This is a Vendor Information Request (VIR) form template used by the NUWCDIVNPT TAHE Facility (Naval Undersea Warfare Center Division Newport Towed Array Handling Equipment Facility) to resolve technical questions or problems involving work orders. The form consists of 25 numbered blocks, with blocks 2-18 to be completed by vendors and blocks 1, 19-25 to be completed by the TAHE Facility.
The form requires vendors to provide company information, part details, quantities, serial numbers, descriptions of technical issues or nonconformances, causes, recommended corrective actions, delivery impacts, and cost implications. The TAHE Facility portion includes logistical acceptability checks, technical reviews, engineering dispositions, and final approvals. Two versions of the completed form are maintained - a vendor copy containing only response and signature information, and a TAHEF copy retaining all internal information for archiving. The form is associated with solicitation N6660425Q0143 for Capstan Main Frame Fabrication, where it serves as an attachment for vendors to report technical issues or request information during contract performance.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| II.E. RFQ N6660425Q0143-0002 Amendment.pdf | ||
| RFQ N6660425Q0143-0001 Capstan Main Frame.pdf | ||
| Attachment 2 - Contract Data Requirements List (CDRLs).pdf | ||
| Attachment 4 - Receipt Inspection Report (RIR).pdf | ||
| Attachment 6 - Welding Cert letter.doc | DOC document | |
| Attachment 1 - Statement of Work.pdf | ||
| Attachment 3 - MIL Performance - Detail - and Standard Specifications.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TAHEF-Form-No. 007 Rev A
NUWCDIVNPT TAHE FACILITY
NUWC, BLDG 6 NEWPORT, RI 02841
Revision Date: 7/3/2023
(REFER TO INTRUCTIONS)
VENDOR INFORMATION REQUEST 1. VIR NO.:
2. SUPPLIER NAME AND ADDRESS 3. DATE
4. DATE DISPOSITION
REQUIRED
5. MATERIAL NOMENCATURE 6. W0 7. PART NUMBER 8. QUANTITY 9. SERIAL NUMBER
10. STATUS OF PART
11. DESCRIPTION:
12. CAUSE OF NONCONFORMANCE:
13. RECOMMENDED CORRECTIVE ACTION:
14. RECOMMENED DISPOSITION:
15. TECHNICAL JUSTIFICATION AND PURCHASER’S BENEFIT:
16. DELIVERY IMPACT
YES [] NO []
17. COST IMPACT
YES [] NO []
IF DISAPPROVED,
DELIVERY WILL BE:
IF YES, REPAIR COST
IF APPROVED, DELIVERY
WILL BE:
IF YES, REPLACMENT COST
THE VENDOR ACCEPTS FULL
RESPONSIBILITY FOR THE
CORRECTNESS OF
INFORMATION AFFECTING
THE ABOVE PARTS
18. REPORTED BY:
SIGNATURE:
PHONE:
VENDOR: PLEASE DO NOT WRITE ON PAGE 2
SEE PAGE 2 FOR TAHEF RESPONSE
Not Started In Process Completed
Typed/Wet Sign Digital Signature
NUWC, BLDG 6 NEWPORT, RI 02841
Revision Date: 7/3/2023
19. VIR POC DATE VIR RECEIVED
PRIORITY ROUTINE []
URGENT []
SOW# WO#
20. LOGISTICAL ACCEPTABILITY
PRODUCTION
REQUIRED []
PRODUCTION SCHEDULE IMPACT
YES [] NO[]
TECHNICIAN ASSIST/INPUT
YES [] NO []
SIGNED
PLANNING or INVENTORY
REQUIRED []
DELIVERY SCHEDULE IMPACT
YES [] NO[]
REPLACMENT PARTS
YES [] NO []
SIGNED
LIBRARY
REQUIRED []
LATEST DWG/STD
YES [] NO[]
OTHER DOCUMENTATION NEEDED
YES [] NO []
SIGNED
PURCHASING
REQUIRED []
ALTERNATE PROCURMENT
YES [] NO[]
COST JUSTIFIED
YES [] NO []
SIGNED
QUALITY ASSURANCE
REQUIRED []
QUALITY ISSUES
YES [] NO[]
NEW/REVISED RIR REQUIRMENTS
YES [] NO []
SIGNED
LOGISTICS NOTES:
21. TECHNICAL ACCEPTABILITY
ENGINEERING DISPOSITION:
RPR REQUIRED
Y[] N[]
RFV REQUIRED Y[] N[]
MAJOR []
MINOR []
ISEA/TDA REQUIRED
ENGINEERING RECCOMENDATION
APPROVE
CONDITIONALLY APPROVE
DISAPPROVE
ENGINEERING SIGNED: PROGRAM MANAGER SIGNED:
APPROVALS
22. FINAL DISPOSITION:
APPROVE
CONDITIONALLY APPROVE
DISAPPROVE
TAHEF MANAGER SIGNED: 23. ISEA or TDA (as required) SIGNED:
24. RESPONSE TO VENDOR:
NOTICE TO SUPPLIER: THE DISPOSITION OUTLINED ABOVE IS
APPLICABLE TO THE MATERIAL ON THIS VIR ONLY. SHIPPING
DOCUMENTS FOR THIS MATERIAL MUST REFERENCE THIS VIR.
25. RESPONSE SENT TO SUPPLIER BY
PURCHASING:
VERSION: Vendor Copy TAHEF Copy
Y[] N[]
Revision Date: 7/3/2023
NUWCDIVNPT TAHE FACILITY
NUWC, BLDG 6 NEWPORT, RI 02841
VENDOR INFORMATION REQUEST FORM INSTRUCTIONS
A PROPERLY APPROVED VENDOR INFORMATION REQUEST (VIR) IS REQUIRED TO RESOLVE TECHNICAL QUESTIONS OR
PROBLEMS INVOLVING TOWED ARRAY HANDLING EQUIPMENT FACILITY WORK ORDERS.
TO FACILITATE THE PREPARATION OF THE FORM, A BRIEF DESCRIPTION APPEARS BELOW INDICATING THE INFORMATION REQUIRED TO BE ENTERED IN THE APPROPRIATE BLOCK. IF MULTIPLE PAGES ARE REQUIRED, LINK
ADDITIONAL PAGES BY BLOCK NUMBER TO THE FIRST PAGE.
BLOCK NO. ENTRY (BLOCKS 2-18 TO BE FILLED IN BY VENDOR)
(BLOCKS 1, 19-25 TO BE FILLED IN BY TAHE FACILITY)
To be completed by vendor:
1. VIR number will be provided after VIR disposition. Refer to this number (provided by the towed array facility) on any inquiry. Record this number on the packing list prior to shipping.
2. Enter your full company name and mailing address.
3. Enter the date the entries are being made.
4. Provide a date a response in needed in order to avoid delay of delivery.
5. Enter the nomenclature of the part that appears on the purchase order.
6. If not populated, enter the TAHEF work order number that pertains to the purchase/service.
7. Indicate the part number affected.
8. Quantity of pieces affected by VIR (not quantity ordered).
9. Serial number of piece affected, where applicable.
10. Check appropriate part status block.
11. Describe the specific problem/question/proposed change, or nonconformance in detail:
• indicate what, if anything, is nonconforming
• when proposing a material substitution, include a full description of the substitute material (i.e.: alloy, class, condition or temper, specification, etc.).
Attach a copy of the test report for the material if available or with the shipment of the completed hardware.
• when reporting a nonconformance involving the heat treatment of material, a copy of the applicable heat treatment procedure used should be attached.
• when reporting chemical and mechanical nonconformance, attach a copy of the test report applicable listing both chemical and mechanical test results of the material.
• use a continuation or sketch sheet if this space is inadequate to show a sketch or to fully describe the problem
12. Indicate what the cause of the nonconformance is.
13. Indicate the recommended corrective action.
14. Indicate the recommended disposition.
15. Include the technical justification for accepting permanent nonconformance by indicating the effect of the deviation on the form, fit or function of the material, part or component. State clearly if unable to provide technical justification. Provide rationale for perceived benefit to purchaser.
16. Indicate if delivery is impacted. If so indicate delivery date for approval/disapproval.
17. Indicate if cost is impacted. For outside services include repair vs replacement cost.
18. Provide name of person to contact in case of any questions regarding VIR.
19. VIR can be sent to the VIR POC via the email provided or the TAHEF representative who solicits the quote.
To be completed by TAHEF:
20. If required by the VIR POC, departments enter required information. Mark each block as applicable. Signature required if department input is required.
NUWC, BLDG 6 NEWPORT, RI 02841
Revision Date: 7/3/2023
21. Engineering enter required information. Mark each block as applicable. Engineering and program manager signatures required.
22. Mark final disposition as applicable. TAHEF manager signature required.
23. ISEA/TDA signature as required by block 21.
24. Engineering: respond to vendor reflecting final disposition and path forward. Two copies should be saved, a vendor copy and
TAHEF copy. The vendor copy should only have the response to vendor and signatures on the second page, redact internal information as required. The TAHEF copy should include all internal information as written for archiving purposes.
25. WARNING: Selecting "Vendor Copy" will erase all "Need to Know" information from the form.
Engineering: Select and save a version of both TAHEF and Vendor Copy. Send both versions to the VIR POC for archiving and send the vendor copy to Purchasing.
Purchasing: Sign and date completed VIR just before sending to the vendor.
| 1 VIR NO: |
| 2 SUPPLIER NAME AND ADDRESS: |
| 3 DATE: |
| 4 DATE DISPOSITION REQUIRED: |
| 5 MATERIAL NOMENCATURE: |
| 6 W0: W04859 |
| 7 PART NUMBER: |
| 8 QUANTITY: |
| 9 SERIAL NUMBER: |
| 11 DESCRIPTION: |
| 12 CAUSE OF NONCONFORMANCE: |
| 13 RECOMMENDED CORRECTIVE ACTION: |
| 14 RECOMMENED DISPOSITION: |
| 15 TECHNICAL JUSTIFICATION AND PURCHASERS BENEFIT: |
| IF DISAPPROVED DELIVERY WILL BE: |
| IF YES REPAIR COST: |
| IF APPROVED DELIVERY WILL BE: |
| IF YES REPLACMENT COST: |
| 18 REPORTED BY: |
| PHONE: |
| 19 VIR POC: |
| DATE VIR RECEIVED: |
| SOW: |
| WO: W04859 |
| LOGISTICS NOTES: |
| ENGINEERING DISPOSITION: |
| 24 RESPONSE TO VENDOR: |
| Check Box7: Off |
| Check Box8: Off |
| Check Box10: Off |
| Check Box1: Off |
| Check Box2: Off |
| Check Box3: Off |
| Check Box4: Off |
| Check Box5: Off |
| Check Box6: Off |
| Check Box9: Off |
| Check Box11: Off |
| Check Box12: Off |
| Check Box13: Off |
| Check Box14: Off |
| Check Box15: Off |
| Check Box16: Off |
| Check Box17: Off |
| Check Box18: Off |
| Check Box19: Off |
| Check Box20: Off |
| Check Box21: Off |
| Check Box22: Off |
| Check Box23: Off |
| Check Box24: Off |
| Check Box25: Off |
| Check Box26: Off |
| Check Box27: Off |
| Check Box28: Off |
| Check Box29: Off |
| Check Box30: Off |
| Check Box31: Off |
| Check Box32: Off |
| Check Box33: Off |
| Check Box34: Off |
| Check Box35: Off |
| Check Box36: Off |
| Check Box37: Off |
| Check Box38: Off |
| Check Box39: Off |
| Check Box40: Off |
| Check Box41: Off |
| Check Box42: Off |
| Check Box43: Off |
| Check Box44: Off |
| Check Box45: Off |
| Check Box46: Off |
| Check Box47: Off |
| Check Box48: Off |
| Group25: Off |
| Vendor Typed/Wet Signature: |
| Group26: Off |
File details come from the government source that posted it. Updated .