This is a combined synopsis/solicitation for dockside repairs to the CGC NEAH BAY. The solicitation seeks bids for work items including cleaning and inspecting fuel, potable water, ballast and waste tanks; cleaning ventilation ducts; inspecting and testing circuit breakers and generators; and other repair and maintenance tasks. Responses are due by August 15, 2023, with the period of performance scheduled from October 2023 to March 2024. The solicitation is set aside for small businesses and issued by the US Coast Guard to maintain one of its vessels.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USCGC NEAH BAY (WTGB 105)

SPECIFICATION FOR DOCKSIDE REPAIRS

FY2023

Developed By: Johnny B Thomas

(Revision-0, 17 Oct 2022)

USCGC NEAH BAY (WTGB-140) DOCKSIDE AVAILABILITY FY2022

ii (Rev-0)

TABLE OF CONTENTS

Revisions Record ......................................................................................................................................... iii Consolidated List of References ................................................................................................................... iv Consolidated List of Government-furnished Property .............................................................................. viii Consolidated List of Critical Inspection Items ............................................................................................. ix Principal Characteristics - Tug, IceBreaking ................................................................................................. x General Requirements WORK ITEM 1: Tanks, MP Fuel Service, Clean and Inspect WORK ITEM 2: Tanks, Potable Water, Clean and Inspect WORK ITEM 3: Tanks, Ballast, Clean and Inspect WORK ITEM 4: Voids, Accessible, Clean and Inspect WORK ITEM 5: Tanks, Dirty Oil and Waste, Clean and Inspect WORK ITEM 6: Ship Service Diesel Generator (SSDG) Exhaust Piping, Commercial Clean WORK ITEM 7: Boiler Exhaust Stack Uptakes, Commercial Clean WORK ITEM 8: Bubbler Diesel Engine Exhaust Piping, Commercial Clean WORK ITEM 9: Circuit Breakers (60 Hz), Inspect and Test WORK ITEM 10: Vent Ducts, Engine And Motor Room, All, Commercial Cleaning WORK ITEM 11: Vent Ducts, Galley and Pantry Room, All, Commercial Cleaning WORK ITEM 12: Vent Ducts, Laundry Exhaust, Commercial Cleaning WORK ITEM 13: Vent Ducts, All Other, Commercial Cleaning WORK ITEM 14: Compressed Air Receivers and System Valves, All, Clean, Inspect, Hydro and Lift ... 51 WORK ITEM 15: Anchor Windlass, Inspect and Service WORK ITEM 16: Anchor Chains and Ground Tackle, Inspect and Repair WORK ITEM 17: Vertical Capstan, Inspect and Service WORK ITEM 18: Hull Fittings (Mooring and Towing), Inspect and Test - Tender WORK ITEM 19: Grey Water Holding Tanks, Clean and Inspect

WORK ITEM 20: Sewage Holding Tanks, Clean and Inspect WORK ITEM 21: Grey Water Piping, Clean and Flush WORK ITEM 22: Sewage Piping, Clean and Flush WORK ITEM 23: Accessible Voids, Preserve, 100 Percent WORK ITEM 24: Deck Covering, Interior, Wet and Dry, Renew WORK ITEM 25: Watertight Doors and Scuttles, External, Renew WORK ITEM 26: Galley Piping, Renewal WORK ITEM 27: Grey Water Valves, Renew WORK ITEM 28: Both Main Diesel and Generator Resilient Mounts, Renewal WORK ITEM 29: Watertight Door Hinges, Repair……………………………………………………..125

WORK ITEM 30: WTGB Magnetic Compass Replacement……………………………………………128

WORK ITEM 31: Boat Cleat Install………………………..……………………………………………134

WORK ITEM 32: Stubmast Repair……………………………...………………………………………137

WORK ITEM 33: Seal Water Piping Renew………………………...………………………………….140

WORK ITEM 34: Fuel System Valve Overhaul.....……………………………………………………..145

WORK ITEM 35: Lead-Based Paint, 100% Abatement ………………………………………………..150

WORK ITEM 36: Engine Room Vestibule, Insulation, Renew ………………………………………..156

WORK ITEM 37: Tanks, Ballast, Preserve, Partial…... ………………………………………………..157

WORK ITEM 38: Tanks, Potable Water, Preserve, Partial…….………………………………………..160 iii (Rev--0)

REVISIONS RECORD

This page is used to record specification revisions, which may have occurred subsequent to a Revision 0 (Rev-0) package. Information listed is intended to provide contractors and field unit personnel a means to ensure all the current specification revision pages are present when reviewing or utilizing this specification package.

DATE REV# WORK

ITEM#

CHANGES MADE

NOTE : All work item and paragraph numbers listed above for a given revision correspond to same numbers in the previous revision. This revised specification is self-contained with all of the above listed changes incorporated.

iv (Rev-0)

CONSOLIDATED LIST OF REFERENCES

The below-listed documents form a part of this specification to the extent specified herein. Approval/publication dates or revision dates/numbers are also identified, to ensure that same document versions are used at the time of specification writing and during contract execution.

All Coast guard drawings, technical publications, and standard specifications will be provided to contractors by the Coast Guard at an appropriate time, or upon request, free of charge. Other Government documents may be accessed – free of charge – from links located on the SFLC website. Commercial sites provide access to their respective documents.

COAST GUARD DRAWINGS

Coast Guard Bill of Materials 627 WMEC 327, Rev G, Watertight Doors, Hatches & Scuttles

Coast Guard Drawing 140 WTGB 171-001, Rev -, Fore Mast

Coast Guard Drawing 140 WTGB 116-001, Rev -, Longitudinal Framing and Side Girder

Coast Guard Drawing 140 WTGB 117-001, Rev -, Transverse Frames

Coast Guard Drawing 140 WTGB 120-001, Rev -, Structural Bulkheads

Coast Guard Drawing 140 WTGB 149-001, Rev -, Tank Tops and Flats

Coast Guard Drawing 140 WTGB 150-002, Rev -, Deckhouse Plating and Framing

Coast Guard Drawing 140-WTGB-167-001, Rev -, Closures & Window List

Coast Guard Drawing 140 WTGB 182-002, Rev -, Foundations, Engine Room & Strainer Compartment

FDN Motor Room 4-61-0-E

Coast Guard Drawing 140 WTGB 201-001, Rev B, Machinery Arrangement

Coast Guard Drawing 140 WTGB 233-001, Rev -, Sway Brace, Propulsion Diesel

Coast Guard Drawing 140 WTGB 259-001, Rev -, Diesel Exhaust Systems, Arrangements & Details

Coast Guard Drawing 140 WTGB 259-002, Rev B, Exhaust Modifications to Suit Bubbler Installation

Coast Guard Drawing 140 WTGB-320-001, Rev -, Power System One-Line Wiring Diagram

Coast Guard Drawing 140 WTGB 401-001, Pilothouse Arrangement

Coast Guard Drawing 140 WTGB 426-001, Gyrocompass Ripout/Instl, Arr, Wiring & Details

Coast Guard Drawing 140 WTGB 426-002, Gyrocompass Wiring Data (COED)

Coast Guard drawing 140 WTGB 506-002, Rev-, Vent and Sounding System A&D

Coast Guard drawing 140 WTGB 506-003, Rev-, Vent and Sounding System Diagram

Coast Guard Drawing 140 WTGB 514-002, Rev-, Ventilation & A/C Arrangements & Details

Coast Guard Drawing 140 WTGB 528-002, Rev-, Sanitary & Deck Drain System

Coast Guard Drawing 140 WTGB 528-003, Rev C, Sanitary & Deck Drain A&D

Coast Guard Drawing 140 WTGB 528-004, Rev -, Grey Water Mods & Tank Transition

Coast Guard Drawing 140 WTGB 533-002, Rev -, Potable Water System A & D

Coast Guard Drawing 140 WTGB 533-003, Rev A, Potable Water System Diagram

Coast Guard Drawing 140 WTGB 541-001, Rev-, Diagram-fuel oil fill and transfer system

Coast Guard Drawing 140 WTGB 541-002, Rev B, Fuel Oil Transfer System, Filter / Coalescer

Replacement v (Rev-0)

Coast Guard drawing 140 WTGB-541-003, Rev-, Fuel Oil Transfer Sys, A&D

Coast Guard Drawing 140 WTGB 541-004, Rev-D, Fue Oil Mods to Suit Davit Install

Coast Guard Drawing 140 WTGB 541-005, Rev C, Fuel Oil Mods to Suit 4-38-0-F Tank

Coast Guard Drawing 140 WTGB 551-001, Rev -, Compressed Air System Diagram

Coast Guard Drawing 140 WTGB 561-001, Steering System Control, Alarms & Autopilot

Coast Guard Drawing 140 WTGB 581-001, Rev-, Anchor Handling A & D

Coast Guard Drawing 140 WTGB 583-002, Rev E, Boat Handling Arr Incid to Vestdavit Install

Coast Guard Drawing 101 WTGB 583-004, Rev F, New Boat/Cargo Boxn & Fdn Dets

Coast Guard Drawing 101 WTGB 583-007, Rev -, Boat/Cargo Boom Control Console

Coast Guard Drawing 140 WTGB 801-003, Rev B, Booklet of General Plans

Coast Guard Drawing 140 WTGB 801-005, General Arrangement Main Deck & Above

Coast Guard Bill of Materials 627 WMEC 327, Rev G, Watertight Doors, Hatches & Scuttles

Coast Guard Drawing FL 3801-67, Rev B, Sheets 1 through 10 of 50 (General Notes – Ductwork) and

Sheet 39 (Handholes for W.T. and N.W.T. Ducts)

COAST GUARD PUBLICATIONS

Coast Guard Bill of Materials 627 WMEC 327, Rev G, Watertight Doors, Hatches & Scuttles

Coast Guard Commandant Instruction (COMDTINST) M10360.3, Jun 2006, Coatings and Colors

Manual

Coast Guard Technical Publication (TP) 10000, May 2015, Manufacturer's Instruction Book - SWBS

Group(s) 583, Single Point Davit, – Model PLA-2000

Coast Guard Technical Publication (TP) 3366, Section 583-A, Dec 2005, Boat Davit Hydraulic System

Coast Guard Technical Publication (TP) 3456, 2001, Ship Information Book, Section B

Coast Guard Technical Publication (TP) 3478, Dec 2020, Manufacturer's Instruction Book-SWBS

Group(s) 324

Coast Guard Technical Publication (TP) 3483, Feb 2012, SWBS Groups 580-583, Anchor Windlass

Coast Guard Technical Publication (TP) 3483, SWBS Groups 580-583, Feb 2012, Vertical Capstan

Coast Guard Technical Publication (TP) 4674A, AutoPilot – Pilotstar D – Type AP02-S01

Coast Guard Technical Publication (TP) E-423-029, Integrated & Fluxgate Heading Sensors - Model PG-

500 & C-500 - Operator's Manual

Coast Guard Technical Publication (TP) 6451 Remote Display Unit- Model RD-33

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General

Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and

Allied Processes

Surface Forces Logistics Center Standard Specification 3020 (SFLC Std Spec 3020), 2020, Overhaul AC

Electrical Motors

Surface Forces Logistics Center Standard Specification 3041 (SFLC Std Spec 3041), 2020, Shipboard

Electrical Cable Test

Surface Forces Logistics Center Standard Specification 3042 (SFLC Std Spec 3042), 2020, Shipboard

Electrical Cable Removal, Relocation, Splice, Repair, And Installation

Surface Forces Logistics Center Standard Specification 5000 (SFLC Std Spec 5000), 2020, Auxiliary

Machine Systems vi (Rev-0)

Surface Forces Logistics Center Standard Specification 5100 (SFLC Std Spec 5100), 2020, Clean

Shipboard Ventilation Systems

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures

Surface Forces Logistics Center Standard Specification 6341 (SFLC Std Spec 6341), 2020, Install Interior

Deck Covering Systems

Surface Forces Logistics Center Standard Specification 8636 (SFLC Std Spec 8636), 2020, Temporary

Hull Accesses

OTHER REFERENCES

American Bureau of Shipping (ABS) Approved Chain, Accessory and Bar Manufacturing Facilities List, Oct 2016

American National Standards Institute/American Water Works Association (ANSI/AWWA) C652, 2019, Disinfection of Water-Storage Facilities

American National Standards Institute/NSF International (ANSI/NSF) 61, 2015, Drinking Water System

Components - Health Effects

American Society for Testing and Materials (ASTM) International F683, 2014, Standard Practice for

Selection and Application of Thermal Insulation for Piping and Machinery

American Society for Testing and Materials (ASTM) International F992, 2011, Standard Specification for

Valve Label Plates

American Society for Testing and Materials (ASTM) International A53, 2005, Standard Specification for

Pipe, Steel, Black and Hot-Dipped , Zinc-coated Welded and Seamless

American Society for Testing and Materials (ASTM) International F1508, 2016, Standard Specification for Angle Style, Pressure Relief Valves for Steam, Gas, and Liquid Services

American Society for Testing and Materials (ASTM) International D1330, 2015, Standard Specification for Rubber Sheet Gaskets

American Society of Mechanical Engineers (ASME) B16.34, 2017, Valves-Flanged, Threaded, and

Welding End

Code of Federal Regulations (CFR) Title 29, Part 1915, 2014, Occupational Safety and Health Standards for Shipyard Employment

Commercial Item Description (CID) A-A-59316, 2016, Abrasive Materials; for Blasting

Department of Defense Standard Practice (MIL-STD-2003-3A), 2009, Electric Plant Installation Standard

Methods for Surface Ships and Submarines

Department of Defense Standard Practice (MIL-STD-1310H), 2009, Shipboard Bonding, Grounding, and other Techniques for Electromagnetic Compatibility, Electromagnetic Pulse (EMP) Mitigation, and

Safety

Federal Specification (Fed Spec) QQ-N-281, Oct 1985, Nickel-Copper Alloy Bar, Rod, Plate, Sheet, Strip, Wire, Forgings, and Structural and Special Shaped Sections

Federal Specification (Fed Spec) RR-C-271, Rev E, Mar 2016, Chains and Attachments, Carbon and

Alloy Steel

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS), SP-58, 2009, Pipe

Hangers and Supports – Materials, Design, Manufacture, Selection, Application and Installation

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-61, 2019 Edition, Pressure Testing Of Steel Valves

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-67, 2017 Edition, Butterfly Valves vii (Rev-0)

Manufacturers Standardization Society of the Valve and Fittings Industry (MSS) SP-72, 2010 Edition, Ball Valves with Flanged or Butt-Welding Ends for General Service

Manufacturers' Standardization Society of the Valve and Fittings Industry (MSS) SP-80, 2019 Edition, Bronze Gate, Globe, Angle and Check Valves

MIL-G-24716, Apr 1993, Gaskets, Metallic-Flexible Graphite, Spiral Wound

MIL-C-24633, Oct 2014, Chain, Stud Link, Anchor, Low Alloy Steel, Flash Butt Welded

MIL-DTL-1222, Dec 2000, Studs, Bolts, Screws and Nuts for Applications Where a High Degree of

Reliability Is Required

MIL-DTL-23549, Sep 2016, Grease, General Purpose

Military Specification MIL-A-22262B, March 1996, Abrasive Blasting Media Ship Hull Blast Cleaning

National Electrical Manufacturers Association (NEMA) Stds, Pub. No. AB4, 2017, Guidelines for

Inspection and Preventive Maintenance of Molded Case Circuit Breakers Used in Commercial and

Industrial Applications

Naval Sea Systems Command (NAVSEA) Drawing 804-5959214, Rev -, Piping Insulation – Installation

Details

National Sanitation Foundation Standard 61 (NSF/ANSI 61), 2016, Drinking Water System Components

– Health Effects

National Sanitation Foundation Standard 372 (NSF/ANSI 61), 2020, Drinking Water System Components

– Lead Content

NAVSEA Drawing 167-7379842, Rev A, Procedure & Welding Sequence for Non-Ballistic, Watertight

& Airtight Quick Acting or Individually Dogged Personnel Doors

NAVSEA Drawing 803-6397268. Rev. -, Doors, W.T. Quick Acting, Arrangement

NAVSEA Drawing 804-5773931, Rev A, Acoustic & Thermal Insulation For Compartments Installation

Details

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2019, Cork and

Rubber Composition Sheet; For Aromatic Fuel And Oil Resistant Gaskets

The Society for Protective Coatings (SSPC) Surface Preparation Specification No. 1 (SSPC-SP 1), 2015, Solvent Cleaning

The Society for Protective Coatings (SSPC) Surface Preparation Standard No. 11 (SSPC-SP 11), 2013, Power-Tool Cleaning to Bare Metal

The Society for Protective Coatings (SSPC)/NACE International (NACE) 2007, Joint Surface Preparation

Standard SSPC-SP 10/NACE No. 2, Near-White Metal Blast Cleaning

The Society for Protective Coatings (SSPC)/NACE International (NACE) Joint Surface Preparation

Standard SSPC-SP 6/NACE No. 3, 2007, Commercial Blast Cleaning

U.S. Navy Resilient Mount Handbook – A User’s Guide of Installation and Inspection Information,”

NAVSEA S9073-A2-HBK-010 of 30 Aug 1988.

Underwriters Laboratories Inc. (UL) 489, May 2016, Molded Case Circuit Breaker viii (Rev-0)

CONSOLIDATED LIST OF GOVERNMENT-FURNISHED PROPERTY

The following is a list of property, which the Government will furnish. This list supersedes any other material obligations indicated or implied by referenced drawings.

WORK

ITEM

MTI ITEM DESCRIPTION NSN/PN QTY ESTIMATED

COST

($/UNIT)

25 N 26” x 66” Quick-Acting

Weathertight Door, Steel, 2-Dog, LH Swing, (including associated coaming)

JUNIPER COMPANY P/N:

JE1602/89-DI-01 Model: CC-

3013-AH-LH

2 ea. 5,800.00

25 N 26” x 66” Quick-Acting

Weathertight Door, Steel, 2-Dog, RH Swing

(including associated coaming)

JUNIPER COMPANY P/N:

JE1602/89-DI-02 Model: CC-

3013-AH-RH

2 ea. 5,800.00

28 N 5B5000 resilient mount NSN: 5340-00-543-3867 24 ea. $800.00

28 N Conical Auxiliary Snubber

Element

NSN: 5340-00-653-3518 16 ea. $500.00

28 N **Sway Brace Adjustable

Shock Mount

Fairbanks-Morse, Part Number

99999-888

2 ea. $800.00

30 N Fluxgate Sensor PN: PG-500R (OEM) NSN:

6605-01-539-0868

1 ea. $949.47

30 N Remote Display, flush mount

PN: RD33 (OEM) NSN:

7025-01-616-1486

1 ea. $416.50

*Government-loaned property, which shall be returned to the vessel upon completion of the availability.

**New or refurbished equipment that the Government may provide for installation in place of existing equipment.

***Government-furnished property, which is to be supplied by either the vessel or the C4IT Service Center

USCGC NEAH BAY (WTGB-140) DOCKSIDE AVAILABILITY FY2023

ix (Rev-0)

CONSOLIDATED LIST OF CRITICAL INSPECTION ITEMS

The following is a list of work items, which contain Critical Inspection reports, which the Contractor must complete within the first 25% of the availability contract period (see SFLC Std Spec 0000, paragraph 3.2.6.5

(Inspection report particulars)):

Work

Item Title

15 Anchor Windlass, Inspect and Service

16 Anchor Chains and Ground Tackle, Inspect and Repair

17 Vertical Capstan, Inspect and Service

24 Deck Covering, Interior, Wet and Dry, Renew

27 Grey Water Valves, Renew

28 Both Main Diesel and Generator Resilient Mounts, Renew

31 Boat Cleats Install

35 Engine Room Vestibule, Preserve x (Rev-0)

PRINCIPAL CHARACTERISTICS - TUG, ICEBREAKING

1.1

140’ WTGB (TUG, ICEBREAKING)

PHYSICAL

Length overall 140' 0"

Length between perpendiculars 130' 0"

Breadth, extreme 37' 7-1/4"

Depth, molded 18' 2-3/8"

Frame spacing 1' 6"

Full load (Winter) draft (at ) 12' 1-1/2"

Full load (winter) displacement 687 Long tons (LT)

Full load (winter) center of gravity

Above base (kg) 13' 1"

Full load trimming moment (forward) 75.6 Ft-LT

Min. operating condition draft (at ) 11' 6-3/8"

Min. operating condition displacement 640 Long tons

Min. operating condition center of gravity

Above base (kg) 13' 4-1/4"

Min. operating condition trimming moment

Forward 76.8 Ft-LT

Height of vessel above DWL Approx. 62' 0"

MACHINERY

Main Propulsion

Engine Type Diesel-electric

Number of units: 2

Total shaft horsepower: 2500

Propeller

Number of propellers 1

Number of blades 4

Diameter of propeller 8' 6"

Pitch Fixed

NOTE

Stability values above are for representative tug. Draft and longitudinal lever values provided above are for tugs in fresh water. Longitudinal lever values are provided to adjust tug's design drag of 1.0 feet by the stern.

1 (Rev-0)

00000_0521_FLT

REC_00000_FLT_Commercial Project @ CG Facility (0121)

General Requirements

1. SCOPE

1.1 Intent. This standard specification invokes general requirements for conducting vessel repairs performed by commercial contractors at a Coast Guard facility for Coast Guard vessels.

1.2 Term interchangeability. The terms 'Contractor', 'CG Yard', 'NAVSTA EVERETT', 'shipyard', 'Base', and

'Coast Guard Industrial' are used interchangeably in this specification. Where the primary service provider is

Coast Guard personnel, references to contractor and other noted descriptors within this specification or within drawings, publications, SFLC Standard Specifications or other commercial and military references are deemed the same as prime service provider.

2. REFERENCES

COAST GUARD DRAWINGS

None

COAST GUARD PUBLICATIONS

Coast Guard Commandant Instruction (COMDTINST) M10360.3 (series), Coatings and Color Manual

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General

Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and

Allied Processes

Surface Forces Logistics Center Standard Specification 6310 (SFLC Std Spec 6310), 2020, Requirements for Preservation of Ship Structures

OTHER REFERENCES

None

3. REQUIREMENTS

3.1 General. The Contractor must conform to all requirements specified in SFLC Std Spec 0000 and in this item, as applicable, during the performance of this availability. The requirements of this WI applies to all work under the scope of this contract, whether explicitly stated in all following work items or not, and to all other work subsequently authorized by changes, modifications, or extensions to the contract.

2 (Rev-0)

3.1.1 NAVSEA drawings listed will be available FOR INSPECTION ONLY from the Coast Guard Port Engineer post-award. SFLC will not redistribute NAVSEA documents. Contractors can apply to NAVSEA headquarters directly for copies.

3.2 Fire watch requirements. The Contractor must provide fire watch personnel and equipment.

3.3 Preservation requirements. The Contractor must accomplish all preservation tasks, including touch-ups, in accordance with SFLC Std Spec 6310.

3.3.1 Brand name approval. Ensure that all contractor-furnished coatings are in accordance with SFLC Std Spec

6310, Appendix C (Authorized Coatings for Use on Cutters and Boats).

3.3.2 Coating colors and system color schemes. The Contractor must obtain a written KO authorization to deviate from any coatings required in SFLC Std Spec 6310 Appendix C before work.

3.4 Welding and brazing requirements. The Contractor must perform all welding and allied processes, and NDE in accordance with SFLC Std Spec 0740.

3.5 Environmental protection requirements. The Contractor must adhere to the following environmental protection requirements in accordance with the SFLC Stand Spec 0000:

3.5.1 USCG facilities. The Contractor must provide and maintain environmental protection as defined in SFLC

Std Spec 0000 Appendix B, Requirements for Environmental Protection at USCG Facilities, during the performance of this availability. Contractor must plan for and provide environmental protective measures to control pollution that develops during normal practice, as well as plan for and provide environmental protective measures required to correct conditions that develop during the project. Contractor must comply with applicable

Federal, state, and local laws, codes, ordinances, and regulations in their entirety. Any reference to a specific portion of a Federal, state, or local law, code, ordinance, or regulation in this or any other item must not be construed to mean that relief is provided from any other sections of the law, code, ordinance, or regulation.

3.5.1.1 USCG Generator status. The activity Generator Status for the Coast Guard Facility is small quantity exempt.

3.5.1.2 Plans and permits. The CG Facility has unit specific permits including the following:

• Spill Prevention Control and Countermeasures (SPCC) Plan: Unit has a SPCC Plan which requires certain unit-specific procedures be followed for the storage, inspection, and transfer of petroleum products in containers 55 gallons or greater.

• National Pollutant Discharge Elimination System (NPDES) Storm Water (SW) Permit: Unit has an

NPDES SW permit which requires unit-specific procedures be followed for the storage and inspection of equipment and materials which may contribute contaminants to storm water discharges.

• Air Emission Permit: Unit has an Air Emission Permit which requires unit-specific procedures be followed for the emissions of VOCs and hazardous air pollutants.

3.5.2 Test and procedures. The Contractor must be required to promptly conduct tests and procedures for the purpose of assessing whether operations are in compliance with applicable Environmental Laws. Analytical work must be done by qualified laboratories; and where required by law, the laboratories must be certified.

3.5.3 Regulatory notifications. The Contractor must be responsible for all regulatory notification requirements in accordance with Federal, State and local regulations. In cases where the Coast Guard must also provide public notification, such as storm water permitting, the Contractor must coordinate with the Contracting Officer or COR, 3 (Rev-0) and if work is being performed at a USCG Facility, the local Facility Engineer or Engineering Officer. The

Contractor must submit copies of all regulatory notifications to the Contracting Officer and the local Facility

Engineer or Engineering Officer prior to commencement of work activities. Regulatory notifications must be provided for including but not limited to demolition, renovation, National Pollutant Discharge Elimination System

(NPDES) defined site work, and remediation of controlled substances such as asbestos, hazardous waste, and lead paint.

3.5.4 Environmental manager. The Contractor must appoint in writing an Environmental Manager for the project, and must be responsible for coordinating Contractor compliance with Federal, State, local, and station environmental requirements. The Environmental Manager must ensure compliance with Hazardous Waste

Program requirements, including hazardous waste handling, storage, manifesting, and disposal; implement the

Contractors’ Environmental Management Plan; ensure that all environmental permits are obtained, maintained, and closed out; ensure compliance with Storm Water Program Management requirements; ensure compliance with Hazardous Materials including storage, handling, and reporting requirements; as well as coordinate any remediation of regulated substances such as lead, asbestos, and polychlorinated biphenyl (PCB). This may be a collateral position; however the individual must be trained to accomplish the following duties; ensure waste segregation and storage compatibility requirements are met; inspect and manage Satellite Accumulation areas;

ensure only authorized personnel add wastes to containers; ensure all Contractor personnel are trained in 40 CFR requirements and individual position requirements; coordinate removal of waste containers; and maintain the

Environmental Records binder and required documentation, including environmental permits compliance and close-out.

3.5.5 HW disposal. Contractor must comply with SFLC Std Spec 0000 Appendix B, Requirements For

Environmental Protection At USCG Facilities for HW disposal, and ensure that waste removals are conducted during normal business hours (0800-1600) on Monday through Friday (excluding holidays).

3.5.6 Additional Requirements. The Contractor must be aware of the following:

3.5.6.1. CGC NEAH BAY is parked and home-ported at the MSU Cleveland Harbor waterfront. A structural evaluation performed on 03 September 2013 resulted in the following waterfront load limits:

• A working load limit of 150 pounds per square foot (psf) uniformly distributed within 20 feet of the bulkhead face. Stockpiling, parking, and material handling is restricted to loads that fall below the 150 psf threshold. For this availability, no crane shall park or maneuver within 25 feet of the bulkhead face.

3.5.6.2 No Contractor or Subcontractor must have the authority to sign a Hazardous Waste Manifest using the

Coast Guard facility’s EPA Generator ID Number or remove contract generated hazardous waste from the Coast

Guard facility without COR or KO-approval.

3.5.6.3 Local environmental regulations at the Government facilities may be more stringent. As with all environmental regulations, the Contractor must prepare for and comply with local and state regulations.

3.5.6.4 Coast Guard facilities do not maintain Facilities Response Plans (FRPs) per 33 CFR 154. Contractor must furnish the FRP when required for over-the-water liquids transfers to and from vessels, and is required for oil/fuel transfers to/from vessels for 250 barrels (10,500 gallons) or more.

3.6 Local Policy. The Contractor must refer to site (e.g. Base) Regulations and Instructions for details regarding local policies (e.g. crane services, parking, or facility usage).

3.7 SFLC Standard Specification approved changes. The Contractor must be aware that the following are

4 (Rev-0) approved changes to published SFLC 2020 Edition Standard Specifications and supersede published content:

3.7.1 SFLC Standard Specification 8636. Add missing paragraphs between 3.2 and 3.5 of Std Spec 8636 as follows:

“3.3 Access cut boundaries. The Contractor shall ensure that access cuts comply with the requirements and restrictions detailed in the following and in SFLC Std Spec 0740, and referenced codes.

3.3.1 Location of boundaries. Boundaries of access cuts and closure plates shall, in general, be located between principal ship framing, bulkheads, and other structural members and shall be at least three inches from any of these members or from the toes of other welds. A reduction in this three inch minimum may be approved by the

KO on a case by case basis provided sufficient clearance is maintained for welding and inspection requirements.

The boundaries of access cuts and closure plates should land on existing butts or seams, wherever practicable. The boundaries of prior access cuts should be utilized wherever possible. Boundaries may extend across one or more frames as required for the size of the opening.

3.3.2 Access hole dimensions and arrangements. Holes or access cuts shall be the minimum size necessary and shall be in accordance with the following:

• Rectangular access cuts and closure plates welded into primary hull structure shall be at least 12 inches wide in the lesser dimension.

• For circular access cuts, the minimum diameter shall be 4T, where T = thickness of the involved structural member, but not less than three inches.

• Circular closure plates for access cuts less than two feet in diameter shall be dished 1/16 to 1/8 inch to allow for shrinkage when welded.

• Corners of rectangular access cuts and closure plates shall have a minimum radius of 6 inches except when a boundary lands on an existing hull longitudinal seam or transverse butt weld.

• Corners at an existing seam or butt shall intersect at a 90 degree angle.

• Cuts that are to cross existing butts or seams shall do so at an angle of 90 degrees plus or minus 15 degrees.

• In primary hull structure, existing welds forming the boundary of a cut shall be cut back 3 inches beyond the toe of the access cut, except that the cut back shall not intersect or cross an existing weld, frame, or structural member. In which case, the cut back may be reduced to a minimum of two inches in length.

• Existing welds crossed by the cut shall not be cut back.

3.3.3 Primary hull structure. Primary Hull Structure includes the shell, main strength decks, principal longitudinal bulkheads, vertical keel, deep web girders and stiffeners designed to withstand the ship bending stress.

3.3.4 Mechanically fastened joints. Welding closer than six inches to a mechanically fastened joint should be avoided. When access cuts cross or come within six inches of a mechanically fastened joint, the fasteners shall be checked for tightness and if necessary, loose fasteners shall be seal welded or removed, and replaced for a distance of 6 inches beyond the edge of the cut. When a cut crosses a mechanically fastened seam the cut plates shall be repaired using single V welds backed with glass tape (MIL-C-20079) to prevent fusion between the mechanically fastened plates.

3.4 Ship integrity maintenance. The Contractor shall maintain safety and ship integrity by installing temporary guarding and coaming, in addition to weathertight and watertight closures. Remove these temporary fabrications after closing the hull access, and grind surfaces flush in way of removals. For shell plating cuts made at or below the waterline where temporary closures are impractical, the Contractor shall secure each vulnerable compartment and subdivision to minimize potential damage to the extent permitted by the scope and urgency of the work.

5 (Rev-0)

3.4.1 Guarding. Install temporary guards in accordance with 29 CFR 1915.73.

3.4.2 Coaming. Ensure that in areas where flammable liquids may be stored, a 4 inch high metal coaming shall be installed on the surface of the deck with tack welds and fully sealed with caulking compound. The coaming shall encircle the access cut in the deck.

3.4.3 Weathertight and contamination closures. Fabricate temporary closures, using fire retardant material, before cutting access openings and install closures whenever access is not in use. Closures shall be:

• Constructed to protect the access from inclement weather and entry of contaminants (shall include a coaming or dam on the deck to redirect rain runoff away from the opening).

• Fitted with fasteners that permit rapid installation and removal.

• Able to support a minimum of 150 pounds per square foot for horizontal deck closures.

• Where the access opening is in way of a removed hatch, scuttle or door, the closure shall be configured to allow normal passage of ship’s personnel and equipment.

3.4.4 Watertight closures. Ensure that access openings created four feet or less above the maximum anticipated waterline shall include temporary watertight closures when the vessel is waterborne.

NOTE

NAVSEA S0600-AA-PRO-160/CH16 provides requirements for design, fabrication, and installation of temporary watertight closures.”

4. NOTES

4.1 QA inspection forms. QA inspection forms (QA-1 thru QA-5), required in SFLC Std Spec 6310 to be completed and submitted during preservation of “critical-coated surfaces”, are provided at the end of this document.

6 (Rev-0)

QA-1 - QUALITY ASSURANCE INSPECTION FORM

(PRESERVATION CHECKLIST)

VESSEL NAME HULL # WORK ITEM

WORK ITEM TITLE

LOCATION OF WORK (INCL. FRAME #’S) AREA (SQFT)

CHECKPOINT 1 – COATING SYSTEM COMPLIANCE

Ensure all coatings are in compliance with SFLC Std Spec 6310, Appendix C.

CHECKPOINT 2 - PAINT STORAGE

Ensure all coatings are kept at a temperature of 65 to 85°F at all times, unless otherwise specified by the coating mfg.

CHECKPOINT 3 - AMBIENT CONDITIONS

Ensure surface and surrounding temperatures are each between 50 and 90°F for water-containing coatings, and 35 and 95°F for other coatings, unless otherwise specified by the coating manufacturer(s).

Ensure maximum relative humidity (RH) is as follows, from surface preparations through final curing of topcoat: 50% for tanks, voids, and vent plenum; and 85% for all other areas, unless otherwise specified by manufacturer(s).

Ensure surface temperature is at least 5°F above the dew point, unless otherwise specified by the coating mfg.

CHECKPOINT 4 - PRE-SURFACE PREPARATION

Remove surface contaminants (soluble salts, loose rust, mud, and marine growth) with low pressure fresh water wash down (maximum 5,000 psi). If oil and grease are present, perform solvent cleaning, as per SSPC SP-1.

Verify equipment setup, blast media, and surface preparation methods match designated test coupon.

CHECKPOINT 5 - SURFACE PREPARATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure cleanliness of prepared surface is as per specification (i.e.: SSPC SP-11, SP-10, SP WJ-2…).

Verify surface anchor profile using ASTM D4417-Methods B or C against SFLC Std Spec 6310. Conduct profile readings at a minimum of 5 locations for the first 1000-sqft area, and 2 locations for each succeeding 1000-sqft area.

Measure soluble salt conductivity in accordance with SSPC-Guide 15. Conduct 5 measurements per each 1000-sqft area (max. threshold: 70 microsiemens/cm for non-submerged surfaces, 30 microsiemens/cm for submerged surfaces).

CHECKPOINT 6 - PRIMER COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Verify proper mixing and stand-in (induction) times.

Ensure no paint is applied when the temperature is expected to drop to freezing before the paint has dried.

Ensure surfaces are completely dry, unless otherwise allowed by the coating manufacturer(s).

Verify wet film thickness (WFT) at random, to prevent under or over application. Verify final DFT.

Brush out all runs, sags, drips, and puddles.

Perform visual inspection for holidays and other defects.

CHECKPOINT 7 – STRIPE COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

After primer coat (mist coat after inorganic zinc), brush-apply un-thinned coat of same primer paint over edges, weld seams, cut-outs, and areas of complex geometries @ 3-4 mils wet film thickness (WFT).

CHECKPOINT 8 – TOP COAT APPLICATION

Verify environmental conditions (see CHECKPOINT 3).

Ensure overcoating window is as per manufacturer’s instructions.

Verify proper mixing and stand-in (induction) times, as applicable.

Verify wet film thickness at random, to prevent under or over application.

Brush out all runs, sags, drips, and puddles.

CHECKPOINT 9 – FINAL INSPECTION

Verify final system dry film thickness. Conduct 5 sets of 3 readings for each of the first 3 100-sqft areas, followed by 5 sets of 3 readings for each succeeding 1000-sqft area.

Ensure that system cure is in accordance with manufacturer's recommendation for intended service.

Ensure potable water tank exhaust ventilation is maintained continuously from and during coating application through final system cure, to exhaust all solvent to the atmosphere and to prevent solvent entrapment.

For immersion coatings (including tank U/W body), record date and time of the following events:

Final coat application: _____/_____; Return to service or removal from environment controls: _____/_____

CHECKPOINT 10 – RECORD KEEPING

Complete, sign, and submit all provided QA Inspection Forms.

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

7 (Rev-0)

QA-2 - QUALITY ASSURANCE INSPECTION FORM

(ENVIRONMENTAL READINGS)

VESSEL NAME HULL #

WORK ITEM

Use one sheet for each activity. Record conditions every four hours from before surface preparation to application of final coating system coat.

DATE

TIME

ACTIVITY (SURFACE

PREPARATION, PRIMER COAT,

BARRIER COAT, TOP COAT,

ETC…)

LOCATION (FRAME &

DECK, RELATION TO

EQUIPMENT, ETC.)

TEMPERATURE % REL.

HUMID-

ITY

DEW

PT.

SURFACE AMBIENT ΔT

| DP -

SURFACE |

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE / TIME

8 (Rev-0)

QA-3A - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-C)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

PLACE SURFACE PROFILE REPLICA TAPES IN THE SPACES PROVIDED BELOW, TO SERVE AS

PERMANENT QA RECORD. MAINTAIN A SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS

DIVIDED INTO SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Place Surface Profile Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Place Surface Profile

Replica Tape Here

Reading (mils): Reading (mils): Reading (mils):

MEAN MIL READING (IAW ASTM D4417-METHOD C) FOR ABOVE 15 READINGS:

NAME OF QP-1/NACE INSPECTOR SIGNATURE CERT. # DATE /

TIME

9 (Rev-0)

QA-3B - QUALITY ASSURANCE INSPECTION FORM

(SURFACE PROFILE LOG FOR PROFILE MEASUREMENTS IAW ASTM D4417-METHOD-B)

VESSEL NAME HULL # WORK ITEM

SURFACE PREPARATION METHOD PROFILE ACHIEVED (MILS)

MIN MAX MEAN

SSPC-SP-10/NACE No. 2

SSPC-SP WJ-1/NACE WJ-1

SSPC-SP WJ-2/NACE WJ-2

SSPC-SP WJ-3/NACE WJ-3

SSPC-SP WJ-4/NACE WJ-4

SSPC-SP-3

SSPC-SP-11

SSPC-SP-11 (inaccessible area)

Brush-blasting (non-metallic substrate)

ABRASIVE MANUFACTURER: ABRASIVE SIEVE SIZE:

RECORD MEASUREMENTS TAKEN IN THE SPACES PROVIDED BELOW, TO SERVE AS PERMANENT QA

RECORD. MAINTAIN SEPARATE LOG FOR EACH LOCATION. WHEN AN AREA IS DIVIDED INTO

SEPARATE SECTIONS, MAINTAIN A SEPARATE LOG FOR EACH SECTION.

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Reading (mils):

Mean Reading

(mils)

Mean Reading (mils) IAW ASTM DD4417).

10 (Rev-0)

QA-4 - QUALITY ASSURANCE INSPECTION FORM

(SURFACE SOLUBLE SALT CONDUCTIVITY LOG)

VESSEL NAME HULL # WORK ITEM

SOLUBLE SALT CONDUCTIVITY MEASUREMENTS IAW SSPC-GUIDE 15.

DATE TEST LOCATIONS CONDUCTIVITY (MICROSIEMENS/CM)

11 (Rev-0)

QA-5 - QUALITY ASSURANCE DATA FORM

(COATING THICKNESS)

(Use one sheet for each sequence)

VESSEL NAME HULL #

WORK ITEM

COATING MFG PRODUCT NAME

BATC

H #

INDUCTI

ON TIME

COATING SYSTEM

SEQUENCE

(PRIMER/TOUCHUP/3RD

COAT, ETC.)

DRY FILM THICKNESS (DFT) MEASUREMENTS IAW SSPC-PA 2.

SPOT 1 2 3 4 5

AVERAGE

VALUE

*BASE METAL READING

(BMR) Required, If Magnetic

Pull-Off (Type I/Banana) Gauge Is

Used.

LOCATION (FRAME REFERENCE):

SPOT 1 2 3 4 5 OVERALL AVG. DFT ADJUSTMENTS

1 AVG. BMR DEVIATION

3 BEFORE ADJUSTMENTS AFTER ADJUSTMENTS

AVG.

1 AVG. BMR DEVIATION

1 AVG. BMR DEVIATION

APPLICATION METHOD (AIRLESS,

CONVENTIONAL SPRAY, ROLLED)

AVERAGE DFT

12 (Rev-0)

12300_ESD_0121_FLT

REC_12311_FLT_140’ WTGB (ALL) (1017)

WORK ITEM 1: Tanks, MP Fuel Service, Clean and Inspect

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following tank(s):

TABLE 1 - FUEL SERVICE TANKS

TYPE OF

TANK

LOCATION CAPACITY - 95%

(GALLONS)

LOW SUCTION

(GALLONS)

Diesel Service 2-45-1-F 1,738 170

Diesel Service 2-45-2-F 1,738 170

1.2 Government-furnished property.

None.

2. REFERENCES

COAST GUARD DRAWINGS

Coast Guard Drawing 140 WTGB 116-001, Rev -, Longitudinal Framing and Side Girder

Coast Guard Drawing 140 WTGB 117-001, Rev -, Transverse Frames

Coast Guard Drawing 140 WTGB 120-001, Rev -, Structural Bulkheads

Coast Guard Drawing 140 WTGB 149-001, Rev -, Tank Tops and Flats

COAST GUARD PUBLICATIONS

Surface Forces Logistics Center Standard Specification 0000 (SFLC Std Spec 0000), 2020, General Requirements

Surface Forces Logistics Center Standard Specification 0740 (SFLC Std Spec 0740), 2020, Welding and Allied Processes

13 (Rev-0)

OTHER REFERENCES

Society of Automotive Engineers (SAE) Aerospace Material Specification (AMS) C6183, 2019, Cork and Rubber Composition Sheet; for Aromatic Fuel and Oil Resistant Gaskets

MIL-DTL-1222, Dec 2000, Studs, Bolts, Screws and Nuts for Applications Where a High Degree of Reliability Is Required

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor must submit a Critical Inspection Report as required by the following paragraphs:

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the below-listed:

• Fuel

• Piping

• Tank access cover

3.1.4.1 The Contractor must remove up to a total of 3,000 gallons of diesel fuel. Document a complete chain of custody record of the removed tank contents from the vessel to the point of final destination or delivery. Submit document to the COR upon completion of work.

3.1.4.2 Dispose of removed fluids in accordance with all applicable Federal, state, and local regulations

(see 4.2 (Tank content restoration)).

NOTE

Vessel may come in with less tank fluid contents than specified above.

Coast Guard Personnel will operate all shipboard machinery and equipment.

3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard

Personnel perform an initial operational test of the equipment listed below to demonstrate existing operational condition. Submit a CFR to include cost of labor and material for replacement.

• Designated tank TLIs

NOTE: Known defective TLI’s for both tanks.

14 (Rev-0)

3.3 Plug log. The Contractor must keep a written record of all plugs put in any tanks vents. A separate list must be kept for each tank being entered.

3.3.1 Ensure that all plugs are removed from each tank upon completion of work in the tank.

3.3.2 Ensure the plug log is available to the Coast Guard inspector when the inspector is performing his close-out inspection on each tank.

NOTE

Initial and post repair operational tests apply only to tanks that possess TLIs.

3.4 Cleaning requirements. The Contractor must remove tank cover(s) and clean tank interior surfaces free of all foreign materials, such as residual fuel or water, sediment, sludge, rust, or biological growth, taking care not to damage the coating system (if applicable). Remove cleaning media and residues continuously during the washing process. Remove any residual wash media; and wipe up residual moisture with clean lint-free cloths. The Contractor must refer to Coast Guard Drawings 140 WTGB

116-001, 140 WTGB 140 -003, 101 WTGB 120-001, 140 WTGB 149-001 for guidance.

3.5 Tank content and waste disposal. The Contractor must dispose of residual tank contents and any cleaning fluids in compliance with all applicable Federal, state, and local laws, ordinances and regulations. Document a complete chain of custody record of the removed tank contents and generated wastes, from the vessel to the point of final destination or delivery. Submit document to the COR upon completion of work.

3.6 Inspection. The Contractor must accomplish the following tasks:

3.6.1 Visually inspect all tank interior surfaces, including, but not limited to bulkheads, floor and overhead plating, structural members, manhole cover surfaces, fasteners and gasket seating surfaces.

Submit a CFR including the following, as applicable:

• Tank structural condition.

• Inaccessible areas.

• Condition of tank coating, including measurements taken, percentage, location, and type of coating failure (if tank interior surfaces are coated).

• Tank level indicator (TLI) and/or float switch condition, as applicable.

• Sounding/vent tube and striker plate condition.

• Suction and discharge piping condition.

• Fastener material and condition (correct fastener material is stainless steel).

3.7 Tank closing. The Contractor must accomplish the following after completion of all KO-authorized repairs and/or preservation procedures:

3.7.1 For unpainted fuel tank(s) that are not ballasted, apply a heavy coat of lube oil to the entire tank interior(s).

3.7.2 Ensure that the tank(s) remain open for at least 24 hours. Notify the COR at least 24 hours prior to closing the tank(s). After satisfactory inspection by the Coast Guard Inspector and completion of all authorized repairs, close tank manhole cover(s) with new gasket material conforming to AMS-C-6183.

Chase threads on studs to ensure even installation of the access covers. Renew any damaged or missing

15 (Rev-0) fasteners. Use MIL-DTL-1222 as guidance. Existing undamaged fasteners may be reused. For purpose of bid, assume 100% of existing fasteners will require renewal. Renew all Nylock hex nuts.

NOTES

For cutters with unpainted fuel tanks, the 24 hour tank opening period begins after completing the lube oil coating.

Coast Guard personnel will operate all shipboard machinery and equipment.

3.8 Operational test, post repairs. After completion of work and in the presence of the Coast Guard

Inspector, the Contractor must thoroughly test and demonstrate the equipment listed below to be in satisfactory operating condition. Submit a CFR.

• Designated tank TLIs

• Vent check valves

3.9 Ultrasonic thickness (UT) measurement. The Contractor must take a total of 50 UT measurements of tank plating, in locations designated by the Coast Guard Inspector, in accordance with SFLC Std Spec

0740, Appendix C. Submit a CFR.

3.9.1 In addition to the UT measurements, take up to 10 pit-depth measurements within each tank, using a suitable pit depth gauge.

4. NOTES

4.1 Tank content removal. The Ship’s force will pump down the tanks to the maximum extent possible with the installed pumping system.

4.2 Tank content restoration. The Ship’s force will procure new fluids and refill all tanks at the appropriate time.

16 (Rev-0)

12314_ESD_0121_FLT

REC_12314_FLT140 WTGB (ALL) (0611)

WORK ITEM 2: Tanks, Potable Water, Clean and Inspect

1. SCOPE

1.1 Intent. This work item describes the requirements for the Contractor to clean and inspect the following

TABLE 1 - TANKS

TYPE OF TANK LOCATION CAPACITY - 95%

(GALLONS)

LOW SUCTION

(GALLONS)

Potable Water 4-19-3-W, Tender 1,976 100

Potable Water 4-19-4-W, Tender 3,367 100

Water Mist 4-24-1-W, Tender 1,261 100

2. REFERENCES

COAST GUARD DRAWINGS

OTHER REFERENCES

American National Standards Institute/NSF International (ANSI/NSF) 61, 2015, Drinking Water

System Components - Health Effects

17 (Rev-0)

American National Standards Institute/American Water Works Association (ANSI/AWWA)

C652, 2019, Disinfection of Water-Storage Facilities

3. REQUIREMENTS

3.1 General.

3.1.1 CIR. The Contractor must submit a CIR for the inspections listed in the following paragraph(s):

None.

3.1.2 Tech Rep.

Not applicable.

3.1.3 Protective measures. The Contractor must furnish and install all protective measures in accordance with SFLC Std Spec 0000, paragraph 3.3.3 (Vessel component, space, and equipment protection).

3.1.4 Interferences. The Contractor must handle all interferences in accordance with SFLC Std Spec 0000, paragraph 3.3.5 (Interferences). Known interferences include, but are not limited to the following:

• Fluid contents

• Piping

• Deck grating.

Coast Guard personnel will operate all shipboard machinery and equipment.

3.2 Operational test, initial. Prior to commencement of work, the Contractor must witness Coast Guard personnel perform an initial operational test of the equipment listed below to demonstrate existing operational condition. Submit a CFR.

• TLI

3.3 Plug log. The Contractor must keep a written record of all plugs put in any tanks vents. A separate list must be kept for each tank being entered.

3.3.1 Ensure that all plugs are removed from each tank upon completion of work in the tank.

3.3.2 Ensure the plug log is available to the Coast Guard inspector when the inspector is performing his close-out inspection on each tank.

3.4 Tank content removal. The Contractor must remove and dispose of all fluids and/or residues in accordance with all applicable Federal, state, and local regulations. The Contractor must notify the

Dockmaster prior…