This document outlines a sources sought announcement from the Department of the Navy for the USS GRAVELY (DDG-107) FY22 Incremental Selected Restricted Availability (ISRA). The Navy seeks information from potential contractors to perform pier-side maintenance, repair, and alterations work anticipated to begin on or around July 5, 2022. The anticipated contract type is firm-fixed price. Interested parties are requested to provide information on their company size and facilities, relevant past performance examples within the last three years, experience completing similar work on naval vessels, planned response to a future solicitation, and approach to executing the availability. Responses are due by August 20, 2021. The document includes an outline of anticipated work categories and ship specifications as attachments.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cat II Standard Items List - 2022 - CH-1 8/5/2021-14:21

Standard

Item Year Standard Item #

2022 009-05

2022 009-09

2022 009-11

2022 009-12

2022 009-15

2022 009-17

2022 009-25

2022 009-26

2022 009-32

2022 009-36

2022 009-57

2022 009-58

2022 009-63

2022 009-65

2022 009-71

2022 009-76

2022 009-78

2022 009-83

2022 009-87

2022 009-88

2022 009-89

2022 009-103

2022 009-104

2022 009-107

2022 009-113

N5005421R0011 DRAFT Cat II Standard Items List - 2022 - CH-1

Title

Temporary Access; accomplish

Process Control Procedure (PCP); provide and accomplish

Insulation and Lagging; accomplish

Weld, Fabricate, and Inspect; accomplish

Rotating Machinery; balance

Rotating Electrical Equipment; repair

Structural Boundary Test; accomplish

Deck Covering; accomplish

Cleaning and Painting Requirements; accomplish

Controller; repair

Reduction Gear Security; accomplish

Pump and Driver Shaft Alignment; accomplish

Lubricating Oil and Hydraulic Fluid; analyze

Polychlorinated Biphenyls (PCBs); control

Piping System; test

Waveguide and Rigid Coaxial Lay-Up; accomplish

Passive Countermeasures System (PCMS) Material; repair

Wire Rope Assembly; Fabricate

Chemical disinfection Procedures; accomplish

Collection, Holding and Transfer (CHT) and Motor Gasoline (MOGAS) Tanks, Spaces, and Piping, including Sewage or MOGAS-

Contaminated Tanks, Spaces, and Piping; certify

Contractor Furnished Anode Purchase and Inspection; accomplish

Weight and Moment Change Data; provide

Vibration Testing and Analysis; accomplish

Piping System Cleanliness Restoration and Flushing (Non-Nuclear); accomplish

Rotating Electrical Equipment with a Sealed Insulation Systems (SIS); rewind

8/5/2021 10:39

Change Change Date

Original 10/01/2018

Original 10/01/2019

Original 10/01/2017

Original 10/01/2019

Original 10/01/2019

Original 10/01/2019

Original 03/06/2020

Original 03/06/2020

CH-1 02/21/2021

Original 08/31/2018

Original 11/18/2016

Original 03/06/2020

Original 04/30/2018

Original 03/26/2018

Original 03/06/2020

Original 10/01/2018

Original 10/01/2018

Original 03/26/2018

Original 10/01/2017

Original 11/18/2016

Original 03/06/2018

Original 04/30/2018

Original 03/06/2020

Original 10/01/2019

Original 10/01/2019

File details come from the government source that posted it. Updated .