B08_Solicitation_Attach_1__Specifications.pdf

PDF 1 MB Posted

Attached to
SOUTH UNIT POTABLE WATER RENOVATION Federal contract opportunity
Solicitation number
140P6324B0008
Issued by
Department of the Interior National Park Service Midwest Region

About this file

This solicitation is for construction services to renovate the water system at Badlands National Park's south unit in South Dakota. Key work includes replacing substandard water mains and service lines with new polyethylene piping installed using horizontal directional drilling, adding a new water connection, demolishing the existing pump house and well, and installing new water service connections and meter pits to serve the visitors center, ranger house, and fire cache buildings. The period of performance is 150 days from notice to proceed. Bids are due by June 15, 2023, and the award will be made thereafter. The contractor must comply with all applicable regulations and complete all work under a single contract, including erosion control, site restoration, and as-built drawings.

View the file

Other files for this federal contract opportunity

Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Div. 1 V. 2022-9-6 Page | 1

BADLANDS NATIONAL PARK

SOUTH UNIT WHITE RIVER VISITOR

CENTER

RENOVATE WATER SYSTEM

PMIS 226271

Drawing No: 137-80015

PROJECT SPECIFICATIONS

NATIONAL PARK SERVICE

FINAL CONSTRUCTION DOCUMENTS SUBMITTAL

15 MARCH 2023

REG

IS

TE

RE

D P

ROFESSIONA L A RCHITECT

SOUT H DA KOTA

14417

STEPHEN R. SMITH

REG. NO.

Page | 2

TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

Section 01 10 00 - Division 01 Short Form General Requirements

DIVISION 02 – EXISTING CONDITIONS

Section 02 41 16 – Structure Demolition

DIVISION 22 – PLUMBING

Section 22 11 13 – Facility Water Distribution Piping

DIVISION 31 – EARTHWORK

Section 31 10 00 – Site Clearing Section 31 10 00 – Earth Moving

DIVISION 32 – EXTERIOR IMPROVEMENTS

Section 32 92 00 – Turf and Grasses

DIVISION 33 – UTILITIES

Section 33 05 23 – Horizontal Directional Drill

DRAWINGS

Appendices A Drawings (submitted under separate cover)

Page | 3

SECTION 01 10 00

DIVISION 1 SHORT FORM GENERAL REQUIREMENTS

PART 1 – GENERAL

ITEM 1 - DESCRIPTION OF WORK

1.1 Background: The existing water services that currently supply water to the site are fed off the Mni

Wiconi system. The goal of this project is to replace the substandard existing water services with new water service lines, and add a new water connection to the Mni Wiconi Rural Water System which provides the feed to the project site. This existing feed enters the old pump house which is to be demolished along with the pump house’s piping and electrical equipment. The site is a sensitive archaeological area with Indian artifacts.

1.2 Work Covered by the Contract Documents:

A. Project Location: Badlands National Park south unit White River Visitor Center, 2734 BIA 2

Porcupine, SD 57772

B. Work consists of: replacing the existing dilapidated water system’s mains and service lines.

Demolition work will include the existing Mni Wiconi Water Main connection, the buried

12,000 gallon water tank, the existing pump house and existing well. New water service lines are to be bored to minimize archeological disturbance.

1. New water services will include a new master meter pit connection to the Mni Wiconi

Rural Water System and new water service connections (corp stops, curb stops and meter pits) to the existing Visitors Center, Ranger House and Fire Cache buildings.

C. All work will be performed under a single contract.

D. Period of performance: Work shall be completed 150 days after the issuance of the Notice to

Proceed.

ITEM 2 – PROTECTING EXISTING UTILITIES

2.1 Protecting Existing Utilities: Notify Contracting Officer (CO), Contracting Officer’s Representative

(COR) and utility companies as required to request location services prior to and to coordinate any excavation/digging operations, and/or for demolition if within Scope of Work.

2.2 Contractor shall be responsible for locating and preventing damage to known utilities on site or indoors. If contractor damage occurs, alert CO and COR as soon as safely possible, and repair utility at no additional expense to the Government. If damage occurs to an unknown utility, contact CO and COR as soon as safely possible.

2.3 Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated below:

Page | 4

A. Notify CO and COR not less than two business days in advance of proposed utility

Interruptions in order to allow NPS time to coordinate with the Wiconi Pine Ridge Council.

B. Hours for Utility Shutdowns: Shutdowns shall not exceed 2 to 3 hours. Temporary provisions will be needed by the Contractor for periods longer than stated allowance or if required for critical systems as determined by COR.

ITEM 3 - CONTRACTOR’S USE OF PREMISES

3.1 Conduct of Operations: At all times the contractor shall conduct his operations in conformance with the rules and regulations promulgated by the Secretary of the Interior for the National Park

Service, and applicable park rules and regulations prescribed by the Park Superintendent.

A. No signs or advertisements (except those specified herein and as required for safety) shall be displayed on the construction site or within the park unless approved by the Contracting

Officer.

B. Smoking is not permitted within any Federal building or within 25 feet of entrances, operable windows, or outdoor air intakes.

C. Public Use of Site: Contractor shall at all times conduct operations to ensure the least inconvenience to the Park’s employees or to the public.

3.2 On-site work hours: Work shall be generally performed during normal business working hours of

8 a.m. to 5 p.m., Monday through Friday, except when otherwise indicated.

A. Work on Saturdays, Sundays, Federal holidays, early morning, or at night may not be performed without prior consent from the CO and COR. Submit requests for work outside of the stated normal business hours to the CO and COR for approval at least 48 hours in advance of the work.

The following Federal holidays are observed by the National Park Service:

New Year Day

Martin Luther King, Jr’s Birthday

Washington’s Birthday

Memorial Day

Juneteenth National Independence Day

Independence Day

Labor Day

Columbus Day

Veterans Day

Thanksgiving Day

Christmas Day

B. Note: Any of the above holidays falling on a Saturday will be observed on the preceding

Friday; holidays falling on Sunday will be observed on the following Monday. The specific

Page | 5 day that each holiday is recognized for each year can be found at the following site: Federal

Holidays (opm.gov).

3.3 Contractor Use of Site:

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to construction area as shown on site plan. Do not disturb portions of Project site beyond areas in which the Work is indicated. General Contractor shall notify COR immediately if contractor encounters sensitive archaeological Indian artifacts while digging.

BIA (The Bureau of Indian Affairs) and/or MWAC (Midwest Archeological Center) monitors are required to investigate within 72 hours (min) notice coordinated by NPS upon a call from the General Contractor. To avoid mitigation delays caused by the potential encounter of archaeological Indian artifacts, General Contractor shall move to another Project work area until NPS investigates what the General Contractor has uncovered.

B. Driveways and Entrances: Keep driveways, access roads, and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. Schedule deliveries to minimize use of driveways and entrances.

C. Define site disturbance area, including earthwork and clearing of vegetation, to:

1. As shown on construction drawings.

D. Utilities

1. General: Cost or use charges for temporary facilities shall be included in the Contract Sum as required.

2. Water Service: Water from existing water system is available for use without metering and without payment of use charges. Contractor can connect to the existing hose bibb.

Provide connections and extensions of services as required for construction operations without any additional permit costs. Use resources wisely and minimize waste of water.

3. Electric Power Service: Electric power from existing system is not available for use without metering and without payment of use charges. Provide connections and extensions of services as required for construction operations without any additional permit costs. Power may or may not meet your construction power tool requirements, provide generators if questionable. Use power in a resourceful manner and avoid excess power waste.

4. Waste Operation:

a. Toilets: Contractor provided for contracting personnel, sufficiently lighted and ventilated toilet facilities in weatherproof, sight proof, handicap accessible (if required), sturdy enclosures with privacy locks. Coordinate with COR for approved location if not shown on site plan.

b. Waste Removal / Recycling: Contractor is responsible for removing all waste created by the project. Contractor shall recycle to the highest degree possible and empty dumpsters as necessary to avoid debris on site. Locate as shown on site plan or coordinated with COR.

E. Security and Protection facilities:

Page | 6

1. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction in ways and by methods that comply with state and federal environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

2. Cleaning of Equipment: The Contractor shall ensure that prior to moving on to the Project Area, all equipment, is free of soil, seeds, vegetative matter, or other debris that could contain or hold seeds. Ensure that all equipment has been pressure washed and is free of exotic species prior to start-up of operations and moving of equipment to Project Area.

Equipment shall be considered free of soil, seeds, and other debris when a visual inspection does not disclose such material. Disassembly of equipment components or specialized inspection tools are not required.

3. Tree and Plant Protection: N/A.

4. Pest Control: Follow best practices to minimize attraction and harboring of rodents and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at project completion. Perform control operations lawfully, using environmentally safe materials.

5. Temporary Enclosures: Provide temporary enclosures such as snow fence as required for protection of construction in progress and completed, from access by visitors or staff, other construction operations, and similar activities.

6. Site Enclosure Fence: N/A

7. Security Enclosure and Lockup: N/A

3.4 Storage - Staging Areas:

A. Confine Storage of materials and equipment to the project staging area noted on Sheet C2

Site Plan. Specific storage and staging area’s may be discussed at the preconstruction briefing.

3.5 Preservation of Natural Features: N/A.

3.6 Hauling Restrictions: Contractor to verify path to site and meet state and county road requirements and height restrictions for all park work/access.

3.7 Housekeeping:

A. Keep project neat, orderly, and in a safe condition at all times.

1. Dispose of waste materials and recycling legally outside the park. The contractor shall not use park dumpsters

2. Address Recycling: Government goal is to salvage and recycle as much nonhazardous construction waste as possible. Use sustainable methods to extent possible during this project, recycling material as is probable with local means. Maintain accurate documentary records for submittal of all recycled materials used including fly ash and slag cement.

Page | 7

3.8 Occupancy Requirements for Buildings:

A. Existing Buildings:

1. Full Government Occupancy: Government will occupy buildings that are getting new water service connections and meters during the entire contract period. Cooperate with

Government during construction operations to minimize conflicts and facilitate

Government usage. Perform the Work so as not to interfere with Government's day-to-day operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO or COR.

b. Repair damage caused by construction operations. Protect building and its occupants during construction period.

3.9 Photo Documentation:

A. Contractor must provide existing condition, progress, and completion photos. All photos shall be in focus, show maximum range of depth of field general photo and then close up detail photo as needed. Shall be in JPEG digital form and submitted electronically by email or via

CD-R Archival Gold or DVD-R Archival Gold media with printed labels and 8 mega pixels minimum within 7 days from time of taken or as approved by COR.

B. Existing Condition Images:

1. Before starting construction, take color, dated, digital images of project site and adjacent property/roads/etc. that may be impacted by construction activity/traffic. Include existing items to remain or be salvaged from different vantage points and with context for location identification.

C. Construction Progress Images:

1. Document all sub-surface work/ trenches etc. prior to backfill with photos covering enough overall field view to show location and then zoom in for details. (Locations and dimensions shall also be noted on as built drawing set.)

2. Maintain organized index for photos with date, description, etc.

3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.

D. Completion Images:

1. Document all completed work within scope of work.

2. Maintain organized index for photos with date, description, etc..

3. Additional images as needed when questions or emergency situations occur. Submit within 24 hours.

3.10 Fire and Life Safety:

Page | 8

A. As a minimum, conduct one weekly 15 minute "toolbox" safety meetings. These meetings shall be conducted by a foreman or supervisor and attended by all construction personnel at the worksite. Topics need to coincide with work scheduled for the following week. Document and submit meeting minutes to the CO and COR within one day after the meeting and document the meetings on the daily reports.

B. Comply with the requirements of NFPA 241 (Standard for Safeguarding Construction, Alteration, and Demolition Operations). Take all necessary precautions to prevent fire during construction.

C. Store and handle hazardous materials in accordance with manufacturers and OSHA 29CFR1926 Subpart D requirements 1926 | Occupational Safety and Health Administration (osha.gov). Maintain readily available, on site, MSDS/Safety Data Sheets (SDS) for each chemical.

1. Immediately report all spills of hazardous materials to the CO, COR, and park.

2. Maintain a spill emergency response kit.

3. Train employees how to respond to a spill and use the emergency response kit.

3.11 Noise and Acoustics Management N/A

ITEM 4 - COMMENCEMENT, PROSECUTION, AND COMPLETION

4.1 The Contractor shall commence work in accordance with the terms and conditions of the contract.

Contractor shall coordinate and incorporate long lead and delivery time items within the schedule.

ITEM 5 - EXAMINATION OF THE SITE

5.1 All bidders are urged to visit the job site and examine existing conditions before submitting bids.

Contractors will be accountable for understanding existing conditions. No cost changes for items viewable during site visit will be allowed.

ITEM 6 - ABBREVIATIONS

6.1 The list of abbreviations, standards and organizations which may be used in/referred within the

Construction Specifications or Special Provisions, may be found linked from the listed page below. On the home page, follow the link under “Contracting and Procurement” labeled “NPS

Reference Standards.” https://www.nps.gov/orgs/1671/do-business-with-us.htm

ITEM 7 - ACCIDENT PREVENTION

7.1 Description: The work of this section consists of establishing and implementing an effective accident prevention program (APP) and providing a safe environment for all personnel and visitors.

7.2 Submittals:

A. Accident Prevention (Safety) Plan (APP): Submit a site-specific accident prevention (safety) plan. The Plan shall be written to comply with OSHA and project requirements (a generic plan is not acceptable) including but not limited to the following:

Page | 9

1. Name and qualifications of responsible supervisor to carry out the program.

2. First aid and rescue procedures.

3. Training, both initial and continuing.

4. Outline of each phase of the work, the hazards associated with each major phase, and the methods proposed to provide for property protection and safety of the public, National

Park Service personnel, and Contractor's employees. Identify the work included under each phase, with a Job Hazard Analysis (JHA)/Job Safety Analysis (JSA), etc. A sample

JHA template may be provided upon request.

5. Planning for possible emergency situations, such as cave-ins, earthquake, explosions, fires, floods, power outages, slides, and windstorms. Such planning shall take into consideration the nature of construction, site conditions, and degree of exposure of persons and property.

6. Contractor to identify nearest location of medical facility for emergencies

7. Recognition that works will be performed in remote areas with limited communication or cell phone coverage if applicable.

8. Supplemental hazard specific plans may be required IAW 29 CFR 1926 or 1910.

B. Meeting and Inspection Reports: Safety Meetings: As a minimum, conduct 15 minute

"toolbox" safety meetings. These meetings shall be conducted by a foreman and attended by all construction personnel at the worksite. Submit a report of safety meetings and inspections to CO and COR within one day after the meeting and document the meetings on the daily reports.

7.3 Qualification of Employees:

A. Ensure that employees are physically qualified to perform their assigned duties in a safe manner to include operators of vehicles and equipment. Provide operating instructions for all equipment.

B. Do not allow employees to work whose ability or alertness is impaired because of drugs, fatigue, illness, intoxication, or other conditions that may expose themselves or others to injury.

7.4 Accident Reporting: The Contractor shall report all accidents to the CO and COR as soon as safely possible and assist the CO and COR and other officials as required in the investigation of the accident.

7.5 First Aid Facilities: Provide access to facilities for the number of employees and appropriate to the hazards associated with the types of ongoing construction work at the site.

7.6 Emergency Instructions: Post telephone numbers and reporting instructions for ambulance, physician, hospital, fire department, and police in conspicuous locations at the work site.

7.7 Personal Protective Equipment (PPE): It is the Contractor's responsibility to require all those working on or visiting the site to wear necessary protective equipment at all times.

A. PPE must meet requirements of applicable ANSI standards. Selection shall conform to OSHA

29CFR 1926 Subpart E.

Page | 10

B. A hard hat use area shall be designated by the Contractor. The hard hat area shall be posted by the Contractor in a manner satisfactory to the Contracting Officer.

C. All PPE will be serviceable at all times. At a minimum, maintain four sets of PPE including hard hats and all other Accident Prevention Plan required equipment.

7.8 Hazardous Materials: It shall be the responsibility of all operators and contractors, functioning within the park to properly cleanup, mitigate and remediate if necessary, all unauthorized discharges of hazardous materials or non-hazardous chemical and biological products released from fleet and/or other support vehicles or stationary sources. Response shall be consistent with guidelines established by federal, state, and local regulations, and as outlined within the operator's Safety or Hazardous Materials Business Plan.

A. If a spill, leak, or other release occurs, the operator shall as soon as possible, without impeding cleanup, notify the National Park Service Emergency Dispatch.

ITEM 8 - PRECONSTRUCTION CONFERENCE

8.1 If the Contracting Officer decides to conduct a preconstruction conference, the successful offeror will be notified and will be required to attend. The Contracting Officer’s notification will include specific details regarding the date, time, and location of the conference, any need for attendance by subcontractors, and information regarding the items to be discussed. See Item 9.1C below.

ITEM 9 - SUBMITTALS

9.1 General Contracting Submittal Procedures:

A. General: Prepare and submit submittals required by individual Technical Specification

Sections. Types of submittals are indicated in individual specific sections.

1. CM-16 Transmittal Form: All submittals shall be transmitted via electronic email using

National Park Service form CM-16 form. The form will be provided by the Contracting

Officer. No action will be taken on a submittal item unless accompanied by the CM-16 transmittal form. Submit completed CM-16 forms to the CO and the COR

B. Submittal List: administrative required submittals are listed below in 9.1.C and does not include technical section submittal requirements included in each technical section.

C. Preconstruction Conference Submittal: Satisfactory evidence of liability insurance coverage and workman’s compensation, and any applicable bonds, must be submitted within 10 calendar days of Notice of Award. The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed may not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to

Proceed has been issued. Contracting Officer will notify Contractor of tentative date for the

Pre-Construction Conference:

1. Letter designating Project Superintendent.

Page | 11

2. Construction Schedule. (Must include shop drawings, procurement time including long lead time items, mobilization, trade work progression and completion at minimum.)

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention (Safety) Plan (see section 7 of this document).

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor

i. standard clauses (SF1413).

7. Quality Control Plan.

8. Waste Management Plan.

9. List of Required Construction Permits:

a. Plumbing Permit Tap. (Contractor shall coordinate tap with MNI Water System)

b. Right-Of-Way Permit and permit to work within existing Right-Of-Way owned by the

Bureau of Indian Affairs (BIA) shall be obtained by the Contractor.

c. South Dakota DENR Permit is not required.

9.2 Project Shop Drawings, Product Data, and Samples: Contracting Officer will provide sample cover sheet and a list of required submittals is included in each technical specification or attached at the end of this document.

A. Shop Drawings: Indicate all coordinating materials and work impacting the installation coordination, connection details, anchorage requirements, hardware locations, and installation details and locations.

1. Submit Shop Drawings according to Part 9.1 of this section to include one digital file (.PDF or .TIF) and two full size hardcopy documents to COR.

B. Product Data: Provide component construction and specification data sheets, anchorage requirements and any other product specific data.

1. Submit Product Data according to Part 9.1 of this section to include one digital file (.PDF or .TIF) to COR.

C. Samples: NA

D. For submittals specified above, forward submittals to Contracting Officer and COR at least 15 days before need for approval (depends on length of project).

E. After approving submittals, Contracting Officer and/or COR will return one copy to the

Contractor. If submittals are not approved, Contracting Officer will return all copies to

Contractor with reasons for rejection. Resubmit, identifying changes. Any work done before approval shall be at Contractor's own risk.

9.3 Approved Equals: If an item in this solicitation is identified as “brand name or equal” or lists more than 1 manufacturer, the description of the proposed item must reflect the characteristics and level of quality that will satisfy the Government’s needs as demonstrated by the salient physical, functional, or performance characteristics that “equal” products must meet and/or exceed that as specified in the solicitation or relevant specification.

A. For each item proposed as an “approved equal,” submit supporting data, including:

Page | 12

1. Drawings and samples as appropriate.

2. Comparison of the characteristics of the proposed item with that specified and with the salient characteristics provided.

3. Changes required in other elements of the work because of the substitution.

4. Name, address, and telephone number of vendor.

5. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists.

Describe availability of maintenance service, and state source of replacement materials.

B. A request for approval constitutes a representation that Contractor:

1. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.

2. Will provide the same warranties for the proposed item as for the item specified.

3. Has determined that the proposed item is compatible with interfacing items.

4. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.

5. Waives all claims for additional expenses that may be incurred as a result of the substitution.

C. Approved Equals will be evaluated and approved/disapproved during the submittal process.

9.4 Schedule of Values: Submit the Schedule of Values a minimum of one week prior to the

Preconstruction Conference for COR review. Schedule of Values shall include defined work line items with cost break downs including labor, material, and equipment for COR approval.

9.5 Progress Reporting: The initial Construction Schedule and Schedule of Values are required a minimum of one week prior to the Preconstruction Conference. After the Notice to Proceed is issued and after on-site work begins, progress will be documented via daily logs and by providing an updated Construction Schedule and Schedule of Values when requested, but minimally with each pay application. Submit digital copy electronically (PDF preferred) of all required documents.

Construction Schedules are normally in bar chart form and indicate estimated starting and completion dates for each part of the work. For a pay application to be reviewed and processed in a timely manner, the following information must either be submitted prior to or accompany submission of the pay application:

A. Daily/weekly progress reports during construction as part of the administration process.

B. Updated Schedule of Values: Breakdown each lump-sum item into component work activities used in the schedule, for which progress payments may be requested. The Schedule of

Values will form the basis for payment. The work activities broken out within the schedule of values shall be integrated into and made a logical part of the construction baseline schedule submitted under this specification. The total costs for the component work activities shall equal the contract price for that lump-sum item. The Contracting Officer may request data to verify accuracy of dollar values. A sample Schedule of Values format may be provided upon request.

ITEM 10 – TEMPORARY SERVICES

Page | 13

10.1 It is the Contractor’s responsibility to provide temporary services, equipment, tools, and skilled labor as required for the chosen means and methods to perform the work in accomplishing this

Contract.

ITEM 11 - PROJECT CLOSEOUT

11.1 Description: The work of this section consists of final cleanup, closeout submittals, final inspection procedures working toward Final Acceptance.

11.2 Cleaning: Remove all tools, equipment, surplus materials, and rubbish. Move attic stock to location coordinated with COR. At time of final inspection, project shall be thoroughly clean and ready for intended use. Inspector holds the right to reschedule if project is not ready for inspection.

11.3 Completion and Final Inspection: Contractor shall submit written certification of project completion and request a final inspection to the Contracting Officer and COR. The Contracting

Officer or designee will make an inspection within 10 days of receipt of request or at a mutually agreeable time.

A. If the work is determined to be complete following the final inspection with minor comments, the COR will prepare and provide the Contractor a Punch List noting outstanding items to be addressed.

B. If the work is not determined to be complete following the final inspection, the Contracting

Officer will notify Contractor in writing, stating reasons. Contractor, after completing the work according to the Contract Documents, shall resubmit completion and request a new final inspection. Re-inspection costs may be charged against the Contractor in accordance with the Inspection of Construction contract clause.

C. Contractor shall complete the Punch List within 30 calendar days, or a time directed by the

CO.

D. Once Contractor completes all items of work on the Punch List and all contractually required items are accepted, Contracting Officer will issue Letter of Final Acceptance of Work and request the final pay application.

E. If the Contractor fails to complete the work within the time frame, the Contracting Officer may correct the work with an appropriate reduction in contract price or charge for re-inspection costs in accordance with the Inspection of Construction contract clause.

F. Disposition of any permits and warranties required by the specifications in this section.

11.4 Final Acceptance of the Work: After all punch list deficiencies have been corrected, a Letter of

Final Acceptance will be issued. A Release of Claims document must be executed and submitted to the Contracting Officer before final payment can occur.

11.5 Warranties

Page | 14

A. Construction Warranty shall be based on date of final acceptance of the work and remain in effect for one year.

B. Provide all manufacturer warranty information of products installed organized by Division. All contact information, extent of coverage and conditions shall be clearly noted as well as date of overall final acceptance.

C. Information shall include operation and maintenance manuals for each warranted product.

PART 2 – PRODUCTS (NOT USED)

PART 3 – EXCUTION (NOT USED)

END OF SECTION

BADL - 226271 02 41 16 - 1

SECTION 02 41 16 - STRUCTURE DEMOLITION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Demolition and removal of buildings and site improvements.

2. Abandoning in-place and/or removing below-grade construction.

3. Disconnecting, capping or sealing, and abandoning in-place or removing site utilities.

B. Related Sections:

1. Division 31 Section 311000 Site Clearing for site clearing and removal of above- and below-grade site improvements not part of building demolition.

1.3 DEFINITIONS

A. Remove: Detach items from existing construction and legally dispose of them off-site unless indicated to be removed and salvaged.

B. Interior Demolition: Demolition and removal activities associated with non-structural building elements.

C. Structural Demolition: Demolition and removal activities associated with building structural elements, including but not limited to: walls, roof, columns, floors or any other removal items which would affect the structural integrity of the building.

1.4 MATERIALS OWNERSHIP

A. Owner has the first right of refusal of all items scheduled for demolition whether specifically indicated or not. If owner does not wish to salvage items, then demolition waste becomes property of Contractor.

B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner.

1. Carefully salvage in a manner to prevent damage and promptly return to Owner.

1.5 REGULATORY REQUIREMENTS

A. Confirm to applicable codes and regulations for deconstruction of buildings, safety of adjacent structures, dust control, and disposal and removal of common and hazardous waste.

BADL - 226271 02 41 16 - 2

B. Codes and Regulations: Complete all deconstruction work according to the requirements of the State of South Dakota.

1.6 SUBMITTALS

A. Proposed Protection Measures: Submit informational report, including Drawings, that indicates the measures proposed for protecting individuals and property, for environmental protection, for dust control and, for noise control. Indicate proposed locations and construction of barriers.

B. Schedule of Building Demolition Activities: Indicate the following:

1. Detailed sequence of demolition work, with starting and ending dates for each activity.

2. Temporary interruption of utility services.

3. Shutoff and capping of utility services.

1.7 QUALITY ASSURANCE

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning demolition. Comply with local hauling and disposal regulations.

B. Standards: Comply with ANSI/ASSE A10.6 and NFPA 241.

C. Predemolition Conference: Conduct conference at location to be determined.

1. Inspect and discuss condition of construction to be demolished.

2. Review and finalize building demolition schedule and verify availability of demolition personnel, equipment, and facilities needed to make progress and avoid delays.

3. Review and finalize protection requirements.

4. Review procedures for noise control and dust control.

5. Review procedures for protection of adjacent buildings.

6. Review items to be salvaged and returned to Owner.

1.8 PROJECT CONDITIONS

A. Building to be demolished will be vacated and the use discontinued before start of the Work.

B. Buildings immediately adjacent to demolition area will be occupied. Conduct building demolition so operations of occupied buildings will not be disrupted.

1. Provide not less than 72 hours notice of activities that will affect operations of adjacent occupied buildings.

2. Maintain access to existing walkways, exits, and other facilities used by occupants of adjacent buildings.

a. Do not close or obstruct walkways, exits, or other facilities used by occupants of adjacent buildings without written permission from the Owner.

C. Owner assumes no responsibility for buildings and structures to be demolished.

1. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.

BADL - 226271 02 41 16 - 3

D. Hazardous Materials: Prior to execution of this contract, hazardous materials, if present, will be abated by the Owner.

1. Do not disturb hazardous materials or items suspected of containing hazardous materials. Notify Architect and Owner immediately if hazardous materials are discovered. Do not proceed with demolition of the area containing the hazardous material until direction is given by the Owner and Architect.

E. On-site storage or sale of removed items or materials is not permitted.

1.9 COORDINATION

A. Arrange demolition schedule so as not to interfere with operations of adjacent occupied buildings.

PART 2 - EXECUTION

2.1 EXAMINATION

A. Verify that utilities have been disconnected and capped before starting demolition operations.

B. Review Project Record Documents of existing construction provided by Owner. Owner does not guarantee that existing conditions are same as those indicated in Project Record Documents.

C. Verify that hazardous materials have been remediated before proceeding with building demolition operations.

2.2 PREPARATION

A. Existing Utilities: Locate, identify, disconnect, and seal or cap off indicated utilities serving building to be demolished in accordance with Section 311000 Site Clearing.

B. Temporary Shoring: Provide and maintain interior and exterior shoring, bracing, or structural support if needed to preserve stability and prevent unexpected movement or collapse of building being demolished.

1. Strengthen or add new supports when required during progress of demolition.

2.3 PROTECTION

A. Existing Facilities: Protect all areas not indicated to be removed within the construction limits during demolition operations.

B. Existing Utilities: Maintain utility services to remain and protect from damage during demolition operations.

1. Do not interrupt existing utilities serving adjacent occupied or operating facilities unless authorized in writing by Owner and authorities having jurisdiction.

C. Temporary Protection: Erect temporary fencing protection, as indicated on Project Drawings.

Comply with requirements in Division 01 Section Temporary Facilities and Controls.

BADL - 226271 02 41 16 - 4

1. Protect adjacent buildings and facilities from damage due to demolition activities.

2. Protect existing site improvements, appurtenances, and landscaping to remain.

3. Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

4. Provide protection to ensure safe passage of people around building demolition area and to and from occupied portions of adjacent buildings and structures.

5. Protect walls, windows, roofs, and other adjacent exterior construction that are to remain and that are exposed to building demolition operations.

D. Remove temporary barriers and protections where hazards no longer exist. Where open excavations or other hazardous conditions remain, leave temporary barriers and protections in place.

2.4 DEMOLITION, GENERAL

A. General: Demolish indicated buildings and site improvements completely. Use methods required to complete the Work within limitations of governing regulations and as follows:

1. Do not use cutting torches until work area is cleared of flammable materials.

2. Locate building demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

B. Site Access and Temporary Controls: Conduct building demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

1. Do not close or obstruct streets, walks, walkways, or other adjacent occupied or used facilities without permission from Owner and authorities having jurisdiction. Provide alternate routes around closed or obstructed traffic ways if required by authorities having jurisdiction.

2. Use water spray and other suitable methods to limit spread of dust and dirt. Comply with governing environmental-protection regulations. Dust control shall be strictly monitored and provided during project duration. During structural demolition, contractor shall provide water spray to limit dust generation at all times.

C. Explosives: Use of explosives is not permitted.

2.5 DEMOLITION BY MECHANICAL MEANS

A. Proceed with demolition of structural framing members systematically, from higher to lower level.

Complete building demolition operations above each floor or tier before disturbing supporting members on the next lower level.

B. Remove debris from elevated portions of the building by chute, hoist, or other device that will convey debris to grade level in a controlled descent.

1. Remove structural framing members and lower to ground by method suitable to minimize ground impact and dust generation.

C. Below-Grade Construction: Demolish foundation walls and other below grade construction.

1. Remove below grade construction, including basements, foundation walls and footings completely to soil subgrade.

BADL - 226271 02 41 16 - 5

D. Existing Utilities: Demolish existing utilities and below-grade utility structures that are within 5 feet outside building footprint.

1. Piping: Disconnect piping at unions, flanges, valves, or fittings.

2. Wiring Ducts: Disassemble into unit lengths and remove plug-in and disconnecting devices.

2.6 SITE RESTORATION

A. Below-Grade Areas: Structure excavation shall be backfilled.

2.7 REPAIRS

A. Promptly repair damage to adjacent buildings caused by demolition operations.

B. Repair to original condition all pavement and/or curb and gutter which was damaged by demolition acitivities.

2.8 DISPOSAL OF DEMOLISHED MATERIALS

A. Remove demolition waste materials from Project site and legally dispose of them in as specified in Section 017419 Construction Waste Management and Disposal.

1. Do not allow demolished materials to accumulate on-site.

2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.

B. Do not burn demolished materials.

2.9 CLEANING

A. Clean adjacent structures and improvements of dust, dirt, and debris caused by building demolition operations. Return adjacent areas to condition existing before building demolition operations began.

1. Clean roadways of debris caused by debris transport.

END OF SECTION 02 41 16

BADL - 226271 22 11 13 - 1

SECTION 22 11 13 - FACILITY WATER DISTRIBUTION PIPING

1.1 SUMMARY

A. This Section includes water-distribution piping and related components outside the building for water service.

1.2 DEFINITIONS

A. Contamination Source: Including, but not limited to, sanitary sewer pipe and manholes, storm sewer pipe and manholes, septic tanks, and subsoil treatment systems.

B. HDPE: High Density Polyethylene plastic.

C. NPS: Nominal Pipe Size.

D. PVC: Polyvinyl chloride plastic.

1.3 ACTION SUBMITTALS

A. Product Data: For each type of product indicated.

1.4 INFORMATIONAL SUBMITTALS

A. Field quality-control test reports.

B. Manufacturer’s installation instructions.

1.5 CLOSEOUT SUBMITTALS

A. Operation and Maintenance Data: For water valves and specialties to include in emergency, operation, and maintenance manuals.

1.6 QUALITY ASSURANCE

A. Regulatory Requirements:

1. Comply with requirements of utility company supplying water. Include tapping of water mains and backflow prevention.

2. Comply with standards of authorities having jurisdiction for potable-water-service piping, including materials, installation, testing, and disinfection.

3. Comply with standards of authorities having jurisdiction for fire-suppression water-service piping, including materials, hose threads, installation, and testing.

B. Piping materials shall bear label, stamp, or other markings of specified testing agency.

C. Valves: Manufacturer’s name and pressure rating marked on valved body.

D. NSF Compliance:

1. Comply with NSF 14 for plastic potable-water-service piping.

BADL - 226271 22 11 13 - 2

2. Comply with NSF 61 for materials for water-service piping and specialties for domestic water.

1.7 DELIVERY, STORAGE, AND HANDLING

A. Preparation for Transport: Prepare valves, including fire hydrants, according to the following:

1. Ensure that valves are dry and internally protected against rust and corrosion.

2. Protect valves against damage to threaded ends and flange faces.

3. Set valves in best position for handling. Set valves closed to prevent rattling.

B. During Storage: Use precautions for valves, including fire hydrants, according to the following:

1. Do not remove end protectors unless necessary for inspection; then reinstall for storage.

2. Protect from weather. Store indoors and maintain temperature higher than ambient dew-point temperature. Support off the ground or pavement in watertight enclosures when outdoor storage is necessary.

C. Handling: Use sling to handle valves and fire hydrants if size requires handling by crane or lift.

Rig valves to avoid damage to exposed parts. Do not use handwheels or stems as lifting or rigging points.

D. Deliver piping with factory-applied end caps. Maintain end caps through shipping, storage, and handling to prevent pipe-end damage and to prevent entrance of dirt, debris, and moisture.

E. Protect stored piping from moisture and dirt. Elevate above grade. Do not exceed structural capacity of floor when storing inside.

F. Protect flanges, fittings, and specialties from moisture and dirt.

G. Store plastic piping protected from direct sunlight. Support to prevent sagging and bending.

1.8 PROJECT CONDITIONS

A. Interruption of Existing Water-Distribution Service: Do not interrupt service to facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary water-distribution service according to requirements indicated:

1. Notify Owner no fewer than 72 hours in advance of proposed interruption of service.

2. Do not proceed with interruption of water-distribution service without Owner's written permission.

B. Field verify all existing facilities and utilities prior to starting work to identify all conflicts with the work.

PART 2 - PRODUCTS

2.1 WATER SERVICES, BURIED

A. Polyethylene Tubing: PE 4710, SIDR-7, 250 psi, with OD conforming to 1” to 2” iron pipe size.

Conforming with AWWA C-901, ASTM D2239, PE-3608/3408. “JM Eagle C901 IPS SIDR”, “Cresline Flexible Pipe”, or equal.

1. No splices or couplings allowed in tubing runs.

2. Fittings: AWWA C901 Brass

BADL - 226271 22 11 13 - 3

3. Joints: Compression with Stainless Steel Inserts

4. Provided bushing or other fitting to connect to existing services.

B. Curb Stop Boxes: Minneapolis or Buffalo Type Box with Hex Nut in Lid. Provide extension rods to within 6” of finish grade and centering ring. Cast iron or combination cast iron and plastic curb boxes. Tracer wire shall be attached to the curb stop terminal nut and continue to the water main.

C. Saddles Corporation Stops and Curb Stops.

1. Saddles: To be Ford FC202 Ductile Iron Saddle with Stainless Steel Band, Mueller, AY McDonald, Smith-Blair Bronze Saddles or Equal with AWWA Tapered Threads.

2. Corporations: To be AWWA C800, Brass Body Inlet to be AWWA Taper, outlet compression Ford Meter Box FB1000, AY McDonald, Smith-Blair Bronze Saddles or Equal. All services unless otherwise noted on the plans.

3. Curb Stop: To be 1” AWWA C800, Bronze Body, ASTM B62, compression connection, Minneapolis or Buffalo Pattern, or approved equal.

D. Meters: Mueller 500 Series (Bronze); 1”, 1.5”, & 2” meter. Readout shall be either CCF or per 1,000 gal.

E. Meter Boxes: Mueller EZ-VAULT meter setters, 8F.10, meter. Insulation Pads; Mueller Meter Box Setter Lids.

2.2 PE PIPE AND FITTINGS

A. PE, AWWA Pipe: ANSI/AWWA C901, conforming to ASTM D3035, ASTM F714, ASTM D2737, ASTM D2239

1. PE, AWWA Fittings: AWWA C901, socket- or butt-fusion type, with DR number matching pipe and PE compound number required to give pressure rating not less than 200 psig.

2.3 COPPER TUBE AND FITTINGS

A. Soft Copper Tube: ASTM B 88, Type K (ASTM B 88M, Type A), water tubed, annealed temper.

1. Copper, Solder-Joint Fittings: ASME B16.18, cast-copper-alloy or ASMe B16.22, wrought-copper, solder-joint pressure type. Furnish only wrought-copper fittings if indicated.

2. Bronze Flanges: ASME B16.24, Class 150, with solder-joint end. Furnish Class 300 flanges if required to match piping

3. Copper Unions: MSS SP-123, cast-copper-alloy, hexagonal-stock body with ball-and-socket, metal-to-metal seating surfaces, and solder-joint or threaded ends

2.4 GATE VALVES

A. Two (2) Inch or Smaller: Solid Wedge Type

1. Gate valves shall be Class 125

2. Each valve shall be of bronze construction with screwed bonnet, rising stem, and Teflon impregnated packing

3. Manufacturers: Threaded End: Milwaukee “1148”, Stockham “B-100”, and Walworth “Fig 55”, or equal.

BADL - 226271 22 11 13 - 4

4. Manufacturers: Threaded End: Milwaukee “149”, Stockham “B-109”, and Walworth“Fig 55SJ”, or equal.

2.5 PIPE ACCESSORIES

A. Tracer Wire:

1. Tracer wire shall be 12 ga. (HDPE Coated) Copper-Clad Steel tracer wire, manufactured for direct bury service, Agave, Copperhead, or approved equal. Wire shall be continuous without breaks. Splices shall be made with petroleum-filled wire nut caps, suitable for direct-bury service 3M direct bury splice DBR/Y, or equal. Bring tracer wire to surface.

PART 3 - EXECUTION

3.1 PREPARATION

A. Review layout of work for conflicts with existing facilities or utilities.

1. Coordinate any necessary layout revisions with Engineer before starting work.

3.2 PROTECTION

A. Protect existing facilities and utilities.

B. Protect existing landscaping and other features remaining as final work.

3.3 EARTHWORK

A. Refer to Section 312000 Earth Moving for excavating, trenching, and backfilling.

3.4 PIPING INSTALLATION

A. Water-Main Connection: Tap water main according to requirements of water utility company and of size and in location indicated.

1. Make connections larger than NPS 2 (DN 50) with tapping machine according to the following:

2. Install tapping sleeve and tapping valve according to MSS SP-60.

3. Install tapping sleeve on pipe to be tapped. Position flanged outlet for gate valve.

4. Use tapping machine compatible with valve and tapping sleeve; cut hole in main.

Remove tapping machine and connect water-service piping.

5. Install gate valve onto tapping sleeve. Comply with MSS SP-60. Install valve with stem pointing up and with valve box.

B. Comply with NFPA 24 for fire-service-main piping materials and installation.

C. Install PE pipe according to ASTM D 2774 and ASTM F 645.

D. Install PVC, AWWA pipe according to ASTM F 645, AWWA M23 and AWWA C605.

E. Bury service piping with depth of cover over top at least 6 feet.

F. Provide 18” minimum vertical clearance and 10 feet minimum horizontal clearance between the outside edge of the water pipe and the outside edge of a contamination source.

BADL - 226271 22 11 13 - 5

1. Install a full length of pipe at crossings so both joints will be as far from the contamination source as possible with the preference to have the water pipe above the contamination source.

2. Any variance with minimum separation distances shall be approved by the reviewing authority.

G. Install piping by tunneling or jacking, or combination of both, under streets and other obstructions that cannot be disturbed.

H. Install underground piping with restrained joints at horizontal and vertical changes in direction.

Use restrained-joint piping, thrust blocks, anchors, tie-rods and clamps, and other supports.

3.5 TRACER WIRE INSTALLATION

A. Install tracer wire with all service water pipe to facilitate detection of the pipe.

B. Tracer wire shall be secured to the top of the pipe by tape at a minimum of three locations in each section of pipe.

C…

This is the start of the file's text. The full file is on GovTribe.