This pre-solicitation notice provides details for a design-build construction project for the Gooseberry Trail in Wyoming. The Bureau of Land Management will issue a request for proposals in May 2022 seeking a contractor to design and construct a walking trail, trailhead area, and interpretive site near Worland, Wyoming between $500,000 to $1,000,000. Key requirements include designing a safe and accessible trail that preserves the visual landscape for 20 years of low-maintenance use. The trailhead must include ADA parking, gazebos, and telescopes to educate visitors. Offerors must be registered in the System for Award Management as a small business. The subsequent solicitation will specify a site visit and proposal deadline approximately 30 days following issuance.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of the Interior
BUREAU OF LAND MANAGEMENT
National Operations Center Building 50, Denver Federal Center
P.O. Box 2547 https://www.blm.gov
Pre-Solicitation Notice
6 April 2022
Solicitation Number: 140L0622R0023 Project Identification: Gooseberry Trail Design/Build Point of Contact: Nick Brazzale, Contracting Officer, nbrazzale@blm.gov Project Location: LAT/LONG-440 00’23.41”N 1080 28’29.68”W (Near Worland, WY) Magnitude of Construction: Between $500M – $1M Estimated Period of Performance: 365 calendar days after issuance of the notice to proceed North American Industry Classification System (NAICS) Code: 237990 / Other Heavy and Civil Engineering Construction Produce Service Code: Y1PA – Construction of Recreation Facilities (non-building) Small Business Size Standard: $39.5M Solicitation Set-Aside: Total Small Business – Only companies that qualify as a small business under the applicable size standard will be considered.
Solicitation Issuance Date: The BLM anticipates issuing a subsequent request for proposals (RFP) in early May 2022.
Proposal Submission Deadline: Exact date unknown at this time / 30-days after the issuance of the RFP (Phase one deadline).
Registration Requirements: Perspective offerors must have a unique entity ID (UEI) and an active System for Award Management profile with completed representations and certifications. https://sam.gov/content/home Site Visit: Yes – Approximately 1-2 weeks after the issuance of the RFP. Refer to FAR provision 52.236-27 within the subsequent solicitation.
Project Description: The subject requirement consists of all labor, materials, equipment, and supervision to design and construct a walking trail. Key project elements are as follows:
a. Design and build a safe, traversable walking trail for the public to enjoy the Gooseberry Trail Wyoming Badlands.
i. Visual Resource Management Class II Objectives and landscape preservation shall be included in all design features.
ii. Safety of visitors shall be included in all design features.
iii. Contractor shall prioritize materials that have long life cycles. The goal is for minimal maintenance for 20 years.
iv. Contractor shall prioritize sustainability and environmentally responsible products throughout the design.
b. Design and build a usable trailhead area including signage, ADA/ABA parking lot utilizing parking barriers placed around the parking lot, two gazebo covered day use picnic areas with wheelchair access free-to-use telescopes (dual head design), and interpretive area that educates the public on the geology and history of the area.
https://www.blm.gov/ https://sam.gov/content/home