Attachment C - Contract Deliverable Requirements List (CDRL).pdf
PDF 1 MB Posted
- Attached to
- Space Weather Next L1 Series Coronagraph Federal contract opportunity
- Solicitation number
- 80GSFC24R0009
About this file
This federal solicitation seeks proposals for three flight Coronagraph instruments for the NASA and NOAA Space Weather Next L1 Series mission. Offerors must submit proposals by April 22, 2024. NASA intends to award a cost-plus-fixed-fee completion contract with technical milestones incentives in October 2024, with deliveries of the first unit by March 2027, the second by June 2029, and the third as a spare for the first two missions. The contract will be performed offsite at the contractor's facilities and utilize existing government furnished property. The North American Industry Classification System code is 336414 with a small business size standard of 1,300 employees.
View the file
Other files for this federal contract opportunity
Show all 43
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Effective Date: February 23, 2024 Expiration Date: February 23, 2029
Check the L1 Series CM tool Server at https://ipdtdms gsfc nasa gov/ to verify that this is the correct version prior to use.
L1SERIES-COR-REQ-0027, Revision - Space Weather Next L1 Series Project, Code 493
Space Weather Next (SW Next) Program
Lagrange (L1) Series Project Coronagraph (COR)
Contract Deliverables Requirements List
(CDRL)
U.S. Department of Commerce (DOC) National Oceanic and Atmospheric Administration (NOAA) NOAA Satellite and Information Service (NESDIS) National Aeronautics and Space Administration (NASA)
GSFC SW Next L1 Series CMO
February 23, 2024
Released
L1 Series Project Coronagraph CDRL L1SERIES-COR-REQ-0027, Revision -ii Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
Lagrange 1 (L1) Series Project Coronagraph
Contract Deliverables Requirements List (CDRL)
Signature/Approval Page
Originally Electronically signed on 02-22-24 by:
Mark Edison SW Next L1 Series Coronagraph Instrument Lead NASA Goddard Space Flight Center
Originally Electronically signed on 02-23-24 by:
Hudson DeLee SW Next L1 Series Instrument Systems Manager
Originally Electronically signed on 02-23-24 by:
J. Timothy Van Sant Project Manager, SW Next L1 Series iii Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
Preface
This document is under L1 Series Program configuration control. Once this document is approved, L1 Series approved changes are handled in accordance with Class I and Class II change control requirements as described in the L1 Series Configuration Management Procedure, and changes to this document shall be made by complete revision.
In this plan, all mandatory actions (i.e., requirements) are denoted by statements containing the term “shall”. The terms “may” or “can” denote discretionary privilege or permission; “should” denotes a good practice and is recommended but not required; “will” denotes expected outcome;
and “are/is” denotes descriptive material.
Any questions should be addressed to:
L1 Series Configuration Management Office
NASA/GSFC
Code 493 Greenbelt, MD 20771 iv Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
Change History Log
Revision Effective Date Description of Changes (Reference the CCR & CCB/ERB Approval Date)
Revision - February 23, This document was reviewed and approved for baseline in CCRs L1SERIES-CCR-0059 and L1SERIES-CCR-0066 and was dispositioned on February 23, 2024.
v Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
Table of Contents
1 INTRODUCTION
1.1 DEFINITION OF DUE DATES/MATURITY, DEFINITION OF CATEGORIES, AND
DELIVERY INSTRUCTIONS
Due Date Maturity NASA Acceptance Code
1.2 CORONAGRAPH CONTRACT DELIVERABLES REQUIREMENTS LIST (CDRL) . 2
1.3 DATA ITEM DESCRIPTION (DID) OVERVIEW
1.4 DELIVERY INSTRUCTIONS
1.5 CDRL ITEMS OVEVIEW
Integrated Baseline Review (IBR) Package Contract Work Breakdown Structure and Dictionary
2 PROGRAM DATA ITEM DESCRIPTIONS
PM-1 PROGRAM MANAGEMENT PLAN
PM-2 WEEKLY STATUS REPORTS AND TELECON MINUTES
PM-3 CONFIGURATION MANAGEMENT PLAN
PM-4 CONFIGURATION CHANGE REQUESTS (CCR) CLASS I
PM-5 PROGRAM MANAGEMENT STATUS REVIEW DATA PACKAGE
PM-6 NASA PROPERTY IN THE CUSTODY OF THE CONTRACTORS
PM-7 CONTRACTOR TASK PLAN
PM-8 DOCUMENT TREE
3 RESOURCE MANAGEMENT
RM-1 EARNED VALUE MANAGEMENT (EVM) PLAN
RM-2 FINANCIAL REPORTS
RM-3 RISK MANAGEMENT PLAN
RM-4 INTEGRATED PROGRAM MANAGEMENT DATA AND ANALYSIS REPORT
(IPMDAR)
RM-5 INTEGRATED BASELINE REVIEW (IBR) PACKAGE
RM-6 CONTRACT WORK BREAKDOWN STRUCTURE AND DICTIONARY
4 REVIEW DATA ITEM DESCRIPTIONS
RVW-1 SYSTEM DEFINITION REVIEW (SDR) DATA PACKAGE
RVW-2 PRELIMINARY DESIGN REVIEW (PDR) DATA PACKAGE
RVW-3 CRITICAL DESIGN REVIEW (CDR) DATA PACKAGE
RVW-4 PRE-ENVIRONMENTAL REVIEW (PER) DATA PACKAGE
RVW-5 PRE-STORAGE/PRE-SHIP REVIEW (PSR) DATA PACKAGE
RVW-6 SUBSYSTEM REVIEW MINUTES AND ACTION ITEMS
RVW-7 RESPONSES TO REQUEST FOR ACTIONS
RVW-8 SUBCONTRACT AND SUBSYSTEM REVIEW DATA PACKAGES
5 SYSTEMS ENGINEERING DATA ITEM DESCRIPTIONS
SE-1 SYSTEMS ENGINEERING MANAGEMENT PLAN
SE-2 ENGINEERING ANALYSES REPORTS
SE-3 COR SYSTEM SPECIFICATION
SE-4 DETAILED DESIGN SPECIFICATIONS
vi Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
SE-5 THERMAL MATH MODEL AND REPORTS
SE-6 STRUCTURAL MATH MODEL AND REPORTS
SE-7 SOLID MATH MODEL
SE-8 INSTRUMENT BLOCK DIAGRAMS, AND APPROVED OR CONTROLLED
DRAWINGS
SE-9 SYSTEM PERFORMANCE VERIFICATION PLAN
SE-10 SYSTEM PERFORMANCE VERIFICATION REPORT
SE-11 PERFORMANCE VERIFICATION PROCEDURES
SE-12 ENVIRONMENTAL VERIFICATION SPECIFICATION
SE-13 ENVIRONMENTAL VERIFICATION REPORTS
SE-14 DIGITAL IMAGE AND VIDEO RECORDS
SE-15 INDIVIDUAL TEST PLANS
SE-16 MAGNETIC CONTROL PLAN
SE-17 COMPONENT AND SUBASSEMBLY TEST REPORTS FOR ALL
SUBCONTRACTED ITEMS
SE-18 EMC/EMI COMPATIBILITY PLAN
SE-19 MAINTENANCE, TEST, AND OPERATIONS MANUAL FOR THE COR
EMULATOR
SE-20 REQUEST FOR USE OF MULTI-MISSION OR PREVIOUSLY DESIGNED,
FABRICATED, OR FLOWN HARDWARE
6 MISSION ASSURANCE AND SAFETY DATA ITEM DESCRIPTIONS
MA 1-1 MISSION ASSURANCE REQUIREMENTS COMPLIANCE MATRIX
MA 1-2 SUPPLIER LIST
MA 2-1 INPUT TO ORBITAL DEBRIS ASSESSMENT REPORT and End of Mission Plan
(EOMP)
MA 3-1 SYSTEM SAFETY PLAN (SSP)
MA 3-2 SAFETY REQUIREMENTS COMPLIANCE CHECKLIST
MA 3-3 OPERATIONS HAZARD ANALYSIS AND HAZARD VERIFICATION
TRACKING LOG
MA 3-4 INSTRUMENT SAFETY ASSESSMENT REPORT
MA 3-5 HAZARDOUS PROCEDURES FOR PAYLOAD I&T AND PRELAUNCH
PROCESSING
MA 3-6 PRE-MISHAP PLAN
MA 4-2 FAILURE MODE, EFFECTS, AND CRITICALITY ANALYSIS, AND
CRITICALITY ITEMS LIST
MA 4-3 FAULT TREE ANALYSIS
MA 4-4 RELIABILITY PREDICTIONS
MA 4-5 LIMITED LIFE ITEMS LIST
MA 4-6 PARTS STRESS ANALYSIS
MA 4-7 WORST-CASE ANALYSES
MA 5-1 SOFTWARE ASSURANCE PLAN
MA 6-1 ELECTROSTATIC DISCHARGE (ESD) CONTROL PLAN
MA 6-2 PRINTED CIRCUIT BOARD (PCB) PROCUREMENT PLAN
MA 6-5 LEAD-FREE CONTROL PLAN (LFCP)
MA 7-1 EEE PARTS CONTROL PLAN
MA 7-2 MASTER EEE PARTS LIST
vii Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
MA 7-3 RADIATION EFFECTS MITIGATION
MA 7-4 RADIATION SHIELDING AND DOSE ANALYSIS REPORT
MA 7-5 SINGLE EVENT EFFECT FAULT MANAGEMENT PLAN
MA 8-1 MATERIALS & PROCESSES SELECTION, CONTROL, AND
IMPLEMENTATION PLAN
MA 8-2 MATERIALS USAGE AGREEMENT EVALUATION FORM
MA 8-3 MATERIALS IDENTIFICATION AND USAGE LIST
MA 8-4 LIFE TEST PLAN AND FINAL REPORT FOR LUBRICATED MECHANISMS . 91
MA 8-5 ADDITIVE MANUFACTURING CONTROL PLAN (AMCP)
MA 8-6 AM PRODUCTION PLAN (PPP)
MA 9-1 CONTAMINATION CONTROL PLAN
MA 9-2 FOREIGN OBJECT DEBRIS PROGRAM
MA 11-1 GIDEP ALERTS/NASA ADVISORY DISPOSITIONS
MA 11-2 INITIATING GIDEP ALERTS
MA 12-1 END ITEM ACCEPTANCE DATA PACKAGE (EIDP)
7 OPERATIONS DATA ITEM DESCRIPTIONS
OPS-1 FLIGHT TELEMETRY AND COMMAND DATABASE
OPS-2 FLIGHT TELEMETRY AND COMMAND HANDBOOK
OPS-3 OPERATIONS HANDBOOK
OPS-4 GROUND PROCESSING ALGORITHMS TEST AND VALIDATION PLAN
OPS-5 GROUND PROCESSING ALGORITHM DOCUMENT
OPS-6 GROUND SOFTWARE ACCEPTANCE PLAN INPUT
OPS-7 TREND ANALYSIS PLAN AND DATA REPORTS
OPS-8 ON-SITE DATA ANALYSIS REPORTS
OPS-9 MASS PROPERTIES AND POWER REPORT
OPS-10 COR PACKETIZED DATA
OPS-11 INSTRUMENT OPERATIONS CONFIGURABLE ITEMS
8 SOFTWARE DATA ITEM DESCRIPTIONS
SW-1 SOFTWARE MANAGEMENT PLAN
SW-2 SOFTWARE DELIVERY PACKAGES
9 INTEGRATION AND TEST DATA ITEM DESCRIPTIONS
I&T-1 TRANSPORTATION, HANDLING PLAN AND PROCEDURES
I&T-2 POST LAUNCH TEST REPORTS
I&T-3 OBSERVATORY LEVEL TEST PROCEDURES
I&T-4 OBSERVATORY LEVEL TEST REPORT
I&T-5 CALIBRATION PROGRAM PLAN
I&T-6 CALIBRATION DATA BOOKS
10 FPGA DATA ITEM DELIVERABLE
FW-1 FPGA DEVELOPMENT PLAN
FW-2 FPGA DESIGN DATA PACKAGE
11 COR HARDWARE/SOFTWARE DELIVERABLE ITEMS
APPENDIX A ABBREVIATIONS AND ACRONYMS
APPENDIX B RECOMMENDED OPERATING PROCEDURES (ROPS) TEMPLATE 124
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
1 INTRODUCTION
This Space Weather Next (SW Next) Lagrange 1 (L1) Series (L1 Series) Instrument Contract Deliverables Requirements List (CDRL) document defines the requirements for deliverable items to be provided by the L1 Series Coronagraph Contractor. All data shall be prepared, maintained/updated, and delivered to the Government in accordance with the requirements specified in the governing contract, delivery order, Statement of Work (SOW), Mission Assurance Requirements (MAR), and this CDRL and its associated Data Item Descriptions (DIDs).
1.1 DEFINITION OF DUE DATES/MATURITY, DEFINITION OF CATEGORIES,
AND DELIVERY INSTRUCTIONS
The following definitions apply to the "Delivery" column in Table 2 L1 Series Coronagraph Contract Deliverables Requirements List (CDRL)
Due Date
a. Proposal: Items that are provided with the proposal.
b. At CDR, PER, etc.: Critical Design Review, Pre-Environmental Review, Pre-Ship
Review, etc.
c. As Generated: After each initial edition, revision, addition, etc. Monthly: Monthly by the 15th of each month or as required or as modified by CO
d. Weekly: Weekly status reports by Tuesday close of business or as modified by
Contracting Officer (CO)
e. L: Launch Date
f. DACA: Days after contract award
g. MACA: Months after contract award
h. NLT: No later than
i. Authorization to Proceed: ATP
Unless otherwise noted, the data in the due date column titled "days" are to be interpreted as calendar days.
Maturity
a. Preliminary: The initial submission of an item. To be completed with available information as of the time of preparation for the due date.
b. Update: The best up-to-date information available at the time.
c. Final: The complete thorough submission of an item for approval, review, or information. This does not preclude updating later.
NASA Acceptance Code
A Approval: Documents in this category require approval by the Goddard Space Flight Center (GSFC) Contracting Officer’s Representative prior to use by the contractor.
If the Government disapproves, the requirement for resubmission by the Contractor shall be as specified by the Government Contracting Officer. Normally, the requirement for
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
resubmission will be within 30 days of receiving the Government’s comments. If the Government does not provide comments in the prescribed time, the Contractor may proceed with the associated work after notifying the Government of the intention to proceed.
R Review: Documents in this category require delivery to the Government prior to use and within the time period specified in the "Due Date" column of this document.
They are subject to evaluation by the Government or its designated representatives to determine Contractor effectiveness in meeting contract objectives. Following submission, the Contractor may proceed with the associated work. Starting when the Government receives the document, the Government Contracting Officer may provide written (electronic) comments within 21 calendar days. When the Government identifies a deficiency, the Contractor shall re-submit within 30 calendar days of receiving Government comments (3 days for Spacecraft-level test and calibration/validation procedures) or provide a plan within 7 calendar days (1 day for test calibration/ validation procedures), as specified by the Government Contracting Officer, for approval by the Government to close the deficiency.
I Information: Data in this category require delivery to the Government within the time period specified in the “Due Date” column of the COR Contract Deliverables Requirements List for the purpose of determining current program status, progress, and future planning requirements. The Government Contracting Officer may provide written (electronic) comments within 21 calendar days to identify errors and omissions, and the Contractor shall make the corrections and re-submit as specified by the Government Contracting Officer. The Contractor shall address Government comments in the next version delivered, or in a revised version if it is the final delivery
1.2 CORONAGRAPH CONTRACT DELIVERABLES REQUIREMENTS LIST
(CDRL)
Items with an “As Generated” due date that are critical to schedule, performance, or interface shall be transmitted to GSFC by within 48 hours of generation.
Any updates to items of “Final” maturity shall require the same "approval/review" process as was required for the previous submissions.
All Data items shall be delivered in electronic format to a GSFC L1 Series specified web portal unless otherwise noted in the Coronagraph Contract Deliverables Requirements List.
Individual CDRL items may be combined with other CDRL items to increase documentation efficiency if the content and requirements of the CDRL items are satisfied.
Electronic deliverables shall be delivered in the following formats unless otherwise approved by the government:
a. Text Documents: PDF (searchable) or MS Word
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
b. Presentations: PDF (searchable) or PowerPoint
c. Spreadsheets: Microsoft Excel
d. Database: Delimited ASCII files accompanied with database schema document defining tables and entries.
e. Schedules: MS Project
f. Schematics and Drawings: PDF
g. Photographs: JPEG or current industry standard.
h. Video: Any readily available open standard (e.g., AVI, MPEG)
1.3 DATA ITEM DESCRIPTION (DID) OVERVIEW
Each CDRL item is defined by a corresponding DID. The DID includes the title, number, SOW reference, purpose, applicable documents, and required preparation information.
Much of the required information specified in the DIDs may already exist in the Contractor’s documentation. In those cases, existing documents and formats should be used if they meet the intent of the DID requirements. If so, a notation shall be supplied in the deliverable which indicates where in the Contractor’s document the information that satisfies the requirement can be found.
1.4 DELIVERY INSTRUCTIONS
a. The Contractor shall deliver each CDRL item via the media indicated below in accordance with the schedule and any special instructions indicated in Table 2 and/or the corresponding DID, and in accordance with the contract or mission-specific Delivery Order (DO) requirements and provisions.
b. All CDRL items shall be delivered electronically (one electronic copy for each CDRL item) to an electronic library designated by the Government. If all or a portion of a CDRL item is not well suited for electronic delivery, the item may be delivered via hard copy upon mutual agreement between the Contractor and the Government.
c. Upon submitting each CDRL item, the Contractor shall notify via email the Government Contracting Officer (CO), the CO Representative, and the Data Management Office.
1.5 CDRL ITEMS OVEVIEW
Table 1 provides a list of CDRL item categories as follows:
a. Item #: An alpha-numeric identifier for each CDRL item category and its respective DID.
The alpha descriptor is based on the subject matter of the deliverable:
Table 1 Alpha-numeric identifiers for each CDRL
PM Program Management RM Resource Management
RVW Reviews SE Systems Engineering
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
MA Mission Assurance and Safety OPS Operations SW Software I&T Integration and Test FW FPGA Development Plan
b. Requirements Reference: The reference indicates the section of the L1 Series Instrument
SOW, MAR, and/or Instrument Requirements Specification (SPEC) where the CDRL item is called out.
c. Title: (self-explanatory)
d. Delivery: The contract baseline schedule of delivery for the CDRL item. Many of the dates are referenced to reviews or other milestones. Unless stated otherwise, days are calendar days.
e. Flight Model: This column describes if a deliverable is required for the first flight model, all fight models or a subset of all flight models.
f. Purpose: The purpose of the CDRL item submission (i.e., The Government’s role following receipt of a CDRL item) is based on the definitions below. The designation for an item applies to all submissions (e.g., preliminary/initial, update, final) of that item unless noted otherwise. UAR indicates Update as Required with the approval letter indicated in the parenthetical. An A, R, or I indicate the delivery is required, with the Government’s role following a receipt as indicated.
Table 2 L1 Series Coronagraph Contract Deliverables Requirements List (CDRL)
CRDL No. SOW/MAR Title Delivery Flight Model Purpose
PM-1 SOW 4.1 Program Management Plan Preliminary: 30 DACA Final: PDR+14 days ALL R
PM-2 SOW 4.1 Weekly Status Reports and Telecon Minutes Weekly ALL I
PM-3 SOW 4.6 Configuration Management Plan
Preliminary: 15 DACA Final: PDR + 14 days FM1 A
PM-4 SOW 4.6 Configuration Change Requests (CCR) Class I As generated ALL A
PM-5 SOW 4.7.6
Program Management
Status Review Data Package
Bi-monthly ALL I
PM-6 SOW 4.2 NASA Property in the Custody of the Contractors
Per Contract Clause 1852.245-73, Oct. 15, of each contract year for prior year. Final at contract closeout.
ALL R
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
CRDL No. SOW/MAR Title Delivery Flight Model Purpose
PM-7 SOW 4 Contractor Task Plan
Per the contract ordering mechanism for Special
Studies (only required once a special study is requested/awarded)
ALL R
PM-8 SOW 4.6 Document Tree Preliminary: PDR Final: CDR ALL R
RM-1 SOW 4.3.1 Earned Value Management (EVM) Plan
Initial Submission:
In accordance with NFS
1852.234-2, or Alternate I, 60 DACA
Frequency:
Revised EVMS description or plan as directed
ALL A
RM-2 SOW 4.3.3 Financial Reports:
533 M Package 533 Q Reports
Initial Submission:
533M package shall be submitted 30 DACA.
533Q Reports: shall be submitted after the initial 533M and contain a full fiscal year estimate by quarter Frequency:
533M are due NLT 10 working days following the close of the contractor’s monthly accounting period, unless otherwise specified in the contract.
The 533Q reports shall be distributed NLT the 15th day of the month preceding the quarter being reported.
RM-3 SOW 4.3.4,
4.9
Risk Management (RM) Plan
Initial Submission:
60 DACA
Frequency:
Revised RM description or plan within 30 days after contractor internal approval or as directed by Contracting Officer.
Update:
The Risk Report shall be updated monthly or more
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
CRDL No. SOW/MAR Title Delivery Flight Model Purpose frequently, as required. A review copy shall be provided to the Government at least 24 h in advance of Monthly
Risk Management Board Meetings.
RM-4 SOW 4.3.5 Integrated Program
Management Data and Analysis Report (IMPDAR)
Initial Submission:
The IMPDAR authoritative data (CPD, Schedule, and Performance Narrative) shall be submitted NLT 16 business days after the end of the first full accounting period following the ATP.
Frequency:
Microsoft Project or
Native Schedule and SPD by the 5th business day after the contractor’s accounting month ends.
CPD and Executive Summary by the 10th business day after the contractor month end.
Then the Government has three days to review, analyze the data and informs the contractor the list of control accounts for detailed variance analysis.
Detailed Analysis Report by the 16th business day after the contractor accounting month end.
Monthly Performance
Narrative Report (Executive Summary and Detailed Analysis) shall be submitted NLT 16 business days after the close of the contractor’s monthly accounting period.
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
CRDL No. SOW/MAR Title Delivery Flight Model Purpose
RM-5 SOW 4.4 Integrated Baseline Review (IBR) Package
Initial Submission:
60 days prior to IBR
Frequency:
Per the direction of the cognizant government contracting officer, updated as required
FM1 A
RM-6 SOW 4.3.2 Contract Work Breakdown Structure and Dictionary
Initial Submission:
Draft CWBS and CWBS dictionary will be submitted with the proposal. The initial CWBS and CWBS dictionary will be submitted 30 DACA Updates:
As required Frequency:
Revised pages are to be submitted 10 calendar days after CWBS changes (following Government approval)
ALL A
RVW-1 SOW
4.7.4.1
System Definition Review (SDR) Data Package
Preliminary:
SDR/SRR –14 days
Update:
SDR/SRR – 7 days
Final:
NLT SDR/SRR review – 2 days
FM1 R
RVW-2 SOW
4.7.4.2
Preliminary Design Review (PDR) Data Package
Preliminary:
PDR– 14 days
Final:
NLT PDR review – 2 days
ALL R
RVW-3 SOW
4.7.4.3
Critical Design Review (CDR) Data Package
Preliminary:
CDR – 14 days
Final:
NLT CDR review – 2 days
ALL
R
RVW-4 SOW
4.7.4.4
Pre-Environmental Review (PER) Data Package
Preliminary:
PER Dry Run– 7 days
Final:
PER
RVW-5 SOW
4.7.4.5
Pre-Storage/Pre-Ship Review (PSR) Data
Package
Preliminary:
PSR Dry Run – 7 days
Final:
PSR
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
CRDL No. SOW/MAR Title Delivery Flight Model Purpose
RVW-6 SOW 4.7.3,
4.7.9
Subsystem Review Minutes and Action Items
Preliminary:
2 days after review
Final:
14 days after review
A
RVW-7 SOW 4.1 Responses to Request for Actions
Preliminary:
30 days after assigned
Updates: As agreed
ALL R
R
RVW-8 SOW 4.7.9 Subcontract and Subsystem Review Data Packages Final: Review ALL R
SE-1 SOW 5.1 Systems Engineering Management Plan
Preliminary: 30 DACA Final: PDR – 30 days FM1 R
SE-2 SOW 5.6 Engineering Analyses Reports As generated ALL R
SE-3 SOW 5 COR System Specification Preliminary: SDR – 14 days Final: SDR
FM1 A
A
SE-4 SOW 6.1 Detailed Design Specifications
Preliminary: Applicable subsystem PDR
Final: Applicable subsystem CDR
ALL R
R
SE-5 SOW 5.3,
6.3.2.5
Thermal Math Model and Reports
Preliminary: PDR Update: CDR, FM1 PER, FM1 PSR, and as generated
FM1 R
R
SE-6 SOW 5.3,
6.3.2.2
Structural Math Model and Reports
Preliminary: PDR Update: CDR, PER, PSR, and as generated
FM1 R
R
SE-7 SOW 5.3,
6.3.2.2 Solid Math Model
Preliminary: PDR Update: CDR, PER, PSR, and as generated
FM1 R
R
SE-8 SOW 4.6 &
6.1.1
Instrument Block Diagrams, And Approved Or
Controlled Drawings
Preliminary: PDR Final: PSR
Update: CDR
FM1
R R
SE-9 SOW 5.1 &
6.3.2
System Performance Verification Plan
Preliminary: SDR/SRR Final: PDR ALL
SE-10 SOW 5.1 &
6.3.2
System Performance Verification Report
Preliminary: PSR – 30 days ALL R
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
CRDL No. SOW/MAR Title Delivery Flight Model Purpose
Final: PSR
SE-11 SOW 5.1 &
6.3.2
Performance Verification Procedures 30 Days prior to use ALL A
SE-12 SOW 6.3.2 Environmental Verification Specification
Preliminary: PDR-14 days Final: CDR – 14 days Update: As Required
ALL
A A A
SE-13 SOW 6.3.2 Environmental Verification Reports
Initial assessment:
1 day after test
Preliminary: 5 days after test
Final: 30 days after Test
R
SE-14 SOW 4.6,
6.3, 8
Digital Image and Video Records
Preliminary: PER Final: PSR
Update: As requested by government
ALL
I I I
SE-15 SOW 6.3 Individual Test Plans Preliminary: CDR Final: 90 days before Test ALL A
SE-16 SOW 5.5 Magnetic Control Plan Preliminary: PDR Final: CDR FM1 R
R
SE-17 SOW 6.2
Component and
Subassembly Test Reports for all Subcontracted Items
As generated Maintained on site ALL I
SE-18 SOW
6.3.2.3
EMC/EMI Compatibility Plan
Preliminary: PDR Final: CDR FM1 R
R
SE-19 SOW 7.1.2
Maintenance, Test, and
Operations Manual for the Coronagraph Emulator
Final: With Delivery of
CORE FM1 R
SE-20 SOW 6.1 &
6.2
Request for Use of Multi- Mission or Previously
Designed, Fabricated, or Flown Hardware
Preliminary: 60 DACA Final: SDR/SRR + 60 days FM1 R
R
MA 1-1 SOW 8
MAR 1.1
Mission Assurance Requirements Compliance
Matrix
Preliminary: With proposal Final: 15 DACA FM1 I
A
MA 1-2 SOW 8
MAR 1.8 Supplier List
Initial: 60 DACA Updates: As updated by
Contractor
ALL I
MA 2-1 SOW 8
MAR 2.3
Input to Orbital Debris Assessment Report (ODAR) and End of
Mission Plan (EOMP)
Preliminary ODAR: 45 days prior to mission PDR ALL
I I
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
CRDL No. SOW/MAR Title Delivery Flight Model Purpose
Interim ODAR and Draft EOMP: 60 days prior to mission CDR Final: 90 days prior to
Instrument PSR
MA 3-1 SOW 8
MAR 3.3.1 System Safety Plan (SSPP)
Preliminary: /SRR Final: 45 days prior to
PDR
Updates: 30 days prior to implementation
ALL
R A A
MA 3-2 SOW 8
MAR 3.3.2
Safety Requirements Compliance Checklist
Preliminary: 45 days prior to PDR
Final: 45 days prior to
CDR
Updates: 45 days prior to Implementation
ALL
A A A
MA 3-3
SOW 8
MAR
3.3.4.2
Operations Hazard Analysis (OHA) and Hazard
Verification Tracking Tool
(HVTL)
Final OHA and HVTL: 45 days prior to first use FM1 A
MA 3-4
SOW 8
MAR 3.3.3,
3.3.4
Instrument Safety Assessment Report (ISAR)
Preliminary: 30 days prior to instrument PDR
Intermediate: 30 days prior to instrument CDR
Final: 30 days prior to instrument PSR
FM1 only (if identical design and build for all FMs)
MA 3-5 SOW 6.5,8
MAR 3.3.6
Hazardous Procedures for Payload I&T and Prelaunch
Processing
I&T Hazardous Procedures: 7 days prior to first use Launch Range Hazardous Procedures: 65 days prior to first use
ALL R
MA 3-6 SOW 8
MAR 3.3.8 Pre-Mishap Plan
Preliminary:
45 days prior to PDR
Final:
45 days prior to CDR
Updates:
45 days prior to PSR
MA 4-2 SOW 8
MAR 4.2.1
Failure Mode, Effects, and Criticality Analysis
(FMECA) and Criticality Items List (CIL)
Preliminary:
30 days prior to PDR
Update:
30 days prior to CDR and each subsequent milestone review leading to LRR
ALL
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
CRDL No. SOW/MAR Title Delivery Flight Model Purpose
MA 4-3 SOW 8
MAR 4.2.2 Fault Tree Analysis
Preliminary: 30 days prior to PDR
Final: 30 days prior to
CDR
Updates: 30 days after identification of updates or changes
ALL
R R R
MA 4-4 SOW 8
MAR 4.2.3 Reliability Predictions Preliminary: PDR
Final: CDR FM1 R R
MA 4-5 SOW 8
MAR 4.3 Limited Life Items List
Draft: 30 days prior to
PDR
Preliminary: 30 days prior to CDR
Updates: 30 days after identification of updates or changes
FM1
R R R
MA 4-6 SOW 7.1, 8
MAR 4.4 Parts Stress Analysis
Draft: 30 days prior to
PDR
Final: 30 days prior to
CDR
Revisions: 30 days after identification of updates or changes
FM1
A A A
MA 4-7 SOW 7.1, 8
MAR 4.5 Worst-case Analyses
30 days prior to CDR Revisions within 30 days after identification of updates or changes
FM1 R
MA 5-1 SOW 8
MAR 5.1 Software Assurance Plan
Preliminary: 30 days prior to SRR
Final: 15 days prior to
PDR
Updates: 30 days prior to implementation
FM1
I
MA 6-1 SOW 8
MAR 6.2
Electrostatic Discharge Control (ESD) Plan 30 days prior to PDR FM1 I
MA 6-2 SOW 8
MAR 6.3
Printed Circuit Board (PCB) Procurement Plan
Preliminary: 30 days prior to CDR
Changes: 14 days prior to manufacturing
FM1
MA 6-5 SOW 8
MAR 6.4 Lead-Free Control Plan 60 DACA FM1 I
MA 7-1 SOW 8
MAR 7 EEE Parts Control Plan 30 DACA FM1 I
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
CRDL No. SOW/MAR Title Delivery Flight Model Purpose
MA 7-2 SOW 8
MAR 7.4 Master EEE Parts List
EEE parts to the Parts Control Board prior to inclusion Updates prior to inclusion
ALL A
MA 7-3 SOW 8
MAR 7.5
Radiation Effects Mitigation 60 DACA FM1 A
MA 7-4 SOW 5.3, 8
MAR 7.5
Radiation Shielding and Dose Analysis Report
Preliminary: PDR Final: CDR FM1 R
MA 7-5 SOW 5.3, 8 Single Event Effect Fault Management Plan
Preliminary: PDR Final: CDR FM1 A
MA 8-1 SOW 8
MAR 8.1
Materials & Processes Selection, Control, and Implementation Plan
(MPCIP)
14 days prior to SRR 30 days prior to PDR 30 days prior to CDR
FM1
I A A
MA 8-2 SOW 8
MAR 8.2 Materials Usage Agreement
30 days prior to CDR New or revised after CDR:
30 days after their identification
ALL A
MA 8-3
SOW 8
MAR 8.3,
9.2
Materials Identification and Usage List (MIUL)
Preliminary:
30 days prior to PDR
Final:
30 days prior to CDR
Updates within 30 days after identification
As-built MIUL 30 days prior to PSR
ALL
R A A A
MA 8-4 SOW 8
MAR 8.4
Life Test Plan and Final Report for Lubricated
Mechanisms
30 days prior to PDR 30 days after acceptance test completion
ALL A
I
MA 8-5 SOW 8
MAR 8.5
Additive Manufacturing Control Plan (AMCP)
14 days prior to SRR 30 days prior to PDR 30 days prior to CDR
FM1
I A A
MA 8-6 SOW 8
MAR 8.6 AM Production Plan (PPP) 30 days prior to CDR
30 days prior to AMRR FM1 I A
MA 9-1 SOW 8
MAR 9.1 Contamination Control Plan
Preliminary: 30 days before PDR
Final: 30 days before CDR Final thermal vacuum bakeout results: within 30 days of completion
Contamination Certificate of compliance with EIADP
ALL
R
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
CRDL No. SOW/MAR Title Delivery Flight Model Purpose
MA 9-2 SOW 8
MAR 9.3
Foreign Object Debris Prevention and Control 30 days prior to PDR FM1 R
MA 11-1 SOW 8
MAR 11.1
GIDEP Alerts/NASA Advisory Dispositions
Disposition of existing Alerts within 30 days of identification Disposition of new Alerts within 30 days of Alert release
MA 11-2 SOW 8
MAR 11.3 Initiating GIDEP Alerts Within 30 days of identification ALL R
MA 12-1 SOW 8
MAR 12
End Item Acceptance Data Package
Preliminary: 30 days prior to PSR
Final: 30 days prior to End Item delivery
Updates: 30 days after identification
OPS-1 SOW 6.5.3 Flight Telemetry and Command Database
Baseline: PER Final: PSR FM1 R
R
OPS-2 SOW 6.5.3 Flight Telemetry and Command Handbook
Preliminary: PDR Final: PSR
Updates: As required
FM1 R
R
OPS-3 SOW 6.5.3 Operations Handbook Preliminary: PER Final: PSR FM1 A
A
OPS-4 SOW 6.1.3
Ground Processing
Algorithms Test and Validation Plan
Preliminary: PDR Update: CDR
Final: PSR - 3 months
FM1
A A A
OPS-5 SOW 6.1.3 Ground Processing Algorithm Document
Preliminary: PDR Update: CDR
Final: PSR -3 months
FM1
A A A
OPS-6 SOW 6.1.3 Ground Software Acceptance Plan Input
Preliminary: CDR Final: PSR - 6 months FM1 R
R
OPS-7 SOW 6.5.3 Trend Analysis Plan And Data Reports
Preliminary: PDR Final:
CDR as generated
ALL R
OPS-8 SOW 6.5.2 On-site Data Analysis Reports As generated ALL R
OPS-9 SOW
6.3.3.2
Mass Properties and Power Report
Monthly NLT 15th of each month FM1 I
OPS-10 SOW 7 COR Packetized Data As generated ALL I
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
CRDL No. SOW/MAR Title Delivery Flight Model Purpose
OPS-11 SOW 6.5.3 Instrument Operations Configurable Items
Preliminary: 30 days prior to launch
Updates: As needed
ALL R
R
SW-1 SOW 6.1.2 Software Management Plan
Preliminary:
30 DACA
Final:
SW Acceptance Review
Update:
PDR, CDR, TRR
FM1
A A A
SW-2 SOW 6.1.2,
6.5.3.1
Software Delivery Packages
Preliminary: PER Final: PSR
Updates: At major revision releases
ALL
R R R
I&T-1 SOW 6.4.1 Transportation, Handling Plan and Procedures
Preliminary: PDR Final: CDR ALL R
I&T-2 SOW 6.5.3,
6.5.5 Post Launch Test Reports
Preliminary: 2 weeks after test
Final: 2 months after test
ALL R
I&T-3 SOW 5.3 Observatory Level Test Procedures
Preliminary: PER Final: PSR ALL R
I&T-4 SOW 5.3 Observatory Level Test Report Observatory PSR ALL R
I&T-5 SOW 6.3.3 Calibration Program Plan Preliminary: SDR/SRR
Update: PDR Final: CDR
ALL
A A A
I&T-6 SOW 6.3.3 Calibration Data Books Final: PSR of each Model ALL R
FW-1 SOW 6.2.1 FPGA Development Plan Preliminary: SRR/SDR
Final: 30 days before PDR
FM-1 R
FW-2 SOW 6.2.1 FPGA Design Data Package
(FDDP)
Preliminary:
30 days before CDR
Updates: As generated Final: 30 days before PER
FM-1
R
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
2 PROGRAM DATA ITEM DESCRIPTIONS
PM-1 PROGRAM MANAGEMENT PLAN
Title:
Program Management Plan
DID for CDRL No.
PM-1
Reference:
COR SOW Section 4.1 Purpose:
Describes how the program is organized and managed. It provides the management structure, its system of operation, responsible lines of communications, and key personnel assignments Preparation Information:
1. The Program Management Plan shall address the overall organization, management approach, and structure of the COR Program plus its interrelationships with the parent company and the subcontractors, and relationship with the Government.
2. The Program Management Plan shall delineate how the requirements of the Statement of Work (SOW) will be achieved and include a description of planned activities for identifiable SOW requirements.
3. The Program Management Plan shall address interfaces with the Government and with any Government Furnished Equipment (GFE) suppliers.
4. The Program Management Plan shall indicate critical paths, long-lead items and significant milestones down to the lowest level of the WBS.
5. The Program Management Plan shall indicate the need for additional definition of spacecraft and mission information, and when this information is required to avoid schedule slippage.
6. The Program Management Plan shall include graphical displays such as flow diagrams, WBS, logic networks, etc., to reduce verbal descriptive material.
7. The Program Management Plan shall provide an organizational chart(s) and sufficient supplemental narrative to describe fully the organization proposed for carrying out the program showing inter- relationships of technical management, business management, and subcontract management, from lower level through intermediate management to top-level management with detailed explanation of:
a. The authority of the COR Program Manager relative to other ongoing programs and applicable support organizations within the company structure.
Discuss the program manager’s control over essential resources and functions necessary to accomplish the work.
b. How and by whom interdepartmental work will be monitored and the authority of the program manager over interdepartmental work.
c. Process to be followed by the program manager in obtaining decisions beyond his/her authority and in resolving priority conflicts for resources and functions
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
not under the program manager’s direct control such as personnel, finances, and facilities.
d. The lead program team members with names, functions, and qualifications
8. The Program Management Plan shall provide contractual procedures proposed for the program to effect administrative and engineering changes, describing any differences from existing procedures.
9. The Program Management Plan shall describe management techniques to be employed in minimizing program costs and schedule impacts, including controls to be exercised over subcontractors and suppliers.
10. The Program Management Plan shall describe how issues will be surfaced in a timely manner and at the proper levels.
11. The Program Management Plan shall describe how supply chain performance will be tracked.
12. The Program Management Plan shall discuss and illustrate the proposed COR Mission Assurance organizational structure, including staffing plans, reporting channels, authority and responsibilities, and management visibility.
13. The Program Management Plan shall discuss whether the technical, test, manufacturing and system safety/quality assurance/ reliability/ configuration management personnel required for this program (as indicated in your proposed labor hours) are presently on payroll and immediately available for this work.
14. The Program Management Plan shall state the number and kind of persons who would have to be hired and plans to obtain them.
15. The Program Management Plan shall describe how the schedules are developed, maintained and updated.
16. The Program Management Plan shall describe how subcontracts will be managed and reviewed and describe the performance milestones of each.
17. The Program Management Plan shall list and describe the planned subsystem reviews.
PM-2 WEEKLY STATUS REPORTS AND TELECON MINUTES
Title:
WEEKLY STATUS REPORTS AND TELECON MINUTES
DID for CDRL No.
PM-2
Reference:
COR SOW Section 4.1 Purpose:
Contract status evaluation.
Preparation Information:
1. The Weekly Status Report shall indicate the status of the contract as of close of business the preceding Friday, including a summary of progress made.
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
2. The Weekly Status Report shall address the work completed during the week against the work planned for the week, and address recovery plans if necessary.
3. The Weekly Status Report shall include technical progress, including significant accomplishments and milestones reached.
4. The Weekly Status Report shall include problems encountered and proposed corrective action.
5. The Weekly Status Report shall indicate any actual or anticipated slip in schedule.
6. The Weekly Status Report shall include identification of any Class I or Class II changes.
7. The Weekly Status Report shall detail the work planned for the next week and summarize the work planned for the next month.
8. The Weekly Status Report shall contain Action Item Status for any overdue action items and any action items due in the next two weeks.
9. The Weekly Status Report shall contain status of any open Non-Conformance
Reports.
10. The Weekly Status Report shall contain status on any open contract actions, including
Special Engineering Analyses.
11. The Weekly Status Report shall contain status on any red risk item.
Note: This weekly report is intended to be timely and informal and should detail the above topics as changes or problems occur.
PM-3 CONFIGURATION MANAGEMENT PLAN
Title:
CONFIGURATION MANAGEMENT PLAN
DID for CDRL No.
PM-3
Reference:
COR SOW Section 4.6 Purpose:
To define the contractor’s configuration management system and provide a means of control for all changes affecting form, fit, or function and any impact on performance, cost or schedule.
Preparation Information:
1. The Configuration Management Plan shall describe the scope, approach, methods, and procedures of the system used to control changes of requirements, design, and any other configuration managed item.
2. The Configuration Management Plan shall describe the organization of the configuration management program and how it relates to the rest of the COR program.
3. The Configuration Management Plan shall list all tools used for configuration management.
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
4. The Configuration Management Plan shall use the following product change classifications:
a. A change or request for Deviation/Waiver is classified as Class I when it affects one or more of the following factors:
i. Program baseline documentation
ii. Technical requirements contained in the product configuration identification, including the following:
1. Form, fit, or function
2. Performance
3. Power
4. Reliability outside stated requirements
5. Weight, balance, moment of inertia
6. Interface characteristics
7. Hardware and process qualifications
iii. Non-technical contractual provisions
1. Fee
2. Incentives
3. Cost
4. Schedule
5. Guarantees or deliveries
iv. Other factors
1. Government-furnished property (GFP)
2. Safety
3. Electromagnetic characteristics
4. Deliverable operational, test, or maintenance computer programs
5. Compatibility with support equipment
b. A change is classified as Class II when it does not fall within the definition of a Class I change.
PM-4 CONFIGURATION CHANGE REQUESTS (CCR) CLASS I
CONFIGURATION CHANGE REQUESTS (CCR) CLASS I
DID for CDRL No.
PM-4
Reference:
COR SOW Section 4.6
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
Purpose:
Class I changes are to be used as a vehicle for orderly processing of change requests to appropriate levels of approval authority for disposition.
Preparation Information:
Class I Configuration Change Requests shall document proposed changes impacting form, fit, function, cost, schedules or performance per the Configuration Management Plan or per the Software Configuration Management Plan section of the Software Management Plan.
PM-5 PROGRAM MANAGEMENT STATUS REVIEW DATA PACKAGE
PROGRAM MANAGEMENT STATUS REVIEW DATA PACKAGE
DID for CDRL No.
PM-5
Reference:
COR SOW Section 4.7.6 Purpose:
To summarize the progress since the previous Program Management Status Review.
Preparation Information:
The Program Management Status Review Data Package shall include the following items:
1. Accomplishments since last review, including 20 milestone events depicting critical items of program status for the succeeding two months with a report on the previous two months milestone events
2. Schedule
3. Technical issues and concerns, including summaries of technical progress and descriptions of the current technical issues and concerns
4. Business issues and concerns, including personnel changes
5. Open contract items
6. Open action items
7. Planned effort for next review period
8. Reliability and quality assurance information
9. Mass properties and power summary
10. Software metrics for each Class A, B or C Computer Software Configuration Item
(CSCI) including:
a. Number of software requirements and their change status
b. Number of software change requests and problem reports and their status
c. Resource utilization estimates and measurements of memory, CPU and I/O
Bandwidth
11. Financial summary including a summary of actuals versus planned manpower
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
12. Subcontractor status including:
a. Efforts under contract
b. Efforts waiting contract award
c. Changes to first tier and sub-tier contractors
d. Change orders, problems, issues
e. Pending subcontractor consent packages
f. Supply chain performance will be tracked using the table below, updated bi-monthly. This includes items 12. a. through 12. e. for subcontracts.
Part Description Supplier Leadtime
Original Date
(on contract)
Delivery Date
Need date
Slack (days)
Affected Constraint
Te ch ni ca l
Sc he du le
C on tra ct
13. A list of actions requested of GSFC management
14. Update of corporate changes, for example: early warning of
a. Restructuring activities (including internal reorganizations)
b. Indirect/direct rate changes
15. Risk assessment including approach for mitigation
16. Any additional data requested by GSFC
PM-6 NASA PROPERTY IN THE CUSTODY OF THE CONTRACTORS
NASA PROPERTY IN THE CUSTODY OF THE CONTRACTORS
DID for CDRL No.
PM-6
Reference:
COR SOW Section 4.2 Purpose:
For budget, cost, and property control Preparation Information:
The NASA Property in the Custody of the Contractors report shall consist of NASA Form 1018 in accordance with NFS 1845.505-14, the instructions on the form, subpart 1845.71, and any supplemental instructions for the current reporting period issued by NASA.
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
PM-7 CONTRACTOR TASK PLAN
Title:
CONTRACTOR TASK PLAN
DID for CDRL No.
PM-7
Reference:
COR SOW Section 4 Purpose:
The task plan is the contractor's resources plan for accomplishing the work described in the task order.
Preparation Information:
The Contractor Task Plan shall be prepared in accordance with the contract ordering mechanism for Special Studies.
PM-8 DOCUMENT TREE
DOCUMENT TREE
DID for CDRL No.
PM-8
Reference:
COR SOW Section 4.6 Purpose:
For ready reference list of all COR and GSE documents.
Preparation Information:
1. The document tree shall list all documents for the COR and separately for the GSE.
2. The document trees shall be organized and identified to serve as a ready reference list.
3. The document tree shall identify documents by name and number.
4. The document tree shall include a brief description defining the scope of each document
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
3 RESOURCE MANAGEMENT
RM-1 EARNED VALUE MANAGEMENT (EVM) PLAN
EARNED VALUE MANAGEMENT (EVM) PLAN
DID for CDRL No.
RM-1
Reference:
COR SOW Section 4.3.1
Purpose:
To provide a comprehensive description of the contractor’s plan for utilizing an earned value management system (EVMS) that complies with the Electronic Industries Alliance (EIA)-748 guidelines.
Preparation Information:
1. The EVMS description or plan shall present the contractor's approach to comply with the EIA-748 guidelines.
2. The EVMS description or plan shall address the processes for conducting variance analysis; developing ongoing comprehensive estimates at completion; flowing down requirements to all applicable subcontracts; and managing technical scope, schedule, cost, and risk.
3. The EVMS description or plan shall address the requirements of NASA’s Federal Acquisition Regulation Supplement (NFS) 1852.234-2 or Alternate I.
4. Guidelines are available in the Earned Value Management Systems EIA-748-D Intent Guide Appendix Compliance Map Template
5. Contractor-selected Format are acceptable
Applicable Documents:
• Industry Guidelines for Earned Value Management Systems, EIA-748-D
• Earned Value Management System, NFS 1852.234-2 (or Alternate I)
• Earned Value Management System, EIA-748-D Intent Guide Appendix Compliance
Map Template
RM-2 FINANCIAL REPORTS
FINANCIAL REPORTS
DID for CDRL No.
RM-2
Reference:
COR SOW Section 4.3.3
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
Purpose:
To provide data necessary for:
a. Projecting cost and hours to ensure that cost and labor resources realistically support the project and its schedules.
b. Evaluating Contractor’s actual cost and fee data in relation to negotiated contract value, estimated costs, and budget forecast data.
c. Planning, monitoring, and controlling project resources.
d. Accruing cost in NASAs accounting system.
Preparation Information:
Financial management reports shall be submitted by the contractor on NASA’s 533 series reports, in accordance with NASA Procedural Requirements (NPR) 9501.2, NASA Contractor Financial Management Reporting (current version), and additional instructions issued by the contracting officer. The following information is required for all 533 series reports:
1. Level of Detail: The contractor’s 533 reports shall contain a summary of total contract costs and per the level specified in the WBS and WBS Dictionary DID (RM-
6) and contract modifications. The reports shall contain a breakdown of hours and costs by the elements of cost categories listed in bullet item (d) below.
2. Variance Narrative Reporting: In accordance with Section 3.6 of NPR 9501.2, the contractor shall include a narrative explanation for variances per items identified exceeding plus or minus 10 percent between the total direct labor hours (prime and subcontractors) and total estimated cost amount shown in the prior month and the actual total direct labor hours and actual total cost amount shown in the current month at the total contract level (for example, the “Estimated Cost Hours to Complete” amount shown for June in column 8a in the May NF 533M report and the “Cost Incurred Actual” June total cost amount shown in column 7a in the June NF 533M report). Each variance narrative shall explain the: (1) reason for the variance, (2) impact(s) on the core baseline and/or each individual task order, and (3) specific corrective action(s) being taken or to be taken.
3. Distribution: The contractor shall distribute 533 reports to each addressee indicated in the contract clause entitled, "Financial Management Reporting." The contractor shall submit an initial report in the NF 533M format within 30 working days after contract award. After the initial report, the NF 533M reports shall be distributed not later than the 10th working day following the close of the contractors' monthly accounting period. The 533Q reports shall be distributed not later than the 15th day of the month preceding the quarter being reported.
4. Reporting Requirements: Each individual report shall, at a minimum, provide cost data (using accruals to match the schedule and earned value management monthly data and end date) by the following elements of cost (EOC) categories and summaries:
a. Prime direct labor hours:
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
i. Prime direct labor hours – onsite
ii. Prime direct labor hours – offsite
iii. Total prime direct labor hours
b. Subcontractor direct labor hours:
i. Subcontractor A direct labor hours – onsite (include once for every subcontractor)
ii. Subcontractor A direct labor hours – offsite (include once for every subcontractor)
iii. Total subcontractors direct labor hours
c. Total prime and subcontractors direct labor hours:
i. Total prime and subcontractors hours – onsite
ii. Total prime and subcontractors hours – offsite
iii. Total prime and subcontractors direct labor hours
d. Prime direct labor costs:
i. Prime direct labor costs – onsite
ii. Prime direct labor costs – offsite
iii. Total prime direct labor costs
e. Prime overhead expenses:
i. Onsite overhead
ii. Offsite overhead
iii. Total prime overhead
f. Other direct costs (ODC):
i. Subcontracts (list separately, Subcontractor A, B, C, etc.)
ii. Material
iii. Travel
iv. Other (specify)
v. Total ODCs
g. Subtotal (direct labor, overhead, and ODCs)
h. General and Administrative expense
i. Total estimated cost
j. Fixed fee
k. Total cost-plus-fee
Check the L1 Series CM tool Server at https://ipdtdms.gsfc nasa.gov/ to verify that this is the correct version prior to use.
5. Financial Period End Date: Financial period end date will reconcile with the schedule status date and the earned value management calendar period end date.
• NPR 9501.2, NASA Contractor Financial Management Reporting
• NASA’s Federal Acquisition Regulation Supplement 1842.72, NASA Contractor Financial Management Reporting
• G.1, Financial Management Reporting (GSFC 52.52.242-90)
•…
This is the start of the file's text. The full file is on GovTribe.