Attachment B Statement of Need.pdf

PDF 120 KB Posted

Attached to
4120--Vertical AC Units Federal contract opportunity
Solicitation number
36C24820Q1235
Issued by
Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 8

About this file

This solicitation from the Department of Veterans Affairs seeks replacement of twenty-five vertical air conditioning and dehumidification units across six trailers at the Malcom Randall VA Medical Center in Gainesville, Florida. Licensed contractors are required to remove the existing units, dispose of them properly, install new higher-efficiency units with dehumidification capabilities from Bard or equivalent matching the specifications provided, replace associated electrical components, and perform start-up services. Contractors must have an applicable Florida state license and 10-hour OSHA construction safety certification. Work must be scheduled on weekdays between 0800 and 1600 hours after coordinating with the contracting officer's representative.

View the file

Other files for this federal contract opportunity

Other files attached to 4120--Vertical AC Units, newest first.
File Type Posted
36C24820Q1235_3.docx DOCX document
Attachment C Price Cost Delivey Schedule - Amended.pdf PDF
Attachment B Statement of Need - Amended.pdf PDF
36C24820Q1235_2.docx DOCX document
Attachment A Combined Synopsis Solicitation SDVOSB.pdf PDF
Attachment C Price Cost Delivey Schedule.pdf PDF
36C24820Q1235.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment B 36C24820Q1235

Statement of Need

Remove and Replace Vertical AC Units

The Malcom Randall VA Medical Center has a requirement to replace twenty-five (25) vertical package units installed in multiple trailers to correct high relative humidity (RH) and temperature issues in the trailers.

OBJECTIVE

A licensed (Florida State Class “A” Air Conditioning or Florida State Mechanical Contractors License) contractor must be brought in to:

Provide “turn-key” replacement of the following vertical package unit air conditioners and dehumidifiers in the following trailers:

1. T-1B: five (5) existing vertical package unit air conditioners two (2) two-and-a-half (2.5) ton vertical package units and two (2) three (3) ton vertical package units and one (1) three-and-a-half (3.5) ton vertical package unit)

2. T-2: four (4) existing four (4) ton Bard vertical package unit air conditioners

3. T-4: four (4) existing three (3) ton Bard vertical package unit air conditioners

4. T-5: five (5) existing three and a half (3.5) ton Bard vertical package unit air conditioners

5. T-6: five (5) existing three (3) ton vertical package unit air conditioners

6. T-8: two (2) existing three (3) ton Bard vertical package unit air conditioners

SCOPE OF WORK

1) Disconnect existing electrical and remove all existing vertical package units. Removal will require soffit and facia removal. These units mount on the outside wall of the trailer and have mounting brackets that hold them in place as well as specific locations for the supply air and return air to pass thru the wall and reach the unit. If another manufacturer is used, it is expected that the contractor will re-work the supply and return connections by closing up existing holes and adding new ones.

2) Requesting the contractor turn over the R-22 refrigerant in the existing units to the VA. Contractor will be responsible for proper refrigerant recovery in recovery drums provided by the VA, for turn-over to the VA AC Shop.

3) Contractor responsible for disposal of old equipment.

4) Install new dehumidification capable vertical package units which meet these salient characteristics for the replacement model. Existing models to be removed are listed below:

a) For Trailer T-1B

i) Two (2) - Bard W30HBDA05 2.5T HP, 208/230VAC, 60HZ, single phase, 11 EER, dehumidification circuit, with 5KW heat strips, with appropriate humidity controlling thermostats.

ii) Two (2) – Bard W36HBDA05 3T HP, 208/230VAC, 60HZ, single phase, 11 EER, dehumidification circuit, with 5KW heat strips, with appropriate dehumidification controlling thermostats.

iii) One (1) – Bard W42HCDA05 3.5T HP, 208/230VAC, 60HZ, single phase, 11 EER, dehumidification circuit, with 5KW heat strips, with appropriate dehumidification controlling thermostat.

b) For Trailer T-2, four (4) Bard W48HCDA05 4T HP, 208/230VAC, 60HZ, single phase, 11 EER, Dehumidification circuit, with 5KW heat strips, with appropriate humidity controlling thermostat.

c) For Trailer T-4, four (4)Bard W36HBDA05 3T HP, 208/230VAC, 60HZ, single phase, 11 EER, Dehumidification circuit, with 5KW heat strips, with appropriate humidity controlling thermostat.

d) For Trailer T-5, five (5) Bard W42HCBD06 3.5T HP, 208/230VAC, 60HZ, single phase, 11 EER, Dehumidification circuit, with 6KW heat strips, with appropriate humidity controlling thermostat.

e) For Trailer T-6

i) Two (2) – Bard W36HBDB06 3T HP, 208/230VAC, 60HZ, three (3) phase, 11 EER, dehumidification circuit, with 6KW heat strips, with appropriate dehumidification controlling thermostats.

ii) Three (3) – Bard W36HBDA05 3T HP, 208/230VAC, 60HZ, single phase, 11 EER, dehumidification circuit, with 5KW heat strips, with appropriate dehumidification controlling thermostat.

f) For Trailer T-8, two (2) new dehumidification capable vertical package units which meet these salient characteristics for the replacement model: Bard W36HBDA05 3T HP, 208/230VAC, 60HZ, single phase, 11 EER, Dehumidification circuit, with 5KW heat strips, with appropriate humidity controlling thermostat.

5) Replace breakers and feeders (wire and conduit) as required.

6) Program all thermostats for cooling temperature range of 72 to 75 degrees and 55% RH between

0700 and 1700, cooling temp of 78 degrees and 55% RH between 1700 and 0700. Heating set point to be set at 68 degrees.

7) Provide and install an outdoor air temperature sensor.

8) Provide and install a remote sensor for return air temperature.

9) Re-install soffit and facia.

10) Conduct start-up in accordance with manufacturers direction – to be verified by VAMC AC Shop personnel.

11) Contractor will remove all construction debris from site and preform proper cleanup.

12) Provide a summary report of all findings and necessary repairs to the COR. Anything the Contractor sees that the VA may need to address is expected to be reported. For example, if rot can be seen when units are removed, etc.

QUALIFICATIONS/LICENSING

1. The contractor shall have a valid Florida State Class “A” Air Conditioning or Florida State

Mechanical Contractors License.

2. The contractor and all of the individuals working on the project site must have taken the OSHA

Certified 10-hour construction safety course.

SAFETY REGULATIONS

1. All OSHA safety regulations shall be observed during the project.

2. The VA Safety Officer shall have full authority to see that the contractor obeys all safety rules and regulations relative to the fulfillment of this project.

3. Provide the necessary barricades/signage where required.

SCHEDULING AND HOURS OF WORK

All work in areas involved shall be scheduled with the COR on first shift, Monday thru Friday, 0800 – 1600.

File details come from the government source that posted it. Updated .