This is a Project Control Log prepared by the Michigan Department of Transportation (MDOT) for landscaping work at the US-12 Five Points Roundabout in Mason Township, Cass County. The project involves removal of existing landscaping and soil excavation within the vegetated roundabout section, placement of landscape fabric and decorative stone at a 6-inch depth, and planting of seven Syringa Reticulata "Ivory Silk" 2-inch trees spaced 15 feet on-center. The work items include 193 cubic yards of earth excavation, 1,050 square yards of landscape fabric, 188 cubic yards of decorative stone (either Meramec Rock or River Rock), and seven trees, with a lump sum contract for site preparation and minor traffic devices. All work must commence following receipt of Notice to Proceed and be completed within 6 days of starting, with a final completion date of September 29, 2023. Work shall be performed during daylight hours with no activities permitted during the Labor Day holiday period (September 1-5, 2023). The contractor must maintain access to all five roundabout approaches and restrict full lane closures to no more than 5 minutes during low-traffic periods between 9 AM and 2 PM.
The contract is structured as a lump sum agreement with quantities provided for estimating purposes only. Traffic control requirements include maintaining the roundabout apron staging area without blocking the traveled way, providing adequate channelizing devices and Type III barriers, delineating excavation areas within 3 feet of traffic at 25-foot spacing intervals, and placing W20-1 Road Work Ahead signs on all intersecting or adjacent roads. The contractor must prevent dirt tracking on traveled lanes and restore elevation and slope to original specifications. The MDOT Operation Engineer, Dharmesh Valsadia, located at 5372 S 9th Street, Kalamazoo, MI 49009, serves as the project engineer and must approve the work start date.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| Schedule B-Pricing-Five Points Roundabout.docx | DOCX document | |
| Attachment C.Landscape Fabric.pdf | ||
| Proposal Inst-SWR-Roundabout.docx | DOCX document | |
| Schedule A-SOW-Five Points Roundabout.docx | DOCX document | |
| Attachment D.Five Points Roundabout Map.pdf | ||
| Attachment B.Decorative Stone.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
7/3/2023
MICHIGAN
DEPARTMENT OF TRANSPORTATION
LOG OF PROJECT
CONTROL SECTION 14041, 14042
US-12 @ Five Points
Mason Township, Cass County
LOCATION:
Control Section 14041,14042, US-12 at Five Points Roundabout in Mason Township, Cass County.
DESCRIPTION OF WORK:
Inside the vegetated section of the roundabout, the Contractor shall perform the following, as directed by the Engineer:
Remove existing established landscaping and excavate soil to a minimum of 6 inch per Special Provision for Decorative Stone.
Place Landscape Fabric per Special Provision for Landscape Fabric between concrete curb and tree mulch rings before placing stone.
Place Decorative Stone, ______ per Special Provision for Decorative Stone at a depth of 6 inch with finish grade being level with concrete curb and top of steel landscape edging. Approved stone types are Meramec Rock and River Rock. Identify the selected stone in the quote.
The grading of the proposed landscaping to match existing grading to maintain the visual barrier.
Restore elevation and slope to original specifications.
Plant 7 Syringa Reticulata “Ivory Silk’, 2 inch trees per R-100 Planting details. Place 4 inch of mulch around each tree over root ball. Do not place fabric or stone within mulch rings. The trees to be spaced 15 ft O.C. centered in the middle of the roundabout. See attached detail.
MAINTAINING TRAFFIC:
The contractor shall always maintain access to the roundabout circle and all 5 approaches of the roundabout.
The work will be performed during daylight hours.
Do not work, deliver material, or close lanes during the holiday periods as defined in Table 1 below:
Table 1: 2023 Holiday Periods
Holiday Start Date and Time End Date and Time
Labor Day Friday, 09/01/2023, 3:00 p.m. Tuesday, 09/05/2023, 6:00 a.m.
The contractor shall stage the work area within the roundabout apron and shall not block the traveled way.
In the event that a lane or partial lane needs to be taken within the circle, all 5 approaches of the roundabout will need to be closed simultaneously for a duration of no more than 5 minutes. This operation will only be permitted during lower traffic volumes on US-12 (9 AM to 2 PM). Provide sufficient channelizing devices and Type IIIs if needed for this operation. The right turns at each approach may be permitted if desired. Prior to closing
Delineate excavated areas located within 3 feet of traffic with channelizing devices at 25 feet spacing along the excavated area.
Include W20-1 Road Work Ahead signs in the quantities to be placed on all intersecting or adjacent roads where construction activities may be encountered.
No tracking of dirt on the traveled lanes.
ITEMS OF WORK:
The following work items and quantities shall apply throughout the project.
PAY ITEM TOTAL UNIT
Excavation, Earth 193 Cyd
Site Preparation, Max 1 LSUM
Landscape Fabric 1050 Syd
Decorative Stone, _________ 188 Cyd
Syringa reticulata ‘Ivory Silk’, 2 inch 7 Ea
Minor Traf Devices 1 LSUM
* Quantities are for estimating purpose only. This contract is Lump Sum.
PROGRESS CLAUSE:
The Engineer for this project is:
Dharmesh Valsadia MDOT Operation Engineer 5372 S 9th Street Kalamazoo, MI 49009 ValsadiaD@michigan.gov
After receiving Notice to Proceed, start work on the date approved by the Engineer. In no case may any work be commenced prior to receipt of formal notice of approval by the Department.
The entire project must be completed within 6 days of starting work.
The entire project must be completed by the final completion date of September 29, 2023.