B08_A1_Statement_of_Work.pdf
PDF 208 KB Posted
- Attached to
- INSTALL DIRECT DIGITAL CONTROLS C-EB Federal contract opportunity
- Solicitation number
- 140A2323R0084
About this file
This statement of work outlines requirements for a direct digital control system upgrade project at Cheyenne Eagle Butte High School in Eagle Butte, South Dakota. The contractor will perform all work shown on the plan set and specifications to upgrade the school's control system within 180 calendar days of receiving notice to proceed. The related federal contract opportunity is solicitation number 140A2323R0084 to install a direct digital control system at Cheyenne Eagle Butte High School issued by the Department of the Interior Bureau of Indian Affairs Bureau of Indian Education. The solicitation is for the project defined in the statement of work, which includes upgrading the school's control system per the attached design and specification documents within the timeframe specified.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B08_A5_Health_and_Safety_Codes.pdf | ||
| B08_A10_SF-25_Performance_Bond_Form.pdf | ||
| B08_A8_IA_Form_C713_Progress_Report.pdf | ||
| B08_A6_IA_Form_3000_Material_Approval_Submittal.pdf | ||
| B08_A9_SF-1413_Statement_and_Acknowledgement_Form_(Subcontracting).pdf | ||
| B08_A2_CEB_DDC_-_Drawings.pdf | ||
| B08_A7_IA_Form_C113_Progress_Schedule_-_Copy.pdf | ||
| B08_A4_Wage_Determination_SD20230012.pdf | ||
| B08_A3_CEB_DDC_-_Specs.pdf | ||
| B08_A11_SF-25A_Payment_Bond_Form.pdf | ||
| Sol_140A2323R0084.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CHEYENNE EAGLE BUTTE BIE SCHOOL
Eagle Butte, South Dakota
Direct Digital Control System Upgrade Building 2006 Project Statement of Work
March 2023
SCOPE
The Contractor shall perform all work as shown on the plan set and in conformance with the specifications for this project. The project shall be completed in 180 calendar days from the date of the notice to proceed. All contract requirements shall be performed as indicated in the project manual.
SECTION J ATTACHMENTS
Great Plains DDC System Upgrade Design Cheyenne Eagle Butte HS Plan Set Great Plains DDC System Upgrade Design Cheyenne Eagle Butte HS Specifications
SITE MAP
| CHEYENNE EAGLE BUTTE BIE SCHOOL |
| Statement of Work |
| March 2023 |