Attachment 2 - Specifications.pdf
PDF 3 MB Posted
- Solicitation number
- W912P922C0015
About this file
This award notice announces that Massman Construction Co. was awarded contract W912P922C0015 for $10,115,316 on September 6, 2022. The contract supports lock wall modifications and construction work at Lock and Dam 25 as part of the Navigation Ecosystem Sustainability Program's Phase 1 under the U.S. Army Corps of Engineers St. Louis District. Work will include modifying the existing lock walls, installing floating mooring bits, filling an existing miter gate recess, and other lock infrastructure upgrades.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 1 - Plans.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
US Army Corps of Engineers St. Louis District
NAVIGATION ECOSYSTEM
SUSTAINABILITY PROGRAM
(NESP)
LOCK AND DAM NO. 25 – NEW
1200’ LOCK
PHASE 1: EXISTING LOCKWALL
MODIFICATIONS
WINFIELD, MISSOURI
CONSTRUCTION SPECIFICATIONS
SOLICITATION NUMBER: W912P9-22-R-0023
CONTRACT NUMBER: W912P9-22-C-0015
MAY 2022
PROJECT TABLE OF CONTENTS
DI VI SI ON 00 - PROCUREMENT AND CONTRACTI NG REQUI REMENTS
00 08 00 SPECIAL CONTRACT REQUIREMENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 11 30 ENVIRONMENTAL PROTECTION
01 13 20 PROJECT SCHEDULE
01 15 00 TEMPORARY CONSTRUCTION FACILITIES
01 22 00.00 10 PRICE AND PAYMENT PROCEDURES
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 10 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM)
01 78 00 CLOSEOUT SUBMITTALS
DI VI SI ON 02 - EXI STI NG CONDI TI ONS
02 41 00.00 01 STRUCTURAL DEMOLITION
DI VI SI ON 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DI VI SI ON 05 - METALS
05 05 20.00 27 POST-INSTALLED CONCRETE ANCHORS
05 50 01 FLOATING MOORING BITTS
05 50 14 STRUCTURAL METAL FABRICATIONS
05 50 15 CIVIL WORKS FABRICATIONS
DI VI SI ON 09 - FI NI SHES
09 97 02 PAINTING: HYDRAULIC STRUCTURES
DI VI SI ON 13 - SPECI AL CONSTRUCTI ON
13 50 00 MOVABLE COFFERDAM
DI VI SI ON 26 - ELECTRI CAL
26 05 00.00 40 COMMON WORK RESULTS FOR ELECTRICAL
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 92 19 SEEDING
DI VI SI ON 35 - WATERWAY AND MARI NE CONSTRUCTI ON
35 20 23 UNDERWATER EXCAVATION AND DEMOLITION
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
Amendment 0001
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 08 00
SPECIAL CONTRACT REQUIREMENTS
PART 1 GENERAL
1.1 WORK AREAS
1.2 PUBLIC UTILITIES AND PRIVATE IMPROVEMENTS
1.3 DAMAGE TO WORK
1.4 QUANTITY SURVEYS
1.5 PARTIAL PAYMENT
1.6 CERTIFICATES OF COMPLIANCE
1.7 PURCHASE ORDERS
1.8 SAFETY AND HEALTH REQUIREMENTS MANUAL EM 385-1-1
1.9 ACCIDENT INVESTIGATIONS AND REPORTING
1.10 DAILY INSPECTIONS
1.11 ENVIRONMENTAL LITIGATION
1.12 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
1.13 RIVER STAGE LIMITATIONS
1.14 SUBCONTRACTS
1.15 REQUIRED INSURANCE
1.16 PROTECTION OF MATERIAL AND WORK
1.17 CONTAMINATION OF WATER
1.18 COMMERCIAL WARRANTY
1.19 ORDER AND COORDINATION OF WORK
1.20 SUBMITTALS
1.21 MEANS OF ESCAPE FOR PERSONNEL QUARTERED OR WORKING ON FLOATING
PLANT
1.22 EMERGENCY ALARMS AND SIGNALS
1.23 USE OF MECHANIZED EQUIPMENT ON FLOATING PLANT
1.24 OBSTRUCTION OF NAVIGABLE WATERWAYS (DEC 1991) DFARS 252.236-7002
1.25 SIGNAL LIGHTS
1.26 INSPECTION FACILITIES
1.27 CONTRACTOR PERFORMANCE EVALUATIONS
1.28 SECURITY REQUIREMENTS
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
DOCUMENT 00 08 00 Page 1
SECTION 00 08 00
SPECIAL CONTRACT REQUIREMENTS
PART 1 GENERAL
1.1 WORK AREAS
In accordance with the Contract Clause entitled, "Operations and Storage Areas", and subject to the approval of the Contracting Officer and the restrictions imposed by SECTION 01 11 30 - ENVIRONMENTAL PROTECTION, of the Technical Provisions, the Contractor will be allowed use of Government-controlled land within the construction limits shown on the drawings or as specified herein.
1.2 PUBLIC UTILITIES AND PRIVATE IMPROVEMENTS
a. Unless otherwise specified, shown on the drawings, or stated in writing by the Contracting Officer, the Contractor shall not move or disturb any public utilities or private improvements. Such removals, alterations, and/or relocations, where necessary, will be made by others. The locations shown on the drawings for underground utilities are approximate only. The exact locations of such utilities shall be determined by the Contractor in the field prior to commencing construction operations in their vicinity.
b. The attention of the Contractor is directed to the possibility that public utilities or private improvements may be encountered within the construction limits, some of which may be buried, and the existence of which is presently not known. Should any such utilities or improvements be encountered, the Contractor shall immediately notify the Contracting Officer so that a determination may be made as to whether they shall be removed, relocated, or altered. After such determination is made, the Contractor shall, if so directed by the Contracting Officer, remove, relocate, or alter them as required and an equitable adjustment will be made. In the event the Contracting Officer arranges for such removals, alterations, or relocations to be performed by others, the Contractor shall cooperate with such others during the latters' removal, alteration, or relocation operations.
1.3 DAMAGE TO WORK
a. The responsibility for damage to any part of the work to be performed under this contract shall be as set forth in the clause of the contract entitled "Permits and Responsibilities". However, if the cofferdam(s) is constructed in accordance with plans and progress schedules approved by the Contracting Officer, but is overtopped by flood and such flood causes damage to the cofferdam or if any part of the permanent work is damaged by flood or earthquake, which damage is not due to the failure of the Contractor to take reasonable precaution or to exercise sound engineering and construction practices in the conduct of the work, the Contractor shall make the repairs ordered by the Contracting Officer and full compensation for such repairs will be made at the applicable contract unit or lump sum prices as fixed and established in the contract. If, in the opinion of the Contracting Officer, there are no contract unit or job prices applicable to any part of such damaged work, an equitable adjustment pursuant to the Contract Clause entitled, "Changes", will be made as full compensation
DOCUMENT 00 08 00 Page 2 therefore.
b. The Contractor may, subject to approval of the Contracting Officer, or the Contracting Officer may order the Contractor to, flood or breach the cofferdam during a rise prior to, and in anticipation of, natural flooding due to overtopping. Such flooding or breach will be considered the same as though the cofferdam, if constructed in accordance with plans and progress schedules approved by the Contracting Officer, had been overtopped, in which event an equitable adjustment will be made for damages to the cofferdam and/or any part of the permanent work, as provided in (a) above.
1.4 QUANTITY SURVEYS
The Contractor shall have a Professional Land Surveyor registered in the state the work is being accomplished conduct pre- and post-construction bathymetric surveys to verify that riprap has been replaced to pre-construction lines and grades. Surveys shall be performed in the presence of the Contracting Officer and all field survey notes be initialed by the Government Representative and furnished to the Government within 24 hours unless directed otherwise by the Contracting Officer.
1.5 PARTIAL PAYMENT
At the discretion of the Contracting Officer, partial payment will be made for equipment delivered and stored on site or off site providing such storage is in accordance with the provisions of these specifications and the Contractor furnishes satisfactory evidence that title to such equipment has been acquired and that it will be utilized on the work covered by these specifications. Partial payment is defined as the invoice amount plus shipping costs. If the equipment is stored off site, the Government shall have the right to inspect the equipment.
1.6 CERTIFICATES OF COMPLIANCE
Any certificates required for demonstrating proof of compliance of materials with specification requirements shall include the signature and title of an official authorized to certify in behalf of the manufacturing company and shall contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates shall contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from responsibility for furnishing satisfactory material if, after tests are performed on selected samples, the material is found not to meet the specific requirements.
1.7 PURCHASE ORDERS
Purchase orders for other than stock materials showing the firm names and addresses and list of material shall be furnished to the Contracting Officer or an authorized representative as soon as issued.
1.8 SAFETY AND HEALTH REQUIREMENTS MANUAL EM 385-1-1
The Safety and Health Requirements Manual EM 385-1-1 forms a part of these specifications. EM 385-1-1 and its changes are available at http://www.publications.usace.army.mil/USACEPublications/Engineer-Manuals/ .
DOCUMENT 00 08 00 Page 3
Contractor shall be responsible for complying with the current edition and all changes posted on the web as of the effective date of this solicitation.
1.9 ACCIDENT INVESTIGATIONS AND REPORTING
Refer to EM 385-1-1, Paragraph 01.D. Accidents, involving contractor and/or subcontractor employees performing any work or related work on a USACE project, shall be investigated and reported immediately to the Contracting Officer or authorized Contracting Officer's representative.
This reporting requirement applies to on-site or off-site accidents. Upon receipt of the initial accident report notification, the Contracting Officer shall issue additional guidance concerning continuing project operations which may include a "cease work" directive. If a cease work directive is issued, the Contractor will not be allowed to resume work related to the accident until all conditions of the "cease work" directive are met. After the initial notification, the Contractor shall ensure a formal investigation is conducted and reports are completed by the immediate supervisor of the employee(s) involved and reported to the Contracting Officer or an authorized representative within one working day after the accident occurs. The accident Investigation report shall be made on ENG Form 3394.
1.10 DAILY INSPECTIONS
The Contractor shall perform daily safety inspections and record them in RMS. Reports of daily inspections shall be maintained at the job site.
The reports shall be records of the daily inspections and resulting actions. Each report shall include, as a minimum, the following:
a. Phase(s) of construction underway during the inspection.
b. Locations of areas inspections were made.
c. Results of inspection, including nature of deficiencies observed and corrective actions taken, or to be taken, date, and signature of the person responsible for its contents.
1.11 ENVIRONMENTAL LITIGATION
a. If the performance of all or any part of the work is ordered by a court of competent jurisdiction to be suspended, delayed, or interrupted as a result of environmental litigation, as defined below, the Contracting Officer, at the request of the Contractor, shall determine whether the order is due in any part to the acts or omissions of the Contractor or a Subcontractor at any tier not required by the terms of this contract. If it is determined that the order is not due in any part to acts or omissions of the Contractor or a Subcontractor at any tier other than as required by the terms of this contract, such suspension, delay, or interruption shall be considered as if ordered by the Contracting Officer in the administration of this contract under the terms of the Contract Clause entitled "Suspension of Work".
b. The term "environmental litigation", as used herein, means a lawsuit alleging that the work will have an adverse effect on the environment or that the Government has not duly considered, either substantively or procedurally, the effect of the work on the environment.
DOCUMENT 00 08 00 Page 4
1.12 TIME EXTENSIONS FOR UNUSUALLY SEVERE WEATHER
a. This provision specifies the procedure for the determination of time extensions for unusually severe weather in accordance with the Contract Clause entitled, "Default (Fixed-Price Construction)". In order for the Contracting Officer to award a time extension under this clause, the following conditions must be satisfied:
(1) The weather experienced at the project site during the contract period must be found to be unusually severe, that is, more severe than the adverse weather anticipated for the project location during any given month.
(2) The unusually severe weather must actually cause a delay to the completion of the project. The delay must be beyond the control and without the fault or negligence of the Contractor.
b. Upon acknowledgement of the Notice to Proceed (NTP) and continuing throughout the contract, the Contractor shall record on the daily CQC report, the occurrence of adverse weather and resultant impact to normally scheduled work. Actual adverse weather delay days must prevent work on critical activities for 50 percent or more of the Contractor's scheduled work day. The delay must be beyond the control and without the fault or negligence of the Contractor. The number of actual adverse weather delay days shall include days impacted by actual adverse weather (even if adverse weather occurred in previous day), be calculated chronologically from the first to the last day of each month, and be recorded as full days. The Contracting Officer will convert any qualifying delays to calendar days, giving full consideration for equivalent fair weather work days, and issue a time extension modification in accordance with the FAR Clause 52.249-10 entitled "Default (Fixed Price Construction)".
1.13 RIVER STAGE LIMITATIONS
The Contractor should be aware that river levels may cause work delays.
The Contractor is responsible for becoming familiar with expected flow rates and river stages, and should monitor river forecasts and weather forecasts. If river levels are forecasted such that they are expected to impact work, the Government may direct the Contractor to stop work and/or remove floating plant from site. In the event of a significant rise in river stages, the Contractor is to protect completed works and prevent damage. Pursuant to the "Default" clause, the Contracting Officer will determine the extent of the delay to the work due to these limitations, and the time fixed for completion of the contract will be extended for the period of the time delay.
1.14 SUBCONTRACTS
In accordance with the Contract Clause entitled "Subcontracts", the Contractor shall, within seven days after the award of any subcontract by the Contractor or a Subcontractor, deliver to the Contracting Officer an electronic copy of a completed Standard Form 1413 with the original signatures of both parties.
1.15 REQUIRED INSURANCE
a. As required by the Contract Clause entitled "Insurance-Work on a
DOCUMENT 00 08 00 Page 5
Government Installation", the Contractor shall within 15 days after receipt of Notice of Award and prior to the commencement of work, furnish to the Contracting Officer, a written statement of required insurance as evidence of the following minimum insurance:
(1) Workmen's Compensation . Amounts required by applicable jurisdictional statutes.
(2) Employer's Liability Insurance . $100,000
(3) Comprehensive General Liability Insurance .
Bodily Injury - $500,000 per occurrence
(4) Comprehensive Automobile Insurance .
Bodily Injury - $200,000 each person $500,000 each accident Property Damage - $ 20,000 each accident
b. Statements of required insurance shall be submitted electronically or to the following address:
Department of the Army St. Louis District, Corps of Engineers Central Area Office; CEMVS-EC-CA 1222 Spruce Street St. Louis, Missouri 63103
1.16 PROTECTION OF MATERIAL AND WORK
The Contractor shall at all times protect and preserve all materials, supplies, and equipment of every description (including property which may be Government-furnished or owned) and all work performed. All reasonable requests of the Contracting Officer to enclose or specially protect such property shall be complied with. If, as determined by the Contracting Officer, material, equipment, supplies, and work performed are not adequately protected by the Contractor, such property may be protected by the Government and the cost thereof may be charged to the Contractor or deducted from any payments due to the Contractor.
1.17 CONTAMINATION OF WATER
In addition to the requirements set forth in SECTION 01 11 30, paragraph Protection of Water Resources, the Contractor shall take positive protective measures to prevent spillage of potential pollutant materials such as fuel, emulsion materials, chemicals etc., from storage containers or equipment, into lakes or tributary waters. Such positive protective measures may include, but are not limited to, the following:
(1) A berm enclosure of sufficient capacity to contain such materials.
(2) Security measures to prevent acts of vandalism which could result in spillage of such materials (fences, guards, etc.).
(3) Storage of such materials in an area where the terrain would preclude leakage into lake or tributary waters.
(4) Utilization of secure Government storage areas if the Contracting
DOCUMENT 00 08 00 Page 6
Officer indicates such space is available. No storage past immediate needs (2 days) without the consent of the Contracting Officer.
The Contractor shall submit its proposals for implementing the above provisions in accordance with SECTION 01 11 30, paragraph Environmental Protection Plan.
1.18 COMMERCIAL WARRANTY
The Contractor agrees that the standard commercial equipment furnished under this contract shall be covered by the most favorable commercial warranties the manufacturer gives to any customer for such equipment, and that the rights and remedies provided herein are in addition to and do not limit any rights afforded to the Government by any other clause of this contract. The Contractor shall furnish an electronic copy of the warranties to the Contracting Officer.
1.19 ORDER AND COORDINATION OF WORK
The Contractor may start and complete the work in such order and sequence as desired subject to compliance with the following paragraphs:
A. SPECIAL CONSIDERATIONS.
(1) These specifications cover the contract work at Lock and Dam No.
25. The contract work is for the fabrication and installation of 3 Floating Mooring Bits; the installation of 3 Floating Mooring Bit recesses, line hooks and kevels; the filling of the existing miter gate recess. The work includes, but is not limited to:
a. Installation and removal of Contractor-designed Movable Cofferdams.
b. Offsite storage of stoplog during construction.
c. Relocation of boat hoist.
d. Diving operations
e. Concrete demolition
f. Underwater Excavation
g. Fabrication of line hooks, kevels, and floating mooring bit.
h. Reroute conduit duct bank.
i. Installation of new concrete and concrete reinforcement.
j. Operational function test of all floating mooring bit slots.
k. Temporary and permanent wiring/conduit for the lock lighting circuits
(2) The Contractor must work around and not conflict with lock operations and maintenance activities. Work shall be limited to the intermediate wall. Work shall not impact navigation or the operating lock. Contractor shall coordinate with lock personnel when construction activities may impact space reserved on the intermediate wall for lock operations. Where lock operations are performed construction activities shall not pose any safety / operational hazards to lock personnel or navigating craft. All work activities shall be identified in the Contractor's work plan submittal for review and approval by the Contracting Officer's Representative to assure no adverse impacts to lock operations.
(3) The stationing and dimensions shown on the contract and reference drawings for the existing structure have been taken from the original contract drawings and the shop drawings for the original
DOCUMENT 00 08 00 Page 7 construction. The Contractor shall verify all the above stationing and dimensions and shall be responsible for making the new material and work fit the existing conditions.
(4) The Contractor is advised there is a potential for unexpected movement of pool ice during the months of December through February.
The Contractor should further be aware that the pool ice can become so thick that work may not be able to be performed upstream of the lock and dam. Any equipment and especially vessels that are captured by the ice will be subjected to severe damage or destruction. The lockmaster will attempt to provide advance notice of ice movement as a courtesy to the Contractor. The failure of the Government to issue such a notice will not entitle the Contractor to seek damages against the Government. Considerable amounts of ice may be encountered while moving equipment on the river and in the locks.
(5) The Contractor shall coordinate its operations so as not to interfere with the functions of the Government personnel and the regulation of the dam. Facilities shall be maintained for operating personnel so they can perform their normal functions. The Contractor shall designate a coordinator to assure that the construction work is coordinated with the operation of the lock and dam. Lock and dam personnel will not accept deliveries, phone calls, or mail or deliver messages for the Contractor.
(6) At least 7 days prior to mobilization of any equipment/material storage, the Contractor shall submit to the Contracting Officer for approval the plan for storage of materials and equipment at the lock and dam site.
(7) Potable water will not be made available to the Contractor. The Contractor shall furnish all potable water.
(8) Contractor personnel shall not use on site public toilet facilities or the toilet facilities at the lock (either in the Control House, Maintenance Buildings or public access). The Contractor shall provide its own portable facilities. Temporary toilet facilities shall conform to paragraph 02.B of the U.S. Army Corps of Engineers "Safety and Health Requirements Manual" EM 385-1-1.
(9) Temporary mooring areas for floating plant will be available as shown on the drawings. Final location of temporary mooring shall be coordinated with the Lockmaster and approved by the Contracting Officer. The Contractor shall develop a plan to enable 24 hours a day, 7 days a week monitoring of the floating plant At least 7 days prior to mobilization, the Contractor's Mooring Plan shall be submitted to the Contracting Officer for approval. In the event of severe high water conditions, at the Governments discretion the Contractor may be required to remove all floating plant from the project area until the water has receded.
(10) Parking areas for Contractor personnel, storage areas for Contractor materials and equipment and areas of egress are available for use and shall be in locations as shown on the drawings and as designated by the Contracting Officer.
(11) The Contractor is advised that other contracts may be ongoing at the project site during the life of this contract, and shall coordinate its work with the other Contractors and shall cooperate
DOCUMENT 00 08 00 Page 8 with the Contracting Officer's Representative and other Contractors to the fullest extent possible so as to not interfere with or hinder the progress of other contracts. The Contracting Officer will have the final decision in the event of a controversy between Contractors.
(12) Access to the work site at Lock and Dam No. 25 is restricted. The Contractor is advised to visit the site prior to bidding on this project. The Contractor is responsible for physically controlling access to the project work site, and for setting up a system to verify the identity and the authorization of all persons who wish to enter during the contract period. The Contractor will provide a gate attendant to watch the gates during all hours the Contractor is working. The gate attendant shall be employed by the Contractor at no additional cost to the Government and must be equipped with a radio and mobile phone to notify Lock personnel in case of unauthorized entry. The Contractor will provide any required attendant station facility or building. The location of the attendant will be coordinated with the Lockmaster. Reasonable access to the site for the Corps of Engineers lock and dam personnel must be maintained at all times. Effectiveness of the Contractor's access control is subject to review by the Contracting Officer.
(13) The Contractor will not be given priority over other waterway users for lockages. The Contractor shall adhere to normal queuing procedures as required unless otherwise permitted by the Lockmaster.
(14) All work required in this contract, including proper containment and disposal of debris, shall be accomplished in place at Contractor's expense.
(15) Spuds shall not be lowered onto the apron/stilling basin.
The floating plant may be located downstream of the lock and dam.
Prior to any floating plant work, a multi-beam survey of the area shall be performed and results provided to the Government.
Additionally, the floating plant shall be powered by a vessel with sufficient horsepower in order to safely maneuver the floating plant.
At the conclusion of the project, the Contractor shall perform a multi-beam survey and provide the results to the Government; any damage from use of floating plant shall be repaired.
(16) The Contractor shall monitor fluctuations of tailwater elevation and make tie off adjustments such that the floating plant shall not damage the piers. At all times when work is not in progress, the Contractor shall be required to have a 24-hour telephone number where the Government may reach a representative of the Contractor to notify of any problems with the floating plant. The representative must be available to be on site to attend to work barge(s) within 60 minutes of a phone call from the Government 24 hours a day, 7 days a week. The Contractor shall post and keep current a list of telephone numbers for emergency action. The Contractor shall submit the contingency plans for addressing headwater and/or tailwater fluctuations to the Contracting Officer for approval at least 7 days before mobilization.
(17) The Contractor shall keep the area adjacent to the lock chamber on the intermediate wall clear of debris and equipment at all times. During contract work on the intermediate wall, all equipment placement and operations on the deck should be minimized and shall be coordinated with the Lockmaster. The Contractor shall keep all
DOCUMENT 00 08 00 Page 9 hatches on the intermediate wall clear.
(18) The Contractor will not be allowed access to the lock and dam control station other than for coordination purposes.
(19) The Contractor shall be responsible for arranging for all temporary utilities required for the completion of work under this contract. No temporary hookups to existing lock facilities will be allowed unless stated otherwise in this specification. The Contractor will be allowed to connect to on-site 480V electrical power receptacles located on the lockwalls; however, it shall be the responsibility of the Contractor to provide and install temporary distribution equipment. The Contractor is responsible for providing a source of emergency backup power for the Contractor's operations and equipment that exceeds on-site power ratings to ensure critical operations can continue in the event of an electrical power disruption.
(20) Construction limits will extend as shown on the drawings.
Contractor personnel may cross the main lock upper and/or lower miter gate when the gates are closed and may cross the auxiliary lock miter gate to gain access to the construction limits. Only hand carried equipment shall be brought across the miter gates and the dam by Contractor personnel. The Contractor shall be provided two keycards to open the front gate, to be used by the QC Superintendent and Guard during working hours. The keycards can be checked out from lock personnel at the start of the work week and checked in at the end of the work week. The QC Superintendent and Guard shall be the sole persons allowed to use the keycard and shall be responsible for Contractor personnel access through the gate during working hours. If the Contractor works multiple shifts, the Government will allow a different, similar method for keeping the keycard.
(21) The Contractor's employees will be required to park personal vehicles outside of Government Property.
(22) No floating plant will be allowed behind the lower guide wall. Size restriction of floating plant moored at Contractor staging area shall be a maximum combined width of seventy (70) feet.
(23) Utilities not shown or identified in the plans or specifications may be encountered by the Contractor during construction activities. The Contractor shall submit plan to relocate and restore such utilities as required for approval by the Contracting Officer's Representative.
(24) Security fencing and hand railing may be removed in work areas during construction as long as safety and security is maintained and replacement made to its original location and condition, including an approved method and type of touch up painting as necessary.
Contractor proposals for fencing and handrails modifications shall meet requirements in EM 385-1-1 and be submitted for approval.
(25) Floating plant and personnel shall comply with the applicable U.S. Coast Guard regulations and licensing requirements. Floating plant equipment shall meet the applicable requirements of 46 CFR Chapter 1 Subchapter E and 46 CFR 44.05-10. Floating vessels operating on the Mississippi River and its tributaries must be operated in accordance with 33 CFR 207.300, "Ohio River, Mississippi River above Cairo, Ill., and their tributaries; use, administration, DOCUMENT 00 08 00 Page 10 and navigation." The Contractor's methods for disposal of sanitary sewage, and bilge water accumulated aboard floating plant, shall meet applicable local, state, and federal requirements.
(26) All elevations and dimensions shall be verified in the field before work begins. The Contractor is responsible for confirming all dimensions prior to shop drawing preparation and material fabrication.
(27) Materials which are not salvaged by the Government shall be disposed of in accordance with contract specifications.
(28) The Contractor shall provide measures to protect all new and existing operating machinery and electrical components adjacent to the work areas from contamination by surface preparation, abrasive blast debris, power spraying, weld splatter, concrete splatter, paint overspray, dust or other related debris during performance of the work. Items to be protected include, but are not limited to, tainter and/or roller gate hoists and appurtenant equipment including electrical panels. The Contractor shall be responsible for any repairs resulting from damage to all new and existing operating machinery and electrical components. If contamination occurs, the Contractor shall adjust the protection to eliminate contamination at other areas as work progresses.
(29) The staging area for the contract shall be the area by both sides of the entrance gate as shown on contract drawings. No loading or unloading of materials and supplies shall be permitted from the lock walls or guide walls.
(30) The Contractor will be allowed to use the riverside of the I-wall for mooring floating plant.
(31) The Contractor shall provide the Contracting Officer and the Lockmaster or the designated representatives a minimum of a two (2) weeks initial notification and a final 48 hour advance notice prior to commencement of any work. The Contractor shall also coordinate access to the construction area with the Contracting Officer and Lockmaster or designated representatives.
(32) A simple span, prestressed concrete multi-girder bridge, identified as the Sandy Slough Bridge (Bridge No. CEPLMSMO-000001), provides vehicular traffic access to Lock & Dam 25. This structure is owned and operated by USACE. Previously performed load rating analysis results indicate this bridge meets criteria for AASHTO inventory and operating design loads as well as routine commercial traffic legal loads and no restrictive load posting is present at this time. If the Contractor intends to cross this bridge with any vehicles exceeding FHWA legal loads, the Contractor shall perform a permit load rating analysis and results shall be submit to the Government for approval.
The permit load rating analysis shall be in accordance with the AASHTO Manual for Bridge Evaluation, Routine/Unlimited Crossings and performed by a licensed Professional Engineer as well as reviewed by an independent third-party licensed Professional Engineer. The submitted analysis shall include results of the permit load rating, detailed description of analysis procedures, axle loads and configuration of the proposed vehicle, explanation of any assumptions utilized, list of references and a complete set of computations supporting the results detailed in the report. The report shall be signed and sealed by both the Licensed Professional Engineer who
DOCUMENT 00 08 00 Page 11 performed the analysis and the independent third-party reviewer.
Requests for original bridge design drawings, construction specifications, recent inspection reports and any other pertinent information needed to complete this analysis shall be submitted to the Contracting Officer.
(33) The Contractor shall be responsible for snow removal in the Contractor's access, work and parking areas as necessary to facilitate Contractor operations. In addition, the Contractor shall be responsible for all ice management within the construction limits during the construction period. Use of salt or corrosive agents shall not be permitted.
(34) If the Contractor has a need to perform an operation which requires the presence of Government personnel to operate gate machinery, valve machinery or other items, the operation must be performed during the normal Government working hours of 7:00 AM thru 5:00 PM, Monday thru Friday. The Contractor may perform all remaining work under this contract during unrestricted hours provided local ordinances are not violated.
(35) The Contractor shall be aware of and adhere to the following lock load restrictions:
a. Lock Walls. Weight limitations in the area of the lockwall shall be a maximum 40 tons within 50 feet of the lock chamber face of the lockwall and maximum 150 tons beyond 50 feet from the lock chamber face of the lockwall.
b. Protection of Existing Grating. Protection shall include all grating that is not replaced under this contract. This protection does not relieve the Contractor of the responsibility for limiting loads on the miter gate to prevent damage to the walkway support system.
c. Miter Gates. The Contractor shall not transport any loads over the miter gates or lock walls that will damage the grating or supports. The following requirements shall apply to transporting materials or supplies across the top of lock walls or miter gates:
1. Maximum loading (gross weight) shall not exceed 5,000 pounds with a maximum wheel load of 700 pounds or loadings in excess of 80 pounds per square foot.
2. All grating shall be covered by the Contractor with 3/4 inch exterior grade plywood.
3. Prior to using the upstream miter gates and intermediate wall to transport material and supplies to the downstream end, the Contractor must coordinate with the Lockmaster.
(36) Water movement due to river current presents hazards to divers and the need for general precautions for all construction activities.
All work requiring divers shall be coordinated with the Lockmaster and approved by the Contracting Officer. The Contractor shall be aware of the requirements for Pre-diving meetings and the Diving Plan as in accordance with EM 385-1-1. All diving shall be performed in accordance with Section 30 of EM 385-1-1. Prior to submitting bids on this contract, Contractors and their diving Subcontractors (if
DOCUMENT 00 08 00 Page 12 applicable), shall obtain copies of this manual, and plan their procedures and staffing requirement accordingly. The U.S. Army Corps of Engineers "Safety and Health Requirements Manual" EM 385-1-1 is available to prospective bidders for review at the U.S. Army Engineer District, St. Louis, MO, or online at:
https://www.publications.usace.army.mil/USACE-Publications/Engineer-Manuals/
B. ORDER AND SEQUENCE OF WORK. The Contractor may start and complete the work in such order and sequence as desired subject to compliance with the following paragraphs. The work tasks, milestones, and lock closure periods shall be entered into the Contractor's network analysis and monitored throughout the contract duration. The Contractor shall strictly adhere to specified Approved Lock Closure Periods. The specified duration of the closure periods will not be lengthened. The Contractor is required to obtain and coordinate the necessary resources to perform the designated work in the allotted closure periods.
(1) During the period of this construction contract, the lock will be continuously open to river traffic except for Approved Lock Closure Periods. The Contractor may be required to schedule work using multiple shifts, multiple crew operations, and work on weekends in order to complete the work. The Contractor shall be responsible for monitoring river conditions. Should ice conditions which would impede river transportation be anticipated, the Contracting Officer and the Contractor shall determine a path forward and payment will be made in accordance with Contract Clause entitled, "Changes". All impacts to navigation for Approved Lock Closure Periods shall be identified in the contractor's schedule and coordinated with and approved by the Lockmaster a minimum of three weeks in advance of the anticipated closure date. Any construction operations which impede lock operations along the landwall outside the scheduled lock closures will not be allowed unless coordinated with the Lockmaster. Upon identification of any additional changes in any previously scheduled impacts to navigation, the Contractor shall inform and coordinate with the Lockmaster as soon as possible, but no later than 7 days prior to the scheduled impact. The Lockmaster shall be given sufficient time to review and approve any changes.
(2) Approval for Lock Closure Periods. Lock Closure Periods will be provided to complete placement of concrete at each of the locations shown. To complete concrete placement at each location, it is anticipated that multiple lifts will be required. The Contractor shall take every step necessary to schedule placement of concrete lifts at multiple locations during a scheduled Lock Closure Period to minimize the total number of Lock Closures needed to complete the work. When the Contractor claims to be ready to perform tasks for which a lock closure period has been assigned, the Contractor and the Contracting Officer shall verify compliance with the Contractor's approved Work Plan. Changes or substitute measures initiated by the Contractor must be approved by the Contracting Officer. Upon acceptance of the readiness of the Contractor, the Contracting Officer will close the lock to river traffic. The Contractor will allow time for this inspection, review and necessary corrective action in his network analysis.
(3) Lock Closure Period for Floating Mooring Bit/Line Hook Concrete.
The Contractor will be permitted an 8 hour continuous lock closure period to place each lift of concrete required for the Floating
DOCUMENT 00 08 00 Page 13
Mooring Bit Recess/Line Hooks for each location. After each concrete lift closure period, the Contractor shall wait at least 24 hours until another lock closure is permitted in order to allow river traffic to pass the lock. The Contractor may work on this task outside the lock closure period provided that, in the determination of the Contracting Officer, river traffic will not be hindered.
(4) Lock Closure Period for Filling of the Existing Miter Gate Recess. The Contractor will be permitted a 12 hour continuous lock closure period to place each lift of concrete required for filling the existing miter gate recess. After each concrete lift closure period, the Contractor shall wait at least 24 hours until another lock closure is permitted in order to allow river traffic to pass the lock. The Contractor may work on this task outside the lock closure period provided that, in the determination of the Contracting Officer, river traffic will not be hindered.
(5) Sequencing of work on Lock 25 is to be determined by the Contractor and shall be submitted as a work plan for Government approval.
(6) The Contractor shall notify the Contracting Officer 14 days prior to scheduled concrete removal activities for Government survey of existing monolith joint bolts.
(7) Decommissioning of electrical conductors must be accomplished before drilling in monoliths which encase these conductors.
(8) Power and control for the dam shall be available continuously, except for temporary outages, not to exceed 4 hours, which are coordinated with the Lockmaster and approved by the Contracting Officer. The outages envisioned are for transferring between temporary and permanent power and control systems.
(9) Contractor must maintain safe access for lock operations personnel (foot traffic) between control building and dam at all times.
(10) Compressed air supply to the lock shall be continuous at all times during the construction period. Any disruptions to the compressed air supply to the lock shall be coordinated with the Lockmaster and approved by the Contracting Officer.
1.20 SUBMITTALS
Additional submittals for this contract that are not listed within individual technical provisions are listed below. Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 - SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Statements of Required Insurance; G Work Plan; G, EC-DS Storage Of Materials And Equipment; G Mooring Plan; G Contingency Plans; G
DOCUMENT 00 08 00 Page 14
Relocate And Restore Such Utilities; G Fencing And Handrails Modifications; G
SD-05 Design Data
Permit Load Rating Analysis; G, EC-DS
1.21 MEANS OF ESCAPE FOR PERSONNEL QUARTERED OR WORKING ON FLOATING PLANT
Two means of escape shall be provided for assembly, sleeping, and messing areas on floating plants. For areas involving 10 or more persons, both means of egress shall be through standard size doors opening to different exit routes. Where 9 or fewer persons are involved, one of the means of escape may be a window (minimum dimensions 24-inch by 36-inch) which leads to a different exit route. Refer to Section 19 of EM 385-1-1.
1.22 EMERGENCY ALARMS AND SIGNALS
a. Alarms. Emergency alarms shall be installed and maintained on all floating plant requiring a crew where it is possible for either a passenger or crewman to be out of sight or hearing from any other person. The alarm system shall be operated from the primary electrical system with standby batteries on trickle charge that will automatically furnish the required energy during an electrical-system failure. A sufficient number of signaling devices shall be placed on each deck so that the sound can be heard distinctly at any point above the usual background noise. All signaling devices shall be so interconnected that actuation can occur from at least one strategic point on each deck.
b. Signals.
(1) Fire Alarm Signals. The general fire alarm signal shall be in accordance with para 97.13-15b of the Coast Guard Rules and Regulations for Cargo and Miscellaneous Vessels, Subchapter I, 1 Sep 77 (CG 257).
(2) Abandon Ship Signals. The signal for abandon ship shall be in accordance with paragraph 97.13-15c of reference cited in (1) above.
(3) Man-Overboard Signal. Hail and pass the word to the bridge.
All personnel and vessels capable of rendering assistance shall respond.
c. Mooring Lines. Eye loops on mooring lines will be equipped with beckets or handling ropes to protect the hands of deckhands.
1.23 USE OF MECHANIZED EQUIPMENT ON FLOATING PLANT
When mechanized equipment is operated on floating plant the Contractor shall provide positive and acceptable means of preventing this equipment from moving or falling into the water. The type of equipment addressed by this clause includes front-end loaders, bulldozers, trucks (both on- and off-road), backhoes, track hoes, and similar equipment. If the Contractor plans to use such equipment on floating plant, an Activity Hazardous Analysis must be developed for this feature of work. The plan must include a detailed explanation of the type or types of physical barriers, curbs, structures, etc., which will be incorporated to protect the
DOCUMENT 00 08 00 Page 15 operator and prevent the equipment from entering the water. Nonstructural warning devices may be considered for situations where the use of structural barriers is determined to be impracticable. The Activity Hazard Analysis must thoroughly address the procedure and shall be submitted to the Contracting Officer for review and acceptance prior to start of this feature of work.
1.24 OBSTRUCTION OF NAVIGABLE WATERWAYS (DEC 1991) DFARS 252.236-7002
a. The Contractor shall--
(1) Promptly recover and remove any material, plant, machinery, or appliance which the contractor loses, dumps, throws overboard, sinks, or misplaces, and which, in the opinion of the Contracting Officer, may be dangerous to or obstruct navigation;
(2) Give immediate notice, with description and locations of any such obstructions, to the Contracting Officer, and
(3) When required by the Contracting Officer, mark or buoy such obstructions until the same are removed.
b. The Contracting Officer may--
(1) Remove the obstructions by contract or otherwise should the Contractor refuse, neglect, or delay compliance with paragraph (a) of this clause; and
(2) Deduct the cost of removal from any monies due or to become due to the Contractor, or
(3) Recover the cost of removal under the Contractor's bond.
c. The Contractor's liability for the removal of a vessel wrecked or sunk without fault or negligence is limited to that provided in Sections 15, 19, and 20 of the River and Harbor Act of March 3, 1899 (33 U.S.C. 410 et.seq.).
1.25 SIGNAL LIGHTS
The Contractor shall display signal lights and conduct its operations in accordance with the General Regulations of the Department of the Army and of the Coast Guard governing lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredges, and vessels engaged in laying cables or pipe in submarine or bank protection operations, lights to be displayed on dredge pipe lines, and day signals to be displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel, and the passing by other vessels of floating plant working in navigable channels, as set forth in Commandant U.S. Coast Guard Instruction M16672.2, Navigation Rules: International-Inland (Comdtinst M16672.2) or 33 CFR 81 Appendix A (International) and 33 CFR 84 through 33 CFR 89 (Inland) as applicable.
1.26 INSPECTION FACILITIES
a. In order to facilitate inspection, the Contractor will be required, without additional cost to the Government:
DOCUMENT 00 08 00 Page 16
(1) To furnish, on the request of the Contracting Officer or any inspector, the use of such boats, boatmen, laborers, and material forming a part of the ordinary and usual equipment and crew of the plant as may be reasonably necessary in inspecting the work.
(2) To furnish, on the request of the Contracting Officer or any inspector, suitable transportation from all points on shore designated by the Contracting Officer to and from the various pieces of plant.
b. Should the Contractor refuse, neglect, or delay compliance with these requirements, the specific facilities may be furnished and maintained by the Contracting Officer, and the cost thereof will be deducted from any amounts due or to become due the Contractor.
1.27 CONTRACTOR PERFORMANCE EVALUATIONS
In accordance with the provisions of Subpart 36.201(Evaluation of Contractor Performance) of the Federal Acquisition Regulation (FAR), construction contractor's performance shall be evaluated throughout the performance of the contract. The United States Army Corps of Engineers (USACE) follows the procedures outlined in Engineering Regulation 415-1-17 to fulfill this FAR requirement. For construction contracts awarded at or above $100,000.00, the USACE will evaluate contractor's performance and prepare a performance report using the Contractor Performance Assessment Reporting System (CPARS), which is a web-based system. After an evaluation (interim or final) is written up by the USACE, the contractor will have the ability to access, review and comment on the evaluation for a period of 30 days. Accessing and using CPARS requires specific software, called PKI certification, which is installed on the user's computer. The certification is a Department of Defense requirement and was implemented to provide security in electronic transactions. The certification software could cost approximately $110 - $125 per certificate per year and is purchased from an External Certificate Authorities (ECA) vendor.
Current information about the PKI certification process and for contacting vendors can be found on the web site: http://www.cpars.navy.mil/. If the Contractor wishes to participate in the performance evaluation process, access to CPARS and PKI certification is the sole responsibility of the Contractor.
1.28 SECURITY REQUIREMENTS
1. The contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .