Attachment 2 - AF Form 66.pdf

PDF 52 KB Posted

Attached to
FXSB 20-1063 Construct Canopy and Pad Bldg. 15380 - JBER, AK Federal contract opportunity
Solicitation number
FA500021R0025
Issued by
Department of the Air Force Pacific Air Forces

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCHEDULE OF MATERIALS SUBMITTALS PROJECT NUMBER PROJECT TITLE SOLICITATION/CONTRACT NO.

FXSB 20-1063

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

L I N E

N U M B E R

ITEM OR DESCRIPTION OF ITEM,

CONTRACT PREFERENCE, TYPE OF

SUBMITTAL

C E

R

TI

FI

C

A

TI

O N

O F

C O

M P

LI

A

N C

E

D R

A W

IN

G

S

P

LA

N

M S

D S

M A

N F'

R R

E C

O M

M E

N D

A

TI

O N

S

R E

Q U

E S

T

LE

TT

E

R

C A

TA

LO

G D

A

TA

R E

P O

R

TS

O

TH

E R

D A

TA

TE

S

T R

E S

U

LT

S

REQUIRED

SUBMISSION

DATE

DATE

RECEIVED IN

CONTRACTIN

G

DATE TO CIVIL

ENGINEERING

RETURN

SUSPENSE DATE

FOLLOW-UP

DATE CONTRACTOR

NOTIFIED

CONTRACTOR RE-

SUBMITTAL

FINAL APPROVAL REMARKS

Notice of Start of Work

10 days prior to start of any work

Record Drawings

30 days after completion of Work

Utility Outages

14 Days prior to start of start of work

Form 3

After completion of Form

Fence Plan

1 NTP +10 Days

Quality Control Plan

1 20 Days after

NTP

Lead Abatement Plan

1 20 Days after

NTP

Material Safety Data Sheet

30 days before brought on Base

Radioactive Usage Request

1 60 days prior to start of work

Fuel Spill Clean Up Plan

1 prior to work start

Record of Proper Disposal

After completion of Disposal

Operation of the On-Base Gravel Extraction 1

If used, submit before any extraction work

13 Geo Fabric Product Data 1 30 days prior to start of work

14 Structural Backfill Sieve Analysis 1 30 days prior to start of work

15 D-1 Sieve Analysis 1 30 days prior to start of work

16 Compaction Test Results 1 3 Days after completion of test

Constuct Canopy and Pad Bldg 15380

SCHEDULE OF MATERIALS SUBMITTALS PROJECT NUMBER PROJECT TITLE SOLICITATION/CONTRACT NO.

FXSB 20-1063

TO BE COMPLETED BY PROJECT ENGINEER TO BE COMPLETED BY CONTRACT ADMINISTRATOR

NO. OF COPIES REQUIRED

L I N E

N U M B E R

ITEM OR DESCRIPTION OF ITEM,

CONTRACT PREFERENCE, TYPE OF

SUBMITTAL

C E

R

TI

FI

C

A

TI

O N

O F

C O

M P

LI

A

N C

E

D R

A W

IN

G

S

P

LA

N

M S

D S

M A

N F'

R R

E C

O M

M E

N D

A

TI

O N

S

R E

Q U

E S

T

LE

TT

E

R

C A

TA

LO

G D

A

TA

R E

P O

R

TS

O

TH

E R

D A

TA

TE

S

T R

E S

U

LT

S

REQUIRED

SUBMISSION

DATE

DATE

RECEIVED IN

CONTRACTIN

G

DATE TO CIVIL

ENGINEERING

RETURN

SUSPENSE DATE

FOLLOW-UP

DATE CONTRACTOR

NOTIFIED

CONTRACTOR RE-

SUBMITTAL

FINAL APPROVAL REMARKS

Constuct Canopy and Pad Bldg 15380

17 Concrete Mix Designs 1 30 days prior to start of work

Concrete Reinforcement product data and shop drawings 1 1 30 days prior to start of work

Concrete Embed Epoxy Product Data 1 30 days prior to start of work

20 Geotechnical Report 1 NTP +15 Days

21 Canopy 65% Design Package 1 NTP +15 Days

Canopy 100% Design / Construction Drawings 1 NTP +45 Days

23 Paint Product Data 1 NTP +10 Days

Backer rod and Sealant Product Data 1 NTP +10 Days

25 Hand Rail Shop Drawings 1 1 NTP +60 Days

26 Special Inspection Reports 1 1 3 Days after completion of inspection