Attachment 2_Statement of Work_Specification.pdf

PDF 1 MB Posted

Attached to
CGC THETIS DEPOT REPAIRS
Solicitation number
70Z080-22-Q-MECP0014
Issued by

View the file

Other files

File Type Posted
Amendment 0001.pdf PDF
0001 page 2 THETIS DEPOT FY22.pdf PDF
Attachment 1 Schedule of Services_ Blank Price Schedule.xls XLS spreadsheet
70Z080-22-Q-MECP0014.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC THETIS (WMEC 910)

SPECIFICATION FOR DEPOT REPAIRS

FY2022

Developed By: Allison J Waters

(Rev-0, 11 May 2022)

USCGC THETIS (WMEC-270B) DEPOT AVAILABILITY FY2022

ii (Rev-0)

TABLE OF CONTENTS

Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ................................................................................. vi Consolidated List of Critical Inspection Items ........................................................................................... vii Principal Characteristics ............................................................................................................................ viii General Requirements WORK ITEM 1: Sewage Piping, Clean and Flush WORK ITEM 2: Grey Water and Sewage Piping, Renew WORK ITEM 3: Auxiliary Seawater Piping, Renew WORK ITEM 4: Auxiliary Seawater Piping, Install WORK ITEM 5: Water Tight Hatches, Internal DC Deck and Below, Renew iii (Rev-0)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iv (Rev-0)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast Guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Drawing 905 WMEC 167-001, Rev M, List of Structural Closures

Coast Guard Drawing 905 WMEC 256-011, Rev -, Mn & Aux SW Cooling Sys Diag

Coast Guard Drawing 905 WMEC 528-001, Rev K, Plumbing Vents & Drain Sys Diagram

Coast Guard Drawing 905 WMEC 593-004, Rev D, Sewage Transfer System, - A&D

Coast Guard Drawing 905 WMEC 593-005, Rev B, Sewage Vacuum System Diagram

Coast Guard Drawing 905 WMEC 593-006, Rev F, Sewage Vacuum System Below Main Deck – A&D

Coast Guard Drawing 905 WMEC 593-007, Rev D, Sewage Vacuum Sys, MN Deck & ABV – A&D

Coast Guard Drawing 905 WMEC 635-001, Rev F, Hull Thermal & Acoustic Insulation A/D

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures

OTHER REFERENCES

ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets

ASTM International (ASTM) F992, 2017, Standard Specification for Valve Label Plates

Commercial Item Description (CID) A-A-59316, 2016, Abrasive Materials; for Blasting

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-58, 2018, Pipe Hangers and Supports – Materials, Design, Manufacture, Selection, Application and Installation

NAVSEA Drawing 167-7379842, Rev A, Procedure & Welding Sequence for Non-Ballistic, Watertight & Airtight Quick Acting or Individually Dogged Personnel Doors

NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure

The Society for Protective Coatings (SSPC) Surface Preparation Standard No. 11 (SSPC-SP 11), 2013, Power-Tool Cleaning to Bare Metal v (Rev-0)

The Society for Protective Coatings (SSPC)/NACE International (NACE) 2007, Joint Surface Preparation Standard SSPC-SP 10/NACE No. 2, Near-White Metal Blast Cleaning vi (Rev-0)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

5 N ***36 x 36 in. Quick-

Acting Watertight Hatch, Steel, 18in.

FQAWTS (hinge aft)

NSN: 2040-01-679-3745 1 ea. 9,456.00

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter vii (Rev-0)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.1.4 (Inspection report particulars)):

Work Item

Title

This section is not applicable to this package.

viii (Rev-0)

PRINCIPAL CHARACTERISTICS

270' WMEC (B-CLASS)

PHYSICAL

Length overall 270' 0" Length between perpendiculars 255' 0" Beam molded 38' 0" Depth molded, main deck amidships, 01 level amidships

23' 7" 31' 4"

Full load displacement 1,886 long tons Draft, full load to baseline amidships 14' 2" Highest projection above baseline *height approximated

≈ 110' 0"

Shore tie voltage requirements 2 cables, 400A / 450V, 3 phase Frame spacing 1' 0"

MACHINERY

Main propulsion 2 ALCO Model 18-251-F Diesel Engines, 3,650 BHP each Ship’s service generators 2 Caterpillar Model D-398-TA Diesel-driven KATO 6P6-1350 Generators. 475

KW each @ 0.8 power factor, 450VAC, 3 phase, 60 cycle

Emergency generators Caterpillar Model D-348-TA Diesel-driven KATO 4P4-1900. 475KW @ 0.8 power factor, 450VAC, 3 phase, 60 cycle

Number of propellers 2 Propeller diameter 9' 0" Number of blades, each 4 Pitch Controllable Shaft RPM 260 Shaft diameter 10.55" at exit of hull Anchor & chain Two 4,000 lb Navy Stockless Anchors, 8 shots of chain each

TANK CAPACITIES

Diesel fuel total (95%) 79,950 gal.

JP-5 total (95%) 19,626 gal.

Potable water total (100%) 8,553 gal.

Hydraulic & lube oil total (95%) 2,561 gal.

1 (Rev-0)

00000_0222_FLT

REC_00000_FLT_Commercial Project @ CG Facility (0121)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and 'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures

OTHER REFERENCES

NAVSEA Technical Publication T9074-AD-GIB-010/1688, (TP 1688), July 2012, Requirements for Fabrication, Welding, and Inspection of Submarine Structure

3. REQUIREMENTS

3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements of this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

2 (Rev-0)

3.1.1 NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents. Contractors can apply to NAVSEA headquarters directly for copies.

3.2 Fire watch requirements. The Contractor must refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec 0000, in accomplishing the following task:

Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to two Coast Guard fire watch personnel.

Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.

3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec 6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.

3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).

3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.

3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.

Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:

ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.

ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.

3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.

For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).

3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;

for each additional 1000 square feet, perform an additional area measurement. A “measurements” for coating thickness is defined as follows:

SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.

SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5 inch diameter circle defining the spot.

3 (Rev-0)

3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.4.1 HY-130 material substitution. The Contractor must be aware that HY-130 steel plating is no longer commercially available. For the purpose of performing flight deck repairs on US Coast Guard WMEC-270 “B- Class” cutters, Weldox 900 steel plating has been approved as a replacement for HY-130. Due to the similarity in material properties and weldability of HY-130 and Weldox 900, all welding procedures and welder qualifications for welding Weldox 900 must be the same as those outlined in NAVSEA TP 1688 as applicable for welding HY- 130.

3.4.2 Standard spec modification. For any welding involving HY-130 on the flight deck of WMEC-270 “B-Class” cutters, perform all welding and allied processes, and non-destructive evaluation (NDE) in accordance with NAVSEA TP 1688. The Contractor must be aware that the welding requirements specified in this document take precedence over paragraph 3.3.6 of SFLC Standard Spec 0000 for the purpose of welding involving HY-130.

3.4.3 Approval to weld HY-130. To obtain Coast Guard approval to weld on HY-130 steel for WMEC-270 “B- Class” cutters, the Contractor must provide written Performance Qualification Records (PQR’s) for each process to be used. The PQR’s must be approved by one of the regulatory agencies affirming that the WPS meets the welding requirements of NAVSEA TP 1688. In addition, the Contractor must ensure that all subcontractors, prior to performing welding operations, have qualified procedures by meeting all the requirements set forth in this document.

NOTE

NAVSEA approval is NOT required for welding procedures submitted but the procedures must be reviewed and shown to satisfy the requirements set forth in NAVSEA TP 1688, by a welding regulatory agency. The requirements for welding Weldox 900 are considered the same as those for welding HY-130.

3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 USCG facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is Small Generator Quantity (SQG).

3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.

3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The

4 (Rev-0)

Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System (NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;

ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix B, Requirements For Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).

3.5.6 Additional Requirements. The Contractor must be aware of the following:

3.5.6.1 No Contractor or Subcontractor must have the authority to sign a Hazardous Waste Manifest using the Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast Guard facility without COR or KO-approval.

3.5.6.2 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor must prepare for and comply with local and state regulations.

3.5.6.3 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor must furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.

3.6 Local Policy. The Contractor must refer to site (e.g. Base) Regulations and Instructions for details regarding local policies (e.g. crane services, parking, or facility usage).

3.7 SFLC Standard Specification approved changes. The Contractor must be aware that the following are approved changes to published SFLC 2020 Edition Standard Specifications and supersede published content:

3.7.1 SFLC Standard Specification 8636. Add missing paragraphs between 3.2 and 3.5 of Std Spec 8636 as follows:

“3.3 Access cut boundaries. The Contractor shall ensure that access cuts comply with the requirements and restrictions detailed in the following and in SFLC Std Spec 0740, and referenced codes.

3.3.1 Location of boundaries. Boundaries of access cuts and closure plates shall, in general, be located between principal ship framing, bulkheads, and other structural members and shall be at least three inches from any of

5 (Rev-0) these members or from the toes of other welds. A reduction in this three inch minimum may be approved by the KO on a case by case basis provided sufficient clearance is maintained for welding and inspection requirements.

The boundaries of access cuts and closure plates should land on existing butts or seams, wherever practicable. The boundaries of prior access cuts should be utilized wherever possible. Boundaries may extend across one or more frames as required for the size of the opening.

3.3.2 Access hole dimensions and arrangements. Holes or access cuts shall be the minimum size necessary and shall be in accordance with the following:

Rectangular access cuts and closure plates welded into primary hull structure shall be at least 12 inches wide in the lesser dimension.

For circular access cuts, the minimum diameter shall be 4T, where T = thickness of the involved structural member, but not less than three inches.

Circular closure plates for access cuts less than two feet in diameter shall be dished 1/16 to 1/8 inch to allow for shrinkage when welded.

Corners of rectangular access cuts and closure plates shall have a minimum radius of 6 inches except when a boundary lands on an existing hull longitudinal seam or transverse butt weld.

Corners at an existing seam or butt shall intersect at a 90 degree angle.

Cuts that are to cross existing butts or seams shall do so at an angle of 90 degrees plus or minus 15 degrees.

In primary hull structure, existing welds forming the boundary of a cut shall be cut back 3 inches beyond the toe of the access cut, except that the cut back shall not intersect or cross an existing weld, frame, or structural member. In which case, the cut back may be reduced to a minimum of two inches in length.

Existing welds crossed by the cut shall not be cut back.

3.3.3 Primary hull structure. Primary Hull Structure includes the shell, main strength decks, principal longitudinal bulkheads, vertical keel, deep web girders and stiffeners designed to withstand the ship bending stress.

3.3.4 Mechanically fastened joints. Welding closer than six inches to a mechanically fastened joint should be avoided. When access cuts cross or come within six inches of a mechanically fastened joint, the fasteners shall be checked for tightness and if necessary, loose fasteners shall be seal welded or removed, and replaced for a distance of 6 inches beyond the edge of the cut. When a cut crosses a mechanically fastened seam the cut plates shall be repaired using single V welds backed with glass tape (MIL-C-20079) to prevent fusion between the mechanically fastened plates.

3.4 Ship integrity maintenance. The Contractor shall maintain safety and ship integrity by installing temporary guarding and coaming, in addition to weathertight and watertight closures. Remove these temporary fabrications after closing the hull access, and grind surfaces flush in way of removals. For shell plating cuts made at or below the waterline where temporary closures are impractical, the Contractor shall secure each vulnerable compartment and subdivision to minimize potential damage to the extent permitted by the scope and urgency of the work.

3.4.1 Guarding. Install temporary guards in accordance with 29 CFR 1915.73.

3.4.2 Coaming. Ensure that in areas where flammable liquids may be stored, a 4 inch high metal coaming shall be installed on the surface of the deck with tack welds and fully sealed with caulking compound. The coaming shall encircle the access cut in the deck.

3.4.3 Weathertight and contamination closures. Fabricate temporary closures, using fire retardant material, before cutting access openings and install closures whenever access is not in use. Closures shall be:

6 (Rev-0)

Constructed to protect the access from inclement weather and entry of contaminants (shall include a coaming or dam on the deck to redirect rain runoff away from the opening).

Fitted with fasteners that permit rapid installation and removal.

Able to support a minimum of 150 pounds per square foot for horizontal deck closures.

Where the access opening is in way of a removed hatch, scuttle or door, the closure shall be configured to allow normal passage of ship’s personnel and equipment.

3.4.4 Watertight closures. Ensure that access openings created four feet or less above the maximum anticipated waterline shall include temporary watertight closures when the vessel is waterborne.

NOTE

NAVSEA S0600-AA-PRO-160/CH16 provides requirements for design, fabrication, and installation of temporary watertight closures.”

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

7 (Rev-0)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK ITEM

WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

NAME OF CG REPRESENTATIVE SIGNATURE UNIT DATE/TIME

8 (Rev-0)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

VESSEL NAME HULL #

WORK ITEM

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE

TIME

ACTIVITY (SURFACE

PREPARATION, PRIMER COAT,

BARRIER COAT, TOP COAT,

ETC…)

LOCATION (FRAME &

DECK, RELATION TO

EQUIPMENT, ETC.)

TEMPERATURE % REL.

HUMID-

ITY

DEW

PT.

SURFACE AMBIENT ΔT

| DP -

SURFACE |

9 (Rev-0)

QA-3a - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

VESSEL NAME HULL # WORK ITEM

LOCATION OF WORK (FRAME REFERENCES) AREA (SQFT)

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS

PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS

DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:

10 (Rev-0)

QA-3b - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area) Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT

QA RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO

SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Mils Reading (IAW ASTM D4417-Method B for above 10 readings (by column):

Mean Reading (mils)

11 (Rev-0)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

VESSEL NAME HULL # WORK ITEM

SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.

DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)

12 (Rev-0)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

VESSEL NAME HULL #

WORK ITEM

COATING MFG PRODUCT NAME

BATC

H #

INDUCTI

ON TIME

COATING SYSTEM

SEQUENCE

(PRIMER/TOUCHUP/3RD

COAT, ETC.)

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.

SPOT 1 2 3 4 5

AVERAGE

VALUE

*BASE METAL READING

(BMR)

*Required, If Magnetic Pull-Off (Type I/Banana) Gauge Is Used.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

APPLICATION METHOD (AIRLESS,

CONVENTIONAL SPRAY, ROLLED)

AVERAGE DFT

13 (Rev-0)

4.2 Tank and Void Assessment form.

14 (Rev-0)

15 (Rev-0)

59321_ESD_1021_FLT

REC_59320_FLT_270B WMEC (ALL) (0420)

WORK ITEM 1: Sewage Piping, Clean and Flush

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean the sewage piping system.

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 905 WMEC 593-004, Rev D, Sewage Transfer System, - A&D

Coast Guard Drawing 905 WMEC 593-005, Rev B, Sewage Vacuum System Diagram

Coast Guard Drawing 905 WMEC 593-006, Rev F, Sewage Vacuum System Below Main Deck – A&D

Coast Guard Drawing 905 WMEC 593-007, Rev D, Sewage Vacuum Sys, MN Deck & ABV – A&D

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements

OTHER REFERENCES

ASTM International (ASTM) D1330, 2010, Standard Specification for Rubber Sheet Gaskets

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

16 (Rev-0)

Not applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:

Sewage pumps

Toilets

3.2 Contamination prevention. The Contractor must take all precautions to prevent contamination of personnel and spaces in accordance with all applicable Federal, state, and local regulations.

3.3 Personnel qualification. The Contractor must ensure that personnel accomplishing this work are qualified and experienced in operating the pressurized water system and handling the chemicals. For each operator/cleaning technician, submit documentation of applicable experience and training obtained within the last twelve months along with the Cleaning Plan.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.4 Operational test - initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.

3.5 Cleaning plan. Submit the written plan for chemical cleaning to the COR for approval 96 hours before work is to commence. The procedure must include products to be used, safety precautions, disposal requirements, sequence of events, etc. Submit a MSDS to the COR for all chemicals proposed for use.

Changes to the chemical cleaning plan as written, need to be approved by the COR (and Facilities).

CAUTION

Although the Coast Guard prefers pressurized water as the cleaning fluid, the Contractor may propose chemical cleaning as an alternative, providing that the proposed chemical cleaning agent is environmentally safe, suitable for use in marine sewage piping application, and pre-approved by the COR.

The chemicals used in the cleaning (including cleaning chemicals, neutralizing compounds, and defoaming chemicals) must not cause any significant detrimental effects to the sewage piping system or any other system components Due to the fact that system piping has historically been difficult to clean by pressure washing only, chemical cleaning is usually required to successfully complete the cleaning process.

3.5.1 Procedure requirements. The Contractor must ensure that the procedure includes the following:

Methods of cleaning.

All safety precautions required during cleaning operations.

List of qualified personnel who will operate machinery or handle chemicals (see paragraph

3.3 (Personnel qualification) herein).

17 (Rev-0)

Locations in the sewage piping where cleaning will take place, and any additional fittings necessary.

Sequence of each location that ensures all piping sections will be cleaned and all foreign debris removed.

3.5.2 Plan submittal. The Contractor must submit the written plan to the COR for approval at least 48 hours prior to commencing cleaning operations. Changes to the chemical cleaning plan as written, need to be approved by the COR (and local Facilities).

3.6 Clean and flush. The Contractor must clean and flush the sewage system piping, using Coast Guard Drawings 905 WMEC 593-004, 905 WMEC 593-005, 905 WMEC 593-006, and 905 WMEC 593-007 as guidance.

3.6.1 Pumps and valves. Replace system tank valve(s) with temporary spool piece(s) and remove sewage pumps before cleaning. Visually inspect system pumps and valve(s); and submit a CFR. Upon completion of work, reinstall the removed sewage pumps and reinstall the removed tank valve(s) with new gaskets.

3.6.2 Cleaning. Continue cleaning until all of the following conditions are met:

All visible calcium carbonate deposits, solid deposits and build-up are removed from pipe walls.

Discharge water from the piping being cleaned is free of all visible scale and deposits.

3.6.3 Inspect the piping interior using a borescope in the presence of the COR, to verify that all solid deposits visible to the unmagnified eye have been removed. Continue the cleaning process until all visible solid deposits are removed from the pipe walls.

3.6.4 Flush twice the volume of the system cleaned with water to include 3 repeated pH tests between 6 and 8. The flushing water shall be collected and disposed by the Contractor.

3.7 Waste disposal. The Contractor must dispose of all cleaning fluids and debris in accordance with all applicable Federal, state, and local regulations. Remove all unused chemicals from USCG property immediately upon completion of work item. Do not drain any fluids (including fresh water) into any space, bilge, or exterior location.

3.8 Gasket renewal. The Contractor must reinstall all removed valves and fittings with new gasket material conforming to ASTM D1330.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.9 Operational test – post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.

3.9.1 Leak test. After all system components are reinstalled, the Contractor must test all disturbed piping for leaks, as follows, and submit a CFR:

Plug all system openings (except the highest) and fill system with water to the point of overflow. Ensure that the water level does not go down (without adding any water) for sufficient time to inspect the entire system (no less than 15 minutes).

18 (Rev-0)

Closely monitor the system for leaks. Repair all leaks detected.

Repeat test and inspection until no leaks are detected.

4. NOTES

This section is not applicable to this work item.

19 (Rev-0)

S_5XXXX_PpngRnwl_SWIT_ESD_0921_SWIT

S21_0024_59300_AJW_0522_910

S21_0031_59300_AJW_0522_910

WORK ITEM 2: Grey Water and Sewage Piping, Renew

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to renew designated sections of Grey Water piping and Sewage piping, located in the Engine Room (Compartment 3-103-0-E), Engineering Control Center (Compartment 3-152-0-E), I.C. Room (Compartment 2-47-1-C), Crew’s Berthing (Compartments 2-66-1-L & 2-165-0-L), Auxiliary Machinery Space No. 1 (Compartment 2-82- 0-E), Auxiliary Space No. 2 (Compartment 3-82-0-E), Sanitary Space (Compartment 3-160-2-L), and Scullery Space (Compartment 1-129-2-Q).

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 905 WMEC 528-001, Rev K, Plumbing Vents & Drain Sys Diagram

Coast Guard Drawing 905 WMEC 593-005, Rev B, Sewage Vacuum System Diagram

Coast Guard Drawing 905 WMEC 593-006, Rev F, Sewage Vacuum System Below Main Deck – A&D

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures

OTHER REFERENCES

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-58, 2018, Pipe Hangers and Supports – Materials, Design, Manufacture, Selection, Application and Installation

20 (Rev-0)

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Interferences include, but are not limited to, the following:

Main switchboard in ECC

Desk and electronics in ECC

Berthing joiner bulkhead

Electrical equipment in I.C. Room

Cables

3.1.5 Contamination prevention. The Contractor must take all precautions to prevent contamination of personnel and spaces in accordance with all applicable Federal, state, and local regulations.

3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.

3.3 Fluid handling. The Contractor must remove and dispose of removed fluids from the affected piping system, in accordance with all applicable Federal, state, and local regulations.

WARNING

Do not drain ANY fluids, including fresh water, into any space, bilge, or exterior location.

3.3.1 Service disruption. When sewage collection service is disrupted due to contractor repairs, the Contractor must refer to SFLC Standard Spec 0000 par 3.2.11 to provide required temporary facilities.

3.4 Piping renewal particulars. The Contractor must renew the following as designated by the Coast Guard Inspector:

Renew 25 linear feet of 2 in 90/10 Copper-Nickel Grey Water piping, located in the overhead of the Engine Room (3-103-0-E) using Coast Guard Drawing 905 WMEC 528-001 as guidance.

Renew 15 linear feet of 2 in 90/10 Copper-Nickel Sewage piping located in the Engineering Control Center (3-152-0-E) using Coast Guard Drawings 905 WMEC 593-005 and 905 WMEC 593-006 as guidance.

21 (Rev-0)

Renew 3 linear feet of 2 in 90/10 Copper-Nickel Grey Water piping, located in the Engineering Control Center (3-152-0-E) using Coast Guard Drawings 905 WMEC 593-005 and 905 WMEC 593-006 as guidance.

Renew 10 linear feet of 2 in 90/10 Copper-Nickel Sewage piping, located against the starboard bulkhead in the I.C. Room (2-47-1-C) using Coast Guard Drawings 905 WMEC- 593-005 and 905 WMEC-593-006 as guidance. The new piping layout must be reconfigured to remove the two 90 degree bends where the pipe enters the compartment, in accordance with the Plan 12-A and Elev 12-A views shown in Coast Guard Drawing 905 WMEC 593- 006, and add a cleanout as designated by the Coast Guard Inspector.

Renew 4 linear feet of 2 in 90/10 Copper-Nickel Sewage piping, located behind the joiner bulkhead by the toilet in Crew Berthing (2-66-1-L) using Coast Guard Drawings 905 WMEC-593-005 and 905 WMEC-593-006 as guidance.

Renew 8 linear feet of 2 in 90/10 Copper-Nickel Sewage piping, located in Auxiliary Machinery Space No. 1 (2-82-0-E) leading into the Engine Room hydraulic door on Bulkhead 103 using Coast Guard Drawings 905 WMEC-593-005 and 905 WMEC-593-006 as guidance.

Renew 5 linear feet of 2 in 90/10 Copper-Nickel Sewage piping, located in the main propulsion shop Sanitary Space (3-160-2-L) using Coast Guard Drawings 905 WMEC-593- 005 and 905 WMEC-593-006 as guidance.

Renew 15 linear feet of 2 in 90/10 Copper-Nickel Sewage piping, located above the CHT tank in the Auxiliary Machinery Space No. 2 (3-82-0-E) using Coast Guard Drawings 905 WMEC 593-005 and 905 WMEC 593-006.

Renew 1 linear foot of 2 in 90/10 Copper-Nickel Sewage piping, located in the overhead of the Crew Berthing Sanitary Space (2-165-0-L) using Coast Guard Drawings 905 WMEC 593-005 and 905 WMEC 593-006 as guidance.

Renew 3 linear feet of 2 in 90/10 Copper-Nickel Grey Water piping located beneath the sink in the Scullery (1-129-2-Q) using Coast Guard Drawings 905 WMEC 528-001 as guidance.

3.4.1 Pipe hangers. Furnish, fit, and install new pipe hangers in accordance with MSS SP-58.

3.4.2 Pipe labeling. The Contractor must label affected piping as follows:

3.4.2.1 Stencil the following onto the pipe surfaces:

Name of the piping system service.

Destination, where feasible.

Direction of flow, indicated by an arrow three inches long pointing away from the lettering (for reversible flow, point an arrow away from each end of the lettering).

3.4.2.2 Ensure all lettering and arrow(s) are as follows:

In general, black color except white for dark-colored piping.

Applied in conspicuous locations and preferably near control valves.

3.5 Testing. After all work has been completed, the Contractor must, in the presence of the Coast Guard Inspector, accomplish the following tasks, and submit a CFR:

22 (Rev-0)

3.5.1 Hydrostatic test. After all authorized repairs, the Contractor must hydrostatically test all new and disturbed piping and components of the affected piping system in accordance with SFLC Std Spec 0740, Appendix C, Hydrostatic Test. Ensure zero leakage from or permanent deformation of pressure-containing parts by repairing all leaks, deformations, and discrepancies. Submit a CFR.

NOTE

Coast Guard personnel will operate all shipboard machinery and equipment.

3.5.2 Operational test, post repairs. After completion of work, the Contractor must thoroughly test, in the presence of the Coast Guard Inspector and demonstrate all items or shipboard devices that have been disturbed, used, repaired, altered, or installed to be in satisfactory operating condition. Submit a CFR.

3.6 Touch-up preservation. The Contractor must prepare and coat all new and disturbed surfaces to match existing adjacent surfaces in accordance with SFLC Std Spec 6310, paragraph 3.1.13 (Touch-ups and minor coating repairs.)

23 (Rev-0)

S21_0032_25600_AJW_0522_910

WORK ITEM 3: Auxiliary Seawater Piping, Renew

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to renew designated sections of ASW piping, located in the Auxiliary Machinery Space No. 2 (Compartment 3-82-0-E).

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 905 WMEC 256-011, Rev -, Mn & Aux SW Cooling Sys Diag

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures

OTHER REFERENCES

ASTM International (ASTM) F992, 2017, Standard Specification for Valve Label Plates

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-58, 2018, Pipe Hangers and Supports – Materials, Design, Manufacture, Selection, Application and Installation

3. REQUIREMENTS

3.1 General.

3.1.1 CIR.

24 (Rev-0)

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Interferences include, but are not limited to, the following:

Removable catwalk

Gauge lines

3.1.5 Contamination prevention. The Contractor must take all precautions to prevent contamination of personnel and spaces in accordance with all applicable Federal, state, and local regulations.

3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of all items or shipboard devices to be disturbed, used, repaired, or altered, to demonstrate existing operational condition. Submit a CFR.

3.3 Fluid handling. The Contractor must remove and dispose of removed fluids from the affected piping system, in accordance with all applicable Federal, state, and local regulations.

WARNING

Do not drain ANY fluids, including fresh water, into any space, bilge, or exterior location.

3.3.1 Service disruption. When auxiliary seawater services are disrupted due to contractor repairs, the Contractor must refer to SFLC Standard Spec 0000 par 3.2.11 to provide required temporary facilities.

3.4 Piping renewal particulars. The Contractor must renew the following, as directed by the Coast Guard Inspector and using Coast Guard Drawing 905 WMEC 256-011 as guidance:

Renew 15 linear inches of 8 in 90/10 Copper-Nickel ASW piping, connecting to the reverse osmosis pump.

Renew 3.5 linear inches of 3 in 90/10 Copper-Nickel ASW piping, located on the offshoot of the reverse osmosis pump piping.

Renew 2 linear feet of 6 in 90/10…