Attachment 2 - Drawings 2021-04-21.pdf
PDF 37 MB Posted
- Attached to
- Z1DA--Correct Interior Deficiencies 539-21-115 Federal contract opportunity
- Solicitation number
- 36C25021B0057
About this file
This document outlines a federal contract opportunity for interior deficiency corrections at the Cincinnati VA Medical Center. The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 10 will issue an Invitation for Bid for Project #539-21-115 to correct interior deficiencies. The solicitation will be set aside 100% for small businesses with a preference for Service-Disabled Veteran Owned Small Businesses. The SDVOSB must be properly registered and verified in the Vendor Information Pages and System for Award Management databases. The project magnitude is between $1,000,000 to $5,000,000 using NAICS code 236220 with a business size standard of $39.5 million. The duration of the project shall not exceed 300 calendar days from receipt of the notice to proceed. Bonds will be required, and safety documentation must be provided prior to award.
View the file
Other files for this federal contract opportunity
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXTERIOR ELEVATION
INTERIOR ELEVATION
SEE A400 SERIES SHEETS
SECTION/DETAIL NUMBER
DRAWING NUMBER
EQUIPMENT TAG
COLUMN GRID
NOTE
WINDOW OPENING
DOOR OPENING
ROOM NAME
ROOM NUMBER
WALL TYPE
SEE SHEET A601
CEILING HEIGHT
FINISH DESIGNATION
X
10'-8"
X
X
XX.X-X
XX
X
1/A101
X
A101
XX
TOILET ACCESSORY TAGX SIGNAGE TAG
X
XXX
X
Ludlow Ave.
C lif to n A v e
CINCINNATI
STATE
TECH.
Hopple St.
M.L.K. Dr.
McMillan St.
UNIV. OF
CINCINNATI
W.H.T Rd.
VAMC
3200 VINE ST.
M.L.K. Dr.
V in e
S t.
ZOO
Jefferson A ve.
UNIV.
HOSPITAL
Mitchell Ave.
R ea di ng
R d.
V ic to ry
P kw y.
XAVIER
UNIV.
N
Area of Work
J O H N
A
P O E
IO
H O
F O
E T A T
S
R EG
IS
E T
R E D
R A
C H
TI
E
CT
3131 Newmark Drive, Suite 200 Miamisburg, Ohio 45342 |www.johnpoe.com| 937.461.3290
VA Project No.
JPA Project No.
Department of Veterans Affairs Medical Center
ARCHITECTURE PLANNING INTERIOR DESIGN
3131 NEWMARK DRIVE, SUITE 200
MIAMISBURG, OHIO 45342
937.461.3290 P
JOHN POE ARCHITECTS
HEAPY ENGINEERING
MECHANICAL ELECTRICAL COMMISSIONING TECHNOLOGY
1400 WEST DOROTHY LANE
DAYTON, OH 45409
937.224.0861 P
937.224.5777 F
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
TERRACON CONSULTING, INC.
ENVIRONMENTAL
611 LUNKEN PARK DRIVE
CINCINNATI, OH 45226
513.321.5816 P
513.321.4540 F
/2
/2
:3
:5
A
M
Correct Interior Deficiencies at Cincinnati
04/21/2021
COVER SHEET
G001
CVKR
20004.00
539-21-115
Cincinnati VAMC
Correct Interior Deficiencies at Cincinnati
3200 Vine Street Cincinnati, OH 45220 PROJECT #: 539-21-115
JASON REEVES - CHIEF ENGINEER
CONSTRUCTION
DOCUMENTS
G001 COVER SHEET
G101 CODE DATA
G111 PHASING PLAN
G112 PHASING PLAN
AD111 DEMOLITION PLAN
A001 SUB-BASEMENT NOTE PLAN
A002 BASEMENT NOTE PLAN
A101 FIRST FLOOR NOTE PLAN
A102 SECOND FLOOR PLAN
A103 THIRD FLOOR NOTE PLAN
A111-D LOBBY DIMENSION PLAN
A111-N LOBBY NOTE PLAN
A121 LOBBY REFLECTED CEILING PLAN
A401 INTERIOR ELEVATIONS
A501 CASEWORK SECTIONS & DETAILS
A502 LOBBY INFO & CLERK DESK DETAILS
A511 MISCELLANEOUS DETAILS
A601 WALL TYPES
A611 DOOR SCHEDULE & DETAILS
IF101 LOBBY FLOOR FINISH PLAN
IF102 LOBBY WALL PROTECTION PLAN
IF103 LOBBY WALL FINISH PLAN
IF109 LOBBY FINISH LEGEND
IFE100 LOBBY FF&E PLAN
FX001 ABBREVIATIONS, SYMBOLS & INDEX OF DRAWINGS
FX111 LOBBY FLOOR PLAN - FIRE SUPPRESSION
P001 ABBREVIATIONS, SYMBOLS & INDEX OF DRAWINGS
PD111 LOBBY FLOOR PLAN - REMOVALS
PP110 LOBBY BASEMENT PLAN - NEW WORK
PP111 LOBBY FLOOR PLAN - NEW WORK
P611 SCHEDULES & SOIL WASTE & VENT DIAGRAM
M001 LEGEND, GENERAL NOTES, & INDEX OF DRAWINGS
MD111 LOBBY FLOOR PLAN - REMOVALS
MH110 BASEMENT FLOOR PLAN - DUCTWORK
MH111 LOBBY FLOOR PLAN - DUCTWORK
MP111 PARTIAL FIRST FLOOR PLAN - PIPING
MJ100A PARTIAL BASEMENT PLAN - DUCT SEAL - AREA A
MJ100B PARTIAL BASEMENT PLAN - DUCT SEAL - AREA B
MJ101A PARTIAL FIRST FLOOR PLAN - DUCT SEAL - AREA A
MJ101B PARTIAL FIRST FLOOR PLAN - DUCT SEAL - AREA B
MJ102A PARTIAL SECOND FLOOR PLAN - DUCT SEAL - AREA A
MJ102B PARTIAL SECOND FLOOR PLAN - DUCT SEAL - AREA B
MJ103 THIRD FLOOR PLAN - DUCT SEAL
MJ104 FOURTH FLOOR PLAN - DUCT SEAL
MJ105 FIFTH FLOOR PLAN - DUCT SEAL
MJ106 SIXTH FLOOR PLAN - DUCT SEAL
MJ107 SEVENTH FLOOR PLAN - DUCT SEAL
MJ108 EIGHTH FLOOR PLAN - DUCT SEAL
MJ109 NINTH FLOOR PLAN - DUCT SEAL
MJ110 PENTHOUSE PLAN - DUCT SEAL
M501 DETAILS - HVAC
M502 DETAILS - HVAC
M601 SCHEDULES - HVAC
M701 CONTROLS
E001 ABBREVIATIONS, SYMBOLS, GENERAL NOTES & INDEX OF
DRAWINGS
ED111 LOBBY FLOOR PLAN - LIGHTING REMOVALS
ED121 LOBBY FLOOR PLAN - POWER & SYSTEMS REMOVALS
EL111 LOBBY FLOOR PLAN - LIGHTING
EP111 LOBBY FLOOR PLAN - POWER
EY111 LOBBY FLOOR PLAN - FIRE ALARM
E501 DETAILS
E502 DETAILS
E601 SCHEDULES - LIGHT FIXTURES
E602 SCHEDULES - LIGHT FIXTURES
E603 SCHEDULES - PANELS
T001 ABBREVIATIONS, SYMBOLS & INDEX OF DRAWINGS
TD111 LOBBY FLOOR PLAN - REMOVALS
TA111 LOBBY FLOOR PLAN - NEW WORK
TY111 LOBBY FLOOR PLAN - PATHWAYS
T400 ENLARGED PLAN - SIGNALS CLOSET C179
T500 DETAILS - TECHNOLOGY OUTLET
T501 DETAILS - SECURITY
T502 DETAILS - TECHNOLOGY
TJ100 BASEMENT PLAN - DOOR REPLACEMENT
TJ101 FIRST FLOOR PLAN - DOOR REPLACEMENT
TJ103 THIRD FLOOR PLAN - DOOR REPLACEMENT
General Construction Notes
8. CONTRACTOR SHALL PROVIDE WOOD BLOCKING AT TOILET ACCESSORIES, HAND RAILS,
BUMPER RAILS, SHELVING, CASEWORK, MOUNTING BRACKETS AND OTHER WALL
MOUNTED ITEMS, AS INDICATED IN THE CONTRACT DOCUMENTS AND AS RECOMMENDED
BY PRODUCT MANUFACTURERS. ALL WOOD BLOCKING SHALL BE FIRE RETARDANT
TREATED.
9. ALL EXPOSED NEW WORK IS TO RECEIVE NEW FINISHES UNLESS SPECIFICALLY NOTED
OTHERWISE. iF NO FINISH IS INDICATED AT A PARTICULAR SURFACE, CONTRACTOR
SHALL PROVIDE FINISH(S) AS INDICATED AT SIMILAR CONDITIONS.
10. CONTRACTOR SHALL PROVIDE COMPLETE AND FULLY OPERATIONAL SYSTEMS WHICH
COMPLY WITH STATED CODES AND REGULATIONS. WHERE THE OMISSION OF A PART OR
ELEMENT OF A SYSTEM WOULD RESULT IN THE NON-OPERATION, OR INCORRECT
OPERATION OF A SYSTEM, CONTRACTOR SHALL INCLUDE SAID PART OR ELEMENT AS
PART OF THE WORK.
11. ALL PENETRATIONS THROUGH NEW AND/OR EXISTING SMOKE OR FIRE RATED WALLS
SHALL BE SMOKE/FIRE STOPPED AS REQUIRED BY THE RATING OF THE WALL.
12. FIRE PROTECTION CONTRACTOR'S SPRINKLER DESIGN WILL BE SUBJECT TO AN
INDEPENDENT REVIEW BY A CERTIFIED FIRE PROTECTION ENGINEER RETAINED BY THE
OWNER. THE FIRE PROTECTION CONTRACTOR IS RESPONSIBLE FOR MAKING ANY
REQUIRED CHANGES TO THE DESIGN AS IDENTIFIED BY THE OWNER'S FIRE PROTECTION
ENGINEER AS NECESSARY FOR COMPLIANCE WITH SPECIFIED NFPA REQUIREMENTS.
13. USE OF THE DUMPSTER LOCATIONS REQUIRES COORDINATION WITH THE COR AND
OTHER ONGOING CONSTRUCTION PROJECTS. SEE DEMOLITION PLAN FOR DESIGNATED
LOCATION.
14. LAYDOWN AREA OUTSIDE OF THE IMMEDIATE AREAS INVOLVED IN THIS WORK WOULD BE
EXTERIOR TO THE BUILDING WITH THE APPROXIMATE AREA OF THE A POD OR SMALL
CONTAINER UNIT. COORDINATE THE LOCATION OF ITEMS ON THE CAMPUS WITH THE COR.
* PLEASE NOTE THAT THE TERM PROJECT ENGINEER REFERS TO THE CONTRACTING
OFFICER'S REPRESENTATIVE (C.O.R.).
1. ALL WORK SHALL COMPLY WITH THE LATEST NFPA 101 LIFE SAFETY CODE,
INTERNATIONAL BUILDING CODE, AND OTHER COES AS IDENTIFIED IN VHA PROGRAM
GUIDE PG-18-3, TOPIC 01, CODES, STANDARDS AND EXECUTIVE ORDERS WHICH CAN BE
FOUND ON THE DEPARTMENT OF VETERAN AFFAIRS, TECHNICAL INFORMATION LIBRRARY
WEBSITE.
2. ALL WORK SHALL COMPLY WITH REQUIREMENTS OF THE LATEST ARCHITECTURAL
BARRIERS ACT ACCESSIBILITY STANDARD (ABAAS) AND DEPARTMENT OF VETERANS
AFFAIRS BARRIER FREE DESIGN GUIDE PG-18-13 WHICH CAN BE FOUND ON THE
DEPARTMENT OF VETERANS AFFAIRS TECHNICAL INFORMATION LIBRARY WEBSITE.
3. CONTRACTOR IS RESPONSIBLE TO VISIT THE SITE, EXAMINE AND ACCEPT EXISTING
CONDITIONS PRIOR TO BIDDING. SITE VISITS TO BE COORDINATED WITH THE
CONTRACTING OFFICER.
4. CONTRACTOR IS RESPONSIBLE TO REPAIR AND/OR REFINISH, TO MATCH ADJACENT
EXISTING SURFACES, ANY EXISTING MATERIALS TO REMAIN THAT ARE DAMAGED DURING
THE COURSE OF DEMOLITION OR NEW WORK.
5. WHERE REMOVAL OF EXISTING WORK IS REQUIRED FOR INSTALLATION OF NEW WORK,
CONTRACTOR SHALL REPAIR EXISTING CONSTRUCTION TO REMAIN OR PROVIDE NEW
CONSTRUCTION TO MATCH EXISTING ADJACENT SURFACES TO REMAIN.
6. CONTRACTOR IS RESPONSIBLE TO FIELD VERIFY ALL CONDITIONS AND DIMENSIONS
PRIOR TO ORDERING, FABRICATING OR INSTALLING NEW MATERIALS.
7. CONTRACTOR IS RESPONSIBLE TO VERIFY SIZES OF ALL EQUIPMENT, ETC. TO BE
INSTALLED AS PART OF THIS PROJECT, AND WHERE NECESSARY, MAKE SPECIAL
PROVISIONS TO INSTALL EQUIPMENT THAT IS TOO LARGE TO FIT THROUGH FINISHED
OPENINGS.
Drawing Index
Graphic Symbols
N.T.S.Scale:
Vicinity Map
N N.T.S.Scale:
First Floor Key Plan
Revisions Date
DN
0-HR Smoke Partition
1-HR Smoke Barrier
2-HR Smoke Barrier
1-HR Fire Barrier
2-HR Fire Barrier
Means of Egress
Existing Wall to Remain
New Wall
Area open to Corridor with Smoke Detection
Code Legend
Common Path of Travel Max. Allowable = 100' Actual = 75'
Travel Distance to Exit Max. Allowable = 200' Actual = 198'
Common Path of Travel Max. Allowable = 100' Actual = 40'
Travel Distance to Exit Max. Allowable = 200' Actual = 75'
Waiting C147
Vestibule C144
Corridor C*1*24
Waiting Room C100A
Waiting Area C100
Mgr. Med.
Surge Office C153
PBS Open Work Area
C154
Volunteer Services
C151
Patient Advocate
Office C158
PBS Office C155
Corridor C*1*10
Corridor C*1*13
Corridor C*1*4
Corridor C*1*4
Pharmacy Consult
C157
Pharmacy Consult
C156
Corridor C*1*23
Mech.
C149
Closet C150
Clerks C152
Corridor C*1*11
Common Path of Travel Max. Allowable = 100' Actual = 20'
Travel Distance to Exit Max. Allowable = 200' Actual = 131'
J O H N
A
P O E
IO
H O
F O
E T A T
S
R EG
IS
E T
R E D
R A
C H
TI
E
CT
3131 Newmark Drive, Suite 200 Miamisburg, Ohio 45342 |www.johnpoe.com| 937.461.3290
VA Project No.
JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
/2
/2
:3
:0
A
M
Correct Interior Deficiencies at Cincinnati
04/21/2021
CODE DATA
G101
CVKR
20004.00
539-21-115
Cincinnati VAMC
JASON REEVES - CHIEF ENGINEER
CONSTRUCTION
DOCUMENTS
N Scale: 1/16" = 1'-0"
First Floor Code Plan
Code: NFPA 101 Life Safety Code (2018 Edition)
Construction Type: Type I (222)
Use Group: Health Care Occupancy
Height: Partial 1 story renovation to existing 4 story building
Area of Work: 8574 SF - Lobby Entrance Renovation
Protection: Fully Suppressed
Chapter 4 - General
• 4.4.2.2 -Prescriptive-based life safety design meeting the requirements of Chapters 1 thru 3, Sections 4.5 thru 4.8, and
Chapters 6 thru 43 of this Code shall be deemed to satisfy the provisions of Sections 4.1 and 4.2.
• 4.4.2.3 -Where req’ts in Chapters 11 thru 43 differ from req’ts in Chapters 1 thru 4 and 6 thru 10, the req’ts of Chapters 11 thru
43 shall govern.
• 4.6.1.1 -The authority having jurisdiction (AHJ) shall determine whether the provisions of this Code are met.
• 4.6.7.1 -Rehabilitation category per 43.2.2.1.4 Reconstruction.
Chapter - 6 Classification of Occupancy and Hazard of Content
• 6.1.11 - Health Care Occupancy
• 6.2.2.1 -Hazard classification = Ordinary
Chapter 7 - Means of Egress
• 7.1.3.1 - Exit Access Corridors: no fire rating is required for corridor walls per 18.3.6.2.2
• 7.1.3.2.1 - Exit Separation:
(1)(3b) Connects 4 or more stories (Existing Egress Stairs with automatic sprinkler system): 1-hr. fire rating (NO CHANGE)
(9)(b) Openings in separation wall: fire doors with closers per 7.2.1.8.
• 7.2.1.8.2 - Door leaves shall be permitted to be automatic closing provided the following criteria are met:
(1) - Upon release of hold open mechanism, door leaf becomes self closing
(3) - Automatic releasing mechanism or medium is activated by the operation of smoke detectors installed in accordance with requirements for smoke detectors for door leaf release service in NFPA 72.
(4) - Upon loss of power, the hold open mechanism is released and the door leaf becomes self closing
• 7.3.1.2 – Occupant Load:
B1 - First Floor (Lobby Renovation): No Change in area or occupant load
• 7.3.2.2 – Max. projection within means of egress on ea. side: 4-1/2” (38” hgt. max.).
• 7.3.3.1 – Egress capacity (Health Care, sprinklered): No Change in occupant load & egress capacity
• Table 7.3.3.1- Stairs = .3” per occup; Level components and ramps = .2” per occup.
• 7.4.1.2 – Min. number of means of egress from any story = 2.
(1) Occupant load >500 and <1,000 = 3 exits minimum.
• 7.5.1.2.1 - Corridors to lead to means of egress without passing through any intervening spaces other than corridors, lobbies or spaces permitted to be open to the corridor.
• 7.5.1.2.2 - Corridors not required to be fire resistance rated shall be permitted to open into open floor plan areas.
Chapter 8 - Features of Fire Protection:
• Table 8.3.3.2.2 – Min Fire Protection for Openings in Fire-rated Assemblies:
Component Walls Fire Drs Vision Panel (size) FR Vision Panel FR Window Vert. shafts 2 hr 1-1/2 hr Max tested D-H-90 NP (stairs, exits):
Fire Barriers: 2 hr 1-1/2 hr Max tested D-H-90 NP
1 hr 3/4 hr Max tested D-H-45 3/4 hr
Smoke Barriers: 1 hr 1/3 hr Max tested D-20 3/4 hr 1/2 hr 1/3 hr Max tested D-20 1/3 hr
• 8.3.4.2.1 – Firestop Systems – Penetrations that pass thru a barrier shall be protected by a firestop system or device.
• 8.3.4.2.2 – The firestop system or device shall be tested in accordance with ASTM E814.
• 8.3.4.8 – Openings thru fire barriers for air-handling ductwork or air movement shall be protected per 9.2.1.
• 8.4.1 - Smoke Partitions shall limit the transfer of smoke.
• 8.5.1 - Smoke Barriers shall restrict the transfer of smoke and have 1 hour fire resistance rating.
• 8.5.3 - Fire Barriers that meet requirements of Section 8.5 shall be permitted to be used as a smoke barrier.
Chapter 9 - Building Service and Fire Protection Equipment
• 9.6.1.3 – Fire Alarm System req’d for life safety shall be per NFPA 70 and 72.
• 9.6.3.1 – Occupant notification shall be provided per 9.6.3, 18.3.4.3.1.
• 9.6.3.4 – Where permitted by Chapters 11 thru 43, a positive alarm sequence shall be permitted per NFPA 72 (See 18.3.4.3).
• 9.6.4.1 – Emergency Forces notification req’d per 9.6.4 and 18.3.4.3.2.1.
• 9.6.5.1 – Emergency Control functions shall be installed per NFPA 72 as req’d per 9.6.5 and 18.3.4.4.
• 9.6.7.1 – Alarm annunciation is required per 9.6.7 and 18.3.4.3.3.
• 9.7.1.1 – Supervised automatic sprinkler system as req’d by 9.7.1 and 18.3.5.1 and shall comply with NFPA 13.
• 9.9 - Portable fire extinguishers shall be selected, installed, inspected, and maintained per NFPA 10.
Chapter 10 – Interior Finish, Contents, and Furnishings
• Table A.10.2.2 Interior Finish Classification Limitations for Health Care (Existing)
Exit Access Corridors: Class A or B.
Other Spaces: Class A or B.
• 10.2.3.1 - Interior wall and ceiling finish materials shall be classified in accordance with NFPA 286 and comply with 10.2.3.2.
• 10.2.3.1.2 - Materials tested in accordance with 10.2.3.1.1 and complying with 10.2.3.2 shall be considered also to comply with the requirements of Class A, Class B, or Class C in accordance with 10.2.3.3.
• 10.2.3.3 – Wall and Ceiling – Classifications characteristics:
(1) Class A: Flame spread: 0-25; Smoke dev.: 0-450.
(2) Class B: Flame spread: 26-75; Smoke dev.: 0-450.
(3) Class C: Flame spread: 76-200; Smoke dev.: 0-450.
(4) Existing interior finish exempt from smoke dev. criteria.
• 10.2.7.2 – Floor finish other than carpet: Min. Rad flux: .1 W/ cm².
• 10.2.8.1 – Wall and Ceiling finishes, where sprinkled:
Class C permitted in any location where Class B is req’d.
Class B permitted in any location where Class A is req’d.
• 10.2.8.2 – Floor finishes, where sprinkled:
Class II permitted in any location where Class I is req’d.
Provisions of 10.2.7.2 shall apply where Class II is req’d.
Chapter 18 - New Health Care Occupancies
• 18.1.1.1.4 - The area of work is an existing hospital and therefore falls under Chapter 18.
• Table 18.1.6.1 - Construction Type Limitations: Type II (222), sprinklered, no story limitations.
• 18.1.7 - Occupant Load per Table 7.3.1.2.
• 18.2.2.2d.8 - Doors in exit passageways, horiz. exits shall be permitted to be held open only by an automatic release device that complies with section 7.2.1.8.2
• 18.2.3.4 - Corridors in hospitals shall be not less than 8 feet in clear an unobstructed width.
• 18.2.5.2 - Dead end corridors shall not exceed 30’.
• 18.2.5.3 - Common path of travel shall not exceed 100’.
• 18.2.5.4 - Every corridor shall have access to not less than two approved exits without passing through any intervening spaces other than corridors or lobbies.
• 18.2.5.6.5 - Rooms within suites shall not be required to an exit access door leading directly to an exit access corridor.
• 18.2.5.7.1.2 - Suite Separation – Suites shall be separated from remainder of the building by walls and doors (0-hr smoke partitions).
• 18.2.6.2.1 - Travel distance from any point in a room to exit shall not exceed 200’.
• 18.3.2.1.3 - Storage rooms (clean supply and clean linen) larger than 50 SF but not exceeding 100 SF shall be protected by smoke partitions.
• 18.3.4.1 - Health care occupancies shall be provided with a fire alarm system IAW Section 9.6.
• 18.3.5.1 - Building containing health care occupancies shall be protected throughout by approved, supervised automatic sprinkler systems IAW Section 9.7.
• 18.3.5.12 - Portable fire extinguishers shall be provided IAW Section 9.9.
• 18.3.6.2.2 - No fire resistance rating is required for corridor walls.
• 18.3.6.2.3 - Corridor walls shall form a barrier to limit the transfer of smoke but are not required to be smoke barriers or smoke partitions.
• 18.3.6.3.1 - Corridor doors shall be doors constructed to resist the passage of smoke.
• 18.3.7.3 - Smoke barrier shall be constructed IAW Section 8.5 and shall have 1 hour fire resistive rating.
• 18.3.7.6 - Doors in smoke barriers shall have 20 minute fire resistive rating.
• 18.3.7.5.1 - Not less than 30 net SF of accumulation space per resident/patient shall be provided in smoke compartment on either side of smoke partition. - The doors shall not be required to swing in the direction of egress travel.
Chapter 43 - Building Rehabilitation
• 43.1.2.1 - Any building undergoing repair, renovation, modification, or reconstruction shall comply with both of the following:
(1) Req'ts of the applicable existing occupancy chapters (Chapter 39).
(2) Req'ts of the applicable secton of this Chapter (Sections 43.4 and 43.5).
• 43.4.1 - Renovations & General Req'ts: all new work shall comply with the req'ts of other sections of this Code applicable to existing construction.
• 43.5.1 - Modifications & General Req'ts: all new work shall shall comply with the req'ts of other sections of this Code applicable to new construction.
N Scale: 1/16" = 1'-0"
Basement Code Plan
Code Notes
Waiting Area
C100
Office
C161
Tlt.
C160
Exam
C159
Exam
C158
Exam
C157
Exam
C156
Corridor
C*1*23
Pharmacy Consult
C162
Pharmacy Consult
C164
Exam
C163
Exam
C155
Office
C154
Office
C153
Office
C152
Break Room
C151
Info
C166A
Clerks
C166
Voluntary Service
C147
Vestibule
C144 Waiting Room
C100D
Waiting Area
C100 Clerks
C166
Info
C166A
Voluntary Service
C147
Common Path of Travel Max. Allowable = 100' Actual = 13'
Travel Distance to Exit Max. Allowable = 200' Actual = 140'
Break Room
C151
Office
C152 Office
C153
Work Area
C164A
Pharmacy Consult
C164
Mech.
C149
Waiting Room
C100D
Corridor
C*1*13
1.11
1.11
Corridor
C*1*4
Temporary Construction Barrier.
See Wall Type T1.0
Existing or work completed in previous phase
Area to be renovated in future phase
Area renovated during indicated phase
Ceiling work to be completed after hours during indicated phase
PHASING LEGEND
PBS Open Work Area
C154
Patient Advocate
Office
C158
PBS Office
C155
Min.
5' - 0"
1.12
1.13
T1.0
C*1*23
1.11
Vestibule
C144
T1.0
1.13
J O H N
A
P O E
IO
H O
F O
E T A T
S
R EG
IS
E T
R E D
R A
C H
TI
E
CT
3131 Newmark Drive, Suite 200 Miamisburg, Ohio 45342 |www.johnpoe.com| 937.461.3290
VA Project No.
JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
/2
/2
:3
:2
A
M
Correct Interior Deficiencies at Cincinnati
04/21/2021
PHASING PLAN
G111
CVKR
20004.00
539-21-115
Cincinnati VAMC
JASON REEVES - CHIEF ENGINEER
CONSTRUCTION
DOCUMENTS
Scale: 3/32" = 1'-0"
EXISTING FLOOR PLAN
Scale: 3/32" = 1'-0"1
PHASE 1 - FLOOR PLAN
GENERAL PHASING NOTES
A. For temporay partition locations see Demolition Plans. Temporary partitions are suggested locations. Coordinate final location in field with C.O.R.
B. Verify all conditions in the field prior to fabrication, erection and construction.
C. All asbestos containing material (ACM) must be abated per the direction of the C.O.R. and project specification 017419 and local state and federal regulations. Abatement if required is to be scheduled in appropriate sequence with demolition, new construction and project phasing.
D. Coordinate phase completion and start-up with requirements as set forth by the C.O.R. to maintain daily operations to near as normal as possible.
E. Coordinate location of job dumpster with the C.O.R. so as to disrupt daily operations as little as possible.
F. Coordinate access to all phases of construction, deliveries, and debris removal with the C.O.R. See General Requirements.
G. Temporary door locations and sizes are as required by the General Contractor. Doors will interfere with daily operations as little as possible. Confirm all locations with the C.O.R.
H. Existing HVAC, medical gases, sprinklers and water supply to be maintained throughout as required during each phase of construction.Coordinate phasing with Mechanical and Plumbing contractor. Support and protect all lines during each phase of construction. See MEP Drawings.
J. Provide and maintain negative air pressure at all construction.
Coordinate with HVAC contractor. See HVAC plans for temporary venting requirements and duct locations.
K. Phasing drawings to be used in conjunction with entire set of construction drawings.
L. Existing power must be maintained throughout as required during each phase of construction.Coordinate phasing with Electrical Contractor. Coordinate power turnover with requirements as dictated by the C.O.R. See Electrical Drawings.
M. Coordinate sequence construction with C.O.R. so that only one side of any corridor in use is obstructed at any one time.
N. Coordinate all operating work hours involving the generation of excessive noise with C.O.R. so as to minimize disturbances to patients. Activities to occur during this time include, but are not limited to saw cutting, jack hammering, hammer drilling and core drilling. If there is any question as to whether an operation should occur during this time the Contractor will contact the C.O.R.
P. All temporary walls to be wall type T1.0 unless otherwise noted.
Temporary wall removal to take place after standard operating hours.
Q. Night Work noted to take place after hours to be scheduled between 7:00 PM - 5:30 AM Monday-Friday, all day Saturday and Sunday.
R. Temporary construction wayfinding signs shall be provided and installed by VA. Locations to be coordinated with C.O.R.
NOTES
1.11 Work in corridors to be completed after hours. Contractor to provide dust separation for the construction area at the beginning of each shift. At the end of each shift Contractor to remove dust separation and clean work areas.
1.12 Maintain 5'-0: minimum around all temporary partitions.
1.13 Construct Temporary Partitions at the beginning of phase.
Remove once permanent wlals and doors have been completed within the area.
Revisions Date
VHACINSchmiZ Typewritten Text Lamiflow device in barrier
T1.0T1.0
Waiting Room
C100AWaiting Area
C100
Pharmacy Consult
C157
Pharmacy Consult
C156 Corridor
C*1*23
Mgr. Med.
Surge Office
C153
Clerks
C152
PBS Open Work Area
C154
Patient Advocate
Office
C158
PBS Office
C155
Volunteer Services
C151
Waiting Room
C100A
Waiting
C147
Closet
C150
Vestibule
C144
1.12
1.13
1.141.14
1.11
T1.0
1.20
Common Path of Travel Max. Allowable = 100' Actual = 40'
Travel Distance to Exit Max. Allowable = 200' Actual = 74'
Common Path of Travel Max. Allowable = 100' Actual = 75'
Travel Distance to Exit Max. Allowable = 200' Actual = 199'
Min.
5' - 0"
1.18
1.18
1.23
1.22
1.20
1.13
1.18
1.11
Temporary Construction Barrier.
See Wall Type T1.0
Existing or work completed in previous phase
Area to be renovated in future phase
Area renovated during indicated phase
Ceiling work to be completed after hours during indicated phase
PHASING LEGEND
Waiting Area
C100 Clerks
C166
Info
C166A
Voluntary Service
C147
Common Path of Travel Max. Allowable = 100' Actual = 61'
Travel Distance to Exit Max. Allowable = 200' Actual = 146'
Common Path of Travel Max. Allowable = 100' Actual = 30'
Travel Distance to Exit Max. Allowable = 200' Actual = 46'
Vestibule
C144
PBS Open Work Area
C154 Clerks
C152
Waiting Room
C100A
Patient Advocate
Office
C158
PBS Office
C155
Volunteer Services
C151
1.13
T1.0 1.19
Mech.
C149
Corridor
C*1*4
Corridor
C*1*10
Corridor
C*1*24
1.21
1.201.20
Closet
C150
T1.0T1.0
1.13
T1.0
1.13
1.201.24
1.21
J O H N
A
P O E
IO
H O
F O
E T A T
S
R EG
IS
E T
R E D
R A
C H
TI
E
CT
3131 Newmark Drive, Suite 200 Miamisburg, Ohio 45342 |www.johnpoe.com| 937.461.3290
VA Project No.
JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
/2
/2
:3
:4
A
M
Correct Interior Deficiencies at Cincinnati
04/21/2021
PHASING PLAN
G112
CVKR
20004.00
539-21-115
Cincinnati VAMC
JASON REEVES - CHIEF ENGINEER
CONSTRUCTION
DOCUMENTS
Scale: 3/32" = 1'-0"3
PHASE 3 - FLOOR PLAN
GENERAL PHASING NOTES
A. For temporay partition locations see Demolition Plans. Temporary partitions are suggested locations. Coordinate final location in field with C.O.R.
B. Verify all conditions in the field prior to fabrication, erection and construction.
C. All asbestos containing material (ACM) must be abated per the direction of the C.O.R. and project specification 017419 and local state and federal regulations. Abatement if required is to be scheduled in appropriate sequence with demolition, new construction and project phasing.
D. Coordinate phase completion and start-up with requirements as set forth by the C.O.R. to maintain daily operations to near as normal as possible.
E. Coordinate location of job dumpster with the C.O.R. so as to disrupt daily operations as little as possible.
F. Coordinate access to all phases of construction, deliveries, and debris removal with the C.O.R. See General Requirements.
G. Temporary door locations and sizes are as required by the General Contractor. Doors will interfere with daily operations as little as possible. Confirm all locations with the C.O.R.
H. Existing HVAC, medical gases, sprinklers and water supply to be maintained throughout as required during each phase of construction.Coordinate phasing with Mechanical and Plumbing contractor. Support and protect all lines during each phase of construction. See MEP Drawings.
J. Provide and maintain negative air pressure at all construction.
Coordinate with HVAC contractor. See HVAC plans for temporary venting requirements and duct locations.
K. Phasing drawings to be used in conjunction with entire set of construction drawings.
L. Existing power must be maintained throughout as required during each phase of construction.Coordinate phasing with Electrical Contractor. Coordinate power turnover with requirements as dictated by the C.O.R. See Electrical Drawings.
M. Coordinate sequence construction with C.O.R. so that only one side of any corridor in use is obstructed at any one time.
N. Coordinate all operating work hours involving the generation of excessive noise with C.O.R. so as to minimize disturbances to patients. Activities to occur during this time include, but are not limited to saw cutting, jack hammering, hammer drilling and core drilling. If there is any question as to whether an operation should occur during this time the Contractor will contact the C.O.R.
P. All temporary walls to be wall type T1.0 unless otherwise noted.
Temporary wall removal to take place after standard operating hours.
Q. Night Work noted to take place after hours to be scheduled between 7:00 PM - 5:30 AM Monday-Friday, all day Saturday and Sunday.
R. Temporary construction wayfinding signs shall be provided and installed by VA. Locations to be coordinated with C.O.R.
NOTES
1.11 Work in corridors to be completed after hours. Contractor to provide dust separation for the construction area at the beginning of each shift. At the end of each shift Contractor to remove dust separation and clean work areas.
1.12 Maintain 5'-0: minimum around all temporary partitions.
1.13 Construct Temporary Partitions at the beginning of phase.
Remove once permanent wlals and doors have been completed within the area.
1.14 Temporary Pharmacy Consult rooms.
1.18 Ceiling work in corridors to be completed after hours.
Contractor to provide dust separation for the construction area at the beginning of each shift. At the end of each shift Contractor to remove dust separation and clean work areas.
1.19 Install new 3070 door in Temporary Partition for staff
access to the existing Info & Clerk Desks.
1.20 Existing wall partition to remain during this phase for
construction barrier.
1.21 Existing fire doors to remain during construction phase
until fire doors in new location have been installed.
1.22 Install information desk after temporary partitions have been removed in previous phase.
1.23 Complete installation of final quartz wall panels after
temporary partitions have been removed in previous phase.
1.24 Existing fire partition to remain during construction phase until new fire doors & partitions have been installed.
Scale: 3/32" = 1'-0"2
PHASE 2 - FLOOR PLAN
2.07
2.102.10
2.102.10
2.102.10
2.08
2.09
2.11
2.14
2.11
2.14
2.142.142.142.142.142.14
2.14
2.14
2.14
2.14
2.14
2.14
2.14
2.14
2.14
2.14
2.14
2.14
2.14
2.14
2.14
2.11
2.12
2.15
2.15
2.092.09
2.13
2.132.13
2.13
2.09
2.092.09
2.11
2.07
2.14
2.11
2.14
2.11
2.12 2.12 2.12 2.12 2.12 2.12
2.14
2.12 2.14
2.12
2.12
2.12
2.11
2.12
2.12 2.12
2.12
2.16
2.16 2.16
2.14
2.15
2.12
2.17
2.102.10
2.10
2.102.10
2.14
2.11
2.14
2.15
2.312.31
2.13
2.192.19
2.19
Dumpster Location
J O H N
A
P O E
IO
H O
F O
E T A T
S
R EG
IS
E T
R E D
R A
C H
TI
E
CT
3131 Newmark Drive, Suite 200 Miamisburg, Ohio 45342 |www.johnpoe.com| 937.461.3290
VA Project No.
JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
/2
/2
:3
:3
A
M
Correct Interior Deficiencies at Cincinnati
04/21/2021
DEMOLITION PLAN
AD111
CVKR
20004.00
539-21-115
Cincinnati VAMC
JASON REEVES - CHIEF ENGINEER
CONSTRUCTION
DOCUMENTS
GENERAL DEMOLITION NOTES
A. Remove all existing partitions shown with dashed line. Repair wall and floor finishes to match adjacent surfaces at areas of removal or scheduled new surfaces as required.
B. Remove all existing borrowed lights, doors and hollow metal frames where indicated with dashed line. Unused hardware shall be turned over to Owner. Box hardware before giving to Owner.
C. Remove wall-hung toilet room accessories and medical equipment as required and turn over to Owner.
D. See Plumbing, HVAC and Electrical Drawings for removal work associated with those trades.
E. Computer and communication cables and/or other wiring, piping, tubing, etc. serving other areas and functions located above ceiling or in walls of area to be remodeled shall be maintained during demolition/construction process. Coordinate any required changes to these systems with the C.O.R.
F. Repair existing walls to match adjacent undisturbed wall where cabinets, countertops, etc. are shown to be removed.
G. Prepare walls and floor slabs as required to receive new fininsh materials where existing finish is indicated to be removed.
H. Remove existing corner guards in areas to be remodeled.
J. Remove all abandoned cables and/or other wiring, piping, tubing, etc. serving other areas and functions located above the ceiling.
K. Remove existing grab bars, mirrors, soap & towel dispensers and all other wall mounted toilet room accessories. Removed items shall be turned over to Owner.
L. Remove all whiteboards, shelving, cabinets and support brackets mounted to walls. Removed items shall be turned over to Owner.
M. Remove all systems furniture. Removed items shall be turned over to Owner.
N. Remove all signage and artwork in corridors. Removed items shall be turned over to Owner.
P. Remove all wall protection and handrails in areas to be remodeled.
Q. Coordinate demolition with project phasing.
R. Any removed electronic devices, including but not limited to, wireless access points, PA speakers, checkpoint sensors, checkpoint repeaters and checkpoint modems shall be turned over to Owner.
S. Use of the dumpster locations requires coordination with the COR and other ongoing construction projects.
N Scale: 1/8" = 1'-0"
First Floor Demolition Plan
NOTES
2.07 Remove casework.
2.08 Remove dumbwaiter.
2.09 Remove bulkhead.
2.10 Remove windows.
2.11 Remove Porcelain tile flooring and base.
2.12 Remove resilient flooring and base.
2.13 Remove gypsum cove ceiling and light fixture.
2.14 Remove acoustical ceiling tiles and grid.
2.15 Remove Terrazzo flooring and base.
2.16 Remove carpet and base.
2.17 Remove drinking fountain and salvage to be reinstalled.
2.19 Remove abandoned Real Time Locating System
electronic devices.
2.31 Remove sliding vestibule doors.
N.T.S.Scale:
First Floor Key Plan
A
SB010C
Areaway
SB10
2.06
J O H N
A
P O E
IO
H O
F O
E T A T
S
R EG
IS
E T
R E D
R A
C H
TI
E
CT
3131 Newmark Drive, Suite 200 Miamisburg, Ohio 45342 |www.johnpoe.com| 937.461.3290
VA Project No.
JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
/2
/2
:3
:5
A
M
Correct Interior Deficiencies at Cincinnati
04/21/2021
SUB-BASEMENT NOTE PLAN
A001
CVKR
20004.00
539-21-115
Cincinnati VAMC
JASON REEVES - CHIEF ENGINEER
CONSTRUCTION
DOCUMENTS
N Scale: 1/32" = 1'-0"
Sub-Basement Floor Plan N
Scale: 1/8" = 1'-0"A Sub-Basement Note Plan - Area A
GENERAL NOTES
A. All dimensions are taken to face of gypsum wallboard or unit masonry.
B. Edge of all door jambs at hinge side not otherwise indicated are to be 6" from the face of intersecting walls. Edge of all door jambs at strike side not otherwise located are to be 18" minimum from the face of intersecting walls.
C. All wood blocking to be fire retardent treated.
D. All partitions shall be type 'S1.0' unless noted otherwise.
E. Provide level 5 finish on all new exposed, public-facing, gypsum board walls.
NOTES
2.06 Remove existing door & frame. Prep existing opening as
required for installation of new door & frame. See Door Schedule.
A
B
C
D
Mechanical Room
C015
+/- 14' - 4"
S6.1
S6.0
S6.0
Supply Warehouse
A001
A001
2.06
Transformer Room
B013B
B013B 2.06
Mechanical Room
C015
7.757.75
7.747.747.74
7.75
7.75
7.747.74
C-B-13
C-B-2
Corridor
C*B*13
2.06
2.06
J O H N
A
P O E
IO
H O
F O
E T A T
S
R EG
IS
E T
R E D
R A
C H
TI
E
CT
3131 Newmark Drive, Suite 200 Miamisburg, Ohio 45342 |www.johnpoe.com| 937.461.3290
VA Project No.
JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
/2
/2
:3
:0
A
M
Correct Interior Deficiencies at Cincinnati
04/21/2021
BASEMENT NOTE PLAN
A002
CVKR
20004.00
539-21-115
Cincinnati VAMC
JASON REEVES - CHIEF ENGINEER
CONSTRUCTION
DOCUMENTS
N Scale: 1/32" = 1'-0"
Basement Floor Plan N
Scale: 1/8" = 1'-0"A1 Basement Dimension Plan - Area A
N Scale: 1/8" = 1'-0"B Basement Plan - Area B
N Scale: 1/8" = 1'-0"C Basement Plan - Area C
N Scale: 1/8" = 1'-0"A2 Basement Note Plan - Area A
N Scale: 1/8" = 1'-0"D Basement Plan - Area D
GENERAL NOTES
A. All dimensions are taken to face of gypsum wallboard or unit masonry.
B. Edge of all door jambs at hinge side not otherwise indicated are to be 6" from the face of intersecting walls. Edge of all door jambs at strike side not otherwise located are to be 18" minimum from the face of intersecting walls.
C. All wood blocking to be fire retardent treated.
D. All partitions shall be type 'S1.0' unless noted otherwise.
E. Provide level 5 finish on all new exposed, public-facing, gypsum board walls.
NOTES
2.06 Remove existing door & frame. Prep existing opening as
required for installation of new door & frame. See Door Schedule.
7.74 Install fire stopping between top of wall and underside fo metal decking. Continuous fire rated sealant all joints and penetrations in walls.
7.75 Continuous fire rated sealant along all joints between new gyp. bd. and existinng CMU wall.
C B
A
D
REFER TO DWG.
SHEET A111-N
Corridor
C*1*6 C-1-6
Corridor
C*1*8 C-1-8
C-1-10
Corridor
C*1*10
2.06
2.06
2.06
Service Lobby
A126
Dry Storage
A127A
A127A
A126
Clean Supply
A1022
SPS Storage
A1023
Volunteer Storage
A1036
Volunteer Lounge
A1035
Volunteer Serviecs
A1037
A1022 A1023
A1035
A1036
A1037
A1002
Dialysis Waiting
A1002
2.06
2.06
2.062.06
2.06
2.06
2.062.06
8.19
8.19
Corridor
C*1*7 C-1-7
2.06 8.19
8.19
J O H N
A
P O E
IO
H O
F O
E T A T
S
R EG
IS
E T
R E D
R A
C H
TI
E
CT
3131 Newmark Drive, Suite 200 Miamisburg, Ohio 45342 |www.johnpoe.com| 937.461.3290
VA Project No.
JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
/2
/2
:3
:3
A
M
Correct Interior Deficiencies at Cincinnati
04/21/2021
FIRST FLOOR NOTE PLAN
A101
CV-
20004.00
539-21-115
Cincinnati VAMC
JASON REEVES - CHIEF ENGINEER
CONSTRUCTION
DOCUMENTS
N Scale: 1/32" = 1'-0"
First Floor Plan
N Scale: 1/8" = 1'-0"B First Floor Note Plan - Area B
N Scale: 1/8" = 1'-0"D First Floor Note Plan - Area C
N Scale: 1/8" = 1'-0"C First Floor Note Plan - Area D
GENERAL NOTES
A. All dimensions are taken to face of gypsum wallboard or unit masonry.
B. Edge of all door jambs at hinge side not otherwise indicated are to be 6" from the face of intersecting walls. Edge of all door jambs at strike side not otherwise located are to be 18" minimum from the face of intersecting walls.
C. All wood blocking to be fire retardent treated.
D. All partitions shall be type 'S1.0' unless noted otherwise.
E. Provide level 5 finish on all new exposed, public-facing, gypsum board walls.
Revisions Date
NOTES
2.06 Remove existing door & frame. Prep existing opening as
required for installation of new door & frame. See Door Schedule.
8.19 Wave to open, touchless door activation sensor.
Coordinate exact locations with COR.
A
Gas Storage
C2029
Soil
C2037
C2037 C2029
2.06 2.06
J O H N
A
P O E
IO
H O
F O
E T A T
S
R EG
IS
E T
R E D
R A
C H
TI
E
CT
3131 Newmark Drive, Suite 200 Miamisburg, Ohio 45342 |www.johnpoe.com| 937.461.3290
VA Project No.
JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
/2
/2
:3
:4
A
M
Correct Interior Deficiencies at Cincinnati
04/21/2021
SECOND FLOOR PLAN
A102
CVKR
20004.00
539-21-115
Cincinnati VAMC
JASON REEVES - CHIEF ENGINEER
CONSTRUCTION
DOCUMENTS
N Scale: 1/32" = 1'-0"
Second Floor Plan N
Scale: 1/8" = 1'-0"A Second Floor Plan - Area A
GENERAL NOTES
A. All dimensions are taken to face of gypsum wallboard or unit masonry.
B. Edge of all door jambs at hinge side not otherwise indicated are to be 6" from the face of intersecting walls. Edge of all door jambs at strike side not otherwise located are to be 18" minimum from the face of intersecting walls.
C. All wood blocking to be fire retardent treated.
D. All partitions shall be type 'S1.0' unless noted otherwise.
E. Provide level 5 finish on all new exposed, public-facing, gypsum board walls.
Revisions Date
NOTES
2.06 Remove existing door & frame. Prep existing opening as
required for installation of new door & frame. See Door Schedule.
FD
UP
UP
UP
UP
UP
UP
A
B
C
C3034
C-3-11
Corridor
C*3*11
SPD Case Cart
C034
2.20
2.20
Corridor
C*3*3 C-3-3
2.06
C-3-12.06
Corridor
C*3*1
J O H N
A
P O E
IO
H O
F O
E T A T
S
R EG
IS
E T
R E D
R A
C H
TI
E
CT
3131 Newmark Drive, Suite 200 Miamisburg, Ohio 45342 |www.johnpoe.com| 937.461.3290
VA Project No.
JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
/2
/2
:3
:0
A
M
Correct Interior Deficiencies at Cincinnati
04/21/2021
THIRD FLOOR NOTE PLAN
A103
CVKR
20004.00
539-21-115
Cincinnati VAMC
JASON REEVES - CHIEF ENGINEER
CONSTRUCTION
DOCUMENTS
N Scale: 1/32" = 1'-0"1 Third Floor Plan
N Scale: 1/8" = 1'-0"A Third Floor Plan - Area A
N Scale: 1/8" = 1'-0"B Third Floor Plan - Area B
N Scale: 1/8" = 1'-0"C Third Floor Plan - Area C
GENERAL NOTES
A. All dimensions are taken to face of gypsum wallboard or unit masonry.
B. Edge of all door jambs at hinge side not otherwise indicated are to be 6" from the face of intersecting walls. Edge of all door jambs at strike side not otherwise located are to be 18" minimum from the face of intersecting walls.
C. All wood blocking to be fire retardent treated.
D. All partitions shall be type 'S1.0' unless noted otherwise.
E. Provide level 5 finish on all new exposed, public-facing, gypsum board walls.
Revisions Date
NOTES
2.06 Remove existing door & frame. Prep existing opening as
required for installation of new door & frame. See Door Schedule.
2.20 Existing door & frame to remain. Add or replace door
hardware per Door Schedule.
Pharmacy Consult
C157
PBS Office
C155
Patient Advocate
Office
C158 PBS Open Work Area
C154
Mgr. Med.
Surge Office
C153
Volunteer Services
C151
Clerks
C152
Pharmacy Consult
C156
2' - 0 7/8"
10' - 2 1/2"
10' - 2 1/2"
R
' - 6
/4
3' - 6" 20' - 4 3/8"
10' - 6 5/8" 37' - 9 3/8"
/8
/8
/8
/8
9' - 6 7/8"
9' - 2 1/2" 9' - 2 1/2"
Corridor
C*1*23
Waiting Room
C100A
Waiting
C147
Corridor
C*1*24
Vestibule
C144
Corridor
C*1*10
Align
/2
14' - 2 3/8"
/8
+/- 3'-4"
S2.4
Align
Align
Waiting Area
C100
26' - 3"
S2.0
S2.0
S2.0
.1
7°
S2.4
S2.0
Align
S2.4
Corridor
C*1*13
3' - 2" 3' - 6 7/8"
B
8' - 2"
Closet
C150
S2.0
' - 0
Corridor
C*1*4
Corridor
C*1*4
3' - 8"
3' - 8"
S2.0
S3.1S3.1
S3.1
B
A
A
A
A
B
3' - 9"
3' - 9"
S5.1
S5.0
S5.1 Mech.
C149
S1.0-F
S7.0-F
S5.1
S5.1
S5.1
S5.1
4' - 0" 2' - 1"
1' - 10"
1'
4' - 0"
' - 0
' - 2
4' - 3"
20' - 0"
S2.0
S2.0
.3
6°
.3
6°
10.36°
10.36°
/8
22' - 5 3/4"
.2
° S1.4S1.4
/2
S1.4
S1.4
R
' - 6
J O H N
A
P O E
IO
H O
F O
E T A T
S
R EG
IS
E T
R E D
R A
C H
TI
E
CT
3131 Newmark Drive, Suite 200 Miamisburg, Ohio 45342 |www.johnpoe.com| 937.461.3290
VA Project No.
JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
/2
/2
:3
:2
A
M
Correct Interior Deficiencies at Cincinnati
04/21/2021
LOBBY DIMENSION PLAN
A111-D
CVKR
20004.00
539-21-115
Cincinnati VAMC
JASON REEVES - CHIEF ENGINEER
CONSTRUCTION
DOCUMENTS
N Scale: 1/8" = 1'-0"
Lobby Dimension Plan N.T.S.Scale:
First Floor Key Plan
GENERAL NOTES
A. All dimensions are taken to face of gypsum wallboard or unit masonry.
B. Edge of all door jambs at hinge side not otherwise indicated are to be 6" from the face of intersecting walls. Edge of all door jambs at strike side not otherwise located are to be 18" minimum from the face of intersecting walls.
C. All wood blocking to be fire retardent treated.
D. All partitions shall be type 'S1.0' unless noted otherwise.
E. Provide level 5 finish on all new exposed, public-facing, gypsum board walls.
A401
Corridor
C*1*23
Volunteer Services
C151
PBS Open Work Area
C154
Mgr. Med.
Surge Office
C153
Pharmacy Consult
C157
PBS Office
C155
Patient Advocate
Office
C158
Waiting Area
C100
Corridor
C*1*24
Waiting
C147
Vestibule
C144 Waiting Room
C100A
Closet
C150
Corridor
C*1*10
Corridor
C*1*13
A401
A
A511
A401
A401
A401
A401
A401
A401
A
A601
C
Pharmacy Consult
C156
C156C157
C155
C154
C158
C-1-23
C153
A
A401
5A
A401
A401
A502
A
12.01 12.01
12.01 Clerks
C152
C150
IF103
A111-N
A
A
Opp.
22.07
6.216.21 6.21
6.21
3.06
PBS
Elegibility
PBS
Elegibility
CPAC
Biling
PBS
ROI
C-1-10
Mech.
C149
C151 C149
C-1-4
C-1-24
Corridor
C*1*4
Corridor
C*1*4
C144A
C144B
A111-N
A511
A401
A511
Sim
A511
A111-N
E x is ti n g F lo o r O p e n in g
F ie ld V e ri fy
Existing Floor Opening
Field Verify
3.18
2.18
3.20
2.02
5.28
5.29
Embed Typ.
8"
Overlap Typ.
1' - 4"
5.29
5.28
Embed Typ.
8" Field Verify
2.02
5.20
3.20
5.29
3.18
5.30
5.28
Overlap Typ.
1' - 4"
/2
3' - 8" fo r n ew w o rk
A s
R eq
'd
S7.0-F
S1.0
S1.0-S
S2.0
S7.0-F
EG-1
7.80
2.41
2.02
8.08
2.03
9.23
7.80
9.239.23
9.23
J O H N
A
P O E
IO
H O
F O
E T A T
S
R EG
IS
E T
R E D
R A
C H
TI
E
CT
3131 Newmark Drive, Suite 200 Miamisburg, Ohio 45342 |www.johnpoe.com| 937.461.3290
VA Project No.
JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
/2
/2
:3
:4
A
M
Correct Interior Deficiencies at Cincinnati
04/21/2021
LOBBY NOTE PLAN
A111-N
CVKR
20004.00
539-21-115
Cincinnati VAMC
JASON REEVES - CHIEF ENGINEER
CONSTRUCTION
DOCUMENTS
NOTES
GENERAL NOTES
A. All dimensions are taken to face of gypsum wallboard or unit masonry.
B. Edge of all door jambs at hinge side not otherwise indicated are to be 6" from the face of intersecting walls. Edge of all door jambs at strike side not otherwise located are to be 18" minimum from the face of intersecting walls.
C. All wood blocking to be fire retardent treated.
D. All partitions shall be type 'S1.0' unless noted otherwise.
E. Provide level 5 finish on all new exposed, public-facing, gypsum board walls.
2.02 Existing structure to remain.
2.03 Existing wall to remain.
2.18 Existing floor opening in structure.
2.41 Existing 2 hour rated fire barrier wall assembly to remain.
3.06 New concrete slab infill in existing floor opening.
3.18 New concrete slab, match existing slab thickness and
composite metal decking to preserve fire rating.
3.20 Dowel #4 rebar into existing structure @ 16" o.c. with 8" minimum embedment with Sikadur Hi-Mod Gel.
5.20 Composite metal form deck.
5.28 C6x8.2 steel channel attached with L3x3x1/4, 3 1/2" long 3/16 fillet welds.
5.29 C6x8.2 steel channel attached to existing framing with
L3x3x1/4, 3 1/2" long 3/16 fillet welds.
5.30 Weld composite metal deck to C6x8.2 steel channels at
12" oc.
6.21 Casework. See Interior Elevations.
7.80 Continuous fire-rated sealant @ rated walls each side.
8.08 Double egress hollow metal frame.
9.23 2 1/2" metal J-runner shaft-wall framing.
12.01 Manual roller window shade, WT-1.
22.07 Reinstall existing salvaged drinking fountain.
Scale: 1/8" = 1'-0"A Lobby Note Plan
N.T.S.Scale:
First Floor Key Plan - Note
Scale: 3/4" = 1'-0"1 Floor Slab Infill Detail
Scale: 1 1/2" = 1'-0"2 Floor Slab Infill Section
FLOOR SLAB INFILL GENERAL NOTES
A. Verify all conditions prior to floor slab infill construction.
B. Infill concrete slab to reach f'c of 4,000 psi in 28 days.
C. NW = Normal weight concrete (145 pcf).
D. All reinforcing steel to be new billet steel, conforming to ASTM A-615, Grade 60.
Scale: 1 1/2" = 1'-0"3 Fire Door Plan Detail
8'-2"
8'-4"
8'-0"
8'-0"
7'-10"
8'-0"
8'-0"
8'-0"
8'-0"
8'-0"
8'-0"
8'-0"
8'-0"
8'-0"
7'-11"
8'-0"
A121
IF103
C100
C*1*24
C147
C144
C100A
C*1*23
C151
C154
C153
C157
C155
C158
C152
C150
C*1*10
C*1*13
C156
C*1*10
7'-10" ACT-1
P-7
ACT-2
ACT-2
ACT-2
8'-0"
P-5
7'-4"
ACT-1
ACT-1
ACT-1ACT-1
ACT-2
ACT-1
ACT-1
ACT-1
ACT-1
ACT-2
ACT-2
ACT-2
P-1
P-6
7'-10"
P-7
7'-10"
ACT-2
P-1
P-1
7'-9"
7'-9"
7'-9"
A121
A121
A121
A121
A121
A121
A121
A121
A121
A121
A121
A121
EQ EQ
3' - 3 3/4"
/4
EQ EQ
Align
/8
Align
ACT-2
7'-11"
26.0226.0226.0226.02
5' - 3 1/4"
12' - 4"
R
2'
/8
R
/8
R 20' - 4 1/4"
/4
19' - 11"
1' - 1 1/2"
12' - 1 1/4"
/2
R
' - 6
9' - 6 1/2"
/2
R 45' - 5"
R
8'
7'-11"
9.04
9.04
9.04
9.04
9.04
9.04
12.02
12.02
A121
A121
C*1*4
REFLECTED CEILING PLAN LEGEND
Recessed Downlight Fixture
Supply Air Diffuser
Return Air Grille
2' x 2' Light Fixture
2' x 2' Acoustical
Tile Ceiling
Gypsum Board
Surface-mounted Light Fixture
Access Panel
Recessed Wall-wash Fixture
Recessed Linear Light Fixture
ACT-1
8'-0" A.F.F.2 5/8"
/2
/8
26.01
AG-1
9.41
3 3/8"
/2
9.46
Gypsum
Height Varies. Refer to R.C.P.
ACT-1
Height varies. Refer to R.C.P.
9.219.21
9.52
9.41
5.065.06
Gypsum
Height varies. Refer to R.C.P.
Gypsum
Height varies. Refer to R.C.P.
9.219.21
9.21
5.065.065.06
9.219.21
9.41
9.52
5.065.06
Gypsum (P-5)
8'-2" A.F.F.
ACT-1
8'-0" A.F.F.
26.01
4 1/4"
ACT-1
7'-10" A.F.F.
ACT-1
Height varies. Refer to R.C.P.
9.41
9.219.21
9.52
5.06
8.63
9.21
AG-2
WT-2
12.02
J O H N
A
P O E
IO
H O
F O
E T A T
S
R EG
IS
E T
R E D
R A
C H
TI
E
CT
3131 Newmark Drive, Suite 200 Miamisburg, Ohio 45342 |www.johnpoe.com| 937.461.3290
VA Project No.
JPA Project No.
Project Number
Building Number
Drawing Number
Project Title
Location
Issue Date Checked Drawn
Drawing Title
Approved:
VA FORM 08 - 6231
A
FULLY SPRINKLERED
U.S. Department of Veterans Affairs
B
C
D
E
F
A
B
C
D
E
F
21 4 5 6 7 8 9 10
Phase
ARCHITECT/ENGINEER OF RECORD STAMPCONSULTANT
321 4 5 6 7 8 9 10
Office of Construction and Facilities Management
/2
/2
:3
:0
A
M
Correct Interior Deficiencies at Cincinnati
04/21/2021
LOBBY REFLECTED CEILING PLAN
A121
MWKR
20004.00
539-21-115
Cincinnati VAMC
JASON REEVES - CHIEF ENGINEER
CONSTRUCTION
DOCUMENTS
N Scale: 1/8" = 1'-0"
REFLECTED CEILING PLAN
GENERAL NOTES
A. All wood blocking shall be fire retardant. Refer to life and safety plans for specific location of rated floor/ceiling assemblies.
B. Light fixtures, sprinkler heads, speakers, and HVAC devices shall be located as close as possible to the center of acoustical ceiling panels. Confirm any deviation from this with the Project Engineer.
C. See P, M, E and FP drawings for additional information regarding final information and quantites of fixtures/devices to be installed in ceiling.
D. See Electrical Drawings for lighting specifications.
E. See specifications for additional information about ceiling systems.
F. Ceiling and soffit heights are noted from their respective floor elevations.
G. Bulkheads shall be diagonally braced to floor deck with metal studs at 4'-0" O.C. minimum.
H. Patch and repair ceilings damaged during demolition and new construction that are to remain.
I. Provide level 5 finish on all new gypsum board ceilings.
J. Coordinate Fire Protection and Technology device locations with general trades. Do not penetrate ceiling without prior approval from Architect.
NOTES
5.06 3-5/8" cold formed metal framing @ 16" O.C. See Structural Drawings.
8.63 Decorative laminated glass.
9.04 Gypsum board control joint.
9.21 5/8"…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .