Attachment 4 - Procurement Timeline.pdf
PDF 84 KB Posted
- Attached to
- Enterprise Vulnerability Scanning Solution (EVSS) Federal contract opportunity
- Solicitation number
- 19AQMM21R0234
About this file
This document outlines a federal procurement timeline and solicitation for an Enterprise Vulnerability Scanning Solution. The Department of State is seeking proposals due by August 10, 2021 for the acquisition of a vulnerability scanning solution to be implemented between September 30, 2021 and September 29, 2031. Offerors must submit any clarifying questions by July 16, 2021 and the government will post answers by July 20, 2021. The agency will notify select offerors to advance to technical demonstrations starting August 20, 2021, with all demonstrations concluding by August 27, 2021. The solicitation number is 19AQMM21R0234 and additional details are in the attached performance work statement, pricing template, and procurement timeline.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 19AQMM21R0234 P00001.pdf | ||
| Updated and revised PWS.pdf | ||
| updated and revised pricing template.xlsx | XLSX spreadsheet | |
| Responses to Questions.xlsx | XLSX spreadsheet | |
| Attachment 2 - Pricing Template.xlsx | XLSX spreadsheet | |
| 19AQMM21R0234.pdf | ||
| Attachment 1 - EVSS_PWS_07062021.pdf | ||
| Attachment 5 - Past Performance Customer Satisfaction Survey.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SBU - CONTRACTING AND ACQUISITIONS
Attachment 4: Procurement Timeline
Event Date
1. Issue solicitation July 9, 2021
2. Questions due from vendors by 4 PM EST Five
(5) business days from issuance of RFP
July 16, 2021
3. Answers due and posted (2 day) July 20, 2021
4. Written proposals due August 10, 2021
5. Notify Offerors of their selection to advance to
Phase II – Technical Demonstrations
August 20, 2021
6. Begin scheduling and conducting Phase II –
Technical Demonstrations
August 20, 2021
7. Last Date to perform Technical Demonstrations August 27, 2021
8. Contract start date September 30, 2021
9. Contract completion date September 29, 2031