This document is a Statement of Work for the construction of a prefabricated pitched roof steel structure to serve as a canopy for an existing aquatic raceway at the Alchesay National Fish Hatchery in Whiteriver, Arizona.
The key requirements include: a minimum 14-gauge galvanized steel frame, minimum 29-gauge steel roof panels, a minimum 3:12 roof slope, a 50 PSF snow load, a 90 MPH wind load, and a minimum 25-year warranty. The structure must be designed and installed by the manufacturer. A site visit is strongly encouraged prior to submitting proposals. The project contact is Craig Thomas, Project Leader at the Alchesay and Williams Creek National Fish Hatcheries. The related federal contract opportunity has a solicitation number of 140FC124Q0033 and a description of "AZ-WILLIAMS CRK NFH-CANOPY". Interested contractors are instructed to submit requests for information and quotes to Nicole Johnson via email.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Sol_140FC124Q0033_Amd_0003.pdf | ||
| Amend3_3-0019_NoticeToOfferors_0003.pdf | ||
| Sol_140FC124Q0033_Amd_0002.pdf | ||
| Amend2_140FC124Q0033_Q-A_0002.pdf | ||
| Sol_140FC124Q0033_Amd_0001.pdf | ||
| Amend1_TermsConditionsUpdated_AZ-WmCrkNFH_Structure_42pp_0001.pdf | ||
| Amend1_Attach3_BidSchedule_0001.docx | DOCX document | |
| 140FC124Q0033_TC_AZ-WmCrkNFH_Structure_42pp.pdf | ||
| Attach4_SiteVisitInformation.pdf | ||
| Attch2_SitePhoto_EbankRaceways_10008672.jpg | JPG image | |
| Sol_140FC124Q0033.pdf | ||
| 3-0019_Notice_to_Offerors.pdf | ||
| Attach3_BidSchedule.docx | DOCX document | |
| Attch5_WD_AZ20240027v3_240719_7pp.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
E-Bank Steel Building Structure Alchesay National Fish Hatchery 36802 North Alchesay NFH Road
Whiteriver AZ, 85941 June, 2024
FACILITY SUMMARY:
Alchesay National Fish Hatchery was authorized in 1959 with a Memorandum of Understanding between the U.S. Fish and Wildlife Service and the Bureau of Indian Affairs.
Alchesay National Fish hatchery was designed to fulfill a federal responsibility for stocking waters on Tribal lands throughout eastern Arizona and western New Mexico. Alchesay National Fish Hatchery serves as a "grow-out rearing unit" for brown trout and rainbow trout fingerlings transferred from Williams Creek national Fish Hatchery. The annual production of these trout species represents the largest Indian Trust, inland recreational fishing program in the National Fish Hatchery System.
FACILITY NEED:
The facility has an existing exterior aquatic raceway, referred to as “E-Bank”, that measures approximately 54’ W x 110’ L, that is in need of a prefabricated pitched roof steel structure that is open on all four sides. Will function as canopy for the existing raceways. See Exhibit A:
Concept Image.
MINIMUM PROJECT REQUIREMENTS/SPECIFICATIONS:
1. Structure Design: The structures design drawings, shall be designed and stamped by a licensed structural engineer. Drawings shall include at a minimum, the concrete footing/stem wall or concrete piers design, and all steel structural components such as columns, roof trusses, beams and purlins.
2. Steel Frame: Minimum 14-gauge galvanized steel.
3. Roof panels: Minimum 29-gauge steel. Panel width minimum 3 feet.
4. Snow Load: The structure design must meet a minimum 50 PSF snow load.
5. Wind Load: The structure design must meet a minimum 90 MPH wind load.
6. Roof Slope: Minimum 3:12.
7. Roof Color: A standard color TBD by Hatchery staff at pre-construction meeting.
8. Structure Installation: To be included and performed by metal building manufacture.
9. Warranty: Minimum 25 year.
Prior to submitting a proposal, government strongly suggests contractors conduct a site visit to assess existing conditions and take field measurements. Upon completion of project, and before staff final inspection, contractor to clean entire site of all project waste and debris.
PROJECT CONTACT: Craig Thomas Project Leader Alchesay & Williams Cr. National Fish Hatchery's Mobile: 509-433-4869
UPS/FedEX Shipping Address Alchesay NFH 8602 N Alchesay NFH RD Whiteriver, AZ 85941
Exhibit A: Concept Image
| FACILITY SUMMARY: |
| Alchesay National Fish Hatchery was authorized in 1959 with a Memorandum of Understanding between the U.S. Fish and Wildlife Service and the Bureau of Indian Affairs. Alchesay National Fish hatchery was designed to fulfill a federal responsibility for... |
| FACILITY NEED: |
| MINIMUM PROJECT REQUIREMENTS/SPECIFICATIONS: |
| PROJECT CONTACT: |