B.01.02_CHK008_Chignik__BID_ABSTRACT1.pdf
PDF 118 KB Posted
- Solicitation number
- W911KB-17-B-0003
About this file
Bid Abstract
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
For Official Use Only
2. DATE ISSUED 3. DATE OPENED PAGE OF PAGES
14-Jul-2017 22-Aug-2017 1 of 3
DATE SIGNED
ITEM
NO.
EST.
QUANTITY UNIT
UNIT
PRICE
ESTIMATED
AMOUNT
UNIT
PRICE AMOUNT UNIT
PRICE AMOUNT
0001 Mobilization and Demobilization, complete. 1 JOB $950,000.00 $950,000.00 $1,600,000.00 $1,600,000.00 $3,000,000.00 $3,000,000.00
Construct South Breakwater Armor Rock Layer STA 35+00 to STA 39+50, Section E, complete
6,700 TON $210.00 $1,407,000.00 $110.00 $737,000.00 $425.00 $2,847,500.00
Construct North Breakwater Armor Rock Layer STA 17+00 to STA 20+03 and North Breakwater Head, Sections A,B & D, complete.
9,500 TON $210.00 $1,995,000.00 $110.00 $1,045,000.00 $425.00 $4,037,500.00
0004 Post-Construction Survey, complete 1 JOB $15,900.00 $15,900.00 $50,000.00 $50,000.00 $110,000.00 $110,000.00 Total of Base Items $4,367,900.00 $3,432,000.00 $9,995,000.00
Construct South Breakwater Armor Rock Layer STA 39+50 to STA 41+80 Section E, complete.
4,700.00 TON $210.00 $987,000.00 $110.00 $517,000.00 $112.00 $526,400.00
Construct South Breakwater Armor Rock Layer STA 41+80 to STA 42+80 and South Breakwater Head Section F, complete.
6,000.00 TON $211.00 $1,266,000.00 $110.00 $660,000.00 $112.00 $672,000.00
Construct North Breakwater Armor Rock Layer STA 17+00 to STA 19+83 Section C, complete.
5,500.00 TON $210.00 $1,155,000.00 $110.00 $605,000.00 $112.00 $616,000.00
Additional Armor Rock To Be Placed As Directed, complete (see Note 3). 1,000.00 TON $254.00 $254,000.00 $110.00 $110,000.00 $112.00 $112,000.00
Total of Option Items $3,662,000.00 $1,892,000.00 $1,926,400.00
Total of Base and Options $8,029,900.00 $5,324,000.00 $11,921,400.00
To be Determined YES YES
C. AMENDEMENTS ACKNOWLEDGED
YES
Christine Dale, Contracting Officer
C. AMENDEMENTS ACKNOWLEDGED
No. 01 Chignik Harbor Breakwater Repairs, Chignik, Alaska
SIGNATURE
9. OFFERS
8. GOVERNMENT ESTIMATE
(Check A, B, C and complete D, E, and F)
No. 02
B. BID SECURTIY (TYPE AND AMOUNT)B. BID SECURTIY (TYPE AND AMOUNT)
YES
6. NUMBER OF AMENDMENTS ISSUED - 2
W911KB-17-B-0003
ABSTRACT OF OFFERS - CONSTRUCTION
4. ISSUING OFFICE
5. PROJECT TITLE
1. SOLICITATION NUMBER
U.S. Army Engineer District, Alaska PO Box 6898
JBER, AK 99506-6898
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
7. NAME AND TITLE OF CERTIFYING OFFICIAL (TYPED)
Western Marine Construction
A. OFFEROR
Trade West Construction
A. OFFEROR
29 Aug 17
For Official Use Only
2. DATE ISSUED 3. DATE OPENED PAGE OF PAGES
14-Jul-2017 17-Aug-2017 2 of 3
DATE SIGNED
ITEM
NO.
EST.
QUANTITY UNIT
UNIT
PRICE AMOUNT UNIT
PRICE AMOUNT UNIT
PRICE AMOUNT
0001 Mobilization and Demobilization, complete. 1 JOB $1,007,399.00 $1,007,399.00 $1,800,000.00 $1,800,000.00 $1,184,000.00 $1,184,000.00
Construct South Breakwater Armor Rock Layer STA 35+00 to STA 39+50, Section E, complete
6,700 TON $274.00 $1,835,800.00 $280.00 $1,876,000.00 $162.00 $1,085,400.00
Construct North Breakwater Armor Rock Layer STA 17+00 to STA 20+03 and North Breakwater Head, Sections A,B & D, complete.
9,500 TON $236.00 $2,242,000.00 $280.00 $2,660,000.00 $162.00 $1,539,000.00
0004 Post-Construction Survey, complete 1 JOB $16,750.00 $16,750.00 $46,000.00 $46,000.00 $28,000.00 $28,000.00 Total of Base Items $5,101,949.00 $6,382,000.00 $3,836,400.00
Construct South Breakwater Armor Rock Layer STA 39+50 to STA 41+80 Section E, complete.
4,700.00 TON $175.00 $822,500.00 $254.00 $1,193,800.00 $154.00 $723,800.00
Construct South Breakwater Armor Rock Layer STA 41+80 to STA 42+80 and South Breakwater Head Section F, complete.
6,000.00 TON $170.00 $1,020,000.00 $254.00 $1,524,000.00 $140.00 $840,000.00
Construct North Breakwater Armor Rock Layer STA 17+00 to STA 19+83 Section C, complete.
5,500.00 TON $170.00 $935,000.00 $254.00 $1,397,000.00 $149.00 $819,500.00
Additional Armor Rock To Be Placed As Directed, complete (see Note 3). 1,000.00 TON $285.00 $285,000.00 $300.00 $300,000.00 $222.00 $222,000.00
Total of Option Items $3,062,500.00 $4,414,800.00 $2,605,300.00 Total of Base and Options $8,164,449.00 $10,796,800.00 $6,441,700.00
To be Determined YES
Chignik Harbor Breakwater Repairs, Chignik, Alaska A. OFFEROR
YES
6. NUMBER OF AMENDMENTS ISSUED - 2
Heko Services Inc.
YES
B. BID SECURTIY (TYPE AND AMOUNT)
C. AMENDEMENTS ACKNOWLEDGED
YES
B. BID SECURTIY (TYPE AND AMOUNT) B. BID SECURTIY (TYPE AND AMOUNT)
YES YES
C. AMENDEMENTS ACKNOWLEDGED C. AMENDEMENTS ACKNOWLEDGED
7. NAME AND TITLE OF CERTIFYING OFFICIAL (TYPED)
U.S. Army Engineer District, Alaska PO Box 6898
JBER, AK 99506-6898
Christine Dale, Contracting Officer
SIGNATURE
I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.
9. OFFERS
ABSTRACT OF OFFERS - CONSTRUCTION
1. SOLICITATION NUMBER
W911KB-17-B-0003
4. ISSUING OFFICE
No. 035. PROJECT TITLE No. 05
Alaska Aggregate Products
A. OFFERORA. OFFEROR
Brice Construction
No. 04
Solicitation Number W911KB-17-B-0003 Project Title Chignik Harbor Breakwater Repair, Chignik, Alaska Date Issued 7/14/2017 Date Opened 8/22/2017
Offeror Total Base + Options No. 01 $5,324,000.00 No. 02 $11,921,400.00 No. 03 $8,164,449.00 No. 04 $10,796,800.00 No. 05 $6,441,700.00 No. 06 $0.00 No. 07 $0.00 No. 08 $0.00
*Remove lines above based on number of bids received **Low bidder cell will automatically highlight green
| B.01.02 CHK008 Chignik BID ABSTRACT.pdf |
| IGE & Offerors 1-2 |
| B.01.02 CHK008 Chignik BID ABSTRACT.pdf |
| Offerors 3-5 |
| 2017-09-06T09:34:39-0800 | |
| DALE.CHRISTINE.A.1101149478 |
File details come from the government source that posted it. Updated .