About this file
This is a landscape design plan document prepared by the Michigan Department of Transportation (MDOT) for the Five Points Roundabout project in Coloma. The plan provides detailed specifications for landscaping improvements at the roundabout intersection, including the installation of seven Syringa reticulata 'Ivory Silk' trees spaced at 15-foot on-center intervals, decorative stone placement, landscape fabric installation, and site preparation work. The project quantities include 188 cubic yards of Meramec Rock or River Rock decorative stone, 1,050 square yards of landscape fabric, seven trees at 2-inch diameter, and a lump sum allocation for site preparation work with a maximum depth of 1 unit.
The landscape design specifications detail the construction sequence and material standards for the roundabout improvement, requiring excavation of existing soil to a minimum depth of 6 inches, installation of landscape fabric between the concrete curb and tree mulch rings, placement of 6-inch-deep decorative stone with finish grade level with the placement surface, application of 4 inches of mulch around each tree without fabric or stone within the mulch rings, and planting of trees per R-100 planting details. The plan was finalized on June 29, 2023, and represents the final right-of-way plan for the Five Points Roundabout landscape improvements in the Coloma design unit area.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| Schedule A-SOW-Five Points Roundabout.docx | DOCX document | |
| Attachment B.Decorative Stone.pdf | ||
| Schedule B-Pricing-Five Points Roundabout.docx | DOCX document | |
| Attachment C.Landscape Fabric.pdf | ||
| Attachment A.Five Points Project Log.pdf | ||
| Proposal Inst-SWR-Roundabout.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CS:
JN:
TSC:
DATE:
FILE:
DESIGN UNIT:
DESCRIPTIONAUTH
DRAWING SHEET
Five Points Roundabout.dgn 1
14041, 14042
6/29/23
0 40
HORZ. (FT)
ROADSIDE DEV.
COLOMA
DESCRIPTIONAUTH
LANDSCAPING
FIVE POINTS ROUNDABOUT
DATE NO. DATENO.
FINAL ROW PLAN REVISIONS (SUBMITTAL DATE: )
Michigan Department of Transportation
SPACED AT 15' O.C.
(7) SYRINGA RETICULATA 'IVORY SILK'
OVER ROOT BALL. DO NOT PLACE FABRIC OR STONE WITHIN MULCH RINGS.
4. PLANT TREES PER R-100 PLANTING DETAILS. PLACE 4" OF MULCH AROUND EACH TREE
CONCRETE CURB AND TOP OF STEEL LANDSCAPE EDGING.
3. PLACE DECORATIVE STONE AT A DEPTH OF 6" WITH FINISH GRADE BEING LEVEL WITH
PLACING STONE.
2. PLACE LANDSCAPE FABRIC BETWEEN CONCRETE CURB AND TREE MULCH RINGS BEFORE
1. EXCAVATE EXISTING SOIL A MIN. OF 6" PER SPECIAL PROVISION FOR DECORATIVE STONE.
NOTES:
Decorative Stone, Meramec Rock or River Rock 188 Cyd
Landscape Fabric 1050 Syd
Syringa reticulata 'Ivory Silk', 2 inch 7 Ea
Site Preparation, Max 1 LSUM
QUANTITIES THIS SHEET
N
U S
FIVE POINTS RD
U
S
FIVE POINTS RD
O L
D M
-2
DECORATIVE STONE