This document contains a project experience questionnaire for a solicitation to replace the water system at Diablo East National Park. The questionnaire requests information on previous relevant projects, including project title, location, description, owner, contractors involved, original and final pricing and schedules, and responses to questions about work performed, experience elements addressed, changes to price and schedule, problems encountered and resolved, successful means and methods, and any additional information. Contractors are asked to submit information on no more than the required number of previous projects within the specified timeframes. The related federal contract opportunity is solicitation number 140P1321R0008 to replace the water system at Diablo East for the Department of the Interior National Park Service Intermountain Region.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| B09 40527268 AM01 RFP Att1 Revised Specs_0001.pdf | ||
| B09 40527268 AM01 RFP Att5 Revised Price Schedule_0001.xlsx | XLSX spreadsheet | |
| B09 40527268 AM01 RFP Att3 Revised Drawings_0001.pdf | ||
| B09 40527268 AM01 RFP Att10 RFP QA_0001.docx | DOCX document | |
| Sol_140P1321R0008_Amd_0001.pdf | ||
| B08 40527268 RFP Att5 Price Schedule.xlsx | XLSX spreadsheet | |
| B08 40527268 RFP Att4 WD TX20210090 1Jan2021.pdf | ||
| B08 40527268 RFP Att3 Drawings.pdf | ||
| B08 40527268 RFP Att2 Submittal Register.pdf | ||
| B08 40527268 RFP Att1 Specs.pdf | ||
| B08 40527268 RFP Att9 Subcontracting Percentage Worksheet.xlsx | XLSX spreadsheet | |
| Sol_140P1321R0008.pdf | ||
| B08 40527268 RFP Att8 General References.doc | DOC document | |
| B08 40527268 RFP Att7 Past Performance Questionnaire.docx | DOCX document |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Experience Questionnaire Solicitation: 140P1321R0008
Submit responses to the questions below that address experience relative to the elements noted under the Project Experience evaluation subfactor in solicitation section L. Limit submittals to the quantity of projects and timeframes required in the solicitation. Expand the response sections shown below as needed to adequately address each question (this questionnaire may be expanded to multiple pages if needed).
| Offeror |
| Company Name |
REFERENCED PROJECT INFORMATION
| Project Title |
| Title |
| Project Location |
| City, State |
| Brief Project Description |
| Description |
| Project Owner |
| Company Name |
| POC: |
| First & Last Name |
| Phone: |
| (XXX) XXX-XXXX |
CONTRACTOR LIST
List Contractor(s) whose experience on the referenced project is being submitted for evaluation on this proposed project. If more than one contractor is listed (i.e. prime and subcontractors), provide information specific to that contractor.
| Contractor Name |
| Role on Referenced Project |
(Prime or Sub)
| Trade |
| Price |
(list for each contractor’s specific work) Performance Period (calendar days) (list for each contractor’s specific work)
| Original |
| Final |
| Original |
| Final |
| Sparky’s Electrical Company |
| Prime |
| Prime |
| $XXX,XXX |
| $X,XXX,XXX |
| XX |
| XX |
| ABC Plumbing & Heating, Co |
| Subcontractor |
| Plumbing & Mechanical |
| $X,XXX,XXX |
| $X,XXX,XXX |
| XXX |
| XXX |
Subcontractor
PROJECT EXPERIENCE QUESTIONS
1. Describe the project work performed by all contractors listed above.
Response
2. Identify which Project Experience elements listed in section L of the solicitation each contractor’s work addresses.
Response
3. Describe & provide reasons for any changes to the original price for the work described in question 2 above.
Response
4. Describe and provide reasons for any changes to the original schedule for the work described in question 2 above.
Response
5. Describe problems, associated with the work described in question 2 above, which were encountered and how they were resolved. Describe how the offeror’s proposal accounts for similar issues.
Response
6. Describe the means and methods, associated with the work described in question 2 above, which were successful. Would you implement the same means and methods on the proposed project? Why or why not?
Response
7. Provide any other additional project information you believe should be presented.