This document is a procedural guide issued by the South Carolina Department of Transportation (SCDOT) Office of Engineering Support that outlines the baseline encroachment permitting application process for commercial development accesses. The guide details the Commercial Development Encroachment Permit Process Flow and serves as an educational resource for both SCDOT permitting staff and customers seeking to access the State's right-of-way. The process begins with an optional preliminary meeting between the applicant and SCDOT staff to identify potential conflicts and design issues. Applications are submitted electronically through the Encroachment Permit Processing System (EPPS), which assigns a unique application number and routes the submission to either a County Permit Manager or District Permit Engineer depending on permit type and work location. Commercial development driveway permits are assigned to District Permit Engineers at the District level. The applicant has one year from the approval date to complete permitted work, and SCDOT performs a final inspection upon completion to ensure compliance with Department standards and specifications.
The permitting process includes multiple review stages: a cursory review assessing immediate design concerns and application completeness; identification of project complexities such as traffic signals or auxiliary lanes; and a technical review utilizing Department design guidelines. If review comments require customer action, SCDOT compiles a comment matrix and returns it to the applicant through EPPS for corrections and resubmission. Applications may require additional review by SCDOT Headquarters Engineering Support Staff for matters involving interstate right-of-way, new structures, or school sites. If an application cannot proceed due to design conflicts, the applicant may request an Access Waiver or Design Exception or withdraw the application. Denied applications may be appealed to the Deputy Secretary for Engineering within 60 days. Upon approval, EPPS generates an Encroachment Permit Number and notifies the customer. After work completion and final inspection, SCDOT releases any Bond or Letter of Credit to the applicant. The document notes this is procedural guidance and does not constitute a binding standard, specification, or regulation, as other encroachment permit types may follow different processes.
View the file
Other files for this state and local contract opportunity
| File | Type | Posted |
|---|---|---|
| ATTACHMENT B EPPS Report.pdf | ||
| EncroachPerm App RFI.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Commercial Development Encroachment Permit Process Flow
SCDOT’s baseline encroachment permitting application process for commercial development accesses.
(intentionally left blank)
South Carolina Department of Transportation – Office of Engineering Support
Commercial Development Encroachment Permitting Desk Procedures 1
Commercial Development Encroachment Permit Process Flow
SCDOT provides several encroachment permitting options to customers wishing to access the State’s right-of-way. Commercial Development encroachment permit applications, “DRIVEWAY – COMERCIAL” type within the Encroachment Permit Processing System (EPPS), often require the most attention of the Department’s permitting staff.
The following outline accompanies the “Commercial Development Encroachment Permit Process Flow” chart (Attachment A) and is intended to serve as a succinct overview of the Department’s baseline encroachment permitting application process for commercial development accesses. Some applications, depending on their complexity, context and type, may require additional steps or procedures not covered in this document.
Notice
This document is provided in the interest of procedural knowledge and acquaintance of the Department’s Commercial Development Encroachment Permit review process and does not constitute a standard, specification, or regulation. The Department provides other encroachment permit type options to customers and those processes may differ from the one outlined in this document.
1.0 Preliminary Meeting With Necessary Staff
At the forefront of a successful application review, is continued communication. Before a customer wishes to apply for encroachment, they should be strongly encouraged (even required if the complexity and context calls for it), to meet preliminarily with Department permitting staff. Preliminary meetings help to ensure customers are aware of potential location and design conflicts, as well as to help permitting staff stay aligned with other nearby projects.
2.0 Application Received by EPPS
When a customer is ready to apply for encroachment, applications and supporting materials are required to be submitted electronically via EPPS. Once the customer fills out the necessary application fields and uploads all relevant documents, EPPS will assign the project an
Commercial Development Encroachment Permit Process Flow
Application Number. This number will be the identification number for permitting staff and the customers to refer to during the review process.
The customer will receive application status notifications from EPPS as the permit staff completes progressive steps.
3.0 Application Assigned to Permit Staff by EPPS
Depending on the permit type and the area in which the work is intended to be performed, EPPS will electronically notify and assign the application to the appropriate permitting staff. Some applications will be assigned to a County Permit Manager (CPM) at the local County Maintenance level; while others will be assigned to a District Permit Engineer at the District level.
Permit types assigned to County permitting staff, CPM:
• Bus Shelters
• Communications (Cable TV, Telephone, & Other)
• Drainage
• Driveway - Single Residential
• Driveway - Temporary Construction
• Electric
• Environmental
• Gas
• Landscaping
• Park and Ride
• Railroad Crossing
• Resurfacing
• Sewer
• Signs
• Traffic Calming
• Traffic Control, Special Event
• Water
Permit types assigned to District permitting staff, DPE:
• Driveway - Commercial
• Driveway - Multiple Residential/Subdivision
• Multi County, Same District, Fiber Optic Broadband
• Municipality/Locally Funded Project
• Road Connection (non-Driveway)
• Schools
• Blanket Permits
• Other
Commercial Development Encroachment Permitting Desk Procedures 3
The DPE or CPM assigned to the application will be the primary point of contact throughout the permitting process.
4.0 Permit Staff Performs a Cursory Review
Before a technical review can begin, permitting staff perform a cursory review. At this stage, the application is reviewed for any immediate concerns, application package completeness, and apparent issues that might delay the process.
4.1 Are there immediate apparent concerns with the site
design that would prevent the permit from moving forward?
Most permitting concerns can be captured and discussed during a preliminary meeting; however, if a preliminary meeting was not held, or if any changes were made since the preliminary meeting, permitting staff first review the site design contextually for any apparent concerns.
These are considered issues that would cause an immediate delay in the review process, such as proximity conflicts with an active project, work that conflicts with a previously agreed upon concept, or perceived project complexities that might require multi-level reviews.
If the permitting staff does not recognize any immediate concerns, the application is reviewed for completeness, as covered in procedural step 4.2.
If the permitting staff recognize concerns that might delay the process, the review is paused and a meeting with all necessary staff is scheduled to determine the best path forward. Project meetings might include internal staff only to outline specific needs the customer must address, or a meeting with the customer to discuss possible alternatives, as covered in procedural step 4.4.
4.2 Is the application submission complete?
SCDOT utilizes an Encroachment Permit Application Checklist (available as Appendix C-3 in the Access and Roadside Management Standards, ARMS) to review the application for completeness and to ensure permitting staff have all of the information required to perform a review. If the application is missing any of these necessary application components, permitting staff are unable to continue successfully with the review and the missing items are noted to be relayed back to the customer, as covered in procedural step 7.0.
4.3 Are there project complexities that need to be
addressed (Traffic Signal, auxiliary lanes, roundabout, turn lanes, etc.)?
If the application submission is complete, permitting staff review the application for project complexities, such as the need for a traffic signal or study, auxiliary lanes, or multiple turn lanes. Permitting staff take the time to recognize these complexities in order to prepare themselves and the customer that there could be possible delays.
If permitting staff recognize complexities that need to be addressed, the review is paused and a meeting with all necessary staff is scheduled to determine the best path forward. The project meeting might include internal staff only to outline specific needs the customer must address, or a meeting with the customer to discuss possible alternatives, as covered in procedural step 4.4.
If there are no project complexities that need immediate attention, or the complexities have already been address through a submitted traffic study, or discussed at a preliminary meeting, permitting staff continues with a technical review, as covered in procedural step 5.0.
4.4 Meeting with necessary staff to discuss alternatives?
When necessary, the review process is paused and a meeting is scheduled to discuss possible alternatives. The meeting may include internal staff, the customer, or both.
4.4.1 Can any of the complexities be resolved by a reasonable site redesign?
Permitting staff review the site design and recognize any needs for reasonable adjustments, such as a shift in the proposed driveway alignment, a reduction in the number of proposed driveways, or additional site clearing, to eliminate or reduce conflicts with design standards.
If reasonable adjustments can be made to the site design so that a review can continue, the adjustments are compiled in a comment matrix and submitted to the customer, as covered in procedural step 7.0.
Commercial Development Encroachment Permitting Desk Procedures 5
4.4.2 Can any of the complexities by resolved by a justifiable waiver or design exception?
If the submitted site design or a resubmitted adjusted site design is the best alternative, but does not meet the Department’s design standards, the Department may consider accepting the design with an Access Waiver or Design Exception.
An Access Waiver (ARMS, Section 1E-2, “Access Waivers”, and Appendix C-5) will only be granted if is determined that:
1. Denial of the waiver will result in loss of reasonable access to the site.
2. The waiver is reasonably necessary for the convenience and welfare of the public.
3. All reasonable alternatives that meet the access requirements have been evaluated and determined to be infeasible.
4. Reasonable alternative access cannot be provided.
5. The waiver will not result in any violations of pedestrian accessibility in accordance with the ADAAG
A Design Exception (ARMS, Section 1E-1, “Design Exceptions”) is required when the proposed design does not meet the Department or AASHTO standards for design speed, lane width, shoulder width, horizontal curve radius, super-elevation rate, horizontal curve radius, stopping sight distance (SSD), maximum grade, vertical clearance, or design loading structural capacity. The standard form for Design Exception Requests can be downloaded from the SCDOT website.
If the complexity can be resolved through an Access Waiver or Design Exception, the DPE or CPM continues with the application technical review, as covered in procedural step 5.0.
The need for an Access Waiver or Design Exception is noted in a comment matrix along with any other comments to be returned to the customer at a later time.
If a reasonable site design adjustment cannot be made to meet acceptable design standards, or if an Access Waiver or Design Exception cannot settle the complexities, the application review cannot continue.
4.4.3 Does the customer wish to “Withdraw” their application?
When permitting staff is unable to continue reviewing the application, the customer has the option to withdraw their application within EPPS. Otherwise, the DPE or CPM concludes any further review by denying the application within EPPS, as covered in procedural step 4.5.
4.4.3.1 Customer withdraws application.
The customer withdraws their application within EPPS and the application is archived. If the customer decides later to submit a redesign of the same project site, a new application must be submitted.
4.5 Permit Staff denies the application in EPPS.
As per the ARMS, Chapter 1, Section 1B “Authority”, the Department “reserves the right to deny or revoke any encroachment that is deemed detrimental…” This includes applications in the early stages of review when a site design is unable to meet design standards through site redesign, Access Waiver, or Design Exception.
4.5.1 Does the customer wish to “Appeal” the decision?
As per the ARMS, Chapter 2, Section 2E “Encroachment Permit Appeal Process Request”, when an application is not approved during the review process, a customer may appeal the decision to the Deputy Secretary for Engineering (DSE) within 60 days from the date of the denial.
If the customer wishes to appeal the decision, Section 2E and Appendix C-7 of the ARMS outlines the procedural steps and an outline of the decision process.
4.5.1.1 Customer submits a formal Appeal to the DSE.
The appeal letter to the DSE shall be submitted to the permit point of contact. The permitting staff will compile the letter and all supporting information and forward to the DSE.
4.5.1.2 DSE reviews the application.
The DSE, with the aid of support staff, collects any additional information needed, reviews all materials, and provides a final decision.
Commercial Development Encroachment Permitting Desk Procedures 7
4.5.1.3 Is the application Approved or Denied?
The DSE makes the final decision for all appealed applications.
If the appeal is approved, the decision is relayed to the permitting staff for final approval processing, as covered in procedural step 8.0.
If the appeal is denied, permitting staff prepares a final denial letter, as covered in procedural step 13.0.
5.0 Internal Permit Staff Review
After an adequate cursory review, the application is given a technical review utilizing the Departments design guidelines. A list of the checklists and guidelines permitting staff uses during the review process are available from SCDOT’s encroachment permit website.
5.1 Does the application need to be reviewed by HQ
Engineering Support Staff?
If the permitting staff requests additional supporting reviews, or the application requires additional reviews by other departments within SCDOT, such as approval for work within interstate right-of-way, new or rehabilitated structures, or school site reviews, the DPE or CPM forwards the application within EPPS to the State Encroachment Permit Engineer office.
5.1.1 Permit Staff routes application to HQ Engineering Support for review.
The State Encroachment Permit Engineer office disburses the application through necessary Headquarters departments for a concurrent review.
At the conclusion of all concurrent reviews (usually within 15 calendar days), review comments are compiled and forwarded back to the permitting staff.
6.0 Permit Staff Completes Review and Compiles Comments.
After a cursory and/or technical review by permitting staff, there may be review comments that outline general notes, errors, or conflicts.
These comments are compiled and stored as part of the review documents within EPPS for later reference.
6.1 Do any review comments need to be addressed by the
customer?
There may be times that review comments do not require any action by the customer; however, if any comments require action, the permitting staff will compile the relevant comments and return to the customer within EPPS, as covered in procedural step 7.0.
If there are no comments to be addressed or acknowledged by the customer, the permitting staff is ready to close all review comments and continue with the approval process, as covered in procedural step 8.0
7.0 Permit Staff Compiles a Comment Matrix and Returns to
Customer
If any of the review notes from procedural step 6.0 require the customer to acknowledge or address for correction, permitting staff will make the comment matrix available to the customer within EPPS to retrieve and review.
7.1 Customer makes corrections and resubmits.
Each review iteration (where comments were submitted) requires the customer to address all comments within the matrix. A comment matrix may require the customer to provide additional information, adjust the details of the site design, or simply acknowledge the inclusion of certain design standards without the need for a resubmission. The customer should provide all updated materials within EPPS.
8.0 Permit Staff Closes All Comments and Signs the Application as Approved
After all technical reviews have been completed and any review comments have been addressed, permitting staff note within the comment matrix that all review comments have been addressed and the comment matrix is closed. Permitting staff then sign the application as “Approved” on the permit application and within EPPS and prepare any final special provisions to the permit.
Commercial Development Encroachment Permitting Desk Procedures 9
9.0 EPPS Assigns a Permit Number and Applicant Is Provided an Approved Permit
After the permitting staff has approved the permit, EPPS will generate an Encroachment Permit Number and will notify the customer of their final approved permit.
10.0 Applicant Performs Work According to the Approved Permit The customer has one-year from the approval date to complete the work approved by the encroachment permit. Any revisions or supplements requested by the customer, require further review and approval by the Department. If the customer requires additional time to complete the permitted work, the customer should request, in writing, an extension to the permit before the expiration date of the original permit.
11.0 Permit Staff Makes a Final Inspection
As outline in the ARMS, Chapter 13, Section 13B “Inspection and Approval”, after the customer has completed the permitted work, the Department will perform a final inspection of the site.
During this time, the permitting staff ensure the permitted work has been completed according to Department standards and specifications and according to the permit drawings and special provisions. If there are any discrepancies, the customer is notified so that corrections can be made in a timely manner.
12.0 Permit Staff Releases Bond/LOC to the Applicant
After the Department determines the work has been completed satisfactorily, any Bond or Letter of Credit is released back to the customer.
13.0 Permit Staff Generates a Final Letter of Denial
If the application requires a denial, either by cursory/technical review or by the appeal process, the permitting staff generates a final letter of denial to the customer and the application is archived, as covered in procedural step 14.0.
14.0 Permit Staff Archives the Permit Within EPPS
Archival is the final step in the application process. Within EPPS, the permitting staff archives all approved, denied, and withdrawn applications and permits, and their accompanying documents, for future reference.
Commercial Development Encroachment Permitting Desk Procedures 11
Attachment A
Commercial Development Encroachment Permit Process Flow
(intentionally left blank)
2.0 Application received by
EPPS
3.0 Application assigned to
Permit Staff by EPPS
4.0 Permit Staff performs a
cursory review
4.1 Are there immediate
apparent concerns with the site design that would prevent the permit from moving forward?
4.2 Is the
application submission complete?
7.0 Permit Staff compiles
a comment matrix and returns to customer
7.1 Customer makes
corrections and resubmits
4.4 Meeting with
necessary staff to discuss alternatives
4.3 Are there project
complexities that need to be addressed? (Traffic Signal, auxiliary lanes, roundabout, turn lanes, etc)
1.0 Preliminary Meeting with
necessary staff
Page 2 Page 2
4.4.1 Can any of the
complexities be resolved by a reasonable site redesign?
NO
NO NO
NO
YES
YES
YES
YES
Customer wishes to apply for SCDOT encroachment
Commercial Development Encroachment Permit Process Flow This flowchart outlines the Department's Encroachment Permit process for most commercial development applications.
Pa ge
4.4.3 Does the customer
wish to "Withdraw" their application?
Page 1 Page 1
4.5 Permit Staff denies
the application in EPPS
4.5.1 Does the customer
wish to "Appeal" the decision?
4.5.1.1 Customer submits a
formal Appeal to the DSE
Page 3 Page 3Page 3
5.0 Internal Permit Staff
review
5.1 Does the application
need to be reviewed by
HQ Support Staff?
4.4.2 Can any of the
complexities be resolved by a justifiable waiver or design exception?
YES
NO
NO
YES
NO
5.1.1 Permit Staff routes
application to HQ Support for review
YES
NO
Pa ge
YES
Page 2 Page 2Page 2 Page 2Page 2
6.0 Permit Staff completes
review and compiles comments
6.1 Do any review
comments need to be addressed by the customer?
8.0 Permit Staff closes all
comments and signs the application as approved
YES
NO
9.0 EPPS assigns a Permit
Number and applicant is provided an approved permit
4.5.1.2 DSE reviews the
application
4.5.1.3 Is the application
Approved or Denied?
11.0 Permit Staff makes a final
inspection
10.0 Applicant performs
work according to the approved permit
Approved
Denied
Pa ge
12.0 Permit Staff releases
Bond/LOC to the applicant
14.0 Permit Staff archives the
permit within EPPS
Project Complete
4.4.3.1 Customer
withdraws application
Page 3Page 3
13.0 Permit Staff generates a
final letter of denial
Pa ge
This flowchart accompanies the Department's "Commercial Development Encroachment Permitting Desk Procedures; Commercial Development Encroachment Permit Process Flow".
Produced by the staff of the State Encroachment Permit Engineer, Office of Engineering Support.
version 2.0.0 February 2023.
| Commercial Development Encroachment Permit Process Flow |
| 1.0 Preliminary Meeting With Necessary Staff |
| 2.0 Application Received by EPPS |
| 3.0 Application Assigned to Permit Staff by EPPS |
| 4.0 Permit Staff Performs a Cursory Review |
| 4.1 Are there immediate apparent concerns with the site design that would prevent the permit from moving forward? |
| 4.2 Is the application submission complete? |
| 4.3 Are there project complexities that need to be addressed (Traffic Signal, auxiliary lanes, roundabout, turn lanes, etc.)? |
| 4.4 Meeting with necessary staff to discuss alternatives? |
| 4.4.1 Can any of the complexities be resolved by a reasonable site redesign? |
| 4.4.2 Can any of the complexities by resolved by a justifiable waiver or design exception? |
| 4.4.3 Does the customer wish to “Withdraw” their application? |
| 4.4.3.1 Customer withdraws application. |
| 4.5 Permit Staff denies the application in EPPS. |
| 4.5.1 Does the customer wish to “Appeal” the decision? |
| 4.5.1.1 Customer submits a formal Appeal to the DSE. |
| 4.5.1.2 DSE reviews the application. |
| 4.5.1.3 Is the application Approved or Denied? |
| 5.0 Internal Permit Staff Review |
| 5.1 Does the application need to be reviewed by HQ Engineering Support Staff? |
| 5.1.1 Permit Staff routes application to HQ Engineering Support for review. |
| 6.0 Permit Staff Completes Review and Compiles Comments. |
| 6.1 Do any review comments need to be addressed by the customer? |
| 7.0 Permit Staff Compiles a Comment Matrix and Returns to Customer |
| 7.1 Customer makes corrections and resubmits. |
| 8.0 Permit Staff Closes All Comments and Signs the Application as Approved |
| 9.0 EPPS Assigns a Permit Number and Applicant Is Provided an Approved Permit |
| 10.0 Applicant Performs Work According to the Approved Permit |
| 11.0 Permit Staff Makes a Final Inspection |
| 12.0 Permit Staff Releases Bond/LOC to the Applicant |
| 13.0 Permit Staff Generates a Final Letter of Denial |
| 14.0 Permit Staff Archives the Permit Within EPPS |
| Quality Assurance Statement |
| Notice |
| Attachment A |
| Commercial Development Encroachment Permit Process Flow |
| EP Desk Procedures - Commercial Development Encroachment Permit Process Flow_Cover Sheet.pdf |
| Commercial Development Encroachment Permit Process Flow |
| EP Desk Procedures - Commercial Development Encroachment Permit Process Flow_Cover Sheet.pdf |
| Commercial Development Encroachment Permit Process Flow |
| EP Desk Procedures - Commercial Development Encroachment Permit Process Flow_edited.pdf |
| Commercial Development Encroachment Permit Process Flow |
| Notice |
| 1.0 Preliminary Meeting With Necessary Staff |
| 2.0 Application Received by EPPS |
| 3.0 Application Assigned to Permit Staff by EPPS |
| 4.0 Permit Staff Performs a Cursory Review |
| 4.1 Are there immediate apparent concerns with the site design that would prevent the permit from moving forward? |
| 4.2 Is the application submission complete? |
| 4.3 Are there project complexities that need to be addressed (Traffic Signal, auxiliary lanes, roundabout, turn lanes, etc.)? |
| 4.4 Meeting with necessary staff to discuss alternatives? |
| 4.4.1 Can any of the complexities be resolved by a reasonable site redesign? |
| 4.4.2 Can any of the complexities by resolved by a justifiable waiver or design exception? |
| 4.4.3 Does the customer wish to “Withdraw” their application? |
| 4.4.3.1 Customer withdraws application. |
| 4.5 Permit Staff denies the application in EPPS. |
| 4.5.1 Does the customer wish to “Appeal” the decision? |
| 4.5.1.1 Customer submits a formal Appeal to the DSE. |
| 4.5.1.2 DSE reviews the application. |
| 4.5.1.3 Is the application Approved or Denied? |
| 5.0 Internal Permit Staff Review |
| 5.1 Does the application need to be reviewed by HQ Engineering Support Staff? |
| 5.1.1 Permit Staff routes application to HQ Engineering Support for review. |
| 6.0 Permit Staff Completes Review and Compiles Comments. |
| 6.1 Do any review comments need to be addressed by the customer? |
| 7.0 Permit Staff Compiles a Comment Matrix and Returns to Customer |
| 7.1 Customer makes corrections and resubmits. |
| 8.0 Permit Staff Closes All Comments and Signs the Application as Approved |
| 9.0 EPPS Assigns a Permit Number and Applicant Is Provided an Approved Permit |
| 10.0 Applicant Performs Work According to the Approved Permit |
| 11.0 Permit Staff Makes a Final Inspection |
| 12.0 Permit Staff Releases Bond/LOC to the Applicant |
| 13.0 Permit Staff Generates a Final Letter of Denial |
| 14.0 Permit Staff Archives the Permit Within EPPS |
| Attachment A |
| Commercial Development Encroachment Permit Process Flow |