STATEMENT OF WORK

PROJECT LOCATION: 182d Airlift Wing, Illinois Air National Guard 2416 S. Falcon Blvd Peoria, IL 61607-5023

PROJECT TITLE: Replace ASU#1 Bldg 728, Mech Rm 124

WORK ORDER NUMBER: 201903493

1.0 SCOPE:

1.1

2.0

2.1 Demolish ASU#1 in facility 728

A) Remove all connections from existing ASU

B)

3.1 Furnish and Install new AHU/DX Unit in B728

A) Place new AHU in same location as existing unit

ii. Reference Attachment #1 Fac. 728 - A1 - Floor Plan

iii. Reference Attachment #2 Fac. 728 - M6 - Mechanical Room Plan, Sections Details

ii. Reference Attachment #3 Fac. 728 - M7 - Piping Plan

iii. Reference Attachment #4 Fac. 728 - A3 - Building Sections, Roof Plan

DATE: June 04, 2020

Work of this contract comprises of providing all materials, tools, equipment and labor necessary to:

CLIN 0001 Demolish ASU#1 in B728, Mech Rm 124, and existing DX Unit on roof

Replace Air Supply Unit #1 (ASU#1) in west mechanical room 124 in B728 and direct expansion unit (DX) located on the roof above. All work shall be done in accordance with UFC 1-200-01, DoD Building Code Requirements , UFC 3-410-01 with Change 4, Heating, Ventilating, and Air Conditioning System.

CLIN 0002 Furnish and install new AHU/DX in B728, Mech Rm 124

i. Connections include hot water piping & vent, electric components, existing controls, and any other associated piping and ductwork to accommodate new unit.

Remove and dispose of existing condensing unit from roof

i. Remove assembly and all necessary piping and controls

ii. Recover remaining R22 refrigerant from existing system and return to owner

i. Unit should be sized appropriately to serve approximately 7485 SF.

B) Install new minimum 20 ton Air Cooled DX unit on exisiting curb on the roof.

C) Reconnect all utilities to include electric, hot water, drains, etc.

D)

E)

3.0 SPECIAL REGULATIONS:

3.1.1

3.1.2

i. Reference Attachment #8 Fac. 728 - M10 - Ventilating & Air Conditioning Plan

ii. Reference Attachment #1 Fac. 728 - A1 - Floor Plan

The Contractor shall meet all existing Government criteria pertaining to safety, air and water pollution, and noise control.

The Contractor shall comply with OSHA regulations and directives pertaining to safety practices and requirements in so far as they pertain to the Contractor's activities at the base.

i. Re-pipe where necessary. Remove unused utility lines.

ii. Reconnect existing ductwork

Install new BAS controls, balance and verify operation of completed system

Leak/ops check all new components

ii. Minimum unit specifications: 2” Foam Insulated Air Handling Unit Split Air Cooled Condensing Unit Hot Water Coil DX Coil Supply Fan w/ VFD Outside Air Filter OA/RA Modulating dampers with actuators Fully Programmable DDC controller with BACnet capability Minumum 1 year unit warranty Minimum 5 year warranty for all compressors Factory Testing Start-up

i. Integral air cooled refrigeration system provided with hermetic scroll compressors, condenser coils and prop condenser fans using 410A refrigerant

ii. Install new DX lineset, refrigerant and complete factory startup

iii. Reference Attachment #2 Fac. 728 - M6 - Mechanical Room Plan, Sections Details

iii. Reference Attachment #3 Fac. 728 - M7 - Piping Plan

iv. Reference Attachment #4 Fac. 728 - A3 - Building Sections, Roof Plan

iii. Reference Attachment #5 Fac. 728 - E9 - One Line Diagram_Elevations_Details

iv. Reference Attachment #6 Fac. 728 - M8 - Heating Details

iii. Reference Attachment #7 Fac. 728 - M9 - Mechanical Equipment Schedules

v. Reference Attachment #8 Fac. 728 - M10 - Ventilating & Air Conditioning Plan

3.1.3

3.1.4

4.0 Contractor shall submit the following:

A)

B) Material Safety Data Sheets C)

D)

E) Security Affidavits F)

G) Product Data

1) Air Handler

2) DX Unit

3) Controls

4) Ductwork

5) Balance Report

H) Operation and Maintenance Manuals I) Specifications & Drawings for all equipment

END OF STATEMENT OF WORK

Schedule of work. For project coordination purposes (i.e. among the Contractor, Contracting Officer's Technical Representative, Fire, Safety, Environmental, Security, etc.), the Contractor shall submit a proposed work schedule. The work schedule shall include but not be limited to the following: date for delivery of material/equipment; service start date; number of days service will occur; hours during which service will occur; etc.

Contractor Hazardous Material Identification Part 1; Part one is a list and specifications of potential hazardous materials that may be used during the contract.

Contractor Hazardous Material Identification Part 2; Part 2 is a list and specifications of hazardous materials that were actually used during the contract.

Written Guarantee. Submit two copies of written guarantee, signed by the Contractor and Installer agreeing to repair or replace defective materials and workmanship of work for a period of one (1) year, which starts on date of substantial completion as agreed upon by the Contracting Officer (KO).

The Contractor shall comply with Federal Acquisition Regulation 52.223-3 in regards to hazardous material. Contractor shall identify all hazardous material that will be on-site via the Hazardous Material Identification Worksheet Part 1 . Contractor shall submit a Material Safety Data Sheets (MSDS) for all material identified on the Hazardous Material Identification Worksheet Part 1. When the physical work is complete, Contractor shall submit the Hazardous Material Identification Worksheet Part 2. This worksheet shall identify all hazardous materials and associated quantities utilized on-site. Contractor shall remove all excess materials, unused materials, and/or hazardous wastes generated during the contract from the base.

Each contractor, material dealer , and any other person who provides labor, material or services of any kind, or who does work of any kind in connection with this project for any trade, must comply at all times, in all respects with the applicable provision of all federal state, county, and municipal laws, ordinances, and statutes.

8. SOW