Attachment 3_AF 66.xlsx

XLSX spreadsheet 63 KB Posted

Attached to
Renovate Bldg. 55 Federal contract opportunity
Solicitation number
FA500021R0041
Issued by
Department of the Air Force Pacific Air Forces

About this file

This document contains a schedule of material submittals for the renovation of Building 55 located at Joint Base Elmendorf-Richardson in Alaska. The contractor shall provide design and construction services including demolition, architectural, mechanical, plumbing, electrical, and closeout work. Submittals are due on various dates after notice to proceed, with 65% design drawings due 30 days after NTP and 100% design drawings due 60 days after NTP. Submittals include shop drawings, color selections, manufacturer recommendations, calculations, warranties, and test results. A pre-proposal site visit will be held on June 16, 2021 and questions are due by June 23, 2021. The solicitation number is FA500021R0041 and is issued by the Department of the Air Force Pacific Air Forces for the renovation of Building 55 with a construction value between $500,000 and $1,000,000.

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittal 1

SCHEDULE OF MATERIAL SUBMITTALSPROJECT NUMBERPROJECT NAMESOLICITATION /CONTRACT NUMBER
HJZH 21-1044Renovate Bldg 55
TO BE COMPLETED BY PROJECT ENGINEER
LINE NUMBERNote: 3 copies required per submittal. Government will retain all submittals.Provide an electronic copy for each submittal.CERTIF. OF COMPLIANCESHOP DRAWINGSCOLOR SELECTIONMANUFATURUR'S RECOMMENDATIONCATALOG DATAO&M RECOMMENDATIONSCALCULATIONSWARRANTYDRAWINGSREPORTTEST RESULTSREQUIRED SUBMISSION DATEDATE TO CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATESUBMITTAL NUMBERSAPPROVEDDISAPPROVEDCONTRACTOR SUBMITTALFINAL APPROVAL
GENERAL
Project Specific Form 66XNTP + 10
Construction ScheduleXNTP + 10
TCN Schedule (electronic required, hard copy optional) AF3064XNTP + 10
Contractor's Health, Safety, and Environment PlanXNTP + 10
Contractor's QA/QC PlanXNTP + 10
Demolition PlanXNTP + 10
HAZMAT ApprovalXNTP + 14
Copy of Engineering License(s) of person or consultancy responsible for designXNTP + 10
65% Design
All submissions to be provided in hard copy and electronically (The electronic submission will include the *.CTB file and any other supporting file required to print the drawing correctly) 65%, and 100% Design Drawings to include:XXNTP + 14
Demolition PlanXNTP + 14
Floor Plan, Elevations, Sections, Schedules, and DetailsXNTP + 20
Plumbing/HVAC PlanXNTP + 30
Environmental PreCon ListXNTP + 14
Waste Water LayoutXNTP + 14
Electrical LayoutXXNTP + 14
100% Design
All submissions to be provided in hard copy and electronically (The electronic submission will include the *.CTB file and any other supporting file required to print the drawing correctly) 95%, and 100% Design Drawings to include:XXXXXXXXXNTP+30
DEMOLITION
Demolition PlanXXNTP + 30
ARCHITECTURAL
Doors and FramesXXXXXNTP + 45
Door HardwareXXXXXXXNTP + 45
Metal StudsXXXXXXXXNTP + 45
Gypsum Board-Type XXXXXNTP + 45
Gypsum Board-Type X-Mold ResistantXNTP + 45
All transition areas from room to room materials and constructionXXXXNTP + 45
Exterior PaintXNTP + 45
Interior PaintXNTP + 45
Guard Railings/ Hand RailingsXNTP + 45
Canopy StructuresXNTP + 45
Roofing MaterialXXXNTP + 45
Floorining & Rubber Base CoveXXNTP + 45
MECHANICAL
Ventilation UnitXXXXXNTP + 45
DuctworkXXXXNTP + 45
PipingXXXXXXNTP + 45
ValvesXXXNTP + 45
PLUMBING
Piping for Water (Washer)XXXXXNTP + 45
ArrestorsXXXXXNTP + 45
Waste and VentXXXXX
ELECTRICAL
Cables(electrical,comm,fire alarm)XXXXXXXXNTP + 45
ReceptaclesXXXXXXXXNTP + 45
Load Study for HeatXXXXXXXXNTP + 45
BreakersXXXXXXXXNTP + 45
ConduitsXXXXXXXXNTP + 45
Lighting FixturesXXXXXXXXNTP + 45
Lighting UPS units (if req'd)XXXXXXXXNTP + 45
Fire Alarm Devices (*All)XXXXXXXXNTP + 45
CLOSEOUT
O&M maint. data and maint manuals & Manufacturer's Warranty for All Equipment InstalledXXXInstall + 5
Factory and Field Test Certificates, Logs and Test ResultsXBefore Acceptance
HAZMAT Usage ReportXNLT 7 after final AC.
Completion of DD 1354XFinal + 7
As Builts (electronic in AutoCAD )XFinal + 7