Attachment 4 - MAHG201064 -- MSS_8 July 2021.xls
XLS spreadsheet 57 KB Posted
- Attached to
- Replace Lint Traps and Stacks Federal contract opportunity
- Solicitation number
- FA301021R0016
About this file
This document contains a material submittal schedule and federal contract opportunity for replacing lint traps and stacks at Magnitude Air Force Base. The material submittal schedule outlines 21 required submittals from contractors, including hazmat questionnaires and reports, warranty documents, project schedules, product data sheets for lint interceptors, piping, fittings, cement, connectors, flooring, outlets, and firestopping materials. Due dates are provided for each submittal ranging from 5 days prior to work starting to the end of the contract.
The related federal contract opportunity is solicitation number FA301021R0016 to replace lint traps and stacks with an estimated value between $250,000 and $500,000. As a 100% SDVOSB set-aside, only service-disabled veteran-owned small businesses may submit proposals in response. An organized site visit will take place on July 29, 2021, with COVID-19 safety protocols in place. Proposals are due based on instructions in Sections L and M, with funds not presently available and no award being made until funding is secured.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment 001_18 Aug 2021.pdf | ||
| Attachment 10 - Questions_Answers 18 Aug 2021.pdf | ||
| Site Visit Sign-in_29 July 2021.pdf | ||
| Attachment 9 - Notice of Compliance.pdf | ||
| Attachment 8 - SF 1444.pdf | ||
| Solicitation - FA301021R0016.pdf | ||
| Attachment 3 - MAHG20-1064 DWG_8 July 2021.pdf | ||
| Attachment 7 - Past Performance Questionnaire.pdf | ||
| Attachment 1 - MAHG20-1064 SOW_8 July 2021.pdf | ||
| Attachment 2 - MAHG20-1064 SPECS_7 July 2021.pdf | ||
| Attachment 6 - Past Performance Reference List.pdf | ||
| Attachment 5 - Wage Det MS20210050_2 Apr 2021.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Schedule
| Project Number: | |||
| MAHG201064 | Project Title: | ||
| Replace Washer Lint Traps and Stacks Phase 2 | Solicitation / Contract Number: |
[ enter here ]
| Line Number | (To be completed by Project Engineer) | (To be completed by Contract Administrator) | ||||||||||||||||||||
| Number of Copies Required | Remarks | |||||||||||||||||||||
| Item or Description of Item, Contract Reference, Type of Submittal | Certificate of Compliance | Shop Drawings | Samples | Color Selection | Manufacturer's Recommendation | Manufacturer's Warranty | Catalog Data | Operating Instructions | Schedules, Listings, Reports, Plans | Technical Data | Test Reports | Field Reports | Required Submission Date | Date Received in Contracting | Date to Civil Engineering | Return Suspense Date | Submittal Numbers | Date Contractor | ||||
| Notified | Contractor Resubmittal | Final Approval | ||||||||||||||||||||
| Approved | Disapproved | |||||||||||||||||||||
| 1 | HazMat Questionnaire | 1 | 1 | 5 Days Prior To Start | ||||||||||||||||||
| 2 | HazMat MSDS | 1 | 1 | 5 Days Prior To Start | ||||||||||||||||||
| 3 | HazMat Reporting Entry Form | 1 | 1 | End of Contract | ||||||||||||||||||
| 4 | Recycling and Landfill Report | 1 | 1 | End of Contract | ||||||||||||||||||
| 5 | Warranty (Manufacturer's) i.e. Lint Interceptor, Solid Surface, Laundry Outlet Boxes | 3 | End of Contract | |||||||||||||||||||
| 6 | 1 Year Warranty (Contractor) | 3 | End of Contract | |||||||||||||||||||
| 7 | Project Schedule | 1 | Within 10 Prior to Work | |||||||||||||||||||
| 8 | Lint Interceptor Submittal | 1 | 1 | 1 | 1 | Within 10 days of NTP | ||||||||||||||||
| 9 | Pipe Submittal | 1 | 1 | 1 | Within 10 days of NTP | |||||||||||||||||
| 10 | Pipe Fittings Submittal | 1 | 1 | 1 | Within 10 days of NTP | |||||||||||||||||
| 11 | Pipe Cement Submittal including MSDS | 1 | 1 | 1 | Within 10 days of NTP | |||||||||||||||||
| 12 | Heavy-Duty No-Hub Connector Submittal | 1 | 1 | 1 | Within 10 days of NTP | |||||||||||||||||
| 13 | Solid Surface Material Samples Submittal (1 set of samples) | 1 | 1 | 1 | Within 10 days of NTP | |||||||||||||||||
| 14 | Floor Tile and Grout Submittals including MSDS for Grout | 1 | 1 | 1 | 1 | Within 10 days of NTP | ||||||||||||||||
| 15 | Exterior Cleanout Covers Submittal | 1 | 1 | 1 | 1 | Within 10 days of NTP | ||||||||||||||||
| 16 | Interior Cleanout Cover Plates Submittal | 1 | 1 | 1 | 1 | Within 10 days of NTP | ||||||||||||||||
| 17 | Recessed Laundry Outlet Boxes Submittal | 1 | 1 | Within 10 days of NTP | ||||||||||||||||||
| 18 | GFCI outlets and Covers | 1 | 1 | 1 | 1 | 1 | Within 10 days of NTP | |||||||||||||||
| 19 | Fire Stop Caulk Submittal including MSDS | 1 | 1 | 1 | 1 | Within 10 days of NTP | ||||||||||||||||
| 20 | Fire Stop Filler Material including MSDS | 1 | 1 | 1 | 1 | Within 10 days of NTP | ||||||||||||||||
| 21 | As-Builts (red line drawing of new drain lines if different and any other changes) | 1 | End of Contract | |||||||||||||||||||
| 22 | ||||||||||||||||||||||
| 20 | ||||||||||||||||||||||
| 21 | ||||||||||||||||||||||
| 22 | ||||||||||||||||||||||
| 23 | ||||||||||||||||||||||
| 24 | ||||||||||||||||||||||
| 25 |
&L&"Verdana,Bold"&12Schedule of Material Submittals&C&12Print on Legal size paper ( 8 x 14 ).
&R&P of &N Enter the due date from the Contractor (MM/DD/YY) Enter the date received from the Contractor. (MM/DD/YY) Enter the date submittal was given to CE for review. (MM/DD/YY) Enter the date the submittal is due back from CE
(MM/DD/YY)
Enter the Submittal Number Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
Enter Resubmittal Number Enter the submittal final approval date
(MM/DD/YY)
1137906887C:
Specifications 06 65 00, Paragraph 1.06(A)
File details come from the government source that posted it. Updated .