Attachment H - Financial Management Reporting Requirements.pdf
PDF 104 KB Posted
- Attached to
- Space Weather Next L1 Series Solar Wind Plasma Sensor (SWiPS) Procurement Federal contract opportunity
- Solicitation number
- 80GSFC23R0035
About this file
This Request for Proposal (RFP) solicits offers for the Space Weather Next L1 Series Solar Wind Plasma Sensor (SWiPS) instrument. The National Aeronautics and Space Administration (NASA) Goddard Space Flight Center (GSFC) and National Oceanic and Atmospheric Administration (NOAA) seek to procure services including design, development, fabrication, integration, testing, evaluation, launch support, ground support equipment supply and maintenance, and mission operations support. The contractor will be responsible for measuring solar wind parameters including ion velocity, temperature, density and dynamic pressure to characterize space weather events. The solicitation requires potential offerors to review all attachments and monitor the website for amendments. Financial reporting requirements include submitting NASA Form 533 reports with a breakdown of direct labor hours and costs by work breakdown structure level and cost elements on a monthly and quarterly basis, along with narratives explaining variances exceeding 10%.
View the file
Other files for this federal contract opportunity
Show all 31
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT H
FINANCIAL MANAGEMENT REPORTING
REQUIREMENTS
RFP 80GSFC23R0035
CONTRACT TBD
FINANCIAL MANAGEMENT REPORTING REQUIREMENTS
Financial Management Reports shall be submitted by the Contractor on the NASA 533 series reports, in accordance with the instructions on the reverse of the forms, NASA Procedural Requirements NPR 9501.2E entitled "NASA Contractor Financial Management Reporting,” dated May 27, 2011, and additional instructions issued by the Contracting Officer.
a. Level of Detail
The Contractor’s 533 Reports shall contain a summary of total contract costs, as well as a separate 533 Report for each Work Breakdown Structure (WBS) Level 3 element of the Statement of Work. The reports shall contain a breakdown of hours and costs by the elements of cost categories listed in Section d below.
b. Variance Narrative Reporting
In accordance with Section 3.6 of NPR 9501.2, the Contractor shall include a narrative explanation for variances exceeding plus or minus 10 percent (+/- 10%) between the Total Direct Labor Hours (prime and subcontractors) and/or Total Estimated Cost amount shown in the prior month and the Actual Total Direct Labor Hours and/or Actual Total Cost amount shown in the current month at WBS Level 3. (For example, the Total Estimated Cost amount shown for June in column 8a in the May NF 533M and the Actual June Total Cost amount shown in column 7a in the June NF 533M.)
Each variance narrative shall explain the: (1) reason for the variance, (2) impact(s) on the Core baseline and/or each individual task order, and (3) specific corrective action(s) being taken or to be taken.
c. Distribution
The Contractor shall distribute 533 reports to each addressee indicated in the contract clause entitled, "Financial Management Reporting." The Contractor shall submit an initial report in the NF 533Q format within 30 working days after contract award.
After the initial report, the NF 533M reports shall be distributed not later than the tenth (10th) working day following the close of the contractors' monthly accounting period.
The 533Q reports shall be distributed not later than the fifteenth (15th) day of the month preceding the quarter being reported. The NF 533M need not be submitted in months in which an NF 533Q is submitted.
d. Reporting Requirements
Each individual report shall, at a minimum, provide cost data by the following elements of cost categories:
1. Prime Direct Labor Hours:
Total Prime Direct Labor Hours
2. Subcontractor Direct Labor Hours:
Subcontractor A Direct Labor Hours
Subcontractor B Direct Labor Hours
Subcontractor C Direct Labor Hours
Total Subcontractors Direct Labor Hours
3. Total Prime and Subcontractors Direct Labor Hours
4. Prime Direct Labor Costs:
Total Prime Direct Labor Costs
5. Prime Overhead Expense
6. Other Direct Costs (ODCs):
a. Subcontracts (list separately, Subcontractor A, B, C, etc.)
b. Material
c. Travel
d. Other (specify)
Total ODCs
7. Subtotal (Direct Labor, Overhead & ODCs)
8. G&A Expense
9. Total Estimated Cost
10. Fixed Fee
11. Total Cost-Plus-Fixed-Fee (CPFF)