B08_Attachment_1_NACE-226875_Final-100_Specs-20220325.pdf
PDF 3 MB Posted
- Attached to
- NACE 226875 Oxon Cove Trail
- Solicitation number
- 140P2023R0027
About this file
This document package includes technical specifications for a federal construction project to resurface a bike trail and add a new pedestrian bridge at Oxon Cove Park in Maryland.
The project involves resurfacing segments of an existing bike trail, replacing a bridge, and adding bank stabilization, soil erosion controls, and new signage. Construction will take place both above and adjacent to a former landfill, requiring safety procedures for working in a landfill area. The specifications provide requirements for the resurfacing work, bridge construction, erosion and sediment controls, landscaping, and temporary traffic controls. Submittal requirements, construction schedules, meetings, and closeout procedures are also outlined. The document identifies a response date of March 25, 2022 and includes appendices with relevant reports on the project area. The National Park Service is listed as the contracting agency for the project.
View the file
Other files
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NATIONAL CAPITAL PARKS - EAST
OXON HILL, PRINCE GEORGE’S COUNTY,
MARYLAND
RESURFACE BIKE TRAIL & BRIDGE DESIGN AT OXON COVE
NACE PMIS NO. 226875
DIVISION 1 & TECHNICAL SPECIFICATIONS
NATIONAL PARK SERVICE (NPS)
DENVER SERVICE CENTER (DSC)
MARCH 25, 2022
CONSTRUCTION DOCUMENTS
NACE - 226875 TOC-1
TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 Summary of Work 01 26 01 Contract Modification Procedures 01 27 00 Definition of Contract Line Items 01 31 00 Project Management & Coordination 01 32 16 Construction Schedule 01 32 33 Photographic Documentation 01 33 23 Submittal Procedures 01 35 13.22 Archeological Protection 01 35 23 Safety Requirements 01 35 29 Health and Safety Plan 01 40 00 Quality Requirements 01 42 00 Reference Standards 01 50 00 Temporary Facilities and Controls 01 56 39 Temporary Tree Protection 01 57 19.12 Noise and Acoustics Management 01 57 23 Temporary Storm Water Pollution Prevention (SWPP) 01 67 00 Product Requirements 01 73 40 Execution 01 74 19 Construction Waste Management and Disposal 01 77 00 Closeout Procedures 01 81 13 Sustainable Design Requirements for Non-LEED Projects
DIVISION 02 – EXISTING CONDITIONS
02 41 00 Site Demolition
DIVISION 03 – CONCRETE
03 30 00 Cast in Place Concrete
DIVISION 05 – METALS
05 50 00 Metal Fabrications
DIVISION 31 – EARTHWORK
31 10 00 Site Clearing 31 20 00 Earth Moving 31 22 19 Topsoil 31 23 19 Dewatering 31 25 00 Erosion and Sediment Control 31 32 50 Watering 31 35 00 Slope Protection
NACE - 226875 TOC-2
DIVISION 32: EXTERIOR IMPROVEMENTS
32 12 16 Asphalt Paving 32 13 73 Concrete Paving Joint Sealants 32 15 40 Stabilized Aggregate and Stabilized Soil 32 33 00 Site Furnishings 32 91 13 Soil Preparation 32 92 19 Seeding and Mulching
DIVISION 33: UTILITY CONSTRUCTION
33 41 00 Storm Utility Drainage Piping
DIVISION 34: TRANSPORTATION
34 01 00 Maintenance of Traffic
Supporting Documents Submittal List Template (01 33 23) Project Waste Management Plan Worksheet Sample (01 74 19)
NACE 226875 01 11 00 - 1
012721 SUMMARY OF WORK
NACE 226875
SECTION 01 11 00 - SUMMARY OF WORK
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes the following:
1. Work Covered by Contract Documents
2. Government-Furnished Materials
3. Contractor Use of Site
4. Public Use of Site
5. Conduct of Operations
6. Work Restrictions
7. Special Construction Requirements
8. Soils Investigation Report
9. Additional Reports
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Location: Resurfacing a segment of the Oxon Cove Trail and addition of a new pedestrian bridge at Oxon Cove Park & Oxon Hill Farm, Prince George’s County, Maryland. The project area is divided into two segments, located north and south of Oxon Creek. Also included is a small segment of trail between the existing bridge over Oxon Creek along the Oxon Cove Trail, to Bell Acres Park located at the intersection of N Huron Drive and Mohican Drive. Reference the drawings for the exact location of the project area.
B. The Work consists of:
1. The Work associated with the trail resurfacing includes, but is not limited to; paving surface rehabilitation, full depth replacement, full or partial depth patching as necessary, bridge structure removal, new bridge and abutment walls, bank stabilization improvements, live staking, soil stabilization matting, turbidity curtain, erosion control, tree protection, removal of benches, removal of trash receptacles, removal of bollards, removal of culverts, new culverts, new bollards, new trail counters, signage and sign posts, landscape improvements and temporary traffic control as specified. Segments of the trail are located above a landfill. Reference the contract documents for the full project scope.
2. The Contractor shall be aware that the site formerly operated as a landfill and encountering waste material should be anticipated. Waste material is present and elevated levels of landfill gasses have been detected. Available reports on the waste material are included in appendices with this package. Recent boring logs included in the Geotechnical report describe the waste encountered and levels of landfill gasses detected.
3. This project is not seeking a Certification Level according to the U.S. Green Building Council's Leadership in Energy & Environmental Design (LEED) Rating System. See
NACE 226875 01 11 00 - 2
Division 01 Section "Sustainable Design Requirements for Non LEED Projects” for additional information.
C. Project will be constructed under a single prime contract.
1.3 CONTRACTOR USE OF SITE
A. General: Contractor shall have full use of the approved designated staging areas and construction areas for construction operations during the construction period. Contractor's use of the site is limited only by the Government's right to perform work or to retain other contractors on portions of Project.
Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Contractor shall coordinate construction areas and the limits of construction for Contracting Officer approval prior to the start of construction.
2. All emergency routes are to remain unobstructed at all times during construction.
3. Limit use of premises to approved project areas. Do NOT disturb the site beyond areas in which the Work is indicated.
4. Reference Section 01 35 29 “Health and Safety Plan” for required safety procedures to be taken before intrusive actions within the landfill footprint, due to the explosive nature of the subsurface landfill gas. Landfill gas to be monitored as per the Health and Safety Plan (HASP).
5. Contractor shall locate all utilities prior to construction.
6. Contractor shall perform maintenance of the designated staging areas and construction area, until final acceptance of the project. Contractor shall provide necessary equipment, materials, and personnel to perform the required maintenance activities.
7. Contractor shall pick up construction-related debris daily.
B. Storage of Materials: Confine storage of materials to staging areas shown on drawings.
1. Reference Civil plans and specifications for erosion control and stormwater management requirements.
C. Parking: Confine parking to hard surface staging areas as shown on drawings.
D. Stockpiling: Confine stockpiling to staging areas as shown on drawings.
1. Reference Civil plans and specifications for erosion control and stormwater management requirements.
E. Existing asphalt, sidewalks, curbs and gutters, landscape, structures, and improvements destroyed, damaged or removed due to construction of this project shall be replaced or restored in like kind at the contractor’s expense.
F. Preservation of Natural Features:
1. Prevent damage to natural surroundings. Restore damaged areas, repairing or replacing damaged trees and plants, at no additional expense to the Government.
2. Provide temporary barriers to protect existing trees and plants and root zones.
3. Do not remove, injure, or destroy trees or other plants without prior approval. Consult with Contracting Officer (CO) and remove agreed-on roots and branches that interfere with construction.
4. Do not fasten ropes, cables, or guys to existing trees.
5. Carefully supervise excavating, grading, filling, and other construction operations near trees to prevent damage.
NACE 226875 01 11 00 - 3
G. Although attempts have been made to locate and evaluate archaeological sites and/or components prior to construction activities, there is a potential that previously unidentified archeological sites, and components will be identified during construction activities. In the event that construction activities inadvertently discover a previously unidentified archeological site and component the contractor will work cease in the immediate area and notify the contracting officer. Any willful destruction of the archeological site and component can result in the prosecution of individuals under the Archeological Resource Protection Act of 1979 (16 U.S.C. 470), and other statutes that protect the Park’s cultural resources.
1. Reference Section 01 35 13.22 “Archeological Protection” for protection and discovery of resources procedures.
2. Any uncovered archeological resources must be protected. If archaeological resources are encountered during work, contractor shall stop work at that location immediately and notify the Contracting Officer. Any artifacts recovered are property of the Government.
H. Driveways and Entrances: Keep driveways and entrances serving premises clear and available to Government employees, and emergency vehicles at all times. Do not use for parking or storage of materials.
1. Schedule deliveries to minimize use of driveways and entrances.
2. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
I. Construction Camp: Establishment of a camp within park will not be permitted.
J. Hauling Restrictions: Comply with legal load restrictions in hauling of materials. Load restrictions on park roads are identical to state load restrictions with such additional regulations as may be imposed by the Park Superintendent. Information regarding rules and regulations for vehicular traffic on park roads may be obtained from the Office of the Park Superintendent. A special permit will not relieve Contractor of liability for damage which may result from moving of equipment.
K. Existing Bridge Restrictions: Vehicle access over the existing bridge is prohibited due to limited load bearing capacity. Bridge to be used only for pedestrian access. Contractor to provide and maintain signage or barriers to prohibit driving over the bridge.
L. Newly Installed Bridge Restrictions: Vehicle access over the new bridge is prohibited. Bridge to be used only for pedestrian access. Contractor to provide and maintain signage or barriers to prohibit driving over the bridge.
M. Access Route for the Prefabricated Bridge Components: due to limited vehicular maneuverability, delivery of large bridge members is to utilize the trail access point from the intersection of N Huron Drive and Mohican Drive, through Bell Acres Park, as shown on drawings.
Property and route conditions and surface materials are to be returned to preconstruction conditions or better, at no additional costs to the Government.
N. Landfill: Reference Section 01 35 29 “Health and Safety Plan” for required safety procedures to be taken before intrusive actions within the landfill footprint, due to the explosive nature of the subsurface landfill gas. Landfill gas to be monitored as per the Health and Safety Plan (HASP).
NACE 226875 01 11 00 - 4
1.4 PUBLIC USE OF SITE
A. The project area will be closed to the public during construction.
1.5 CONDUCT OF OPERATIONS
A. Contractor shall conduct his operations in conformance with rules and regulations promulgated by the Secretary of the Interior for the National Park Service, and applicable park rules and regulations prescribed by Park Superintendent.
B. Work on Saturdays, Sundays, Federal holidays or at night may not be performed unless stated in the Work Restrictions below or without prior consent from the Contracting Officer. Submit requests 2 business days in advance of the work to the Contracting Officer for approval.
C. No signs or advertisements (except those specified herein) shall be displayed on the construction site or within the park unless approved by the Contracting Officer.
1.6 WORK RESTRICTIONS
A. On-Site Work Hours: Work shall be generally performed during normal business working hours of 7:00 a.m. to 4:30 p.m., Monday through Friday, except when otherwise indicated.
1. Weekend Hours: are permitted upon request and approval by the Contracting Officer.
2. Early Morning Hours: are permitted upon request and approval by the Contracting
Officer.
3. Hours for noisy activity: are permitted during normal business working hours, upon request and approval by the Contracting Officer.
4. Federal holiday: work is permitted upon request and approval by the Contracting
Officer.
a. Work is not permitted on January 1st, Thanksgiving and Christmas, no exceptions.
5. No work in the event of Federal Government Closers (Weather, etc.).
6. Tree Removals: All tree removals will need to be reviewed on a case by case basis with
NPS staff. Individual trees or groupings of trees will need to be reviewed with an NPS staff biologist to determine current active nesting or roosting status. If active nesting or roosting activity is observed, additional coordination with NPS and or USFWS is necessary. Removal of trees should be completed outside of migratory bird nesting season, April 1st – August 31st.
7. Migratory Bird Treaty Act: No grubbing or cutting of nesting habitat should occur during the nesting season, generally April 1 through August 31. If that is not possible, a qualified biologist should consult with NPS and or USFWS to identify alternatives or best management practices to limit potential impacts.
B. Existing Utilities
1. Contractor shall be responsible for locating and verifying existing utilities.
2. Existing Utilities: Notify Contracting Officer and utility companies of proposed locations and times for excavation.
3. Contractor shall be responsible for locating and preventing damage to known utilities.
If damage occurs, repair utility at no additional expense to the Government.
4. If damage occurs to an unknown utility, repair utility. An equitable adjustment will be made in accordance with the Changes clause of the contract.
NACE 226875 01 11 00 - 5
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Government or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Contracting Officer not less than (2) two business days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Contracting Officer’s written permission.
3. Hours and length of Utility Shutdowns: are per approval by the Contracting Officer for no longer than 2 hours maximum in duration.
1.7 SPECIAL CONSTRUCTION REQUIREMENTS
A. Project Website: A project website administered by CMR will be used for purposes of managing communication and documents during construction stage.
1. See Section 01 31 00 "Project Management and Coordination" for requirements on using Project Website.
B. Landfill: Reference Section 01 35 29 “Health and Safety Plan” for required safety procedures to be taken before intrusive actions within the landfill footprint, due to the explosive nature of the subsurface landfill gas. Landfill gas to be monitored as per the Health and Safety Plan (HASP).
C. Tree Removals: All tree removals will need to be reviewed on a case by case basis with NPS staff.
Individual trees or groupings of trees will need to be reviewed with an NPS staff biologist to determine current active nesting or roosting status. If active nesting or roosting activity is observed, additional coordination with NPS and or USFWS is necessary. Removal of trees should be completed outside of migratory bird nesting season, April 1st – August 31st.
D. Migratory Bird Treaty Act: No grubbing or cutting of nesting habitat should occur during the nesting season, generally April 1 through August 31. If that is not possible, a qualified biologist should consult with NPS and or USFWS to identify alternatives or best management practices to limit potential impacts.
E. Wetlands/WOUS: Impacts to mapped wetlands should be avoided or minimalized to the extent possible. To limit impacts, field identify and flag/fence wetland boundary. Incorporate BMPS including silt fencing and straw wattles where appropriate to limit sedimentation in or adjacent to mapped wetlands.
F. Contractor to provide all third-party inspections and testing. Contractor to submit inspection and testing reports to the Contracting Officer.
G. Excavation and paving work may be affected seasonally. Paving subbase preparations to take place per Geotechnical report and Civil specifications.
1.8 SOILS INVESTIGATION REPORT
A. The report “Geotechnical Engineering Report Oxon Cove Trail Bridge and Trail Resurfacing”, June 9, 2021, prepared by Schnabel Engineering is available, in the appendices with this package.
NACE 226875 01 11 00 - 6
B. In case of conflict between report and drawings or specifications, the drawings and specifications govern. Contractor to present conflicts to Contracting Officer, for approval.
1.9 ADDITIONAL REPORTS
A. The report “Aquatic Resources Inventory Report”, September 22, 2021 prepared by DHM Design, is in the appendices with this package.
B. The report “Hydrology and Hydraulic Report”, September 24, 2021 prepared by WSP, is in the appendices with this package.
C. The report “Oxon Cove Multi-Use Biker Trail Environmental Assessment Report”, September 2016, prepared by NPS and Louis Berger, is in the appendices with this package.
D. In case of conflict between report and drawings or specifications, drawings and specifications govern.
Contractor to present conflicts to Contracting Officer, for approval.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 01 11 00
NACE 226875 01 26 01 - 1
012721 CONTRACT MODIFICATION PROCEDURES
NACE 226875
SECTION 01 26 01 – CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section consists of administrative and procedural requirements for contract modifications.
1.2 DEFINITIONS AND ALLOWANCES
A. Home Office Overhead: Costs incurred in support of all of a contractor’s projects and not attributable to a specific job. The cost for home office overhead is only allowed as a percentage of all direct work excluding profit. The following items represent allowable home office overhead costs identified in Part 31 of the Federal Acquisition Regulation (FAR):
1. Rent
2. Utilities
3. Furnishings
4. Office equipment
5. Executive and management staff not exclusively assigned to the project
6. Support, accounting, and administrative staff
7. Preparation of cost proposals, estimating, and schedule analyses connected with
Modifications
8. Estimating and preconstruction services
9. Mortgage costs
10. Real estate and corporate taxes
11. Automobile maintenance and travel costs for home office personnel
12. Home office insurances i.e. structure, automotive, umbrella, flood, etc.
13. Depreciation of equipment and other assets
14. Home office supplies (paper, staples, etc.)
15. Legal services
16. Accounting and data processing
17. Professional fees/registration
B. General Conditions (Field Office Overhead): Management and administrative costs incurred on site for the designated project. Costs associated with preparation of modifications will not be allowed. Costs for these items are to be included only in the general conditions of the modification estimate. Only in the case of a contract time extension are additional general conditions included in modifications. The following items, if applicable, are considered allowable costs for calculating General Conditions:
1. Project Manager (PM), Assistant Project Manager
2. Superintendent, Assistant Superintendent
3. Quality Control, Safety Officer, Environmental Manager, etc.
4. Engineers
NACE 226875 01 26 01 - 2
5. Travel, lodging, and per diem (as established by Federal Travel Regulations)
6. Scheduling
7. Field Office Trailers and associated temporary utilities
8. Field office supplies
a. Mailing and couriers
b. Reproduction costs
c. Storage
d. Phones
e. Computers
f. Copiers
9. Personal vehicles i.e. Superintendent Pickup trucks
C. General Requirements: Costs directly associated with the project and are necessary to perform the actual work of the modification. These costs shall be shown as direct costs in the estimate.
The following items, if applicable, are considered allowable costs for calculating General Requirements:
1. Hoisting
2. Material handling
3. Temporary fencing
4. Port-a-lets
5. Trash removal, dumpsters
6. Barricades
7. Small tools
8. Safety supplies
9. Scaffolding
10. Daily cleaning
11. Traffic control
12. Temporary signage
13. Temporary heating and power
D. Personnel Costs: Costs included in the modification must only be for General Conditions staff and workers actually present and working on project site. Modification costs for salaried workers are only allowed within the structure of a 40-hour week and no overtime or holiday pay will be allowed.
1. Worker Hourly Rates are costs directly associated with the individual worker and consist of the following:
a. Base Rate: The hourly rate paid directly to the worker
b. Labor Burden: Employer payments of all applicable burdens; includes insurance and taxes the business must pay on behalf of the worker to government entities and educational forums, such as:
1) Social Security
2) Medicare
3) Workers Compensation – Policy and company calculation to be made available.
4) Federal Unemployment Tax Act (FUTA) - Cap Rate and percentage to be proportionally allocated over one year.
NACE 226875 01 26 01 - 3
5) State Unemployment Tax Act (SUTA) - Cap Rate and percentage to be proportionally allocated over one year.
6) Union agreement costs - Other costs required under an enforceable collective bargaining agreement.
c. Fringe Benefits: Various non-wage compensations provided to employees such as:
1) Health Care Insurance Premiums
2) Cell Phone
3) Clothing
4) 401K and Pensions
5) Vehicle allowances
6) Gas allowance
7) Life insurance premiums
8) Disability insurance
9) Other Fringe Benefits required under an enforceable collective bargaining agreement
E. Bonuses or Deferred Compensation: No Bonus or Deferred Compensation will be allowed within any components of pricing including Home Office Overhead, General Conditions, General Requirements, Hourly Worker Rates, or the direct costs of work.
F. General Liability Insurance: An insurance policy that protects Contractor from claims resulting from bodily injury or property damage to a third party. Include as a separate line item within all modification proposals and provide a current insurance quote upon request.
G. Performance and Payment Bonds: A performance bond is a surety bond issued by an insurance company or bank to guarantee satisfactory completion of a project. The Payment Bond guarantees the Contractor will pay the labor and material costs incurred. Banks and Insurance companies charge a premium for individual project based on a sliding scale related to the size of the project.
Include as a separate line item in modification proposals and provide current company bonding rates upon request.
H. Builder’s Risk Insurance: Covers the contractor’s loss due to fire, high winds, or other natural forces. Not reimbursed by the National Park Service (NPS) and shall not be included in modification proposals.
1.3 MODIFICATION PROPOSAL PRICING REQUIREMENTS
A. General:
1. Proposal be received in the format and within the time frame specified in the Request for Proposal (RFP) letter. Costs or delays resulting from failure of contractor to submit within the time frame specified will not be compensable.
2. Proposal shall be detailed with itemized lists of equipment, materials, labor, production rates, overhead, profit, and bond markup for each item. Labor costs must be itemized by craft and hourly rate, including Fringe Benefits and Labor Burden. If the costs of Fringe Benefits and Labor Burden are not itemized, it is assumed they are included in the hourly rate shown, or contractor is not requesting reimbursement. Contractor may http://en.wikipedia.org/wiki/Employee http://en.wikipedia.org/wiki/Surety_bond http://en.wikipedia.org/wiki/Insurance http://en.wikipedia.org/wiki/Bank
NACE 226875 01 26 01 - 4
utilize the government provided Contractor Estimate Form, or their own form, provided that it contains the same information and level of detail as the Government’s form.
3. Requests for extensions of contract time as a result of change must be justified with a Time Impact Analysis (TIA). Refer to Section 01 32 16 "Construction Schedule", for time impact analysis requirements. TIA and associated costs shall be received with the proposal by the date shown within the Request for Proposal letter. Contractor’s failure to submit within the specified time frame will be construed as the Contractor waiving right for additional time and no time extension will be allowed.
4. All supporting documentation used to justify the proposed modification will be made available to the Contracting Officer (CO) upon request.
5. Contractor shall review and approve all subcontractor/supplier pricing in detail for proper format, scope, production rates, and pricing prior to submission to NPS. All delay costs associated with not reviewing and approving subcontractor/supplier pricing will be borne by the Contractor.
6. All pricing and production rates within the estimate must be based on fair and reasonable pricing and cannot include built-in contingency.
B. Labor:
1. Contractor shall estimate cost of labor by itemizing each craft involved, indicating worker hourly rate (base rate + labor burden + fringe benefits) for each and itemizing hours required for each craft directly engaged in modification work. Any work proposed requiring overtime work or premium pay shall be itemized separately. Rates shall be in accordance with the Davis-Bacon Act as incorporated herein. Labor Burden may include payroll taxes, Social Security, unemployment insurances, workers compensation insurance, Federal Insurance Contributions Act (FICA), FUTA, and other direct costs resulting from Federal, State or local laws.
2. Itemize labor costs for equipment operators separate from equipment costs.
3. Labor cost for foremen shall only be costs for related work required for the modification.
C. Materials:
1. Estimated cost for materials shall include quotes from multiple sources. Material prices shall include applicable fees and credits, including but not limited to, sales tax, freight and delivery charges, and tax rebates.
2. No markup shall be applied to any material provided by NPS.
D. Equipment:
1. Equipment used for the project must be appropriately sized for work being performed.
2. Do not include costs for "miscellaneous tools and equipment", in your proposal for a replacement value of $500 or less. Costs shown in excess of $500 shall be broken out separately.
3. Regardless of ownership, rates to be used in determining equipment rental costs shall be the lowest cost from one of the following sources:
a. United States (U.S.) Army Corps of Engineers, Ownership and Operating Expense Schedule (use latest edition and applicable region)
b. Construction Blue Book http://www.nps.gov/dscw/publicforms.htm#CP___PAGEID=396735|
NACE 226875 01 26 01 - 5
c. Local equipment rental rates, documented by actual invoice charges, or itemized vendor quotes.
4. Estimated equipment rates shall include operating costs of all fuel, oil, lubrication, supplies, small tools, necessary attachments, ground engaging components, tires and tracks, routine repairs and maintenance (cost of major repair and overhaul is not allowed per Federal Acquisition Regulation (FAR) 31.105(d)(2)), depreciation, storage, insurance, and all incidentals. Mobilization, if applicable, may be included for equipment solely used on the modification work but must be listed separately.
5. Estimate full rate for equipment only for duration that equipment will be utilized to accomplish work of the modification.
6. Standby unit rates used in accordance with paragraph 1.3, D, 2, above. If the U.S. Army Corp of Engineers is utilized then their standby rates prevail. If Bluebook or local equipment pricing is accepted, then 1/2 of equipment costs minus any operating costs, major repair and overhaul will be accepted.
7. If equipment is in standby mode due solely to a documented NPS delay, established standby rate shall apply from the first day of the delay.
8. Equipment not used and on job site for up to five consecutive days may be classified at standby rates, provided the equipment is or has been used solely to perform work on the modification and will be necessary to complete additional modification work.
Equipment still on the jobsite but not in use after five consecutive days will not be considered in the modification pricing.
9. Requests for compensation for equipment stand by time must be justified, documented and itemized separately.
10. The estimated timeframe (daily, weekly, monthly) for use of the equipment must reflect the lowest cost to the Government.
E. Establishment and Application of Overhead and Profit Percentages:
F. Home Office Overhead and Profit (OH&P) shall be applied to direct costs only. Profit shall not be applied to overhead amounts; and overhead shall not be applied to profit. Home office overhead shall contain only allowable, allocable, and reasonable costs per the contract documents and FAR Part 31. Profit percentages are based on risk factors found in FAR Part 31which have been applied to the specific type of work included in this project. Negotiated rates shall not exceed the following percentages for OH&P for contractor self-performed work:
Overhead……………… 8.00% Profit……………… 7.00%
1. Total aggregate limit of markup (OH&P) for Contractor and Subcontractors on modification work shall not exceed 25%. The NPS will not be responsible for allocation of percentages between contractor and subcontractors at any tier.
2. If Contractors form a partnership, partnership may only receive home office overhead and profit in same amount as an individual Contractor (refer to paragraph 1.3,E,1 above). It is the responsibility of the partners to decide on division of revenue.
3. Combined Increases and Decreases: On proposals involving both increases and decreases in the Contract Price, overhead and profit mark-ups are required on net increases and deducted on net decreases.
4. At no time can profit be calculated on Overhead or itself, it must be calculated on direct costs of work only.
NACE 226875 01 26 01 - 6
PART 2 - PRODUCTS
PART 3 - EXECUTION
END OF SECTION 012601
NACE 226875 01 27 00 - 1
012721 DEFINITION OF CONTRACT LINE ITEMS
NACE 226875
SECTION 01 27 00 – DEFINITION OF CONTRACT LINE ITEMS
PART 1 - GENERAL
1.1 SUMMARY
A. Section explains in general, what is and is not included in a contract line item, and limits or cut-off points where one item ends and another begins.
B. If no contract line item exists for a portion of work, include costs in a related item.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 LIST OF CONTRACT LINE ITEMS
A. Contract Line Item No. 1 Resurface Bike Trail.
1. This item consists of all Work associated with the trail resurfacing including, but not limited to; trail demolition, paving surface rehabilitation, full depth replacement, full or partial depth patching as necessary, bank stabilization improvements, live staking, soil stabilization matting, turbidity curtain, erosion control, tree protection, removal of benches, removal of trash receptacles, removal of bollards, removal of culverts, new culverts, new trail counters, signage and sign posts, landscape improvements and temporary traffic control as specified. Segments of the trail are located adjacent to and above a landfill.
Reference the contract documents for the full project scope.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract Lump Sum (LS) price.
B. Contract Line Item No. 2 Prefabricated Bridge.
1. This item consists of all Work associated with the new prefabricated bridge including, but not limited to; trail demolition, new paving surface, bridge structure removal, new bridge and abutment walls, bank stabilization improvements, soil stabilization matting, erosion control, tree protection, signage and sign posts, landscape improvements and temporary traffic control as specified. Segments of the trail are located adjacent to and above a landfill.
Reference the contract documents for the full project scope.
2. Measurement for payment will be percentage of the work completed in the previous month.
3. Payment will be made at the contract Lump Sum (LS) price.
END OF SECTION 01 27 00
NACE 226875 01 31 00 - 1
012721 PROJECT MANAGEMENT AND COORDINATION
NACE 226875
SECTION 01 31 00 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. Definitions
2. Construction Coordination
3. Submittals
4. Coordination Drawings
5. Requests for Information (RFIs)
6. Project Website
7. Project Meetings
8. Environmental Coordination
9. Permits
B. Related Requirements:
1. Section 01 32 16 "Construction Schedule" for preparing and submitting Contractor’s construction schedule.
2. Section 01 35 29 “Health and Safety Plan” for management and planning of work within landfill.
3. Section 01 73 40 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
4. Section 01 77 00 "Closeout Procedures" for coordinating closeout of the Contract.
1.2 CONSTRUCTION COORDINATION
A. Coordination: Coordinate construction operations included in different Sections of Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, which depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other Contractors to ensure maximum accessibility for required maintenance, service, and repair.
3. Make provisions to accommodate items scheduled for later installation.
4. Where availability of space is limited, coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair of components.
NACE 226875 01 31 00 - 2
5. Properly plan construction operations to include permit requirements. Allow enough time to execute permit provisions to maintain work schedule, site visits, inspections, and reporting deadlines.
B. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
C. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to:
1. Preparation of Contractor's Construction Schedule
2. Preparation of the Schedule of Values
3. Installation and removal of temporary facilities and controls
4. Delivery and processing of submittals
5. Progress meetings
6. Permit requirements
7. Pre-installation conferences
8. Project closeout activities
1.3 SUBMITTALS
A. Coordination Drawings: Prepare Coordination Drawings if limited space availability necessitates maximum utilization of space for efficient installation of different components or if coordination is required for installation of products and materials fabricated by separate entities.
1. Content: Project-specific information, drawn accurately to scale. Do not base Coordination Drawings on reproductions of Contract Documents or standard printed data. Include following information, as applicable:
a. Indicate functional and spatial relationships of components of architectural, structural and civil.
b. Indicate dimensions shown on Contract Drawings and make specific note of dimensions that appear to be in conflict with submitted products and minimum clearance requirements. Provide alternate sketches to Contracting Officer (CO) for resolution of such conflicts.
c. Indicate space requirements for routine maintenance and anticipated replacement of components during the life of the installation.
d. Indicate required installation sequences.
2. Sheet Size: At least 8-1/2 by 11 inches (215 by 280 millimeters) but no larger than 30 by 40 inches (750 by 1000 millimeters).
3. Number of Copies: Submit two opaque copies of each submittal. Contracting Officer will return one copy.
4. Refer to individual Sections for Coordination Drawing requirements for Work in those Section
NACE 226875 01 31 00 - 3
B. Coordination Drawing Organization: Organize coordination drawings as follows:
1. Slab Edge and Embedded Items: Indicate slab edge locations and sizes and locations of embedded items for metal fabrications, sleeves, anchor bolts, bearing plates, angles, curbs and similar items.
2. Review: Contracting Officer will review coordination drawings to confirm Work is being coordinated; details of coordination are Contractor's responsibility. If Contracting Officer determines coordination drawings are not prepared in scope or detail, or are otherwise deficient, Contracting Officer will inform Contractor, who shall make changes and resubmit.
3. Coordination Drawing Prints: Prepare coordination drawing prints according to requirements in Section 01 33 23 "Submittal Procedures."
C. Coordination Digital Data Files: Prepare coordination digital data files according to:
1. File Preparation Format: Same digital data software program, version, and operating system as original Drawings.
2. File Submittal Format: Submit or post coordination drawing files using Portable Document Format (PDF) file format.
3. Contracting Officer will furnish Contractor one set of digital data files (AutoCad.dwg) of Drawings for use in preparing coordination digital data files.
a. Contracting Officer makes no representations as to accuracy or completeness of digital data files as they relate to Drawings.
b. Digital Data Software Program: Drawings are available in AutoCad.dwg.
D. Division 1 documents: The following items shall be submitted a minimum of one week prior to Preconstruction Conference. Contracting Officer will notify Contractor of tentative date for Pre- Construction Conference.
1. Letter designating Project Superintendent
2. Construction Schedule
3. A Comprehensive Schedule of Values
4. Accident Prevention Plan
5. Health and Safety Plan
6. A List of Subcontractors for this project
7. Written statements from Subcontractors certifying compliance with applicable labor standard clauses.
8. Certificates of Insurance or SF1413 for Contactor and all Subcontractors
9. Waste Management Plan
10. Quality Control Plan
11. Temporary Storm Water Pollution Prevention Plan (SWPP)
12. Contractors Commissioning Plan
13. List of Required Construction Permits. Include the following information for each permit:
a. Name of Permit
b. Agency(ies) with Jurisdiction issuing the permit
c. Information required from Government to complete permit application
E. Provide items listed to Contracting Officer before Pre-Construction Conference. If all documents have not been received one week prior to scheduled Pre-Construction Conference date, conference may be cancelled, Notice to Proceed may not be issued, and Contracting Officer will
NACE 226875 01 31 00 - 4
consider other contractual remedies. Work shall not commence until written Notice to Proceed has been issued.
1.4 REQUESTS FOR INFORMATION (RFIs)
A. General: Immediately on discovery of the need for additional information or interpretation of Contract Documents, Contractor shall prepare and submit an RFI utilizing preapproved form created on CMR website. No action will be taken on an RFI unless accompanied by the RFI Form.
1. Contracting Officer will not respond to RFIs submitted by other entities controlled by Contractor.
2. Coordinate and submit RFIs in a prompt manner to avoid delays in the work.
B. Content of RFI: Include detailed, legible description of item needing information or interpretation and the following:
1. RFI number, numbered sequentially
2. Date
3. RFI subject
4. Specification Section number and title and related paragraphs, as appropriate.
5. Drawing number and detail references, as appropriate.
6. Field dimensions and conditions, as appropriate.
7. Contractor's suggested resolution: If Contractor's suggested resolution impacts Contract
Time or Contract Sum, Contractor shall state impact in RFI.
8. Contractor's signature
9. Requested date for response
10. Attachments: Include sketches, descriptions, measurements, photos, Product Data, Shop
Drawings, coordination drawings, and other information necessary to fully describe items needing interpretation.
a. Include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments on attached sketches.
C. Contracting Officer’s Action: Contracting Officer will review each RFI, determine action required, and respond. Contracting Officer will determine critical nature of each RFI and issue response accordingly.
1. The following are not considered to be RFIs and will receive no action:
a. Requests for approval of submittals.
b. Requests for approval of substitutions.
c. Requests for approval of Contractor's means and methods.
d. Requests for coordination information already indicated in Contract Documents.
e. Requests for adjustments in Contract Time or Contract Sum.
f. Requests for interpretation of Architect's actions on submittals.
g. Incomplete RFIs or inaccurately prepared RFIs.
2. Contracting Officer's action may include a request for additional information; time for response will date from time of receipt of additional information.
NACE 226875 01 31 00 - 5
3. Contracting Officer's action on RFIs may result in need for a change to Contract Time or Contract Sum. All contract changes will be processed following terms and conditions of contract.
1.5 PROJECT WEB SITE
A. Use CMR provided management software website for communication throughout contract period on:
1. Project directory
2. Project correspondence
3. Meeting agendas and minutes
4. Contract modifications forms and logs
5. RFI form and processing
6. Task and issue management
7. Photo documentation
8. Baseline schedule, schedule updates and calendar management
9. Submittal form and processing
10. Payment coordination documentation
11. Drawing and specification document hosting, viewing, and updating
12. Online document collaboration
13. Reminder and tracking functions
14. Archiving functions
15. Notification of submittal and RFI statuses and current responsible party
16. Permits and addendums
17. Health and Safety Plan
B. Some documents are not suitable to be shared using the CMR provided management software website. Documents containing Personal Identifying Information (PII) (i.e. certified payrolls) shall not be shared using CMR provided management software website and shall be coordinated with Project team as appropriate.
C. Contractor to coordinate a list of all project team members (NPS and design) and required information for website registration who will need access to the website and provide to the Government.
D. All users will be required to have the following software packages:
1. Internet Explorer version 7 or later.
2. Adobe Acrobat Professional (Pro) version 9 or later.
1.6 PROJECT MEETINGS
A. Preconstruction Conference: Before start of construction, Contracting Officer will arrange an on-site meeting with Contractor. Meeting agenda will include the following as a minimum:
1. Roles & Responsibilities / Lines of Authority
2. Park rules and regulations
3. Jobsite Safety
NACE 226875 01 31 00 - 6
4. Health and Safety Plan
5. Resolution of comments on required Division 1 documents
6. Coordination of Subcontractors
7. Labor law application
8. Modifications
9. Payments to Contractor
10. Payroll reports
11. Contract time
12. Liquidated damages
13. Contractor Performance Evaluation
14. Display of Hotline posters
15. Notice to proceed
16. Correspondence procedures
17. Project website
18. Acceptance/rejection of work
19. Progress meetings
20. Submittal procedures
21. NPS Final Accessibility Inspection
22. Environmental requirements
23. Permit requirements
24. As-constructed drawings
25. Saturday, Sunday, holiday and night work.
26. Reference materials
27. Value engineering
28. Schedule of Values
B. Progress Meetings: Contracting Officer will schedule weekly meetings with Contractor.
1. Attendees: In addition to Government Representatives, each Contractor, Subcontractor, supplier, and other entity concerned with current progress or involved in planning, coordination, or performance of future activities shall be represented. Participants at meeting shall be familiar with Project and authorized to conclude matters relating to the Work.
2. Agenda: Review and correct or approve minutes of previous progress meeting. Review other items of significance that could affect progress. Meeting agenda will include:
a. Approval of minutes of previous meetings
b. Submittal status
c. Review of off-site fabrication and delivery schedules.
d. Requests for information (RFI) and other issues.
e. Modifications
f. Work in progress and projected.
1) Status of required inspections (Special Inspections, Accessibility, etc.)
g. Inspections of work in progress and projected (Special inspections, Accessibility, etc.)
h. Construction Schedule update (provide updated Critical Path Method (CPM)).
i. Status of Project Record Drawings
j. Other business relating to work.
k. Permit requirements
l. Health and Safety Plan
NACE 226875 01 31 00 - 7
C. Preinstallation Conferences: Conduct at Project site before each construction activity that requires coordination with other construction.
1. Attendees: Installer and representatives of manufacturers and fabricators involved in or affected by installation and its coordination or integration with other materials and installations that have preceded or will follow, shall attend meeting. Advise Contracting Officer of scheduled meeting dates.
2. Agenda: Review progress of other construction activities and preparations for particular activity under consideration, including requirements for:
a. Contract Documents
b. Options
c. Related RFIs
d. Related Change Orders
e. Purchases
f. Deliveries
g. Submittals
h. Sustainable design requirements
i. Review of mockups
j. Possible conflicts
k. Compatibility requirements
l. Time schedules
m. Weather limitations
n. Manufacturer's written instructions
o. Warranty requirements
p. Compatibility of materials
q. Acceptability of substrates
r. Temporary facilities and controls
s. Space and access limitations
t. Regulations of agency(ies) with jurisdiction
u. Testing and inspecting requirements
v. Installation procedures
w. Coordination with other work
x. Required performance results
y. Protection of adjacent work
z. Protection of construction and personnel
aa. Health and Safety Plan
3. Record significant conference discussions, agreements, and disagreements, including required corrective measures and actions.
4. Reporting: Distribute minutes of meeting to each party present and to other parties requiring information.
5. Do not proceed with installation if conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of Work and reconvene conference at earliest feasible date.
NACE 226875 01 31 00 - 8
1.7 ENVIRONMENTAL COORDINATION
A. Contractor’s Environmental Manager: Designate on-site party responsible for overseeing Contractor’s conformance to environmental goals for project and implementing procedures for environmental protection.
1. Qualifications: Minimum 3 years Construction experience on projects of similar size and scope; with environmental procedures similar to this project; familiarity with Environmental Management Systems (EMSs) such as International Organization for Standardization (ISO) 14001 and familiar with environmental regulations applicable to construction operations.
2. Responsibilities: Responsibilities shall include:
a. Compliance with applicable Federal, State, and local Health and Safety Plan and environmental regulations, including maintaining required documentation and training.
b. Implementation of Waste Management Plan (WMP).
c. Implementation of Storm Water Pollution Prevention Plan (SWPPP).
d. Present overview of environmental issues and summarize site specific procedures relating to management plans at Preconstruction conference.
e. Training for Contractor personnel in accordance with position requirements.
f. Monitoring and documentation of environmental procedures.
B. Perform project quality control in accordance with requirements specified in Related Sections, including:
1. Quality Requirements
2. Regulatory Requirements
3. Noise and Acoustics Management
4. Temporary Storm Water Pollution Prevention Environnemental Management
5. Construction Waste Management
6. Hazardous Waste Management
C. Contractor’s Environmental Training Program: Contractor shall provide environmental training for workers performing work on project site. Training shall include:
1. Overview of environmental issues related to building industry.
2. Overview of environmental issues related to Project.
3. Review of site-specific procedures and management plans:
a. Construction Waste Management
b. Noise and Acoustics Management
c. Temporary Storm Water Pollution Prevention
d. Pollution Prevention (P2) practices: Submit evidence of P2 training
e. Soil and Landfill Materials Management
f. Landfill Gas Field Practices and Procedures
4. Compliance with environmental regulations: As specified in Regulatory Requirements.
Submit Contractor 40 CFR (Code of Federal Regulations) employee training records upon request of Contracting Officer.
NACE 226875 01 31 00 - 9
D. Provide documentation for environmental procedures as specified herein and in accordance with approved Waste Management Plan, and Storm Water Pollution Prevention Plan.
1.8 PERMITS
A. General:
1. Permits and Responsibilities: Contractor shall, without additional expense to the Government, be responsible for obtaining necessary licenses and permits, and for complying with Federal, State and municipal laws, codes, and regulations applicable to the performance of the work.