawings and As-Constructed Drawings: As specified above.

• Spare Parts and Materials: As specified in Performance Requirements and Specifications

• Operation and Maintenance Data: As specified below and in Performance Requirements and Specifications.

• System Demonstration and Training: As specified below and in Performance

Requirements and Specifications.

Operation and Maintenance Data: Provide one set of 3-ring binders with operation and maintenance data, to the Contacting Officer for review, prior to the final inspection. Data shall include manufacturer's standard literature, equipment data sheets, vendor-furnished as-built drawings; custom written data not included in manufacturer’s standard literature; schedules, warranties, parts lists, test results, and subcontractor list.

After NPS review is completed, incorporate comments, and submit 3 final sets of operation and maintenance data to the Contracting Officer.

System Demonstration and Training: Train designated personnel in adjustment, operation, including seasonal and emergency operations, if applicable; maintenance; and safety requirements of equipment and systems. Instructors shall be thoroughly trained in operating theory as well as practical operation and maintenance work for each type of equipment or system. The sequence of the training shall follow the approved outline of the training guide; i.e.

Operating and Maintenance Data. Individual sections specify the duration of training required. If no duration is listed, provide training of sufficient duration to adequately cover the subjects.

2.3.12 Substantial Completion and Final Inspection

https://www.nps.gov/policy/DOrders/DO10A.html

Submit written certification to the CO that the project, or designated portion of project, is substantially complete, and request a final inspection. Upon receipt of written request that project is substantially complete, the Contracting Officer will proceed with inspection within 10 days of receipt of request or will advise the Contractor of items that prevent the project from being designated as substantially complete.

When work is determined to be substantially complete, the Contracting Officer will prepare a list of deficiencies ("Punch List") to be corrected before final acceptance. The Contracting Officer will issue a Letter of Substantial Completion. If work is not determined to be substantially complete, the Contracting Officer will notify the Contractor in writing. After completing work, the Contractor shall resubmit certification and request a new final inspection.

If, following final inspection, the work is determined to be substantially complete, Contracting

Officer will prepare a list of deficiencies to be corrected before final acceptance and issue a

Letter of Substantial Completion. Contractor shall complete the work described on the list of deficiencies within 30 calendar days, as weather permits. If the Contractor fails to complete the work within this time frame, the Contracting Officer may either replace or correct the work with an appropriate reduction in the contract price or charge for re-inspection costs in accordance with the Inspection of Construction clause of the contract.

Acceptance of the work: After all deficiencies have been corrected, the Contracting Officer will issue a Letter of Final Acceptance.

2.4 Forms

• PERFORMANCE REQUIREMENTS

3.1 Facility Performance

All work performed shall comply with applicable laws, regulations, and NPS policies and guidelines, http://www.nps.gov/dscw/laws-policies.htm.

3.2 Elements and Products

In addition to requirements specified in other articles, provide products and elements that comply with the following:

• Where “no substitutions” is indicated, use only the product (or one of the products) specified.

• Products:

▪ Where a product is specified only by a manufacturer name and model number/brand name, the Contractor shall use only that model/brand product.

▪ Where the properties of a product are specified by description and/or with performance criteria, the Contractor shall use products that comply with the description and/or performance criteria.

▪ Where manufacturers are listed for a particular product, the Contractor shall use a product made by one of those manufacturers that also complies with other requirements.

▪ Where actual brand name products are not identified by either the Contracting Officer or the Contractor, the Contractor shall identify the products to be used.

▪ During Construction:

o The Contractor shall identify actual brand name products used for every product, except commodity products specified by performance or description.

o Where a product is specified by performance requirements with test methods, and if so specified, the Contractor shall provide test reports showing compliance.

o The Contractor shall provide manufacturer's product literature for each brand name product.

o The Contractor shall provide the manufacturer's certification that the product used on the project complies with the contract documents.

▪ Before End of Closeout:

o The Contractor shall provide copies of all manufacturer warranties that extend for more than one year after completion.

http://www.nps.gov/dscw/laws-policies.htm

• TECHNICAL REQUIREMENTS

The technical requirements are comprised of specifications and construction drawing with performance and quality requirements specific to the project. The contractor shall adhere to the requirement in the attached listed below:

• Attachment A –Specifications and construction drawings

• Photos of existing electrical equipment

• 3roject Introduction
1.1 Scope
1.2 Location
1.3 Background and Description
1.4 Schedule
1.5 Information
1.6 Data and Materials to be provided by the NPS
• PROJECT Requirements
2.1 General Requirements
2.1.1 Scope of Work and Project Summary/Requirements
2.1.2 Definition of Contract Line Items
2.1.3 Progress Payments
2.1.4 Project Meetings
2.1.5 Project Schedule
2.2 Design Requirements
2.2.1 Deliverables
2.3 Construction Requirements
2.3.1 Environmental and Sustainability Requirements
2.3.2 Schedule of Values
2.3.3 Construction Support
2.3.4 Submittals During Construction
2.3.5 Quality Control
2.3.6 Working Hour Restrictions
2.3.7 Temporary Services
2.3.8 Access
2.3.9 Existing Utilities
2.3.10 Accident Prevention
2.3.10 Temporary Controls
2.3.11 Project Close-out
2.3.12 Substantial Completion and Final Inspection

2.4 Forms

• Performance Requirements
3.1 Facility Performance
3.2 Elements and Products

• Technical REQUIREMENTs