ATTACHMENT A - Inspection Checklist.pdf
PDF 113 KB Posted
- Attached to
- J065--ARJO Lift maintenance
- Solicitation number
- 36C24623Q0239
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 36C24623Q0239_2.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT A
INSPECTION CHECKLIST
Model : ARJO LD10011
Serial Number: Inspector:
Building Number: Date:
Room Number: Bed Number if Applicable:
Checklist Item Pass Fail Corrective Action Taken
Structural Components
Verification of proper connections of structural system to the building's structure including seismic bracing if applicable.
Verification of proper interface of lift unit at ceiling (hard deck or soft tile) and proper installation of all protective features around the support rods and rails/tracks.
Mechanical Components
Inspection of lift motor casing for cracks and alignment.
Visually check all exposed parts.
Check mechanical attachments including all connectors, nuts and bolts.
Check operation of wheels and swivel. Lubricate and clean as needed.
Verification that all rail end stops are in place and tightened.
Confirm track is clean and clear of all debris.
Inspection of spreader bar and clips for cracks and for loose or missing rings or cotter pins.
Electrical Components
Visually check all electrical components and scales if applicable.
Visually check battery charger and battery.
Confirm any and all motor case indicator lights are functioning (e.g., red service warning light, charging state light).
Operational Test
Check handset & cable. Inspection and activation of hand control for full operation (e.g., up, down, left, right) and “return to charge” function if applicable.
Verification of any “soft start” or “soft stop” features and that lifting speed does not exceed 2.5 inches per second with “zero” load.
Inspection and activation of emergency up/down motor case control buttons if applicable.
Straps and Slings
Full extension and inspection of lift strap for loose threads or frays.
Inspection of sling material and sling stitching for loose threads or frays.
Annual Load Test
Verification of load testing and deflection testing at lift listed maximum for each lift unit at its maximum rated lift capacity. Conduct this test in three progressive stages starting with a 100 lbs load, then 50% of maximum rated lift capacity, then 100% of maximum rated lift capacity.
Verification of any “soft start” and “soft stop” features and that lifting speed does not exceed 1.5 inches per second under maximum rated lift capacity.
Verification of function of emergency brake at maximum rated lift capacity.
Verification of emergency lowering feature at maximum rated lift capacity.
Comments/Concerns:
File details come from the government source that posted it. Updated .