Sheet1 Attachment Y - Schedule Template for CAVE Contractor to fill in all yellow boxes
| Title of project/park name | Carlsbad Caverns National Park Comprehensive Sign Place for Caverns |
| Contract Number | |
| Contractor Name | |
| Contract award date |
| Contract end date |
Post award conference call date
| Item | # days to complete task | Due Date |
| Contractor Schedule | 10 fed. business days from Post Award Call | |
| Kick-off call Notes | TBD by Contractor | |
| Government Review of Notes | 5 fed. Business days | |
| Task 1: Project Overview and Existing Conditions Documentation | |
| Site visit with Contractor, COR, and Park staff | |
| Existing Sign Survey, Location Plan, | TBD by Contractor |
| Review by government | 7 fed. business days |
| Recommendation Report | TBD by Contractor | |
| Initial HFC Only Review | 6 fed. business days | |
| Revision of RR | TBD by Contractor | |
| HFC and Park Review or approval | 10 fed. business days | |
| Revision of RR | TBD by Contractor | leave blank unless needed |
| Additional Reviews if required | 6 fed. business days | |
| After approval of Task 1 contractor may continue on to Task 2 | |
| Task 2: Sign Planning and Locating | |
| Sketches Meeting Notes | TBD by Contractor |
| Government Review of Notes | 5 fed. Business days |
| Sign Type Menu | TBD by Contractor | |
| Initial HFC review | 10 fed. business days | |
| Revision of SM | TBD by Contractor | |
| HFC and Park Review | 15 fed. business days | |
| Revision of SM | TBD by Contractor | |
| Additional Review or approval | 10 fed. business days | |
| Revision of SM | TBD by Contractor | leave blank unless needed |
| Additional Reviews if required | 10 fed. business days | |
| Message Programming, Location, and Demolition Plan | TBD by Contractor | |
| Initial HFC review | 10 fed. business days | |
| Revisions of MP, LP, and DP | TBD by Contractor | |
| HFC and Park Review | 20 fed. business days | |
| Revision of MP, LP, and DP | TBD by Contractor | |
| Additional Review or approval | 10 fed. business days | |
| Revision of MP, LP, and DP | TBD by Contractor | leave blank unless needed |
| Additional Reviews if required | 10 fed. business days | |
| After approval of Task 2 contractor may continue on to Task 3 | | |
| Task 3: Sign Drawings and Fabrication Details | | |
| Verify locations, Structural and Electrical Connection Visit | TBD by Contractor | |
| Sign Panel Layouts, Structures, and Sign Location Plans | TBD by Contractor | |
| Initial HFC review | 10 fed. business days | |
| Revisions of SPL, S, and LP | TBD by Contractor | |
| 1st Review with Park | 20 fed. business days | |
| 1st Revision of SPL, S, and LP | TBD by Contractor | |
| 2nd Review with Park | 10 fed. business days | |
| 2nd Revision of SPL, S, and LP | TBD by Contractor | leave blank unless needed |
| Additional Reviews if required | 10 fed. business days | |
| Fabrication Details | TBD by Contractor | |
| Initial HFC review | 7 fed. business days | |
| Revisions of FD | TBD by Contractor | |
| 1st Review with Park | 10 fed. business days | |
| 1st Revision of FD | TBD by Contractor | |
| 2nd Review with Park | 7 fed. business days | |
| 2nd Revision of FD | TBD by Contractor | leave blank unless needed |
| Additional Reviews if required | 7 fed. business days | |
| After approval of Task 3 contractor may continue on to Task 4 | |
| Task 4 | |
| All final files in PDF and native design program | TBD by Contractor |
| Government Review | 7 fed. business days |
Contract end date