Attch1_SOW_ConstructNewCanopyForExistingE-BankRaceway.pdf

PDF 155 KB Posted

Attached to
AZ-WILLIAMS CRK NFH-CANOPY Federal contract opportunity
Solicitation number
140FC124Q0033
Issued by
Department of the Interior Fish and Wildlife Service

About this file

This document is a Statement of Work for the construction of a prefabricated pitched roof steel structure to serve as a canopy for an existing aquatic raceway at the Alchesay National Fish Hatchery in Whiteriver, Arizona.

The key requirements include: a minimum 14-gauge galvanized steel frame, minimum 29-gauge steel roof panels, a minimum 3:12 roof slope, a 50 PSF snow load, a 90 MPH wind load, and a minimum 25-year warranty. The structure must be designed and installed by the manufacturer. A site visit is strongly encouraged prior to submitting proposals. The project contact is Craig Thomas, Project Leader at the Alchesay and Williams Creek National Fish Hatcheries. The related federal contract opportunity has a solicitation number of 140FC124Q0033 and a description of "AZ-WILLIAMS CRK NFH-CANOPY". Interested contractors are instructed to submit requests for information and quotes to Nicole Johnson via email.

View the file

Other files for this federal contract opportunity

Other files attached to AZ-WILLIAMS CRK NFH-CANOPY, newest first.
File Type Posted
Sol_140FC124Q0033_Amd_0003.pdf PDF
Amend3_3-0019_NoticeToOfferors_0003.pdf PDF
Sol_140FC124Q0033_Amd_0002.pdf PDF
Amend2_140FC124Q0033_Q-A_0002.pdf PDF
Sol_140FC124Q0033_Amd_0001.pdf PDF
Amend1_TermsConditionsUpdated_AZ-WmCrkNFH_Structure_42pp_0001.pdf PDF
Amend1_Attach3_BidSchedule_0001.docx DOCX document
140FC124Q0033_TC_AZ-WmCrkNFH_Structure_42pp.pdf PDF
Attach4_SiteVisitInformation.pdf PDF
Attch2_SitePhoto_EbankRaceways_10008672.jpg JPG image
Sol_140FC124Q0033.pdf PDF
3-0019_Notice_to_Offerors.pdf PDF
Attach3_BidSchedule.docx DOCX document
Attch5_WD_AZ20240027v3_240719_7pp.pdf PDF
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

E-Bank Steel Building Structure Alchesay National Fish Hatchery 36802 North Alchesay NFH Road

Whiteriver AZ, 85941 June, 2024

FACILITY SUMMARY:

Alchesay National Fish Hatchery was authorized in 1959 with a Memorandum of Understanding between the U.S. Fish and Wildlife Service and the Bureau of Indian Affairs.

Alchesay National Fish hatchery was designed to fulfill a federal responsibility for stocking waters on Tribal lands throughout eastern Arizona and western New Mexico. Alchesay National Fish Hatchery serves as a "grow-out rearing unit" for brown trout and rainbow trout fingerlings transferred from Williams Creek national Fish Hatchery. The annual production of these trout species represents the largest Indian Trust, inland recreational fishing program in the National Fish Hatchery System.

FACILITY NEED:

The facility has an existing exterior aquatic raceway, referred to as “E-Bank”, that measures approximately 54’ W x 110’ L, that is in need of a prefabricated pitched roof steel structure that is open on all four sides. Will function as canopy for the existing raceways. See Exhibit A:

Concept Image.

MINIMUM PROJECT REQUIREMENTS/SPECIFICATIONS:

1. Structure Design: The structures design drawings, shall be designed and stamped by a licensed structural engineer. Drawings shall include at a minimum, the concrete footing/stem wall or concrete piers design, and all steel structural components such as columns, roof trusses, beams and purlins.

2. Steel Frame: Minimum 14-gauge galvanized steel.

3. Roof panels: Minimum 29-gauge steel. Panel width minimum 3 feet.

4. Snow Load: The structure design must meet a minimum 50 PSF snow load.

5. Wind Load: The structure design must meet a minimum 90 MPH wind load.

6. Roof Slope: Minimum 3:12.

7. Roof Color: A standard color TBD by Hatchery staff at pre-construction meeting.

8. Structure Installation: To be included and performed by metal building manufacture.

9. Warranty: Minimum 25 year.

Prior to submitting a proposal, government strongly suggests contractors conduct a site visit to assess existing conditions and take field measurements. Upon completion of project, and before staff final inspection, contractor to clean entire site of all project waste and debris.

PROJECT CONTACT: Craig Thomas Project Leader Alchesay & Williams Cr. National Fish Hatchery's Mobile: 509-433-4869

UPS/FedEX Shipping Address Alchesay NFH 8602 N Alchesay NFH RD Whiteriver, AZ 85941

Exhibit A: Concept Image

FACILITY SUMMARY:
Alchesay National Fish Hatchery was authorized in 1959 with a Memorandum of Understanding between the U.S. Fish and Wildlife Service and the Bureau of Indian Affairs. Alchesay National Fish hatchery was designed to fulfill a federal responsibility for...
FACILITY NEED:
MINIMUM PROJECT REQUIREMENTS/SPECIFICATIONS:
PROJECT CONTACT:

File details come from the government source that posted it. Updated .