This document summarizes a determination and findings for the consolidation of a federal contract opportunity. The U.S. Army Corps of Engineers, Kansas City District, has a need for construction services along the Missouri River between River Miles 360-498 to repair damage to navigation structures from the 2019 floods. The work includes repairing stone dikes and revetments and will be awarded as a 100% small business set-aside contract with a NAICS code of 237990 and size standard of $39.5 million. The estimated value of the contract is between $25-100 million. Consolidating the repair work is necessary to complete the repairs quickly and restore navigation on the river, and will provide opportunities for small businesses to participate as prime contractors or subcontractors.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DEPARTMENT OF THE ARMY

DETERMINATION AND FINDINGS

CONSOLIDATION MEMORANDUM

Fiscal Year 2019 Flood Damage Repair, Missouri River Navigation Channel Structures, Bank Stabilization and Navigation Program (BSNP)- River Miles (RM) 498-360

Infrastructure Investment and Jobs Act Funding

The Federal Acquisition Regulation (FAR) 2.101 defines “Consolidation or consolidated requirement” as follows:

“Consolidation or consolidated requirement --

(1) Means a solicitation for a single contract, a multiple-award contract, a task order (TO), or a delivery order to satisfy–

(i)Two or more requirements of the Federal agency for supplies or services that have been provided to or performed for the Federal agency under two or more separate contracts, each of which was lower in cost than the total cost of the contract for which offers are solicited; or (Services)

(ii)Requirements of the Federal agency for construction projects to be performed at two or more discrete sites. (Construction)

Consolidation of requirements with a total value exceeding $2 Million must be justified.

(2) “Separate contract” as used in this definition, means a contract that has been performed by any business, including small and other than small business concerns.”

FAR 7.107-2 requires that consolidation of requirements with an estimated total dollar value exceeding $2 million shall be supported by a written determination that consolidation is necessary and justified in accordance with 15 U.S.C. § 657q.

I have reviewed this requirement and associated market research and determined in accordance with 15 U.S.C. § 657q, FAR 2.101, and FAR 7.107-2 that consolidation is both necessary and justified. This approval is made in accordance with the approval thresholds set forth in Army Federal Acquisition Regulation Supplement (AFARS) 5107.107-2(ii), USACE UAI 5107.107-2(b)(ii)), AFARS Appendix GG, and the USACE UDG Attachment 1 Approval Matrix. My review resulted in the following findings:

FINDINGS

1. Introduction: U.S. Army Corps of Engineers (USACE), Kansas City District (NWK) plans to solicit offers for a stand-alone C-type contract for Fiscal Year 2019 flood damage repair to the Missouri River Navigation channel between river miles (RM) 498- 360 as part of the Bank Stabilization and Navigation Program (BSNP). Market research using NAICS code 237990-Other Heavy and Civil Engineering Construction, has demonstrated that consolidation of this procurement is both necessary and justified.

2. Description of Procurement Action:

a. Project Description:

NWK has a need for construction services from contractors who can construct, modify, and/or repair stone dikes and revetments on the Missouri River in support of the BSNP, Missouri River Recovery Program (MRRP), and other miscellaneous Missouri River operations, maintenance, and repair projects from RM 498-360 due to damage caused by the 2019 Flood Event.

All work is typically to be performed by floating plant. Rock is typically placed or excavated by way of track-hoe from a work barge. Tonnage on each structure will range from 500 tons up to 30,000 tons with an average tonnage per structure of 2,500 tons.

Placement rates per foot will range from 3 tons per linear foot up to 40 tons per linear foot with an average placement rate per linear foot of 6 tons per foot.

b. Procurement History:

The damage being repaired under this requirement is unique due to extensive damage to structures that control the navigation channel of the Missouri River. This damage was done during the FY 19 Flooding and caused many navigation issues during FY 20, 21 and 22. Work of this scale and urgency has not been completed before. Similar repairs on a smaller scale have been completed under small business MATOCs since approximately 2010. Those MATOCs typically have a 5-year period of performance with task orders done for various amounts for routine repairs or improvements to the navigation structures.

c. Requirements Being Consolidated:

There will be a variety of structures from multiple river miles addressed in this requirement. Below is a synopsis of what that break out will generally look like with current working estimates. The CLINS will cover the same reaches of the river, but each CLIN will have specific structures identified by surveys that are most in need of repair. The base CLIN is the highest priority requirements, with each option decreasing in priority. Work will be further detailed in supplemental bid schedules that break the work down into approximately 20 mile reaches with structure identified in each reach.

The standard repairs are typical O&M maintenance of damage from high water, which are simpler and the majority of the funding. The overlay is considered “non-routine” as they are structures with more severe damage that require additional design effort and more detailed specifications.

CLIN 0001 - Overlay Repairs

Item Start River Mile Stop River Mile

Total Tons

Approx Tons/Linear Foot

1 360 380 64,400 2-6 2 380 400 50,000 2-6 3 400 420 40,700 2-6 4 420 440 37,600 2-6 5 440 460 67,500 2-6 6 460 480 48,800 2-6 7 480 498 109,600 2-6

CLIN 0002 (Option) - Standard Repairs Item Start River Mile Stop River

Mile Total Tons

Approx Number of Structures

8 360 380 8,400 3-7 9 380 400 2,500 2-4 10 400 420 11,500 4-8 11 420 440 21,300 8-16 12 440 460 20,900 8-16 13 460 480 12,000 4-8 14 480 498 21,700 8-16 15 360 380 8,400 3-7

16 380 400 2,500 2-4 17 400 420 11,500 4-8 18 420 440 21,300 8-16 19 440 460 20,900 8-16 20 460 480 12,000 4-8 21 480 498 21,700 8-16

CLIN 0003 (Option) - Overlay Repairs Item Start River Mile Stop River

Mile Total Tons

Approx Tons/Linear Foot

22 360 380 13,000 2-6 23 380 400 13,000 2-6 24 400 420 13,000 2-6 25 420 440 13,000 2-6 26 440 460 13,000 2-6 27 460 480 13,000 2-6 28 480 498 16,000 2-6

CLIN 0004 (Option) - Standard Repairs Item Start River Mile Stop River

Mile Total Tons

Approx Number of Structures

29 360 380 9,000 6-10 30 380 400 3,000 2-4 31 400 420 9,000 6-10 32 420 440 9,000 6-10 33 440 460 9,000 6-10 34 460 480 9,000 6-10 35 480 498 9,000 6-10

e. Definition of Consolidation: §1671 of the FY13 NDAA amended the definition of consolidation as set forth in Sec 44 of the Small Business Act, 15 U.S.C. § 657q. As implemented in FAR 2.101, “consolidation” or “consolidated requirement” means a solicitation for a single contract, a multiple-award contract, a task order, or a delivery order to satisfy -- (i) Two or more requirements of the Federal agency for supplies or services that have been provided to or performed for the Federal agency under two or more separate contracts, each of which was lower in cost than the total cost of the contract for which offers are solicited; or (ii) Requirements of the Federal agency for construction projects to be performed at two or more discrete sites.

f. Applicability of Consolidation Definition: This requirement meets the definition of consolidation as stated above because there will be construction performed at two or more discrete sites on the Missouri River. There will be multiple structures within each twenty-mile range, and there will be 7 ranges between RM 360-498.

g. Rationale for Consolidation:

In order to be determined necessary and justified, the benefits of the consolidated acquisition must substantially exceed the benefits that would be derived from alternative contracting approaches that involve a lesser degree of consolidation. Such benefits may include quantifiable cost savings or price reductions as well as other benefits, regardless of whether quantifiable in dollar amounts, to include quality improvements that will save time or improve or enhance performance or efficiency, reduction in acquisition cycle time, better terms or conditions, or any other supportable benefit. Benefits that are quantifiable are considered substantial if they meet the dollar amounts set forth in FAR 7.107-2(d). If the quantifiable benefits do not meet these thresholds, the approving authority may determine that consolidation is necessary and justified if the expected benefits of the consolidated approach are critical to the agency’s mission success and the procurement strategy provides for maximum practicable participation by small business. See Section 5 analysis below for alternate contracting approaches.

For this procurement, the quantifiable benefits do meet the threshold set forth in FAR 7.107-2(d). The expected benefits of the consolidated approach are critical to the agency’s mission success and the procurement strategy provides maximum practicable participation by small business. Consolidation is necessary to meet mission objectives due to the current conditions of the Missouri River navigation control structures, as the self-scouring design of the channel is not functioning correctly. There is an urgent need to complete this work as quickly as possible and without delay to restore as many structures as needed to ensure navigation can continue with minimal risk and impedances. The current condition of the structures led to widespread shoaling and disruption of the navigation industry and the cargo shipments going up and down the river. It is crucial that this work be completed in a coordinated manner to ensure flood damage is repaired as quickly as possible. It is anticipated that small businesses will have opportunities to participate either as prime contractors or subcontractors. This is assuming they have the ability to bond to this level of effort.

Consolidating this workload will also mitigate in-house administration. The large amount of work being funded by the Infrastructure and Investment Job Act (IIJA) will require a much greater effort to administer than NWK has dealt with in over 15 years. NWK does not have enough personnel for USACE oversight needed if all these projects were to be awarded as multiple stand-alone contracts and were active at the same time. If these requirements were to be spread out to alleviate the oversight problem, the amount of administrative actions (post-award documents, scheduling, RFIs, modifications, etc) to coordinate with multiple contractors would be overwhelming and would affect the necessary period of performance for this requirement.

e. Impacts of Consolidation on Small Business: This acquisition is planned as a 100% small business set aside procurement. Therefore, any small business with this capability, and who meets the solicitation requirements, can submit a bid for this requirement.

a. Definition. FAR 2.101 defines “bundling” as consolidating two or more requirements for supplies or services, previously provided, or performed under separate smaller contracts, into a solicitation for a single contract that is likely to be unsuitable for award to a small business concern due to:

(i) The diversity, size, or specialized nature of the elements of the performance specified;

(ii) The aggregate dollar value of the anticipated award;

(iii)The geographical dispersion of the contract performance sites: or

(iv) Any combination of the factors described in paragraphs (i) through (iii) of this definition.

b. Applicability of FAR Bundling Definition. This acquisition does not meet the definition of bundling. The damage repair being completed under this requirement is unique and the result of the extreme flooding experienced in FY 2019. Therefore, the work being done for these repairs has not been previously performed under separate smaller contracts. It is unique situation that has created unprecedented impacts to the navigation channel.

c. The Competition in Contracting Act (CICA) Bundling Principle.

(i) Definition: Competition in Contract Act (CICA) Bundling. The CICA Bundling Principle, as developed by the Government Accountability Office (GAO) case law, focuses on whether the combined requirement (new, old, or otherwise) restricts competition, and whether the agency is consolidating or bundling a new requirement unnecessarily. In order to justify CICA Bundling the agency must show "a reasonable basis for why the bundling is necessary to meet the agency need." (Vantex Serv., Inc., B-29041 5, Aug. 8, 2002 and Outdoor Venture Corp., B-299675; B-299676, Jul. 19, 2007).

(ii) Applicability of CICA Bundling Principle. The combination of requirements into a single contract does not restrict competition under the CICA bundling principle. All the tasks involved are in support of NWK and can be performed by firms classified under the same NAICS codes.

7. Considerations, facts, and reasoning supporting the determination:

All facts, considerations and rationale have been covered previously in the findings.

The DD2579 has been signed by the Contracting Officer, Deputy for Small Business, and SBA Procurement Center Representative. All concur that consolidation of this requirement is both necessary and justified.

8. Summary:

Consolidation of this portion of the FY 19 Flood damage repair, under a SB set-aside, single stand-alone contract is in the best interest of the government with regard to mission, time, and cost. The findings of the market research and the documentation provided support the conclusion that consolidation of requirement is both necessary and justified, based on sound business judgement.

DETERMINATION

Based upon the basis of the findings above and with the concurrence of the SBA, I hereby determine, pursuant to the authority of FAR 7.107-2, 15 USC § 657q, and Army Federal Acquisition Regulation Supplement 5107.107-2(ii), that the proposed consolidation of the requirements for Bank Stabilization and Navigation, FY19 Flood Damage Repair, Missouri River Navigation Channel Structures (RM 360-498), is both necessary and justified.