Attch 1_CDC Cpt Repl_SOO_20201217.docx
DOCX document 39 KB Posted
- Attached to
- Child Development Center Carpet Replacement, VAFB Federal contract opportunity
- Solicitation number
- FA4610-21-Q-0010
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA4610-21-Q-0010_Question and Response.docx | DOCX document | |
| Solicitation Amendment FA461021Q00100003 SF 30.pdf | ||
| Atch4_SCA WD 15-5648 Rev 11_20200828.pdf | ||
| Solicitation Amendment FA461021Q00100002 SF 30.pdf | ||
| Solicitation Amendment FA461021Q00100001 SF 30.pdf | ||
| Attch 1_CDC Cpt Repl_SOO_20201217v2.docx | DOCX document | |
| Attch 3_CDC Cpt Repl_Floor Plan.pdf | ||
| Solicitation - FA461021Q0010.pdf | ||
| Attch 2_CDC Cpt Repl_Salient Char_202011217.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Objectives Remove/Replace Shock Abosrbing Carpet System B16177, Child Development Center Vandenberg AFB, CA
Background: This purchase shall include the installation of shock absorbing carpet at Building 16177,Child Development Center, in the following 14 rooms (see attached floor plan for additional information):
| Rm 110 | Rm 111 | Rm 112 | Rm 114 |
| Rm 115 | Rm 116 | Rm 117 |
Rm 204 Rm 205 Rm 206
Rm 304 Rm 305 Rm 306 Rm 307
This effort will be phased with only three adjacent rooms available for work at any time. Area of work and adjacent building will be occupied during carpet replacement. Contractor shall coordinate all work to be performed with the 30 CES POC and CDC facility manager to ensure minimal disruption to building occupants.
Furniture Moving/Lifting: Contractor shall not be responsible to lift and/or move any existing furniture or equipment as described to remove and install flooring. Building occupants will be responsible to remove all items to include personal items, files, books, binders, computers, monitors and all electrical equipment from the room prior to contractor’s arrival.
Flooring Removal: Contractor shall be responsible to remove all existing shock absorbing carpet system flooring as indicated on the plans and to replace all shock absorbing carpet systems. All removed flooring shall be recycled at an appropriate recycling facility. Contractor shall report quantities and recycling facility used for recycling at end of the job to the 30 CES POC noted above for state reporting requirements.
Subfloor Preparation: Removal and cleanup of subfloor shall be adequate to allow installation of new shock absorbing carpet system flooring to the manufacturer’s specifications. Do not install carpet on surfaces that are unsuitable and will prevent a proper installation. Prepare subfloor in accordance with flooring/padding manufacturer’s recommended instructions. Repair holes, cracks, depressions or rough areas using a material recommended by the carpet or adhesive manufacturer. Free floor of any foreign materials and sweep clean prior to installation.
Once subfloor is clean, concrete subfloor shall be moisture sealed using a moisture mitigation product with the following characteristics:
· Zero VOC’s (0.0 g/l) and LEED compliant (LEED v2009 IEQ Credit 4.1)
· Single component (no mixing required)
· Blocks moisture up to 99% relative humidity, 20 lbs. Moisture Vapor Emissions Rate (MVER)
· Compliant with ASTM E96 – Permeance Rate (< 0.4 gr/hr/sf)
Materials: Proposed product shall meet all requirements in Attachment 1, Shock Absorbing Carpet System Salient Characteristics. Carpet color shall be selected after award but in general shall be a blue/brown tweed. Contractor shall fully and clearly demonstrate compliance with all of the minimum required specifications/characteristics.
Contractor shall also provide all rubber transitions as needed to transition between the existing floor to remain and the newly installed carpet, neutral, coordinating color to be selected after award. If existing rubber base currently installed on adjacent walls needs to be replaced, contractor shall be responsible to replace, coordinating color to be selected after award.
The contractor shall be responsible for any storage of all new flooring, components, parts and assemblies prior to and during installation in accordance with the agreed upon delivery schedule.
Services shall include removal and/or disposal of all excess product and transport to the Air Force approved warehouse or other location as specified.
Quantities: The contractor shall be responsible for measuring and confirming all quantities prior to bidding project. The following quantity is provided for information only:
465 SY carpet with pad 500 LF rubber transition 500 LF rubber base, 4” minimum height with wall repair as needed or 6” with wall repair as needed
Testing: Compliance with ASTM F1292 and ASTM F2373 with a critical fall height of three (3) feet shall be demonstrated through testing of two (2) Government selected locations by a Certified Playground Safety Inspector/Certified Impact Testing Consultant, as indicated in the ASTM standards.
General Services: Coordination and management of all new product, equipment and people required to create, deliver and install flooring within an Air Force location. This includes ongoing servicing of any items defective due to manufacturing error as well as for replacement or repair of any damaged item after purchase.
The contractor shall be responsible for all personnel, equipment, tools, materials, supervision, storage, assembly, transportation, incidentals and all other items and services necessary to provide and install flooring.
The vendor shall manage ordering, shipment, delivery and installation of all new carpet from manufacturer to final acceptance by the designated Government Acceptor.
The contractor shall provide customer service during normal duty hours, 0730-1630 hours, Monday through Friday; except for federal holidays or when the Government facility is closed due to local/national emergencies, administrative closings or similar Government directed facility closings.
Recognized US Federal Holidays are as follows: New Year’s Day, Martin Luther King Day, Presidents Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving and Christmas. If the holiday falls on a Saturday, it is observed on Friday. If the holiday falls on Sunday, it is observed on Monday.
When the contractor desires to work other than standard times, a written request shall be submitted to the Government Acceptor for approval. Written approval from the Contracting Officer must be received before proceeding with the work. The request shall be submitted at least five (5) work days prior to the proposed performance of work, and it shall indicate the day/days, time/amount of work, and reason why performance is necessary during nonstandard hours.
Site Conditions: Threat condition level of the base is Bravo. This requires contractor personnel to get base access in order to complete the product installation. Standard site conditions shall be considered those that include:
· Free and clear hard surface access to the receiving and installation location during regular working hours.
· A staging area adequate to sort, stage and uncrate/unpack products.
· Includes electric power, working lights, heating and air conditioning.
· A building ready for the installation of flooring as described above.
Contractor shall notify the Contracting Officer of any deviations from the above standards, as well as any requests for equitable adjustment to the contract price.
Base Specifics: All commercial trucks must enter through Lompoc Gate Vehicle Inspection Station, which is located at the intersection of Santa Lucia Canyon Road and Washington Avenue south of Highway 1 for inspection. In accordance with the Installation policies, base entry procedures must adhere to delivery vehicle process requirements mandated by the Wing. Once at Lompoc Gate, the driver must have a current base pass from Bldg. 17595, Visitor Control Center located at the Santa Maria Gate and be able to show:
· Current Vehicle Registration
· Current Proof of Insurance
· Valid and current Driver's License for the driver
· Valid and current Driver's License or other State Identification for any passenger(s) in the vehicle.
Lost vehicle and entry passes shall be reported immediately to the Security Police as well as the Government Acceptor in accordance with the local security forces policy.
Gate Procedures: Once at Lompoc Gate Vehicle Inspection Station, be prepared to exit the vehicle and allow for vehicle inspection. At this time you may ask for directions to your final destination.
If the final destination requires the driver to leave Lompoc Gate, and re-enter the base through an alternate gate, the pass received will be sufficient documentation for entry into both gates, within a pre-established time directed by the Security Forces representative.
Arrival at the appropriate gate after the designated allotted time will result in non-admittance to the installation.
This procedure will occur each time a commercial truck requests access to the base.
Current Bill of Lading (BOL) to get delivery driver and the vehicle on base. BOL must include the AF installation name, date of anticipated delivery, and specific destination (including building number, street address, and point of contact information to include office telephone number).
Personnel should the following items when entering an installation:
· Current Registration for all vehicles
· Current Proof of Insurance for all vehicles
· Valid driver’s license for each driver
· Valid driver’s license or other state identification for each passenger
Depending on the current Force Protection Condition, a government representative may be required to sponsor those people in person at Pass & ID, Bldg. 17595, Visitor Control Center located at the Santa Maria Gate.
The sponsor must state the guest's purpose and destination. It is the responsibility of the contractor to validate this need with their government POC prior to their arrival so as to coordinate the arrival time accordingly. Sponsors may request that a pass be applicable for multiple days if needed.
Prohibitions: Firearms may not be brought on base under any circumstances. Individuals with criminal records are not allowed on base. Contractor personnel are prohibited from sponsoring guests onto the installation.
Points of Contact (POC)
| Customer POC: | David Rutledge, 30 CES/CENM, (805) 605-2965 | |
| Facility Manager: | Christina Sutton, 30 FSS/FSY, (805) 606-0313 | |
| Contracting Officer: | Alyson Kolding, 30 CONS/PKB, (805) 606-4692 |
3 | Page
File details come from the government source that posted it. Updated .