Attachment 2 -Statement of Work - 70Z03824QJ0000349.pdf
PDF 102 KB Posted
- Attached to
- Repair Esis Indicators
- Solicitation number
- 70Z03824QJ0000349
About this file
This document is a Statement of Work (SOW) for the repair of ESIS Indicators for the United States Coast Guard (USCG). The SOW outlines the requirements for the contractor to perform test and evaluation, repair, and provide certifications for the ESIS Indicators. The initial requirement is for 13 repairs, with an option for up to 7 additional repairs, for a total maximum of 20 repairs. The contractor must be the Original Equipment Manufacturer (OEM) or an OEM-authorized repair facility. Pricing should be provided on the attached schedule, and the anticipated award date is on or about 7/11/2024. The contractor must provide a Certificate of Conformance and maintain a quality system that complies with ISO 9001-2000 or equivalent. The components are serial number tracked, and the contractor must provide a Component Repair Record and maintain a Significant Component History Record. Delivery is required within 15 calendar days for test and evaluation and 90 days for repairs.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ATTACHMENT 2 - STATEMENT OF WORK (SOW)
ESIS INDICATORS
70Z03824QJ0000349
1.0 Contractor Requirements for Repair
1.1 The United States Coast Guard (USCG) will furnish the components and quantities specified in the following table for repair:
Description Quantity Option
Quantity
National Stock Number
(NSN)
Part Number
(P/N)
ESIS INDICATOR 13 7 6610-01-545-0766 501-1851-2402
1.2 The part(s) are utilized on the MH-60T aircraft. Upon receipt of the component(s), the
Contractor shall perform test and evaluation to determine the condition of the component. If the component is found to be Ready for Issue (RFI) a frim-fixed price test and evaluation fee would be applicable. Any components determined to be Beyond Economical Repair (BER), the Contractor will be allowed the firm-fixed BER/Scrap fee. Only one of the firm-fixed prices below would be applicable:
Service Total
Test/Evaluation TBD at time of service
BER/Scrap Fee TBD at time of award
Repair TBD at time of award
1.2.1 When a component is found to be BER, the BER/Scrap fee shall apply. The Contracting Officer shall provide a teardown report in accordance with (IAW) Section 2.11. The Contracting Officer will provide disposition instructions IAW Section 2.9 via a modification for all parts found to be BER.
2.0 Repair
2.1 Non-RFI components shall be repaired and returned to RFI condition IAW the Original
Equipment Manufacturer (OEM) functional performance specifications. Components shall be repaired for the specific fault noted on the DD Form 1577-2, Unserviceable (Repairable) Tag-Material, or CG-1577-A
(11-90), Unsatisfactory Report Tag, which will be attached to each non-RFI component. The Contractor shall perform an inspection and correct all deficiencies found. This may include the replacement of missing or broken parts and the removal of any foreign matter or corrosion, however significant and recurring corrosion may include additional cost. Such components shall be inspected, additional repair costs determined, and authorization to proceed obtained from the Contracting Officer, via modification, prior to commencement of work.
2.2 During inspection and functional test, the presence of corrosion in a component shall constitute reason for a more thorough disassembly and inspection. Should corrosion be found, disassembly shall be made to the extent necessary to remove corrosion or replace the part, or parts, affected. Corroded parts shall be replaced, except in those cases where removal of corrosion from a part will not impair efficiency or safe operation of the part. Corrosion removal and treatment of affected areas will be accomplished
IAW OEM specifications and Federal Aviation Administration (FAA) Advisory Circular AC 43-4B, dated 9/11/2018, Corrosion Control for Aircraft.
2.3 Work under this purchase order shall be performed at the Contractor’s facility or USCG approved facility. The Contractor shall provide all necessary parts, materials, labor, tooling, test equipment and facilities to evaluate and repair the components listed in this purchase order at the firm-fixed prices listed in the schedule (or modification).
2.4 Repair services must be performed IAW the procedures established in this SOW. The documents are listed in order of precedence. Latest revisions of any instruction or manual shall apply. The information contained within is not intended to be all inclusive nor to detract from or modify procedures outlined in the manuals. If the applicable technical manual does not cover a procedure, the Contractor shall utilize the OEM repair manual. If the OEM manual does not cover a procedure, the Contractor shall utilize the best commercial business practice. Where an application of “best commercial practice” is in conflict with these manuals, the Contracting Officer may approve deviation from requirements. When applicable, each manual will specify if the Export Control Act applies. The following document(s) are required to complete the services required by this acquisition. The USCG does not own nor can it provide the technical documents specified herein.
• All OEM shop, inspection, overhaul, repair, or other OEM Component Maintenance Manuals
(CMM)
• All OEM service bulletins, amendments, modifications, and specifications as applicable
2.5 The Contractor shall have access to required repair specifications and test/acceptance criteria and data to ensure all components are tested and repaired IAW the current specifications and procedures. The
USCG may review repair manuals and performance/test/ acceptance criteria as required. The Contractor is solely responsible for obtaining all specifications required for this effort. Original design or functional capabilities of the end component and parts thereof shall not be changed unless authorized or directed by the requirements of this SOW.
2.6 Parts of a component found to be in a serviceable condition as a result of functional testing shall be reused. Missing parts and parts found to be defective or that require replacement by manufacturer’s instructions shall be replaced with parts meeting the manufacturer’s specifications and drawings or as otherwise authorized in writing by the Contracting Officer. Replacement parts shall be factory new and accompanied with OEM traceability. The use of cannibalized parts in leu of factory new replacement parts may be authorized in writing by the Contracting Officer. The cost for parts that are replaced systematically during repair shall be included in the price listed in the schedule for these operations.
2.7 Prices do not include components that have been cannibalized or severely damaged due to mishandling. Additionally, USCG aircraft is used primarily around salt water at low altitude for search and rescue missions. Therefore, corrosion is to be anticipated, is considered "normal" for the aircraft and does not constitute unusual damage. However, significant corrosion may require more parts, time and effort to return the component to RFI condition. Any significant and recurring corrosion that warrants an exclusion from the prices specified in the contract scheduled costs shall be noted during the test and evaluation and on the teardown report. Instructions shall be followed as outlined in section 2.8.
2.8 Components received which indicate obvious misuse, cannibalization, or severe damage due to mishandling or crash damage may dictate an exclusion from the prices specified in the contract schedule.
Such components shall be inspected, repair costs determined, and authorization to proceed obtained from the Contracting Officer prior to commencement of work. Once notified of a possible exclusion, The
Contracting Officer will make a written determination within thirty (30) days as to exclusion validity. The
Contracting Office may approve the quote, decline the quote and have the component returned as-is, or consider the component BER. A response must be provided by the Contracting Officer in the timeframe defined above or components will be subject to the stranded/abandoned policy as outlined in the standard terms and conditions.
2.9 The USCG will provide disposition instructions (either to scrap the component at the
Contractor’s facility or to return the component to ALC) for all components that are considered BER.
The Contractor shall not dispose of a component until they have been notified by a written modification to the order. When returning the component to ALC, the components shall be clearly marked as “BER” with the supporting evidence.
2.10 The Government shall not be liable for any amount expended by the Contractor in excess of the applicable firm fixed price reflected in the schedule unless prior written authorization has been given by the Contracting Officer.
2.11 The Contractor shall submit a teardown report for each component repair. This report shall include NSN, P/N, Serial Number (S/N), nomenclature, date of repair, purchase order number, line item number, description of repaired failure, the USCG’s reported failure, a listing of parts repaired and a listing of parts replaced. The Contractor’s in-house work order may be used to satisfy this requirement if it includes the information requested above. This report shall be attached to the packing slip and shipped with the repaired component.
2.12 The Contractor shall be required to be certified and maintain a quality system that complies with the requirements of ISO 9001-2000 Quality Management Systems – Requirements or equivalent. The
Contractor is responsible for performing or assuring all inspections and tests necessary to substantiate that the goods or services furnished conform to Government’s requirements. The Contractor shall take prompt action to correct conditions that have or could result in goods or services that do not conform to contractual requirements. Records of conformance shall be maintained on file at the Contractor’s facility and made available or provided for review by the Government upon request. The Government reserves the right to conduct surveillance at Contractor’s facility to verify the existence, adequacy, and effectiveness of the quality system.
2.13 ALC considers components RFI upon acceptance. Components determined to be non-RFI upon installation may be returned to the Contractor with deficiencies described in a Product Quality Deficiency
Report.
2.14 All parts must be thoroughly cleaned IAW applicable CMMs. ALC may take random samples of parts to ensure they are free as practicable of all hazards. Information on these hazards can be found in
Occupational Safety and Health Standards 1910.1025 (lead), 1910.1026 (Hexavalent Chromium) and
1910.1027 (Cadmium).
2.15 Audits are conducted by ALC on Government Furnished Property at commercial Contractor facilities at intervals IAW the Contractor's Control of Government process. The Contractor shall follow the instructions provided and comply with its instructions. The Contractor’s role shall be to validate each component identified by S/N by ALC. Validation shall take place on the same date as the audit.
3.0 Certifications
3.1 When checked the Contractor shall:
Maintain OEM certification for the repair of the components listed in this statement of work.
The Contractor shall provide immediate notification to the Contracting Officer upon loss of any required certifications. The Contractor shall also:
• Comply with the certification/documentation requirements specified herein.
• Attach certifications/documentation to the outside of the shipping container.
All parts repaired under the provisions of this contract must be airworthy and suitable for installation on USCG aircraft. Each returned component shall be tagged with a DD Form 1574
Serviceable Condition Code Tag or a FAA Form 8130-3, Airworthiness Approval Tag, completed in its entirety. The Contractor shall furnish a Certificate of Airworthiness in accordance with
FAA procedures (or USCG approved alternate procedure) and a Certificate of Conformance
(COC) IAW FAR 52.246-15 for all components. These forms shall be packaged with each component.
The COC shall be signed by an authorized official of the approved source and must specify the nomenclature, manufacturer's part number, and date of manufacture. For Production
Approval Holder, a COC and a copy of the FAA Parts Manufacturer Approval (PMA) or other manufacturing authority shall be provided. Contractors shall also provide documentation reflecting the complete unbroken history of ownership of the parts from purchase from the approved manufacturing source until delivery to the USCG.
4.0 Tracked Components
4.1 Serial number tracking shall be used for validating the correct component(s) were received at the
Contractor’s repair facility and returned to the USCG. Upon receipt of the component(s) from the USCG, the Contractor shall verify each component received to ensure that the S/Ns match the ones specified in the order. Should a discrepancy be identified, the Contractor shall notify the Contracting Officer in writing of the discrepancy.
4.2 When checked the Contractor shall comply with the following documentation requirements:
The components to be repaired under this Purchase Order are tracked in the USCG’s Asset
Computerized Maintenance System (ACMS). ACMS is the management information system used to schedule and record all USCG equipment maintenance actions and calibration intervals. In addition, the
Contractor will utilize their own standard commercial tool that tracks the progress of each component while in-house for repair. A month status report can be provided to the USCG upon request.
Tracked components will be shipped to the Contractor with a Significant Component History Record
(SCHR). The SCHR records the maintenance history of the serial number tracked components. It remains with its corresponding part until reinstalled on an aircraft or is annotated “BER” and scrapped.
(NOTE: written approval from the Contracting Officer is required prior to scrapping a serial number tracked component). The SCHR for scrapped components shall be returned with the component. The
Contractor shall retain a copy of the SCHR for ninety (90) calendar days.
The Contractor shall provide a Component Repair Record (CRR) with the repaired component(s).
The CRR records the maintenance performed on a serial number tracked component and enrolls or disenrolls components from ACMS when those components are scrapped, added to, or removed from the
USCG inventory. At a minimum, the CRR shall identify the equipment and contain a description of the maintenance action performed, parts replaced, service bulletins and modifications. The Contractor shall mail one (1) copy of the CRR to USCG ALC, ATTN: AVENG/ACMS, Elizabeth City, NC 27909-5001 no later than five (5) business days following completion of the rework effort. The original CRR shall be packed with the component. The Contractor shall retain a copy of each CRR for ninety (90) calendar days. The Contractor's standard commercial teardown report will be provided with each unit. This will include but not limited to: part number, serial number, evaluation summary, the parts replaced and maintenance action performed. The standard commercial tear down report will be accepted in order to fulfill the CRR requirement.
5.0 Delivery Requirements
5.1 The following table shows the requested delivery for each priced line item listed in the schedule.
Early deliveries, when appropriate, are desired and acceptable.
Item Description Due No Later Than:
Test and Evaluation Fifteen (15) calendar days after receipt of components
Repair ESIS
Indicators
Ninety (90) days after induction
File details come from the government source that posted it. Updated .