REPAIR/REPLACE ROOFING ON AZ STRUCTURES Federal contract opportunity
Solicitation number
140P8624Q0053
Issued by
Department of the Interior National Park Service Pacific West Region

About this file

This document is a set of project specifications for roofing repair and replacement work on various structures on Alcatraz Island, which is part of the Golden Gate National Recreation Area. The work includes repairs to the Dock Restroom roof and replacement of the Electric Shop roof. Key details include:

The project location is Alcatraz Island in San Francisco Bay, California. The work consists of roof repairs on the Dock Restroom and roof replacement on the Electric Shop. The project will be constructed under a single prime contract. The contractor is responsible for arranging and coordinating all transportation of workers and materials to and from the island, which has unique access and staging requirements. The work must be performed in a manner that minimizes disruption to the public's use of the facilities. Asbestos-containing materials and lead-based paints are present and must be properly abated. The contractor must comply with various environmental, safety, and quality control requirements specified in the document.

View the file

Other files for this federal contract opportunity

Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GOLDEN GATE NATIONAL RECREATION AREA

ALCATRAZ ISLAND

Repair or Replace Roofing on Various Structures

GOGA

PMIS NO. 306945B

PROJECT SPECIFICATIONS

NATIONAL PARK SERVICE

GGNRA

12/11/2023

TABLE OF CONTENTS

Division ............. Section Title ..........................................................................................................................…..Page

DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS

00 31 26 Existing Hazardous Material Information

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00 Summary of Work

01 27 00 Definition of Contract Line Items

01 31 00 Project Management & Coordination

01 32 16 Construction Schedule

01 33 23 Submittal Procedures

01 35 23 Safety Requirements

01 40 00 Quality Requirements

01 42 00 References

01 50 00 Temporary Facilities and Controls

01 67 00 Product Requirements

01 77 00 Closeout Procedures

DIVISION 02 - EXISTING CONDITIONS

02 82 33 Removal and Disposal of Asbestos-Containing Materials

DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES

06 05 73 Eradication of Insects in Wood

06 10 00 Rough Carpentry

06 16 00 Sheathing

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

07 41 15 Aluminum Roof Panels

07 62 00 Sheet Metal Flashing and Trim

DIVISION 09 – FINISHES

09 91 13 Exterior Painting

EXHIBITS/SUPPLEMENTAL INFORMATION

Exhibit A: Dock Restroom and Electric Shop Existing Conditions

Exhibit B: Electric Shop Blocking Installation Sketch

Exhibit C: NPS GOGA Guidance on Site Specific Safety Plans 2015-01-09

Exhibit D: Contractor Badge Template

Exhibit E: California Code of Regulations, Title 8, Section 1529. Asbestos

Exhibit F: Dock Restroom plans-partial

Exhibit G: OQMG Historical Records of Buildings - AL089 (Electric Shop plans)

Exhibit H: General Requirements for Contractors on Alcatraz Feb 2020 Update

SECTION 00 31 26 - EXISTING HAZARDOUS MATERIAL INFORMATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Document discloses Reference Documents that are available to the Contractors regarding the hazardous materials investigations and/or past hazardous materials remediation work that was utilized by the Government and its Consultant(s) in preparing the Contract Documents.

1.2 HAZARDOUS MATERIALS REPORT(S)

A. The Contractor’s attention is directed to the fact that a hazardous materials survey report was prepared for the site and is known as:

1. “Asbestos-Containing Materials Survey Report for National Park Service, United States Department of Interior, Golden Gate National Recreational Area, San Francisco, California,” prepared by MACTEC Engineering and Consulting, Inc., September 28, 2012, MACTEC Proj.

No. 6141-10-0320.

1.3 HAZARD SUMMARY

A. Asbestos Hazards: Certain existing building components or materials, which may be impacted by the Work of this Project, are known or presumed to contain asbestos.

1. The following materials were assumed to contain asbestos at concentrations greater than one percent (>1%):

a. Corrugated exterior cement roofing (Transite, non friable) throughout the Electric Shop building over older wood shingles, totaling about 1197 SF [Sample I.D.

GOGA.38356.004a].

B. Lead Hazards: Certain existing painted or coated surfaces to be impacted by the Work of this Project are known or suspected to contain lead.

1. The following materials were not all tested but, the Contractor, for the purposes of this Contract and for Cal/OSHA (8 CCR 1532.1) and Cal/EPA (Title 22 CCR) compliance shall assume and manage them as lead containing.

a. Roof flashings.

b. Caulking.

c. Mastic and adhesives.

2. Disturbance of painted surface, flashings, caulking, mastics and adhesives is not anticipated on either structure. The Government has not has not verified that any paints, coatings, dusts, or materials are “lead free,” therefore, all “ trigger 1” construction activities, such as demolition of painted surfaces, manual scraping or sanding of painted surfaces, or renovations impacting painted surfaces and primed structural steel shall be completed using dust controls and personal protective measures in compliance with the Cal/OSHA Construction Lead Standard, 8 CCR

1532.1. All settled dust within ductwork, ceiling plenums, crawl spaces, attics, chases and non-regular housekeeping areas shall be treated as having a lead content greater than 600 ppm requiring dust controls in compliance with 8 CCR 1532.1 during [demolition] [renovations].

C. Other Hazards:

1. Biological Hazards requiring compliance with Cal/OSHA’s Bloodborne Pathogen standards, include, but are not necessarily limited to:

a. Sea gull, pigeon or animal waste.

2. Mold requiring remediation and personal protection in compliance with the “Guidelines on Assessment and Remediation of Fungi in Indoor Environments” (New York City Department of Health, April 2000), guidelines established in Bioaerosols Assessment and Control (J.

Macher, Editor, ACGIH, 1999) and “Mold Remediation in Schools and Commercial Buildings” (U.S. Environmental Protection Agency, March 2001) and as otherwise noted in the Contract Documents.

1.4 USE OF DATA

A. Environmental consultation was obtained only for the use of the Government and its Consultants for planning and design stages of this Project. The above mentioned report(s) are not, as a whole, part of the Contract Documents, but the survey data contained therein can be relied upon by the Contractor to characterize general site conditions, although quantities, friability and other factors may have changed or been altered since the published report date(s).

B. All statements, findings, and interpretations in the above mentioned report(s) are those of the Survey or Abatement Consultant(s). The Government makes no representations, either expressed or implied, as to the completeness or adequacy of the above-mentioned reports. Contractors are advised that the limited testing of components allow for generalizations in describing the extent of hazardous materials. Specific components or materials, should be checked against the referenced survey report(s) and the Contract Documents, or be tested at affected locations, prior to disturbance of such components or materials.

C. Contractors shall visit the work site and acquaint themselves with its existing conditions.

Difference in conditions, if any, shall be brought to the Government’s attention prior to bidding.

1.5 PRE-BID VISIT TO WORK SITE

A. Prior to bidding, Contractors may make their own investigations to satisfy themselves as to the Site and subsurface conditions, but such investigations shall be performed only under the provisions set by the Government during the Bid Walk Phase.

END OF SECTION 00 31 26

SECTION 01 11 00 - SUMMARY OF WORK

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes the following:

1. Work covered by the Contract Documents.

2. Work under other contracts.

3. Contractor use of site.

4. Public use of site.

5. Occupancy requirements for buildings.

6. Worker transportation to Alcatraz Island.

7. Materials transport to Alcatraz Island.

8. Work Restrictions.

9. Special Construction Requirements.

10. Supplemental Information and Reports.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

A. Project Location: The project is located on Alcatraz Island, in the San Francisco Bay, California.

Alcatraz Island is part of the Golden Gate National Recreation Area.

B. The Work consists of the following:

A. The Work includes roof repairs on the Dock Restroom and roof replacement on the Electric Shop.

B. Project will be constructed under a single prime contract.

1.3 WORK UNDER OTHER CONTRACTS

A. General: Cooperate fully with separate contractors so work on those contracts may be carried out smoothly, without interfering with or delaying work under this Contract. Coordinate the Work of this Contract with work performed under separate contracts.

1.4 CONTRACTOR USE OF SITE

A. General: Contractor shall have limited use of the site for construction operations. Limit use of premises to areas within the Contract limits indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.

1. Limits: Confine constructions operations to the buildings noted above and the approved staging areas.

B. Storage of Materials: Confine storage of materials to designated staging areas.

C. Roadway and Entrances: Keep roadway and entrances serving premises clear and available to Government, Government's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.

1. Schedule deliveries to minimize use of driveways and entrances.

2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.

D. Construction Camp: Establishment of a camp within the park will not be permitted.

E. Hauling Restrictions: Comply with all legal load restrictions in the hauling of materials. Load restrictions on park roads are identical to the state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.

1. Some materials arriving at the island must pass through the historic sallyport or be crane lifted around the sally port. See the supplemental information for approximate sally port dimensions. Contractor is responsible for taking exact measurements to verify feasibility of moving materials and equipment through the sally port without damaging the structure.

2. Road usage requirements are specified in: National Park Service. September 15, 2001.

Golden Gate National Recreation Area Standard Operation Procedure 609: Vehicle Use on Alcatraz.

3. Roads on the island have multiple hairpin turns that will preclude the use of some construction equipment.

4. Do not block the shuttle route or the main road for any reason during hours of public visitation.

5. All vehicles on the main road must have a spotter on foot to interface with the interpretive staff and public, and to aid in the prevention of accidents. The main road speed limit is 5 miles per hour.

F. Worker Orientation and Identification: All workers must attend an orientation meeting with Park Staff to review the unique requirements of working on Alcatraz Island, interfacing with the public and safeguarding natural and cultural resources.

1. All workers are required to attend additional natural resource briefings once per month during the bird nesting season. Natural resource briefings will be held in conjunction with the regularly scheduled safety meetings.

2. Provide all workers with photo identification badges listing the worker’s name, employer (if other than the prime contractor) and the prime contractor’s name. Refer to “EXHIBIT D - Contractor Badge Template” in the Supplemental Information.”

1.5 WORKER TRANSPORTATION TO ALCATRAZ ISLAND

A. The Contractor is responsible for parking and transportation of the construction crew to and from Alcatraz Island. Please refer to “Exhibit H – General Requirements for Contractors on Alcatraz_Feb 2020 Update.” Contractor to verify all services and pricing noted within, as they are subject to change.

B. Park Concessionaire can transport workers to Alcatraz Island via ferry service designated as "Staff Boats." Only materials that can be hand carried onto and offloaded from the ferry without multiple trips will be allowed on ferries. Park Concessionaire is not required to transport workers to Alcatraz Island except as listed below.

1. Park Concessionaire will transport workers from Alcatraz Island to San Francisco on regularly scheduled passenger ferries.

2. Notify and coordinate with Park Concessionaire when work crew size will vary from an established norm in order to ensure adequate room on passenger ferries.

C. Ferry service outside the service listed above must be arranged and paid for by Contractor and coordinated with Park Concessionaire. Do not interfere with Park Concessionaire's regular ferry schedule.

D. If Contractor provides other ferry service:

1. Coordinate with Park Concessionaire to avoid conflict with scheduled passenger ferries.

2. Coordinate with Park Concessionaire for requirements of use of government facilities managed by Concessionaire.

1.6 TRANSPORT OF MATERIALS AND EQUIPMENT TO ALCATRAZ ISLAND

A. Contractor is responsible for arranging transport and delivery of materials and equipment to and from the island. Please refer to “Exhibit H – General Requirements for Contractors on Alcatraz_Feb 2020 Update.” Contractor to verify all services and pricing noted within, as they are subject to change.

B. Alcatraz Cruises/City Experiences has the Concession Agreement with the NPS. Use of the finger pier, floating dock and/or fixed wharf, for the purposes of transporting passengers, and/or transportation or storage of equipment or supplies, must be coordinated with the NPS and its concessionaire Alcatraz Cruises.

C. Westar Marine operates a material barge that services the island using a 20 ton crane to off-load and take on material. Westar also operates a water taxi service that is used outside of Alcatraz Cruises operating hours, or if Alcatraz Cruises cannot supply a vessel.

D. Manson Construction is used for heavy lift in cases where heavy equipment is needed on the Island and it will not fit through the Sally Port. This may apply to equipment needed for the Project.

Restrictions on this service apply during bird breeding season.

E. The Golden Gate National Parks Conservancy operates a monthly barge to meet the operational needs of both the Conservancy and the NPS. Any barge activities that are arranged by the Contractor shall not interfere or conflict with this monthly barge. The Conservancy barge schedule is set in October/November of each year for the following calendar year.

1. The Conservancy will allow Contractor limited use of the monthly barge as follows:

a. Availability will be determined by the Conservancy based on availability of space, time and equipment/personnel limitations.

b. Use of Conservancy barge will be subject to "per lift" fees.

c. Coordinate use of Conservancy barge directly with the Golden Gate National Parks

Conservancy a minimum of 1 week prior to barge run.

F. Other arrangements can be made by receiving written permission from the Contracting Officer for the Concession Agreement or their Representative and filing the proper insurance papers and bonds.

G. Contacts:

1. Alcatraz Cruises/City Experiences: Aaron Warren 415.559.3126

2. Westar Marine Dispatch: 415.495.3191

3. Manson Construction: Charlie Gibson 415.279.2792

4. Golden Gate National Parks Conservancy: Patrick McAllister 415.561.4923

1.7 PUBLIC USE OF SITE

A. Alcatraz Island and its facilities, including the Dock restroom, will be open to the public during construction. Contractor shall at all times conduct operations to ensure the least inconvenience to the public and to the Government. The Library roadway (behind and to the south of the Electric Shop) can be closed periodically and pedestrians redirected, however the Contractor shall conduct operations to ensure uninterrupted SEAT shuttle service through the Sally Port entrance. SEAT is an accessible shuttle that runs twice an hour from the dock to the prison building and twice an hour from the drop off location back to the dock. Service vehicles, including the ambulance, forklift and pickup truck(s) will also need intermittent access up and down the roadway and should be coordinated with Park operations.

B. Existing Buildings

1. Partial Government Occupancy: Government will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Government during construction operations to minimize conflicts and facilitate Government usage. Perform the Work so as not to interfere with Government’s operations. Maintain existing exits, unless otherwise indicated.

a. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from the CO.

1.8 WORK RESTRICTIONS

A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 9:00 a.m. to 4:30 p.m., Monday through Friday, except when otherwise indicated.

1. Weekend Hours: No on-site work shall be performed on weekends unless approved in advance by the Contracting Officer. Weekend work is at the discretion of the Contracting Officer and may not be approved.

2. Early Morning Hours: In order to perform the dock restroom repairs without closing the restroom it may be necessary to perform work during night/early morning hours before the staff arrive at 8:30am.

3. Holiday work Restrictions: No on-site work shall be performed on national and federal holidays unless approved by the Contracting Officer.

B. Existing Utilities

1. No potable water is available on the island for construction activities such as pressure washing. Contractor to arrange with Park Concessionaire for purchase, delivery and storage of water required for the project.

2. Existing Utilities: Electricity on the island is provided by a solar photovoltaic system, with limited capacity and distribution. Coordinate with the Contracting Officer regarding activities that require site electricity. Contractor is responsible for providing all necessary electricity for the project.

3. The island does not have a telephone land line and limited cellular reception. Contractor is responsible for providing their own phone and data access.

4. Contractor shall be responsible for locating and preventing damage to known utilities. If damage occurs, repair utility at no additional expense to the Government.

5. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.

C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:

1. Notify Contracting Officer not less than two days in advance of proposed utility interruptions.

2. Do not proceed with utility interruptions without Contracting Officer’s written permission.

D. Nonsmoking Building: Smoking is not permitted anywhere on the island except the designated smoking area located on the dock.

1.9 SPECIAL CONSTRUCTION REQUIREMENTS

A. Comply with the reference document, “EXHIBIT H - General Requirements for Contractors on Alcatraz_Feb 2020 Update.” Contractor to verify all services and pricing noted within, as they are subject to change.

B. Special environmental requirements:

1. Placement, intensity and direction of nighttime lighting are subject to approval of Contracting Officer.

2. The following activities are not permitted:

a. Approaching birds

b. Disturbing or harassing birds

c. Feeding birds

d. Taking of migratory birds or their nests

C. Bird guano exists in significant quantities at most exterior areas. Take necessary precautions when working in these areas.

D. Alcatraz Island has a severe weather exposure and frequent high winds.

E. If conflicts occur between the supplemental information and drawings or specifications, the drawings and specifications govern.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 01 11 00

SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS

PART 4 - GENERAL

4.1 SUMMARY

A. The intent of this section is to explain, in general, what is and what is not included in a contract line item, and the limits or cut-off points where one item ends and another begins. Please refer to the following supplementary documents:

1. EXHIBIT A - Dock Restroom and Electric Shop Existing Conditions.

2. EXHIBIT B: Electric Shop Blocking Installation Sketch

3. EXHIBIT F - Dock Restroom plans_partial

4. EXHIBIT G - OQMG Historical Records of Buildings - AL089

If no contract line item exists for a portion of the work, include the costs in a related item.

4.2 HAZARDOUS MATERIALS AND PROTECTION

A. Include the cost of hazardous materials abatement that is necessary to conduct the work in the Contract Line Item for the related work.

B. Include protection of all existing construction to remain in the Bid Items as appropriate for Contractor’s chosen methods.

PART 5 - PRODUCTS (Not Used)

PART 6 - EXECUTION

6.1 LIST OF CONTRACT LINE ITEMS

A. Contract Line Item No.1 - Dock Restroom Roof Repairs:

1. Pressure wash entire roof to remove biological growth from roof tiles and provide a safe working environment.

2. Clean out debris at all confined rakes.

3. Clean debris on four (4) existing skylights and repair flashing as needed.

4. Repair dry rot on approx. 106 SF of 2x6 sheathing and framing material. Where unit quantity items are listed, payment shall be up to the contract price amount. For this contract, a variation in estimated quantities of unit-priced items is authorize for all unit-pried line items at the approval and direction of the CO. Should quantities exceed the contract amount a contract modification shall be required.

a. Remove and store existing tile as needed to access the repair areas.

b. Remove underlayment, repair dry rot, place new underlayment and replace concrete tile. Dispose of dry rot material in island dumpsters. NPS will provide a limited supply of spare ridge and field tiles to address breakages.

5. Borate treat all new wood installations and existing rafter and sheathing assemblies.

6. Replace approx. 155LF dry rot members and approx. 104SF of ½” lexan sheets on dock restroom water/comfort station cover.

7. Paint all exterior repairs to match surrounding, using a color determined by the CO.

8. Payment will be made at the contract lump sum price.

B. Contract Line Item No.3 - Electric Shop Roof Replacement:

1. Demo/dispose transite roof and wood shingles

2. Remove/reset existing skip sheathing to allow dry rot repair and seismic blocking installation from above.

3. Install seismic blocking.

4. Repair dry rot on 110LF of 2x6 rafters. Where unit quantity items are listed, payment shall be up to the contract price amount. For this contract, a variation in estimated quantities of unit-priced items is authorize for all unit-pried line items at the approval and direction of the CO. Should quantities exceed the contract amount a contract modification shall be required.

5. Borate treat all new wood installations and existing rafter, skip sheathing and roof plate assemblies.

6. Install new plywood sheathing panels.

7. Provide and install moisture barrier underlayment, aluminum drip edge and corrugated aluminum roof panel system to match existing in color and corrugation profile.

8. Paint drip edge to match fascia color.

9. Payment will be made at the contract lump sum price.

END OF SECTION 01 27 00

SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION

PART 7 - GENERAL

7.1 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:

1. Construction Coordination.

2. Coordination Drawings.

3. Requests for Information (RFIs).

4. Project meetings.

5. Environmental Coordination.

B. Related Requirements:

1. Section 01 3 200 “Construction Progress Documentation” for preparing and submitting Contractor’s construction schedule.

2. Section 01 73 00 “Execution” for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 “Closeout Procedures” for coordinating closeout of the Contract.

7.2 CONSTRUCTION COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.

1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.

2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.

3. Make adequate provisions to accommodate items scheduled for later installation.

4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of all components, including mechanical and electrical.

B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.

C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:

1. Preparation of Contractor's Construction Schedule.

2. Preparation of the Schedule of Values.

3. Installation and removal of temporary facilities and controls.

4. Delivery and processing of submittals.

5. Progress meetings.

6. Pre-installation conferences.

7. Project closeout activities.

8. Commissioning activities.

7.3 SUBMITTALS

A. Division 01 documents: The following items shall be submitted a minimum of one week prior to the Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for the Pre-Construction Conference.

1. Letter designating Project Superintendent.

2. Construction Schedule.

3. A comprehensive breakdown of the Schedule of Values.

4. Accident Prevention Plan.

5. A list of Subcontractors for this project.

6. Written statements from subcontractors certifying compliance with applicable labor standard clauses.

7. Satisfactory evidence of liability insurance coverage and workman’s compensation for the

Contactor and all subcontractors.

8. Waste Management Plan.

9. Quality Control Plan.

B. All items listed must be provided to the Contracting Officer before the Pre-Construction Conference is held. If all of these documents have not been received one week prior to the scheduled Pre-Construction Conference date, the conference will be cancelled, Notice to Proceed will not be issued, and the Contracting Officer will consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.

7.4 REQUESTS FOR INFORMATION (RFIs)

A. General: Immediately on discovery of the need for additional information or interpretation of the Contract Documents, Contractor shall prepare and submit an RFI utilizing the form created on the NPS/DSC SharePoint Project website.

1. CO will not respond to RFIs submitted by other entities controlled by Contractor.

2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.

B. Content of the RFI: Include a detailed, legible description of item needing information or interpretation and the following:

1. RFI number, numbered sequentially.

2. Date.

3. RFI subject.

4. Specification Section number and title and related paragraphs, as appropriate.

5. Drawing number and detail references, as appropriate.

6. Field dimensions and conditions, as appropriate.

7. Contractor's suggested resolution. If Contractor's suggested resolution impacts the

Contract Time or the Contract Sum, Contractor shall state impact in the RFI.

8. Contractor's signature.

9. Requested date for response.

10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop

Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.

a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.

C. Contracting Officer’s Action: CO will review each RFI, determine action required, and respond.

CO will determine the critical nature of each RFI and issue a response accordingly.

1. The following are not considered to be RFIs and will receive no action:

a. Requests for approval of submittals.

b. Requests for approval of substitutions.

c. Requests for approval of Contractor's means and methods.

d. Requests for coordination information already indicated in the Contract Documents.

e. Requests for adjustments in the Contract Time or the Contract Sum.

f. Requests for interpretation of Architect's actions on submittals.

g. Incomplete RFIs or inaccurately prepared RFIs.

2. CO's action may include a request for additional information, in which case time for response will date from time of receipt of additional information.

3. CO's action on RFIs may result in the need for a change to the Contract Time or the Contract Sum. All contract changes will be processed following the terms and conditions of the contract.

7.5 PROJECT MEETINGS

A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. The meeting agenda will include the following as a minimum:

1. Roles & Responsibilities/ Lines of Authority.

2. Park rules and regulations.

3. Jobsite Safety.

4. Resolution of comments on required Division 01 documents.

5. Coordination of Subcontractors.

6. Labor law application.

7. Modifications.

8. Payments to Contractor.

9. Payroll reports.

10. Contract time.

11. Liquidated damages.

12. Contractor Performance Evaluation.

13. Display of Hotline posters.

14. Notice to proceed.

15. Correspondence procedures.

16. NPS/DSC SharePoint Project website.

17. Acceptance/rejection of work.

18. Progress meetings.

19. Submittal procedures.

20. NPS Final Accessibility Inspection.

21. Environmental requirements.

22. As-constructed drawings/operation and maintenance (O&M) manuals.

23. Saturday, Sunday, holiday and night work.

24. Reference materials.

25. Value engineering.

B. Progress Meetings: The Contracting Officer will schedule weekly meetings with the Contractor.

1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented at these meetings. All participants at the meeting shall be familiar with the Project and authorized to conclude matters relating to the Work.

2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. The meeting agenda will include the following:

a. Approval of minutes of previous meetings.

b. Submittal status.

c. Review of off-site fabrication and delivery schedules.

d. Requests for information (RFI) and other issues.

e. Modifications.

f. Work in progress and projected.

1) Status of required inspections (Special Inspections, Accessibility, etc.)

g. Inspections of work in progress and projected (Special inspections,

h. Construction Schedule update (provide updated CPM).

i. Status of Project Record Drawings and O&M manuals.

j. Other business relating to work.

C. Preinstallation Conferences: Conduct a preinstallation conference at Project site before each construction activity that requires coordination with other construction.

1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by the installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend the meeting. Advise CO of scheduled meeting dates.

2. Agenda: Review progress of other construction activities and preparations for the particular activity under consideration, including requirements for the following:

a. Contract Documents.

b. Options.

c. Related RFIs.

d. Related Change Orders.

e. Purchases.

f. Deliveries.

g. Submittals.

h. Sustainable design requirements.

i. Review of mockups.

j. Possible conflicts.

k. Compatibility requirements.

l. Time schedules.

m. Weather limitations.

n. Manufacturer's written instructions.

o. Warranty requirements.

p. Compatibility of materials.

q. Acceptability of substrates.

r. Temporary facilities and controls.

s. Space and access limitations.

t. Regulations of authorities having jurisdiction.

u. Testing and inspecting requirements.

v. Installation procedures.

w. Coordination with other work.

x. Required performance results.

y. Protection of adjacent work.

z. Protection of construction and personnel.

3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.

4. Reporting: Distribute minutes of the meeting to each party present and to other parties requiring information.

5. Do not proceed with installation if the conference cannot be successfully concluded.

Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at earliest feasible date.

7.6 ENVIRONMENTAL COORDINATION

A. Contractor’s Environmental Manager: Designate an on-site party responsible for overseeing the Contractor’s conformance to environmental goals for the project and implementing procedures for environmental protection.

1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to those of this project; familiarity with Environmental Management Systems (EMSs) such as ISO 14001; must be familiar with environmental regulations applicable to construction operations.

2. Responsibilities: Responsibilities shall include:

a. Compliance with applicable Federal, State, and local environmental regulations, including maintaining required documentation.

b. Implementation of the Waste Management Plan (WMP).

c. Present an overview of environmental issues and summarize site specific procedures relating to management plans at the Preconstruction conference.

d. Training for Contractor personnel in accordance with their position requirements.

e. Monitoring and documentation of environmental procedures.

B. Perform project quality control in accordance with requirements specified in Related Sections, including:

1. Quality Requirements.

2. Regulatory Requirements.

3. Construction Waste Management.

C. Mandatory Bird Sensitivity Training

1. All personnel, including subcontractors, who will be on-site during the period of February

15 through September 15 are required to attend training.

2. Training is provided by park staff and typically lasts about 1 hour.

3. Training shall be coordinated with Contracting Officer in advance of on-site work during the period of February 15 through September 15.

PART 8 - PRODUCTS (Not Used)

PART 9 - EXECUTION (Not Used)

END OF SECTION 01 31 00

SECTION 01 32 16 – CONSTRUCTION SCHEDULE

PART 10 - GENERAL

10.1 SUMMARY

A. This Section consists of Construction Schedule requirements including but not limited to the following:

1. Schedule of Values

2. Construction Schedule Requirements.

3. Construction Schedule Updates.

4. Time Impact Analysis.

B. Purpose: The purpose of the Construction Schedule is to ensure adequate planning, coordination, scheduling, and reporting during execution of the work by the Contractor. The Construction Schedule will assist the Contractor and Contracting Officer in monitoring the progress of the work, evaluating proposed changes, and processing the Contractor's monthly progress payment.

10.2 DEFINITIONS

A. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources.

1. Critical activities are activities on the critical path. They must start and finish on the planned early start and finish times.

2. Predecessor Activity: An activity that precedes another activity in the network.

3. Successor Activity: An activity that follows another activity in the network.

B. Cost Loading: The allocation of the Schedule of Values for the completion of an activity as scheduled. The sum of costs for all activities must equal the total Contract Sum, unless otherwise approved by the Contracting Officer.

C. CPM: Critical path method, which is a method of planning and scheduling a construction project where activities are arranged based on activity relationships. Network calculations determine when activities can be performed and the critical path of Project.

D. Critical Path: The longest connected chain of interdependent activities through the network schedule that establishes the minimum overall Project duration and contains no float.

E. Float: The measure of leeway in starting and completing an activity.

1. Float: Float is not for the exclusive use or benefit of either the Government or the Contractor but is jointly owned.

2. Free float is the amount of time an activity can be delayed without adversely affecting the early start of the successor activity.

3. Total float is the measure of leeway in starting or completing an activity without adversely affecting the planned Project completion date.

10.3 SUBMITTALS

A. Construction Baseline Schedule: After contract award and before the Pre-Construction conference, submit two paper copies of baseline schedule, large enough to show entire schedule for entire construction period.

B. Construction Schedule Updates: On or before the 7th day preceding the progress payment request date, submit estimates of the percent completion of each schedule activity and necessary supporting data. Provide two paper copies.

PART 11 - PRODUCTS

11.1 CONSTRUCTION SCHEDULE REQUIREMENTS

A. Construction Baseline Schedule: Prepare Construction Baseline Schedule using a computerized, cost and resource-loaded, time-scaled CPM network analysis diagram for the Work.

1. Develop and finalize Construction Baseline Schedule so it can be accepted for use no later than 30 days after date established for the Notice of Award.

a. Failure to include any work item required for performance of this Contract shall not excuse Contractor from completing all work within applicable completion dates, regardless of Governments acceptance of the schedule.

2. Establish procedures for monitoring and updating Construction Baseline Schedule and for reporting progress. Coordinate procedures with progress meeting and payment request dates.

B. Construction Baseline Schedule Preparation: Prepare a list of all activities required to complete the Work. Using the preliminary CPM network diagram, prepare a skeleton network to identify probable critical paths.

1. Activities: Indicate the estimated duration, sequence requirements, and relationship of each activity in relation to other activities.

2. Critical Path Activities: Identify critical path activities, including those for interim completion dates. Scheduled start and completion dates shall be consistent with Contract milestone dates.

3.

Procurement Activities: Include procurement process activities for the following long lead items and major items, requiring a cycle of more than 60 calendar days, as separate activities in the schedule. Procurement cycle activities include, but are not limited to, submittals, approvals, purchasing, fabrication, and delivery.

1) Corrugated aluminum roofing.

PART 12 - EXECUTION

12.1 CONSTRUCTION SCHEDULE UPDATES

A. Progress Meeting Updates: Provide updated schedule information before each weekly progress meeting.

END OF SECTION 01 32 16

SECTION 01 33 23 - SUBMITTAL PROCEDURES

PART 13 - GENERAL

13.1 SUMMARY

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.

13.2 DEFINITIONS

A. Action Submittals: Written, graphic information, and physical samples that require Government’s responsive action.

B. Informational Submittals: Written information that does not require Government’s responsive action. Submittals may be rejected for not complying with the requirements.

C. File Transfer Protocol (FTP): Communications protocol that enables transfer of files to and from another computer over a network and that serves as the basis for standard Internet protocols. An FTP site is a portion of a network located outside of network firewalls within which internal and external users are able to access files.

D. Portable Document Format (PDF): An open standard file format licensed by Adobe Systems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.

13.3 GENERAL SUBMITTAL PROCEDURES

A. General: Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual specific sections.

1. Contracting Officer reserves the right to require submittals in addition to those called for in individual sections.

B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Review them for legibility, accuracy, completeness, and compliance with Contract Documents.

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. Contracting Officer reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

C. Submittal List: A submittal list has been attached to the end of this Specification Section. The intent is to provide an overall summary of submittal requirements and not a comprehensive list.

The requirements of the individual Specification Sections, terms and conditions of the Contract still apply regardless of what is shown on the submittal list.

D. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence when an e-mail notification is received by the Contracting Officer (or designee) indicating the submittal has been posted on the NPS SharePoint website and is ready for review. When the Contracting Officer has completed their review, an e-mail notification will be sent to the Contractor indicating the submittal has been processed. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including re-submittals.

1. Action Submittals

a. Initial Review: Allow 30 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required.

b. Re-submittal Review: Allow 30 days for review of each re-submittal.

2. Informational submittals

a. Review: Allow 10 days for review of each submittal.

E. Approved Equals:

1. For each item proposed as an “approved equal,” submit supporting data, including:

a. Drawings and samples as appropriate.

b. Comparison of the characteristics of the proposed item with that specified.

c. Changes required in other elements of the work because of the substitution.

d. Name, address, and telephone number of vendor.

e. Manufacturer’s literature regarding installation, operation, and maintenance, including schematics for electrical and hydraulic systems, lubrication requirements, and parts lists. Describe availability of maintenance service, and state source of replacement materials.

2. A request for approval constitutes a representation that Contractor:

a. Has investigated the proposed item and determined that it is equal or superior in all respects to that specified.

b. Will provide the same warranties for the proposed item as for the item specified.

c. Has determined that the proposed item is compatible with interfacing items.

d. Will coordinate the installation of an approved item and make all changes required in other elements of the work because of the substitution.

e. Waives all claims for additional expenses that may be incurred as a result of the substitution.

F. Electronic Submittals: Identify and incorporate information in each electronic submittal file as follows:

1. CM-SPE Transmittal Form: All submittals shall be transmitted using National Park Service form CM-SPE form. The form is accessed and completed on the NPS/DSC SharePoint Project website. No action will be taken on a submittal item unless accompanied by the CM-SPE transmittal form.

a. Complete the general information at the top of the form.

b. Provide all required information based on the submittal type

c. Attach all related documents.

d. Sign the CM-SPE form in the contractor section at the bottom of the form, and select “submit” when complete.

2. Physical samples: Complete the CM-SPE on the NPS/DSC SharePoint Project website as described above. Deliver the physical sample to the CO (or designee) on site for processing.

All comments and actions will be documented on the CM-SPE form on the NPS/DSC SharePoint Project website.

G. Identification: Submittal number or other unique identifier, including revision identifier.

1. Submittal number shall use a sequential number (e.g., .001). Re-submittals shall include an alphabetic suffix after another decimal point (e.g., .001.A).

H. Re-submittals: Make re-submittals using the same process used with the initial submittal.

1. Note date and content of previous submittal.

2. Note date and content of revision in the title block on the CM-16E and clearly indicate the extent of revision.

3. Re-submit submittals until they are marked “Approved” or “Approved with notations”.

I. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, and others as necessary for performance of construction activities.

J. Use for Construction: Use only final submittals with mark indicating “Approved” or “Approved with notations”. Ensure all notations have been incorporated and, at a minimum, keep one copy of the final approved submittal on site for use during construction.

PART 14 - PRODUCTS

14.1 ACTION SUBMITTALS

A. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer’s catalog cuts.

b. Manufacturer’s product specifications.

c. Manufacturer’s installation instructions: When Contract Documents require compliance with manufacturer’s printed instructions, provide one complete set of instructions to Contracting Officer and keep another complete set of instructions at the project site until substantial completion.

d. Manufacturer’s catalog cuts: Submit only pertinent pages; mark each page of standard printed data to identify specific products proposed for use.

e. Wiring diagrams showing factory-installed wiring.

f. Printed performance curves.

g. Operational range diagrams.

h. Compliance with specified referenced standards.

i. Testing by recognized testing agency.

4. Submit product data in PDF file format before or concurrent with samples.

B. Samples: Submit Samples for review of kind, color, pattern, and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.

1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.

2. Post the CM-16E on the NPS SharePoint website for processing and documentation of action on submitted samples.

3. Identification: Attach label on unexposed side of Samples that includes the following:

a. Generic description of Sample.

b. Product name and name of manufacturer.

c. Sample source.

d. Submittal Number and title of appropriate Specification Section.

4. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity. Sample sets may be used to determine final acceptance of construction associated with each set.

5. Samples for Initial Selection: Submit manufacturer’s color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.

a. Number of Samples: Submit two full set(s) of available choices where color, pattern, texture, or similar characteristics are required to be selected from manufacturer’s product line. Contracting Officer will return submittal with options selected.

6. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.

a. Number of Samples: Submit four sets of Samples. Contracting Officer will retain three Sample sets; remainder will be returned. Retain Sample set as a Project Record Sample.

C. Construction Materials: The Contractor is encouraged to submit for approval products made out of recycled or environmentally responsible material. Every effort will be made by the National Park Service to approve these materials.

14.2 INFORMATIONAL SUBMITTALS

A. General: Prepare and submit Informational Submittals required by individual Specification Sections.

1. Post informational submittals as PDF electronic files directly to the NPS SharePoint website.

2. Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification.