This is a solicitation for commercial services to perform dockside repairs of the USCGC MAPLE, a 225-foot seagoing buoy tender. The contractor shall provide all necessary labor, materials, and equipment to complete various repair items in accordance with the specification over a 42-day period of performance starting March 7, 2023 at the cutter's homeport in Atlantic Beach, North Carolina. The solicitation will result in a firm fixed-price contract awarded under FAR Part 12 and FAR Subpart 13.5 Simplified Procedures for Certain Commercial Items, subject to availability of funds, with a small business set-aside and NAICS code of 336611. Quotes are due by November 7, 2022 and award is anticipated on or around January 6, 2023. Questions are due by November 2nd. The scope of services includes ship repair and associated support work.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0002 USCGC MAPLE DS.pdf | ||
| 225-WLB_512_16_1_-_B.pdf | ||
| Amendment 0001 USCGC MAPLE DS.pdf | ||
| MAPLE DS GFE.xlsx | XLSX spreadsheet | |
| Attachment 5 - USCG Ombudsman Notice.docx | DOCX document | |
| (S1.12) Combined Synopsis Sol CGC MAPLE DS.doc | DOC document | |
| Attachment 4 - Request for Clarification.docx | DOCX document | |
| Attachment 1 - SOS.xls | XLS spreadsheet | |
| Attachment 6 - Redacted J and A.pdf | ||
| Attachment 3 - Past Performance Information Form.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
USCGC MAPLE (WLB 207)
SPECIFICATION FOR DOCKSIDE REPAIRS
FY2023
Developed By: Peyton E. Henderson
(Rev-0, 23 August 2022)
USCGC MAPLE (WLB-225B) DRYDOCK AVAILABILITY FY2023
ii (Rev-0)
TABLE OF CONTENTS
Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property ............................................................................... vii Consolidated List of Critical Inspection Items ............................................................................................. ix Principal Characteristics ................................................................................................................................ x General Requirements WORK ITEM 1: Chain Lockers, Clean and Inspect WORK ITEM 2: Tanks, Ballast, Clean and Inspect WORK ITEM 3: Tanks, Dirty Oil and Waste, Clean and Inspect WORK ITEM 4: Heat Exchangers, Clean, Inspect And Hydro WORK ITEM 5: Anchor Windlass, Inspect and Service WORK ITEM 6: Anchor Chains and Ground Tackle, Inspect and Repair WORK ITEM 7: Tanks, Potable Water Preserve, 100 Percent WORK ITEM 8: Decks – Exterior (Buoy or Construction Deck), Preserve 100% WORK ITEM 9: Superstructure, Preserve, Partial WORK ITEM 10: Tanks, Potable Water, Clean and Inspect WORK ITEM 11: Hawse Pipes, Preserve WORK ITEM 12: Watertight Scuttle (External), Renew WORK ITEM 13: Galley, Renew WORK ITEM 14: Cargo Hatch Repair WORK ITEM 15: Weather Tight Doors, Renew WORK ITEM 16: Watertight Hatch (External DC Deck and Below), Renew WORK ITEM 17: Pad Eye Installation WORK ITEM 18: Compartment Insulation Renew WORK ITEM 19: Crane Pedestal, Preserve WORK ITEM 20: AMR Bulkheads, Preserve WORK ITEM 21: Anchor Pocket Repair WORK ITEM 22: Potable Water Pump Room Bulkhead, Preserve WORK ITEM 23: PFD Locker Ventilation, Install WORK ITEM 24: Vent Duct Insulation, Renew WORK ITEM 25: Weatherdeck Non-Skid Surfaces, Preserve WORK ITEM 26: Watertight Doors (External), Renew WORK ITEM 27: Vent Ducts, Laundry Exhaust, Commercial Cleaning WORK ITEM 28: Grey Water Holding Tanks, Clean and Inspect WORK ITEM 29: Sewage Holding Tanks, Clean and Inspect WORK ITEM 30: Grey Water Piping, Clean and Flush WORK ITEM 31: Sewage Piping, Clean and Flush WORK ITEM 32: Tank Level Indicators, Renew WORK ITEM 33: Potable Water Pneumatic Tanks, Clean and Inspect WORK ITEM 34: Potable Water System Relief Valves, Test and Renew WORK ITEM 35: Hydraulically Operated Cargo Hatch, Inspect and Service WORK ITEM 36: Compressed Air Receivers and System Valves, All, Clean, Inspect, Hydro and Lift . 135 WORK ITEM 37: Y-Strainer, Renewal WORK ITEM 38: Plenum Ventilation, Renew
USCGC MAPLE (WLB-225B) DOCKSIDE AVAILABILITY FY2023
iii (Rev-0)
REVISIONS RECORD
This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.
DATE REV# WORK
ITEM#
CHANGES MADE
NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.
iv (Rev-0)
CONSOLIDATED LIST OF REFERENCES
The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.
All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.
COAST GUARD DRAWINGS
Coast Guard Drawing 225 WLB 167-001, Rev W, Structural Closures
Coast Guard Drawing 225 WLB 256-001, Rev P, Seawater Cooling System Diagram
Coast Guard Drawing 225 WLB 259-005, Rev C, Combustion Intake & Exhaust A&D Hull Block 940
Coast Guard Drawing 225 WLB 581-001, Rev E, Anchor Handling System Arrangement
Coast Guard Drawing 225 WLB 801-020, Rev B, Tank CAPACITY - 95% Curves
Coast Guard Drawing 225 WLB-512-21, Rev B, SOLAS Locker Ventilation Modifications
Coast Guard Drawing 225B WLB 111-001, Rev A, Shell Expansion
Coast Guard Drawing 225B WLB 201-001, Rev D, Machinery Spaces Arrangement
Coast Guard Drawing 225B WLB 509-001, Rev A, Duct, Trunk, and Machinery Insulation Details
Coast Guard Drawing 225B WLB 512-001, Rev K, HVAC Diagram
Coast Guard Drawing 225B WLB 512-007, Rev B, HVAC A&D, Fr 66-92, Innerbttm & 1st Platform
Coast Guard Drawing 225B WLB 528-001, Rev G, Plumbing and Interior Deck Drains
Coast Guard Drawing 225B WLB 541-001, Rev J, Fuel Oil System Diagram
Coast Guard Drawing 225B WLB 556-001, Rev F, Hydraulic System Diagram
Coast Guard Drawing 225B WLB 593-001, Rev E, Sewage and Waste Water System Diagram
Coast Guard Drawing 225B WLB 593-009, Rev B, Sewage Holding Tank
Coast Guard Drawing 225B WLB 601-001, Rev P, General Arrangements Inboard & Outboard Profiles
Coast Guard Drawing 225B WLB 635-001, Rev E, Hull, Thermal, & Acoustic Insulation Schedule
Coast Guard Drawing 225B WLB 801-005, Rev A Tank CAPACITY - 95% Curves
Coast Guard Drawing 225B WLB-601-2, Rev N, Booklet of General Drawings
Coast Guard Drawing 225B-WLB 167-001, Rev M, Structural Closures
Coast Guard Drawing 225B-WLB 631-001, Rev G, Painting Schedule
NAVSEA Drawing 803-6397268, Rev -, Doors WT Quick Acting Arrangement
Coast Guard Drawing 225B-WLB 801-013, Rev B, Midship Section & Typical Sections
Coast Guard Drawing 225B-WLB 801-015, Rev B, Scantling, Decks, & Platforms
Coast Guard Drawing 225B-WLB 801-016, Rev -, Scantlings, Watertight Bulkheads
Coast Guard Drawing 225B-WLB-651-001, Rev D, Galley & Pantry Arrgt & Details
Coast Guard Drawing 225-WLB-437-001, Rev J, Tank Lvl Ind System Block, Wrg Deck Plan
Coast Guard Drawing FL-1602-89, Rev , Fleet 26 IN X 66 IN Weathertight Door v (Rev-0)
Coast Guard Fleet Drawing FL 2804-22, Rev-, Consolidated Visual ID for Cutters
NAVSEA Drawing 804-5773931, Rev A, Acoustic & Thermal Insulation for Compartments Installation
Details
NAVSEA Drawing 805-1624092 Rev E , Hatch W.T. Raised Individually Dogged 30" x 30" with
Scuttle' 30 PSI Arrangement
Coast Guard Drawing 225B WLB 532-002, Rev F, Potable Water Sys Dia
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors Manual
Coast Guard Technical Publication (TP) 0965-LP-109-1010, Tank Level Indicating (TLI) System - Type
No. 36000
Coast Guard Technical Publication (TP) 3498, Section A, Jul 2015, Buoy Chain Winch
Coast Guard Technical Publication (TP) 3518, Oct 2007, MDE Model 3608/1
Coast Guard Technical Publication (TP) 3523, SWBS 241-B, Nov 2007, Reduction Gear - Model
96DHCMGH-CP
Coast Guard Technical Publication (TP) 3523-242-A-C, 225 WLB MIB, SWBS 242, Coupling, Torsional, MMC PN 242-01-01 & 242-01-02
Coast Guard Technical Publication (TP) 3524, 2013, Manufacturer's Instruction Book-SWBS Group(s)
243-262
Coast Guard Technical Publication (TP) 3524, SWBS 245-B, May 2009, Propeller System, CPP - Model
110251007
Coast Guard Technical Publication (TP) 3559, SWBS 581B, Anchor Windlass, P/S - Model BMD-478
Coast Guard Technical Publication (TP) 3717, Jun 2003, Hydraulic Cargo Hatch
Coast Guard Technical Publication (TP) 3796, Section A, Aug 2006, Galley Hood – Model NBDL-60
(13’-4”)
NAVSEA Dwg 2803-980209, Plates, Label
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2020, Shipboard
Electrical Cable Removal, Relocation, Splice, Repair, and Installation
Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2020, Auxiliary
Machine Systems
Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2020, Clean
Shipboard Ventilation Systems
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures
Surface Forces Logistics Center Standard Specification 8635 (SFLC Std Spec 8635), 2020, Temporary
Services
Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2020, Temporary
Hull Accesses vi (Rev-0)
OTHER REFERENCES
The Society for Protective Coatings SSPC-SP 10/NACE No.2, Rev 7; Near-White Blast Cleaning
American Bureau of Shipping (ABS) Approved Chain, Accessory and Bar Manufacturing Facilities List, Oct 2016
American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2011, Disinfection of Water-Storage Facilities
American National Standards Institute/NSF International (ANSI/NSF) 61, 2015, Drinking Water System
Components - Health Effects
American Welding Society (AWS) D1.1/D1.1M:2020, Structural Welding Code–Steel
ASTM International (ASTM) D1330, 2015, Standard Specification for Rubber Sheet Gaskets
ASTM International (ASTM) F992, 2017, Standard Specification for Valve Label Plates
Commercial Item Description (CID) A-A-59316, 2003, Abrasive Materials for Blasting
Commercial Item Description (CID) A-A-59588, 2013, Rubber Silicone
Federal Specification (Fed Spec) RR-C-271, Rev E, Mar 2016, Chains and Attachments, Carbon and
Alloy Steel
MIL-A-22262, Mar 1996; Abrasive Blasting Media Ship Hull Blast Cleaning
MIL-C-24633, Oct 2014, Chain, Stud Link, Anchor, Low Alloy Steel, Flash Butt Welded
MIL-DTL-23549, Sep 2016, Grease, General Purpose
MIL-PRF-24667, Jun 2005, Coating system, Non-Skid, for Roll or Spray Application
MIL-S-22473 , Rev E(8); Sealing, Locking, and Retaining Compounds: (Single Component), 01/21/04
Naval Sea Systems Command (NAVSEA) Underwater Ship Husbandry Manuals (UWSH) S0600-AA-
PRO-160, Nov 2011, Chapter 16, Cofferdams
QPL-24667, May 2006, Qualified Product List of Products Qualified under Performance Specification
MIL-PRF-24667, Coating system, Non-Skid, for Roll or Spray Application
Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2019, Cork and
Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.1 (SSPC-SP 1), 2016, Solvent Cleaning
The Society for Protective Coatings (SSPC) Surface Preparation Specification No.11 (SSPC-SP 11), 2012, Power Tool Cleaning to Bare Metal
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP 10/NACE No.2, 2007, Near-White Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP 6/NACE No. 3, 2007, Commercial Blast Cleaning
The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation
Standard SSPC-SP WJ-2/NACE WJ-2, 2012, Waterjet Cleaning of Metals – Very Thorough
Cleaning
The Society for Protective Coatings (SSPC)/NACE-International (NACE) Joint Surface Preparation
Standard SSPC-SP 12/NACE No.5, Surface Preparation and Cleaning of Steel & Other Hard
Materials by High and Ultrahigh Pressure Water Jetting Prior to Recoating
American Society for Testing and Materials (ASTM), F1508, 2010, Standard Specification for Angle
Style, Pressure Relief Valves for Steam, Gas, and Liquid Services vii (Draft-3)
CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY
The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.
WORK
ITEM
MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED
COST
($/UNIT)
10 N TLI Sensor with Amplifier for tank 2-25-1-W
NSN: 5930-01-470-7052
P/N: 25165-01 1 ea. $2995
10 N TLI Sensor with Amplifier for tank 2-25-2-W
NSN: 5930-01-470-7052
P/N: 25165-01 1 ea. $2995
12 N RQAWTS 01-5-2; 21in
Diameter, Raised Quick-
Acting Watertight Scuttle
Lid, Steel
Juniper Industries JE31892-
SRQ-A 01-5-2
1 ea. $2240
13 N Lang Electric Fryer: Model:
130FM, 450VAC, 12.0 Kw,
14.4 Amps
Lang Model: 130FM 2 ea.
13 N Lang Electric Range w/Convection Oven Model:
R36C-ATCM, 12" x 24" X
3/4 thick hot plates (x2) and
8" diameter French plates
Lang Model: R36C-ATCM 1 ea
13 N Lang Electric Range w/Convection Oven Model:
R36C-ATDM, 36" x 24" x
1/2" thick Griddle
Lang Model: R36C-ATDM 1 ea
13 N Cleveland Electric Griddle
Model: KEL-25, 480VAC,
13.1 Kw, 27.2 Hp, and 15.7
Amps
Cleveland Model: KEL-25 1 ea
14 N Cargo Hatch Gasket Walz & Krenzer P/N D-WK-
831-1-8 or equivalent
2 $200
15 N 26 IN x 66 IN Weather Tight
Door, Steel, RH Swing, Without Fixed Light
NSN: 1
16 N 24 Inches x 36 Inches C.O., RSD, WTRTT, 4 Dog, Hinged on 36 Inches RH
Side, Hatch Coaming 6 Inch
Height
NSN: PN: 1 ea.
17 Y 2,000LB WLL ATON Flush
Deck Padeye (Buoy Tie-down)
NSN/PN Schoellhorn-
Albrecht S299
3 $125
26 N QAWTD 01-67-1; 26in x
66in Quick-Acting
Watertight Door Panel, Steel, 10-Dog, RH Swing, 9in Dia
Fixed Light
Juniper Industries JE-268-
DQ-24 01-67-1
1 ea.
viii (Draft-3)
26 N QAWTD 01-67-4; 26in x
66in Quick-Acting
Watertight Door Panel, Steel, 10-Dog, RH Swing, 9in Dia
Fixed Light
Juniper Industries JE-268-
DQ-24 01-67-1
1 ea.
32 N Tank Level Indicator for tank
01-78-1-F
NSN: 5930-01-470-7052
P/N: 25165-01 1 ea. 2,995.00
32 N Tank Level Indicator for tank 3-
48-1-F
NSN: 5930-01-470-7052
P/N: 25165-01
1 ea. 2,995.00
32 N Tank Level Indicator for tank 3-
48-2-F
NSN: 5930-01-470-7052
P/N: 25165-01
1 ea. 2,995.00
32 N Tank Level Indicator for tank 3-
54-0-F
NSN: 5930-01-470-7052
P/N: 25165-01
1 ea. 2,995.00
32 N Tank Level Indicator for tank 4-
30-1-F
NSN: 5930-01-470-7052
P/N: 25165-01
1 ea. 2,995.00
32 N Tank Level Indicator for tank 4-
30-2-F
NSN: 5930-01-470-7052
P/N: 25165-01
1 ea. 2,995.00
*Government-loaned property, which shall be returned to the vessel upon completion of the availability.
**New or refurbished equipment that the Government may provide for installation in place of existing equipment.
***Government-furnished property, which is to be supplied by either the vessel or the C4IT ServiceCenter
USCGC MAPLE (WLB-225B) DRYDOCK AVAILABILITY FY2023
ix (Draft-3)
CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS
The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5
(Inspection report particulars)):
Work
Item Title
5 Anchor Windlass, Inspect and Service
6 Anchor Chains and Ground Tackle, Inspect and Repair x (Rev-0)
PRINCIPAL CHARACTERISTICS
225' WLB (B-CLASS)
PHYSICAL
Length overall 225' 0"
Length between perpendiculars 206' 0"
Maximum beam 46'
Designed draft 13' 0"
Full load displacement 1905.6 Long Tons SW
Light ship displacement 1500.7 Long Tons SW
Minimum operating displacement 1869.2 Long Tons SW
Mast height (above 12' waterline) 67' 5"
Anchor Two 4000 lb standard Navy stockless anchors, 8 shots each, port and starboard, 1-
3/8 die lock chain
HULL
Bilge keels (port & starboard) Frames 42-79
Frame spacing
FR 0 to 12 21"
FR 12 to 30 22"
FR 30 to 102 24"
MACHINERY
Main propulsion Diesel Reduction
Diesel engines Two Caterpillar 3608, TA, 3100 BHP each @ 900 RPM
Number of propellers 1
Number of blades 4
Diameter 10'
Pitch Controllable
RPM 254
Ship's service diesel generators Two Caterpillar 3508 TA, 450 KW
Emergency diesel generator One Caterpillar 3406 DITA, 280 KW
Shore tie Two 450 VAC, 400 Amp, 3-wire
Shaft bearing, forward Cooper Bearing 01-BCP-1400-EX-TL
Shaft bearing, aft Water Lubricated Cutlass Bearing
TANK CAPACITIES
Diesel oil 76,498 gal.
Fresh water capacity 8056 gal.
Hydraulic oil capacity 2785 gal.
Lube oil storage 764 gal.
Grey water tank 2700 gal.
Sewage holding tank 1700 gal.
1 (Rev-0)
00000_0222_FLT
REC_00000_FLT_Commercial Project @ Contractor’ Facility (0121)
General Requirements
1. SCOPE
1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed at a commercial contractor’s facility for Coast Guard vessels.
1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and
'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is
Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.
2. REFERENCES
COAST GUARD DRAWINGS
None
COAST GUARD PUBLICATIONS
Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual
Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General
Requirements
Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and
Allied Processes
Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures
OTHER REFERENCES
None
3. REQUIREMENTS
3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements of this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.
2 (Rev-0)
3.1.1 NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents. Contractors can apply to NAVSEA headquarters directly for copies.
3.2 Fire watch requirements. The Contractor must refer to 3.3.1.3 (Fire watch requirements) of SFLC Std Spec
0000, in accomplishing the following task:
Provide portable fire extinguishers for Coast Guard fire watch personnel. Coast Guard fire watch is in lieu of contractor personnel during the hours of 0800-1600, Monday through Friday, and limited to four (04) Coast Guard fire watch personnel.
Provide fire watch personnel and fire extinguishers for the duration of the availability period, during and beyond noted Coast Guard fire watch support.
3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.
3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec
6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).
3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.
3.3.3 In-process quality control measures. The Contractor must abide by all the safety, preservation, and quality control requirements specified in SFLC Std Spec 0000, paragraph 3.2.4.2 (In-process QC measures for “critical-coated surfaces”).
3.3.3.1 Quality control requirements. The Contractor must abide by the following when performing preservation related inspections. The following measurements must be randomly spaced throughout for the purposes of providing a representation of the entire prepared or coated surface.
3.3.3.1.1 Surface profile measurements. One surface profile measurement must be taken for every 200 square feet for the first 1000 square feet; for each additional 500 square feet or less, one profile measurement must be taken.
Profile measurements must be taken in accordance with SFLC Std Spec 6310, paragraph 3.1.8.3 (Surface profile measurements). A “measurement” for surface profile is defined as follows:
ASTM D4417, Method B: One profile measurement is the average (mean) of 10 individual readings.
ASTM D4417, Method C: One profile measurement is the average (mean) of 2 individual readings.
3.3.3.1.2 Soluble salt conductivity measurements. 5 conductivity measurements must be taken every 1000 square feet. For submerged (immersed) applications conductivity measurements must not exceed 30 microsiemens/cm.
For non-submerged (non-immersed) applications conductivity measurements must not exceed 70 microsiemens/cm. If a conductivity check fails, clean the surface in accordance with SFLC Std Spec 6310, paragraph 3.1.8.5 (Soluble salt removal).
3.3.3.1.3 Coating thickness measurements. Three area measurements must be taken for the first 1000 square feet;
for each additional 1000 square feet, perform an additional area measurement. A “measurements” for coating thickness is defined as follows:
SSPC-PA 2 defines an area measurement as 5 separate spot measurements randomly spaced throughout a 100 square foot area.
SSPC-PA 2 defines a spot measurement as 3 gage readings and each new gage reading the probe must be moved to a new location within a 1.5 inch diameter circle defining the spot.
3 (Rev-0)
3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.
3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:
3.5.1 Contractor operated (non USCG) facilities. The Contractor must provide and maintain environmental protection as defined in SFLC Std Spec 0000 Appendix A, Requirements for Environmental Protection at
Contractor Operated (Non USCG) Facilities, as applicable, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.
3.5.2 Test and procedures. The Contractor is required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.
3.5.3 Regulatory notifications. The Contractor is responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The
Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility
Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System
(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.
3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, who is responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the Contractors’
Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out;
ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous
Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas; ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the Environmental
Records binder and required documentation, including environmental permits compliance and close-out.
3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix A, Requirements For
Environmental Protection At Contractor Operated (Non USCG) Facilities for HW disposal.
3.6 Local Policy. The Contractor must refer to site (e.g. Base) Regulations and Instructions for details regarding local policies (e.g. crane services, parking, or facility usage).
3.7 SFLC Standard Specification approved changes. The Contractor must be aware that the following are
4 (Rev-0) approved changes to published SFLC 2020 Edition Standard Specifications and supersede published content:
3.7.1 SFLC Standard Specification 8636. Add missing paragraphs between 3.2 and 3.5 of Std Spec 8636 as follows:
3.8 Access cut boundaries. The Contractor shall ensure that access cuts comply with the requirements and restrictions detailed in the following and in SFLC Std Spec 0740, and referenced codes.
3.8.1 Location of boundaries. Boundaries of access cuts and closure plates shall, in general, be located between principal ship framing, bulkheads, and other structural members and shall be at least three inches from any of these members or from the toes of other welds. A reduction in this three inch minimum may be approved by the
KO on a case by case basis provided sufficient clearance is maintained for welding and inspection requirements.
The boundaries of access cuts and closure plates should land on existing butts or seams, wherever practicable. The boundaries of prior access cuts should be utilized wherever possible. Boundaries may extend across one or more frames as required for the size of the opening.
3.8.2 Access hole dimensions and arrangements. Holes or access cuts shall be the minimum size necessary and shall be in accordance with the following:
Rectangular access cuts and closure plates welded into primary hull structure shall be at least 12 inches wide in the lesser dimension.
For circular access cuts, the minimum diameter shall be 4T, where T = thickness of the involved structural member, but not less than three inches.
Circular closure plates for access cuts less than two feet in diameter shall be dished 1/16 to 1/8 inch to allow for shrinkage when welded.
Corners of rectangular access cuts and closure plates shall have a minimum radius of 6 inches except when a boundary lands on an existing hull longitudinal seam or transverse butt weld.
Corners at an existing seam or butt shall intersect at a 90 degree angle.
Cuts that are to cross existing butts or seams shall do so at an angle of 90 degrees plus or minus 15 degrees.
In primary hull structure, existing welds forming the boundary of a cut shall be cut back 3 inches beyond the toe of the access cut, except that the cut back shall not intersect or cross an existing weld, frame, or structural member. In which case, the cut back may be reduced to a minimum of two inches in length.
Existing welds crossed by the cut shall not be cut back.
3.8.3 Primary hull structure. Primary Hull Structure includes the shell, main strength decks, principal longitudinal bulkheads, vertical keel, deep web girders and stiffeners designed to withstand the ship bending stress.
3.8.4 Mechanically fastened joints. Welding closer than six inches to a mechanically fastened joint should be avoided. When access cuts cross or come within six inches of a mechanically fastened joint, the fasteners shall be checked for tightness and if necessary, loose fasteners shall be seal welded or removed, and replaced for a distance of 6 inches beyond the edge of the cut. When a cut crosses a mechanically fastened seam the cut plates shall be repaired using single V welds backed with glass tape (MIL-C-20079) to prevent fusion between the mechanically fastened plates.
3.9 Ship integrity maintenance. The Contractor shall maintain safety and ship integrity by installing temporary guarding and coaming, in addition to weathertight and watertight closures. Remove these temporary fabrications after closing the hull access, and grind surfaces flush in way of removals. For shell plating cuts made at or below the waterline where temporary closures are impractical, the Contractor shall secure each vulnerable compartment and subdivision to minimize potential damage to the extent permitted by the scope and urgency of the work.
5 (Rev-0)
3.9.1 Guarding. Install temporary guards in accordance with 29 CFR 1915.73.
3.9.2 Coaming. Ensure that in areas where flammable liquids may be stored, a 4 inch high metal coaming shall be installed on the surface of the deck with tack welds and fully sealed with caulking compound. The coaming shall encircle the access cut in the deck.
3.9.3 Weathertight and contamination closures. Fabricate temporary closures, using fire retardant material, before cutting access openings and install closures whenever access is not in use. Closures shall be:
Constructed to protect the access from inclement weather and entry of contaminants (shall include a coaming or dam on the deck to redirect rain runoff away from the opening).
Fitted with fasteners that permit rapid installation and removal.
Able to support a minimum of 150 pounds per square foot for horizontal deck closures.
Where the access opening is in way of a removed hatch, scuttle or door, the closure shall be configured to allow normal passage of ship’s personnel and equipment.
3.9.4 Watertight closures. Ensure that access openings created four feet or less above the maximum anticipated waterline shall include temporary watertight closures when the vessel is waterborne.
NOTE
NAVSEA S0600-AA-PRO-160/CH16 provides requirements for design, fabrication, and installation of temporary watertight closures.”
3.9.4.1 SFLC Standard Specification 0000. Definitions and paragraphs updated and added as follows:
“Fire Boundary: Any physical barrier, fitting, bulkhead or deck, utilized to limit the passage of flame and smoke identified during a fire casualty.
Fire Zone: Fire zones are designed to confine a fire within an identified zone and provide a protected staging area for fire parties. Fire Zones are not yet indicated on all classes of CG cutter, though Transverse Water tight
Bulkheads will be indicated on Damage Control plates.
Fire Zone Boundary: A bulkhead or deck designed to limit the passage of flame and smoke. Fire zone boundaries confine a fire within a zone and provide protected staging areas for fire parties. Fire zones are formed using selected main subdivision bulkheads and portions of decks where the subdivision is stepped.”
3.9.4.2 Firefighting and Fire Prevention Conference. Conduct a firefighting and fire prevention conference in conjunction with the arrival conference or no later than 5 days after start of the availability. This conference must familiarize Ship’s Force with the Contractor’s Fire Safety and Response Plan for fire prevention and firefighting capabilities and responsibilities and with the procedures that will be in use by the Contractor and the region/installation or municipal fire and emergency services, as well as familiarize the Contractor and the region/installation or municipal fire and emergency services with the ship arrangement, shipboard fire prevention and firefighting systems, equipment, and organization, and familiarize all parties with the scope of work and aspects of the work or ship conditions that have significance in fire prevention and firefighting.
3.9.4.3 The Conference must specifically address the following matters:
Fire alarm and response procedures
Contractor firefighting capability and procedures
Region/installation or municipal fire and emergency services firefighting capability and procedures
6 (Rev-0)
Firefighting jurisdictional cognizance
Communication system for fire reporting and control or firefighting efforts
Shipboard arrangement including access routes, availability or firefighting systems (installed and temporary), and communication systems
Shipboard firefighting organization, systems, drills, and equipment
Ship, space, and equipment security consideration; including confirmation of service disconnects at designated main fire boundaries.
Compatibility of ship, Contractor, and region/installation or municipal fire and emergency services firefighting equipment
Industrial work scope, including location of ship, and effect on firefighting systems, access, and communications
3.9.4.4 The firefighting and fire prevention conference must include a table top fire drill.
3.9.4.5 Fire Responsibility Familiarization Tour. Conduct a tour of the ship with the COR, Ship’s Force for municipal fire and emergency services/or municipal fire department personnel, and Contractor key personnel assigned specific responsibilities during fires, to familiarize personnel concerned with the ship’s normal access and anticipated condition while industrial work is in progress.
3.9.4.6 Fire Prevention Responsible Party. The Contractor must designate a Fire Prevention Responsible Party who shall comply in all respects to 29 CFR 1915, NFPA 51B and NFPA 312. The Fire Prevention Responsible
Party attend the firefighting and fire prevention conference, conduct a weekly formal fire prevention and housekeeping audit, and act as the point of contact for firefighting and fire prevention concerns during the entire availability.
3.9.4.7 Fire Prevention and Safety Inspections. The Contractor shall conduct fire prevention and safety inspections to note and initiate actions to eliminate fire hazards or to implement work procedures to keep these hazards to a minimum.
3.9.4.8 An initial inspection shall be made by the Fire Prevention Responsible Party, jointly with the COR, to evaluate potential fire hazards in conjunction with the Fire Responsibility Familiarization Tour, or as soon as practicable after the tour and before any work commences. Submit one legible copy, in approved transferrable media, of a written report of the discrepancies and corrective actions to the COR and the Fire Safety
Representative within 4 hours after completion of the inspection.
3.9.4.9 Weekly inspections shall be made jointly with the COR or designated inspector. Submit one legible copy, in approved transferrable media, of a written report of the discrepancies and corrective actions, to the COR and the Fire Safety Representative within 1 hours after completion of the inspection. The Contractor’s responsible party attends daily work meeting to assess and compile project provided data to determine where additional focus is required to improve project safety and fire prevention performance.
3.9.4.10 Once on each manned/ regular workday, follow on inspections (which should rotate through different areas on large deck ships) shall include: a ship’s representative, ship’s safety officer, or equivalent. Deficiencies noted shall be corrected immediately, and forwarded to the project superintendent, ship’s CO and COR. The
Contractor’s Fire Prevention Responsible Party shall compile project provided data to determine where additional focus is required to improve project safety and fire prevention performance.
3.9.4.11 Minimum requirements for inspection. All inspections shall note the following, as a minimum:
Housekeeping conditions, including location of trash.
Type and amount of cargo aboard.
7 (Rev-0)
Type, amount, and condition of the fire protection equipment.
The types and approximate amounts of fuel and other flammable liquids, including all associated piping systems.
The visible requirements of this manual such as cleanliness, access and egress routes, temporary systems, fire extinguishers, condition of combination smoke and heat detectors, fire reporting and communication systems, and observe fire watch and hot work authorizations for hot work in progress.
3.9.4.12 Fire Safety Plan. Develop and implement a written fire safety and emergency fire response plan in accordance with 29 CFR 1915. Implement the plan with all Contractor employees and subcontractors. In addition to the requirements of 29 CFR 1915, the plan must identify:
3.9.4.13 Fire Watches. Identify all work items containing hot work requiring Fire watchers.
3.9.4.14 Material Condition and Fire Zone Boundary obstructions. In those instances where shipyard work equipment or services prevent setting the designated Material Condition of the asset, or obstructs the setting of
Fire Zone boundaries, address the disconnection/ severability of the materials and provide plans to:
remove obstructions when not in use, ensure any obstruction, i.e. hoses, cables, or ventilation has quick-disconnect points placed at or near identified fire protection boundaries fittings.
and/or propose other mitigation steps such as setting additional roving contractor firewatch or requesting augmented ship’s force assistance, and installing additional fire alarms at or near obstructed fittings
3.9.4.15 Fire zone fire curtains. Provide UL Listed (i.e. UL 10 D & UL 1784) and approved temporary “egress” fire curtains at the top and bottom of the ladder wells, and at each watertight closure on the longitudinal passageways to mitigate the spread of fire and smoke should it occur. Curtains shall be rolled DOWN during any hotwork occurring within an identified fire zone.
3.9.4.16 Fire Zone location will be conveyed by the COR.
3.9.4.17 All inoperable fittings must be relayed to the COR for inclusion to the Ship’s DC Closure Log.
3.9.4.18 Ensure access to temporary and Ship’s Force firefighting equipment is not obstructed or restricted.
Ensure Ship’s Force firefighting equipment is not relocated without written authorization from the COR. Provide a secure, Ship’s Force accessible temporary storage facility for firefighting equipment that is moved from its original location.
3.9.4.19 Identify each integrated fire protection system during the performance of the maintenance availability.
Indicate shipboard fire systems online/offline, and systems installed/provided by the Contractor, along with the types and frequency of tests of equipment and devices.
3.9.4.20 Details of all communication links (telephones, drop boxes, alarms, horns) location, testing interval, and interface with shore side response systems.
3.9.4.21 Each normal and emergency source of electric power, firefighting water, lighting, testing interval, and interface with shore side response systems.
3.9.4.22 Each location of all normal and emergency backup support equipment to be used in support when combating a fire, and the equipment's testing cycle.
8 (Rev-0)
3.9.4.23 Each organization to be used, designation of responsibility for all shifts, training, anticipated response times, and interface with shore side response units.
3.9.4.24 General procedures for directing Contractor employees on fire reporting, fire responses, firefighting actions, personnel accountability, and prolonged firefighting responsibilities.
3.9.4.25 Provide copy of training, and training records of employees within at least 30 days of the start of the avail, refresher training at the halfway point with all employees reached within 2 weeks.
3.9.4.26 Provision for portable communication devices for Contractor use during firefighting operations between site, fire, and Contractor's/shipyard’s operations center.
3.9.4.27 Submit one legible copy, in hard copy or approved transferrable media of the Fire Safety and Response
Plan to the COR no later than 10 days prior to commencement of work, and prior to any modification to the plan after initial approval.
3.9.4.28 Post the fire plan and a full set of DC plates at the quarter deck for use by casualty response.”
3.9.4.29 Fire Alarm. When requested, install a fire alarm system on the quarterdeck as designated by the COR, arranged to send a signal directly to a central station service, a remote station service, a cognizant fire department, a shipyard fire department, or a continuously manned location within the shipyard where trained operators can take immediate action to transmit an alarm.
3.9.4.30 Test the fire alarm system daily to ensure its reliability. Repair or replace defective or inoperative alarms immediately.
3.9.4.31 Fire alarm devices placed aboard ship shall be either a fire alarm pull box or a non-dial telephone.
3.9.4.32 In addition, place a telephone on the quarterdeck as an alternate means of calling the cognizant fire department, shipyard fire department, or a continuously manned location within the shipyard where trained operators can take immediate action to transmit an alarm.
3.9.4.33 When a cutter is in dry dock, place a means of reporting a fire at least every 100 feet on the dry dock floor under the length of the ship.
3.9.4.34 Alternate Power Disconnect. At the same location on the quarterdeck as the Fire Alarm, provide a shunt trip disconnect that will cut all Alternate Power to all circuits in the event of a fire.”
3.10 Vessel access. During work at the Contractor’s facility, provide access and/or egress to and from the vessel in accordance with 29 CFR 1915.74, Subpart E. Provide a minimum of two gangways that have the following:
Adequate walking surface width and strength and be safely secured.
A railing, with a mid-rail, on each side of the gangway, and a turn table if necessary.
Substantial steps properly secured and equipped with at least one handrail, when the upper end of the gangway rests on or is flush with the top of the bulwark of the dock.
Nets or other suitable protection on both sides, when there is a danger of personnel falling between the ship and the dock. Nets and other suitable protection must extend beyond the projected area of the access and egress points so as to catch a personnel that may be falling outward: i.e., the nets must be wider than the gangway.
Proper trimming at all times.
Adequate illumination for their full length.
Separated by one-fourth the length of the vessel, at a minimum, as to mitigate the possibility that an
9 (Rev-0) incident could block both means of escape.
3.10.1 Gangway alternative. If gangways are not practicable, submit to the COR a proposal for a suitable alternative.
3.11 Safety. Do not lay obstructions on or across the means of access/egress. Do not pass loads or cargo over the means of access/egress while personnel are on them.
3.11.1 The permanent (or temporary) announcing system must be used to inform workers and crew of all secured access and egress routes, and the information must also be posted on status boards.”
3.11.1.1 SFLC Standard Specification 8635. Paragraphs updated and added as follows:
3.11.1.2 Shipboard access/egress and routing of temporary services. Shall maintain a primary and secondary means of access/egress for each vessel, where practicable. Pre-plan for the installation of temporary services to minimize the total number of service leads penetrating the hull by maximizing the use of backbones and/or manifolds for industrial services. Pre-planning for the installation of temporary services shall include removal
(first in, last out, when no longer required). Pay special attention to transitional spaces (cross passages, top and bottom of stairwells) where services could potentially fall and restrict emergency personnel egress and/or casualty responder access.
3.11.1.3 Routing of temporary services through installed ship hull openings. The following applies to routing of temporary services through installed ship hull openings, both exterior and interior, designated for personnel egress and/or casualty responder access:
• For doorways, temporary services shall be limited to the topmost 8 inches of the opening.
The vertical height of the door, with services run, shall be no less than 50 inches unless the doorway has been “secured” specifically for temporary services. Service lines which are normally depressurized may remain be routed in doorways if their resultant pressurized configuration does not violate the 50 inch minimum clearance requirement.
• Temporary services may be run through hatches, provided the services fit between the hatch coaming and ladder. Additionally, the size of the opening, with services run, shall be no smaller than 28 inches in diameter unless the doorway has been “secured” specifically for temporary services. Services lines which can be easily collapsed (e.g., vent trunks) may encroach the 28 inch clearance area, by no more than 6 inches, if the collapsing of the service line reestablishes the 28 inch minimum clearance requirement.
Service lines which are normally depressurized may remain be routed in hatches if their resultant pressurized configuration does not violate the 28 inch minimum clearance requirement.
3.11.1.4 Additional Hull Cuts. When temporary services cannot be routed through interior and exterior installed shipboard personnel openings in accordance with paragraph 3.2.4., existing (or additional) access cuts utilized for routing of temporary service, personnel egress, and/or casualty responder access shall be approved by the COR.
3.11.1.5 Materials used for suspending temporary services. Temporary services shall be suspended at regular intervals, to prevent impeding personnel access/egress and emergency response, using a high temperature line that meets the noncombustibility test requirements contained in reference (e). When using steel wire rope, or other potentially abrasive material, an anti-chafing material shall be used to prevent damage of the temporary service line. When available, temporary service lines may be run through the ship’s structural elements (i.e., cable ways, light stanchions, etc.). When the routing of temporary services overhead is not practicable, temporary services, rigging of hoses, welding leads, and temporary lights shall be clear of the decks on temporary “trees” or brackets and be arranged to minimize tripping and other hazards.
10 (Rev-0)
3.11.1.6 Drawing of Services Entering the Ship. For each availability, the Contractor shall provide a simplified ship drawing showing compartments, access status, and temporary service system configuration of major service backbones/trunks and/or lines (including isolations). The drawing shall be suitable for use by emergency responders for isolation of services during an emergency and located at the CASCON Station and/or
DCC/Quarterdeck. The Contractor shall update the drawing as significant conditions change. At a minimum, the drawing shall include:
• Type, description of service.
• Shore side shut-off points.
• Route of service through the ship.
• Locations of quick disconnect fittings.
• Identification of vital services and any cautions for vital services.
3.11.1.7 Marking Temporary Services. All temporary services shall be positively identified with highly visible, durable, unique markings that include maintenance activity name, service type, location, and shore side shut-off points. Tags will be located (at a minimum) at the source, point of entry aboard ship, termination point, and at
Quick Disconnect Fittings (QDFs).
3.11.1.8 Quick Disconnect Fittings. QDFs shall be located within 10 feet of designated vertical and horizontal fire zone boundaries. When practicable, QDFs shall be installed within 10 feet of hull penetrations used for personnel access, to facilitate the deployment of smoke control curtains. QDFs must be capable of being disconnected safely on pressurized or energized systems unless approved for use as described in paragraph 10.4.9. Pressurized and disconnected QDFs must prevent wetting of energized equipment. For hull openings used for services only, QDFs are not required, provided the opening is fitted with an air and smoke control “sock” that remains in place around the services. Air and smoke control curtains are not intended to provide an air tight seal of the hull opening.
Rather, the curtains, or “socks” are to ensure that emergency responders can control the flow of air and smoke through the opening to allow for de-smoking of compartments, and minimize “chimney” effects. Curtains shall be made of fire resistant fabric meeting the requirements of reference (f).
3.11.1.9 Air flow control. The Contractor, in conjunction with SF, shall stage material to provide for temporary closure of access cuts, hatches, and other hull penetrations to control air flow in the event of a shipboard fire.
Temporary enclosures erected around hull access openings shall be constructed with the ability for emergency responders to rapidly deploy smoke control ventilation fans (i.e., damage control box fans). If the enclosures are constructed with ventilation fans installed, the fans shall have the ability to reverse air flow, in order to provide emergency responders the ability to actively de-smoke an affected compartment.
3.11.1.10 Service lines crossing fire zone boundaries. When service lines transit a fire zone boundary which cannot be safely disconnected locally (e.g., high voltage cables), the COR shall approve, in advance, the method to safely secure and remove the service.
3.11.1.11 Protection during installation, operation and removal of temporary services.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .