This document contains a schedule of material submittals for the renovation of Building 55 located at Joint Base Elmendorf-Richardson in Alaska. The contractor shall provide design and construction services including demolition, architectural, mechanical, plumbing, electrical, and closeout work. Submittals are due on various dates after notice to proceed, with 65% design drawings due 30 days after NTP and 100% design drawings due 60 days after NTP. Submittals include shop drawings, color selections, manufacturer recommendations, calculations, warranties, and test results. A pre-proposal site visit will be held on June 16, 2021 and questions are due by June 23, 2021. The solicitation number is FA500021R0041 and is issued by the Department of the Air Force Pacific Air Forces for the renovation of Building 55 with a construction value between $500,000 and $1,000,000.
View the file
Other files for this federal contract opportunity
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Submittal 1
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER | PROJECT NAME | SOLICITATION /CONTRACT NUMBER |
| HJZH 21-1044 | Renovate Bldg 55 | ||
| TO BE COMPLETED BY PROJECT ENGINEER |
| LINE NUMBER | Note: 3 copies required per submittal. Government will retain all submittals.Provide an electronic copy for each submittal. | CERTIF. OF COMPLIANCE | SHOP DRAWINGS | COLOR SELECTION | MANUFATURUR'S RECOMMENDATION | CATALOG DATA | O&M RECOMMENDATIONS | CALCULATIONS | WARRANTY | DRAWINGS | REPORT | TEST RESULTS | REQUIRED SUBMISSION DATE | DATE TO CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | SUBMITTAL NUMBERS | APPROVED | DISAPPROVED | CONTRACTOR SUBMITTAL | FINAL APPROVAL |
| GENERAL | |||||||||||||||||||||
| Project Specific Form 66 | X | NTP + 10 | |||||||||||||||||||
| Construction Schedule | X | NTP + 10 | |||||||||||||||||||
| TCN Schedule (electronic required, hard copy optional) AF3064 | X | NTP + 10 | |||||||||||||||||||
| Contractor's Health, Safety, and Environment Plan | X | NTP + 10 | |||||||||||||||||||
| Contractor's QA/QC Plan | X | NTP + 10 | |||||||||||||||||||
| Demolition Plan | X | NTP + 10 | |||||||||||||||||||
| HAZMAT Approval | X | NTP + 14 | |||||||||||||||||||
| Copy of Engineering License(s) of person or consultancy responsible for design | X | NTP + 10 | |||||||||||||||||||
| 65% Design | |||||||||||||||||||||
| All submissions to be provided in hard copy and electronically (The electronic submission will include the *.CTB file and any other supporting file required to print the drawing correctly) 65%, and 100% Design Drawings to include: | X | X | NTP + 14 | ||||||||||||||||||
| Demolition Plan | X | NTP + 14 | |||||||||||||||||||
| Floor Plan, Elevations, Sections, Schedules, and Details | X | NTP + 20 | |||||||||||||||||||
| Plumbing/HVAC Plan | X | NTP + 30 | |||||||||||||||||||
| Environmental PreCon List | X | NTP + 14 | |||||||||||||||||||
| Waste Water Layout | X | NTP + 14 | |||||||||||||||||||
| Electrical Layout | X | X | NTP + 14 | ||||||||||||||||||
| 100% Design | |||||||||||||||||||||
| All submissions to be provided in hard copy and electronically (The electronic submission will include the *.CTB file and any other supporting file required to print the drawing correctly) 95%, and 100% Design Drawings to include: | X | X | X | X | X | X | X | X | X | NTP+30 | |||||||||||
| DEMOLITION | |||||||||||||||||||||
| Demolition Plan | X | X | NTP + 30 | ||||||||||||||||||
| ARCHITECTURAL | |||||||||||||||||||||
| Doors and Frames | X | X | X | X | X | NTP + 45 | |||||||||||||||
| Door Hardware | X | X | X | X | X | X | X | NTP + 45 | |||||||||||||
| Metal Studs | X | X | X | X | X | X | X | X | NTP + 45 | ||||||||||||
| Gypsum Board-Type X | X | X | X | X | NTP + 45 | ||||||||||||||||
| Gypsum Board-Type X-Mold Resistant | X | NTP + 45 | |||||||||||||||||||
| All transition areas from room to room materials and construction | X | X | X | X | NTP + 45 | ||||||||||||||||
| Exterior Paint | X | NTP + 45 | |||||||||||||||||||
| Interior Paint | X | NTP + 45 | |||||||||||||||||||
| Guard Railings/ Hand Railings | X | NTP + 45 | |||||||||||||||||||
| Canopy Structures | X | NTP + 45 | |||||||||||||||||||
| Roofing Material | X | X | X | NTP + 45 | |||||||||||||||||
| Floorining & Rubber Base Cove | X | X | NTP + 45 | ||||||||||||||||||
| MECHANICAL | |||||||||||||||||||||
| Ventilation Unit | X | X | X | X | X | NTP + 45 | |||||||||||||||
| Ductwork | X | X | X | X | NTP + 45 | ||||||||||||||||
| Piping | X | X | X | X | X | X | NTP + 45 | ||||||||||||||
| Valves | X | X | X | NTP + 45 | |||||||||||||||||
| PLUMBING | |||||||||||||||||||||
| Piping for Water (Washer) | X | X | X | X | X | NTP + 45 | |||||||||||||||
| Arrestors | X | X | X | X | X | NTP + 45 | |||||||||||||||
| Waste and Vent | X | X | X | X | X | ||||||||||||||||
| ELECTRICAL | |||||||||||||||||||||
| Cables(electrical,comm,fire alarm) | X | X | X | X | X | X | X | X | NTP + 45 | ||||||||||||
| Receptacles | X | X | X | X | X | X | X | X | NTP + 45 | ||||||||||||
| Load Study for Heat | X | X | X | X | X | X | X | X | NTP + 45 | ||||||||||||
| Breakers | X | X | X | X | X | X | X | X | NTP + 45 | ||||||||||||
| Conduits | X | X | X | X | X | X | X | X | NTP + 45 | ||||||||||||
| Lighting Fixtures | X | X | X | X | X | X | X | X | NTP + 45 | ||||||||||||
| Lighting UPS units (if req'd) | X | X | X | X | X | X | X | X | NTP + 45 | ||||||||||||
| Fire Alarm Devices (*All) | X | X | X | X | X | X | X | X | NTP + 45 |
| CLOSEOUT | |||||||
| O&M maint. data and maint manuals & Manufacturer's Warranty for All Equipment Installed | X | X | X | Install + 5 | |||
| Factory and Field Test Certificates, Logs and Test Results | X | Before Acceptance | |||||
| HAZMAT Usage Report | X | NLT 7 after final AC. | |||||
| Completion of DD 1354 | X | Final + 7 | |||||
| As Builts (electronic in AutoCAD ) | X | Final + 7 |